Project Introduction Rev 2-1
Project Introduction Rev 2-1
Introduction
£
Courses never 12+ Months
Cancelled Schedule
24 Months UK Wide
Online Support Delivery
MicrosoftTraining.net
Contents
Task Creation......................................................................................................... 14
Manual Scheduling vs. Auto Scheduling ............................................................................................... 15
Setting Auto Scheduling by Default ....................................................................................................... 16
Using the Gantt Chart to enter tasks ...................................................................................................... 16
Create the Work Breakdown structure................................................................................................... 18
Manually outlining tasks into summary tasks and subtasks .......................................................... 18
Modifying a Task List .................................................................................................................................... 19
Copying a task ................................................................................................................................................. 21
Using AutoFill to enter repeat data ......................................................................................................... 21
Using AutoComplete .................................................................................................................................... 21
Using AutoCorrect ......................................................................................................................................... 22
Entering a milestone task ............................................................................................................................ 23
Editing Tasks using the Gantt Chart........................................................................................................ 23
Tips for naming tasks and setting level of detail ............................................................................... 24
Scheduling Tasks................................................................................................... 25
Working with Base Calendars .................................................................................................................... 25
Recurring exceptions and work weeks................................................................................................... 26
Creating Task Dependencies ..................................................................................................................... 29
Types of task dependency .......................................................................................................................... 29
Five ways to create task links ..................................................................................................................... 31
1. Build a plan
2. Track and manage a project
3. Close a project
Project Triangle
All projects involve time, money, and scope. Change one and the others are impacted.
At the centre of the triangle is Quality - affected by any change in the other three.
PRINCE2 offers best practice guidance on project management and has the following
features:
First released as Microsoft Project V1 in early 1990 the software has grown into a rich
application designed to help Project Managers:
Organise
List and group the tasks that together will lead to the desired Project outcome
Identify and assign the resources required to their respective tasks
Schedule
Use dependencies between tasks plus constraints to position tasks on the Gantt
chart
Manage
Forecast costs and spending (Cash flow)
Allow the plan to be modified to account for actual progress
Monitor and report on progress including spend and workload
The content of this course refers to features available in the two desktop versions (Standard and
Professional). Most of the end user features are available in both versions, the main
difference being that the Professional version is required if you want to connect to
Project Server or sync tasks with SharePoint.
Templates
o File New Select a template or from one of the suggested searches
or select New from an existing project.
Microsoft Project 2016 has numerous features not available in versions prior to
Project 2010 which are explored during this course:
Customisable fluent user interface (the new ribbon) and Quick Access Toolbar
Backstage view
Timeline view
Team Planner (Professional version only)
Manual v Auto scheduling
Navigation
The default Project view is the Gantt Chart view which consists of a table of data on the
left hand side of the screen and a Gantt bar chart on the right. The Divider Bar separates
the two and can be repositioned to display more of the table or more of the chart. The
Gantt table consists of rows and columns. Just like on a spreadsheet, the intersection
of a row and a column is called a cell. The Gantt bar chart graphically displays your
schedule.
Tip: to add commands (buttons) to the Quick Access Toolbar, right click
any existing command and from the shortcut menu choose Add to Quick
Access Toolbar:
The Ribbon, which is part of the Microsoft Office Fluent user interface, is designed to
help you quickly find the commands that you need. Commands are organized in
logical groups that are collected together under tabs.
Tip: To quickly collapse the Ribbon, double-click the name of the active
tab. Double-click a tab again to restore the Ribbon. The Keyboard
shortcut to collapse or view the Ribbon is CTRL+F1. You can also select
Pin the Ribbon on the bottom right of the Ribbon.
On the right of the status bar is the Zoom Slider and quick buttons for displaying the
main views of Project (Gantt Chart, Task Usage, Team Planner and Resource Sheet):
Note: Unlike previous versions of Project, the Entry Bar is not displayed
by default. To display the Entry Bar:
Getting Help
Tell Me box
New to Project 2016 and across other Microsoft Office 2016 is a box to the right of the
ribbon tabs with the prompt ‘Tell me what you want to do’.
Type is a feature and Project 2016 actually does what you ask! For example if you select
some tasks and type ‘Link tasks’ or ‘Indent tasks’ Project does it for you.
2. Type a word or phrase and click Search to find help on that specific topic:
3. Click on any of the blue hyperlinks to display the various help topics
4. Exit the Help system by clicking the red Close button X
Simple Check-List
File Info Project Information Advanced Properties Summary tab - enter the
Project Title and other relevant information (can re-use this later in reports.)
The order of entry for tasks does not need to follow any set pattern: to keep the Gantt
Chart as simple as possible, enter your tasks in approximate chronological order, but
this is by no means essential.
There is no need to enter all the tasks at this stage: additional tasks can be inserted,
tasks can be moved, copied or deleted. A practical approach is to initially enter only
the main tasks (Summary Tasks) and afterwards fill in the detailed tasks (Subtasks): this
is a ‘brainstorming’ stage where you and the project team are recognising all the tasks
necessary to meet the project’s objectives. This method is also known as Top-down
Planning.
Do not at this stage be concerned regarding the resources for each task or the duration: concentrate on
thinking of all the requirements which need to be covered by creating the necessary tasks.
Tasks are by default "Manually Scheduled", meaning that you have complete control
over their dates. For example, when you start typing tasks the Start, Finish & Duration
fields are blank. When tasks are in this ‘Manually Scheduled’ mode, Project will not
automatically calculate and fill in dates for you.
If you have specific dates for some tasks and just a rough idea for others you can enter
the information, even using text in the duration, start or finish columns:
If you want to set all new projects to use Auto Scheduling select:
File, Options, Schedule
For In Scheduling Options for this project change to All New Projects.
In New Tasks select Auto Scheduled.
1. Click the Summary command to insert your first main task and overtype the
placeholder text with the correct task/phase name:
5. the Undo button on the Quick Access Toolbar will undo your recent actions: by
default up to 20 actions, but you can increase this to a maximum of 99 actions (on
the File, Options, Advanced tab)
6. The cells which are affected by your last modification are automatically
temporarily highlighted in a blue colour so you easily see if other cells have been
affected by the change
7. It is possible to use In-Cell Editing but you may prefer to double click the task and
make the changes on the general tab of the Task Information Dialog Box:
To show the Entry bar select File, Options, Display, tick Entry Bar.
Tip: more than one Task can be indented/ outdented at once by selecting
the required Tasks with the mouse before the indent/ outdent operation
Tip: You can also press the Insert key (Ins) on the keyboard
Deleting a task
Moving a task
Drag and drop
1. Select the whole Task on the ID number
2. Release the mouse button
3. Hold down the mouse button while you drag and drop the Task to
the new position already visible on the screen – the task is inserted
between existing tasks
Cut and paste
1. Select the whole Task on the ID number
2. Click the Cut command
3. Click on the Task Name of the task which is to be below the moved Task
4. Click the Paste command
Using AutoCorrect
AutoCorrect automatically corrects mistyped words and expands abbreviations as you
type. Project provides an extensive list of predefined typing corrections and
abbreviations, and enables you to customise the list by adding your own:
1. Positioning the pointer at the beginning of a bar will change the pointer to a %
sign and dragging with the mouse to the left will update the percentage
complete of the task.
2. If the pointer is placed in the centre of the bar it will change to a four-way arrow
pointer. It is then possible to drag the bar to the left or right. A label will appear
informing you of what you are doing:
If you change a date that then causes a conflict, the Planning Wizard dialog box will
alert you of the problem:
are self-contained
are likely to be carried out by parties outside your project
If you still need to add further detail you can avoid having to create more tasks by
adding the additional information into the task notes tab (double click on the task
name)
Add Notes to tasks to provide details - double click the task name and go to Notes
tab
Double Click
Microsoft Project comes with three base calendars of working and non-working time:
Standard, 24-Hours and Night Shift. By default, the Microsoft Standard Calendar is
used. You can amend any of the base calendars or create your own and you can
assign different resources to different calendars. For tasks to which no resources have
been assigned, the base calendar you choose to be the ‘Project Calendar’ is used. The
‘Project Base Calendar’ is set in the Project Information dialog box.
It is important that you amend the Calendars because no bank holidays or festivals are
included in the Standard calendar.
Note: Whilst all calendars will be applied, the Gantt Chart can only display
one calendar - the vertical grey columns indicate the non-working time
in the calendar which is currently chosen to be displayed.
4. Using the form on the right of the dialog box enter the pattern of work that will
follow on those days(e.g. 9:00 to 12:00 and 13:00 to 17:30) then click OK
2. Set the Hours per day to 7.5 and Hours per week to 37.5
Note: If your revised hours apply only to this project click OK,
alternatively if all your projects will follow these new hours click set as
default
3. Finally confirm your project start time is correct. To help you do this set Project
to show task times as well as hours. Go to File then choose Options General
Project View Date Format. Choose a date format that also includes time
and click OK.
4. From the Project ribbon choose Project Information. Check the start date and
time of your project and if necessary bring it into line with the new start time for
your tasks. Click OK. Go back to options and set the date format back to date
only.
5. If your project already contains tasks you will need to correct their durations,
therefore it is best practice to set the calendar options first and then add tasks.
6. New tasks will align with the new hours you have applied.
Predecessor is the task whose start or finish drives the start or finish of the successor
Successor is the task whose start or finish is driven by the predecessor task
There are four types of dependency that can link Predecessors and Successors. You
choose the type that best describes the relationship between them:
AA Finish
Start
Finish-to-Start B
Start to Start (SS) - Start of Predecessor drives Start of Successor
Finish
Start
AA
Finish
Start
B
Start-to-Start
Finish
Start
AA
Finish
Start B
Finish-to-Finish
Finish
Start
AA
Finish
Start
B Start-to-Finish
2. Hover the mouse over the middle of the predecessor bar on the Gantt Chart,
left click and drag a link up/down to its successor
3. Double click on the name of a task, on the predecessors tab choose the name
of the predecessor(s) and set the link type
4. On the successor task row, in the predecessor column enter the ID number of
the predecessor followed by the initials of the relationship (e.g. 11FS)
5. Split the screen and in the top half of the screen select a task that will be the
successor and in the lower right half of the screen click below task name to
choose the predecessor and type of link. Click OK to commit the change.
7. Highlight or Ctrl click the tasks to be disconnected and click the unlink tasks
button on the Schedule group on the Task ribbon.
8. Double click on the task name. On the predecessors tab click on the predecessor
to remove and press the delete key.
9. On the successor task row, in the predecessor column delete the values in the
cell.
10. With a split screen in the lower right half of the screen select the predecessor to
remove and press delete.
Double click on the name of the successor and choose the predecessor tab then
In the lag field add the number of days, estimated days or % delay
A negative value produces “lead” rather than lag, and brings the successor earlier into
the plan as opposed to delaying it.
All automatically scheduled tasks have a constraint. By default this is set to As Soon As
Possible (ASAP). This means that unless another task or link gets in the way Project will
position the task as early in the plan as it can.
Double clicking on the name of the task to be constrained then from the advanced tab
choose the constraint type and if appropriate add a date:
As Late As Possible (ALAP) the task will take place as late it can
Finish No Earlier Than (FNET) models a task that is not able to finish before a
certain date, but could be delayed beyond it
Finish No Later Than (FNLT) is used to describe tasks that are not able to
finish beyond a date, but are able to finish earlier
Must Finish On (MFO) positions the task’s finish on the specified date
Must Start On (MSO) as MFO but positions the task’s start on the
specified date.
Start No Earlier Than (SNET) the task starts on or after the specified date but
no earlier
Start No Later Than (SNLT) for activities that must start on or before a
specified date.
Creating Resources
Each resource is entered on its own line as follows:
Use the Work resource type for people and equipment whose
availability is capped (Max Units) so you can see if they become
over-allocated.
Use the cost resource type to track variable items such as expenses.
The rate for this type of resource is not stored in the resource sheet.
Each time this resource is assigned to a task you can enter the cost
that applies just to that task.
Material Only applicable for material resources. This is the volume that the
Label resource is purchased in. For example paint might be purchased in
litres.
Initials An alternative to having the full name beside bars on the GANTT
chart
Max Units The maximum number of units of the resource. 100% generally
means one individual; 300% 3 individuals. (Work type only)
Cost/Use A one off cost associated with the resource. Is charged every time
resource is allocated to a task. Can also be used in addition to
Standard Rate.
Accrue At Determines if the resource costs are charged at the start of the task;
throughout the task, or at its end.
Base The base calendar which determines the resource’s working time.
Calendar (Work Type only)
Once the resource is assigned its name appears on the Gantt Chart to the right of the
task bar.
This assigns 100% to the Units column which means 1 person assigned. This is a good
way to assign resources where only part of their time is required on that tsk (for
example 50% units). Also, for example if there were 2 developers available it would be
Then in the lower pane, under resource to assign and press OK.
This is especially helpful way assign a resource to multiple tasks at once. To do this:
1. Select the first task then keeping the Ctrl key pressed click on the other tasks
2. Now select Resource, Assign Resources
3. Click the Assign button
4. Press the Close button
If using the Assign Resources click one resource then press the Ctrl key and click on
each other resource to assign then press the Assign button followed by Close.
Example
A two day task starts on Monday and finishes on Tuesday. Two resources are then
allocated to it.
Resource 1, works both Monday and Tuesday, thus finishing its contribution within the
2 day duration. Resource 2 however is on holiday on Monday, and therefore starts its
2 day contribution on Tuesday, finishing Wednesday.
Therefore the task starts on Monday with resource 1 and finishes on Wednesday with
resource 2; thus having a new duration of 3 days.
Fixed Units
The default setting for a task is Fixed Units. (See Information, Advanced tab, Task Type).
This means that if a task duration is increased the Units remains fixed and it is the Work
that increases. Similarly if the work done on a task is decreased then its duration will
decrease. The Units will not change so it is called Fixed Units.
Work for a task can be entered for a task by selecting View, Details (split screen task
view) To calculate how much work is done it is helpful to use this formula:
Fixed Duration
There are times when you change the units of a resource but don’t wish the task
duration to change. For example, add an extra trainer to a workshop (100% to 200%)
or adding extra managers to attend an interview panel. In those cases you can keep
the task duration the same by changing the task type to Fixed Duration. What will
change is the amount of work done.
Fixed Cost
There are other times where you wish to increase duration of a task but keep the work
on a task fixed. Normally the work would increase but to keep it fixed select the task
type Fixed work. This also has the effect of keeping the cost of the task unchanged if
the resource has been given a standard cost rate.
Click the Existing Tasks command to display a list of tasks then tick specific tasks you
wish to add to the timeline (for example the summary tasks):
Tip: You can also drag and drop tasks onto the Timeline.
Copy Timeline
After clicking in the existing Timeline select File, Print to print or PDF on its own as a
full page document. Click Copy Timeline to copy the Timeline for pasting into a
PowerPoint slide into an email message.
To add further Timeline bars click the +Timeline button. Then after clicking inside the
second Timeline choose Existing Tasks as before and click the tasks to display. In
this way it is possible to present each phase of a project as a separate Timelines.
To display the Calendar view selects View, Calendar from the 'Task Views' section.
This view has three options for viewing your project tasks: -
Right-clicking the calendar will give you options to modify settings such as the
Timescale where in the 'Week Headings' tab you can change the default view of 7 days
to 5 days.
The Network Diagram view displays tasks and task dependencies in a network or
flowchart format. A box (sometimes called a node) represents each task, and a line
connecting two boxes represents the dependency between the two tasks.
Task ID
Task Name
Task Duration
Scheduled
Start Date
Scheduled Resource
Finish Date
1. Under Box Layout, in the Arrangement list, click how you want the boxes to be
arranged.
2. For rows and columns, specify alignment, spacing, height, and width in the
corresponding boxes.
3. To space boxes evenly, click Fixed in the Height and Width boxes.
4. If you can't arrange Network Diagram boxes the way you want, you may want
to position them manually: Click Allow manual box positioning, click OK, and
then drag the boxes to the location you want
Page to the left or right CTRL+ PAGE UP On the horizontal scroll bar,
or click the gray area on the left
CTRL+ PAGE or right of the scroll box to
DOWN scroll left or right in
increments
Critical Path
The Critical Path is made up of those tasks that determine the end date of your project.
In other words if a task on the critical path moves, the finish of the project will move as
well (positively or negatively)
A quick way to see the critical path is to switch to the Tracking Gantt view. Critical tasks
are coloured red.
From the Task ribbon View group on the left hand side, click the lower half of
the Gantt Chart button and choose Tracking Gantt.
On the Format tab of the ribbon, click the Critical Path check box:
Modifying Views
Resource Usage and Task Usage views
The Usage views are useful for quickly adjusting the amount of work a resource needs
to do and the dates when the work needs to be done.
With the Task Usage view, resources are grouped under the tasks to which they
are assigned:
With the Resource Usage view, tasks are grouped under the resources assigned
to them:
Double click a task to display the Assignment Information dialog box and use this to:
Note: if you change the contour in the Task Usage view, an indicator
representing the contour pattern appears in the Indicators field next to
In the Timescale dialog box you can choose to display up to three tiers (Top, Middle
and Bottom) and within each of these it is possible to alter the units, the label and the
count of the interval.
Tab Function
Custom Allows you to enter project properties by which you can search
and define links to actual values in your project.
for a quick view of the Note’s first paragraph, point the mouse at the Task’s Note
indicator
to view all of a Task Note or to edit a Note, click in any of the Task’s fields and
again click the Task Notes button on the Task ribbon Properties group
or double-click the Note icon in the Indicators field
Task Notes can be printed out with your project plan
1. To insert a Hyperlink into a task first right-click the task and select hyperlink at
the bottom of the menu to open the Insert Hyperlink dialogue box. You can also
use the short cut key CTRL+K.
If you use Paste Special you can select Microsoft Project Document Object which will
paste the table data and the Gantt chart if visible.
Copy Picture
You can capture an image of the project plan as a non-
editable picture using the Copy Picture dialog box which
is opened when using the 'Copy Picture' button located in
the 'Task' ribbon, 'Clipboard' section. Click the drop-down
arrow of the 'Copy' button then click the 'Copy Picture'
button. The Copy Picture dialog box provides various options to set the way in which
Copy Specify the rows to be included in the picture. The user can
include the selected rows or all the rows on screen.
Gantt Charts form the significant part of a regular communication about your project
and can be quickly formatted to display the critical tasks, the current progress,
comparison with the original plan, and the new projected completion.
Use the Text tab of the Bar Styles dialog box to change what information is displayed
next to the bars on the Gantt Chart:
Page Setup
To set up the page for
printing
Scaling
Paper size
Header / Specify data to go into the header and footer of each page
Footer
All Columns
First X columns
Notes associated with tasks
Blank Pages
And also select here if the timescale is to run to the end of the page
E&OE
STL Training reserves the right to revise this publication and make changes from time
to time in its content without notice.
www.MicrosoftTraining.net 0207 987 3777 63