Transmission_Congestion_Management_of_IEEE_24-Bus_Test_System_by_Optimal_Placement_of_TCSC
Transmission_Congestion_Management_of_IEEE_24-Bus_Test_System_by_Optimal_Placement_of_TCSC
Abstract—In the deregulated power system congestion of there is need to manage congestion in the network to achieve
transmission network is a key challenge. Any attempt to improved power quality & system stability.
operate transmission system beyond its line limits leads to
congestion. By use of FACTS devices, the power transfer Basically in a vertically integrated utility market the central
capability of network increases & reactive power compensation agency or single utility directly controls the activities like
is done thereby improving the power system stability and generation, transmission and distribution. It is a fact that
network power quality. This paper presents the optimal irrespective of relative geographical location of buyer and
placement of Thyristor controlled series compensators (TCSC) seller, every buyer wants to buy the power from cheapest
to avoid congestion in the transmission network. The optimal price/generator.
placement is figured out by factors like line utilisation factor
(LUF), line loading, voltage profile at each bus & real and In de-regulated parlance Congestion refers to transmission
reactive power losses between buses. An algorithm is presented line hitting its limits. There are certain characteristics which
for finding the optimal location for placing TCSC. The limits the network to reliably transfer the electric power, they
reactance model of TCSC is considered to hike the power are
capabilities of the line. The potency of the model is tested on
Thermal limits
IEEE 24-bus system with the standard data using MATLAB-
PSAT Simulink. Voltage limits
Keywords— Percentage line loading, LUF, TCSC, Stability limits.
voltage stability
44
Authorized licensed use limited to: NATIONAL INSTITUTE OF TECHNOLOGY SRINAGAR. Downloaded on December 17,2024 at 06:10:36 UTC from IEEE Xplore. Restrictions apply.
a. Economic efficiency Since the loads in the power sector are constantly changing
& it is difficult to predict sometimes the role of TCSC in
b. Non Discriminative
transmission network is vital.
c. Be transparent
FSC (Fixed Series Compensation): Because of the effects
d. Be robust due to line reactance modification the FSC of line is
desirable for power transfer in an efficient manner. FSC is
II. THYRISTOR CONTROLLED SERIES CAPACITOR(TRSC) nothing but adding a series capacitance in the line to provide
compensation which is shown in Fig.1.The reactive
First, confirm that you have the correct template for your impedance of the line decreases because of the presence of
paper size. This template has been tailored for output on the series capacitance in the line, thereby lowering/minimizing
A4 paper size. If you are using US letter-sized paper, please the voltage drop across the lines in the network. In this
close this file and download the Microsoft Word, Letter file approach the reactance of the line is counteracted by the
TCSC comes under one among four types of FACT devices series capacitance inserted in between buses resulting in
which are used to compensate lines for enhancement of overall minimum/lower line impedance thereby minimizing
power quality and system stability [5]. It is a series type the voltage drops across the line.
FACT device uses series compensation technique to govern
the line flow in an economic manner by compensating the
reactance of the transmission line. The configuration of
TCSC consists of parallel combination of controlled reactor
along with a capacitor bank. This parallel combination of
reactor and capacitor allows smooth control of the basic
frequency over a wide range. To stop overvoltage across
capacitor a Metal oxide varistor (MOV) is connected across
it. Fig.1 FSC of Transmission line
45
Authorized licensed use limited to: NATIONAL INSTITUTE OF TECHNOLOGY SRINAGAR. Downloaded on December 17,2024 at 06:10:36 UTC from IEEE Xplore. Restrictions apply.
line between bus2 & bus6 is coming out to be 117.65%. At
(4) the same time the voltage at bus number 6 is marked very
low among other bus which is given by 0.721359[p.u]. The
active & reactive power losses are high between bus2 &
Whereas the MLR (Maximum Line Rating) of a bus6. Thus the line between bus2 & bus6 is the best possible
transmission line is a manufactured/default value assigned location to install TCSC. Therefore the optimal location for
to line. the placement of TCSC is between bus2 & bus6.
Table I shows the parameters cause to choose the optimal
LUF (Line Utilization Factor): In power system concepts the
location for the placement of TCSC
utilization factor is defined as “the ratio of
highest/maximum load which could be drawn to the rated
capacity of the system. This LUF concept is closely related TABLE I. PARAMETERS RELATED TO BUS 2 & 6
to the LF (Load Factor) Voltage at bus 2 1.035pu
Voltage at bus 6 0.721359pu
LUF can also be represented in terms of % line loading Active power loss between bus 2 & 6 0.200423pu
concept. Reactive power loss between bus 2 & 6 0.732887pu
% Line loading between bus 2 & 6 117.65%
(5) Line Utilization Factor 1.1765
III. SIMULATION AND RESULTS Table II shows the total generation, total load, & total losses
The simulation of IEEE 24 bus system is carried out in the of both real & reactive power.
MATLAB - 2016a (Matrix-oriented programming)
environment using PSAT-2.1.10(Power System Analysis
Toolbox).The SLD(single line diagram) of IEEE 24-bus TABLE II. TOTAL GENERATION,LOAD,LOSSES UNDER BASE CASE
WITHOUT TCSC
system for simulation analysis is as shown in Fig.2
SYSTEM GENERATION pu
Real power 29.46
Reactive power 9.809
SYSTEM LOAD pu
Real power 28.7082
Reactive power 6.363
SYSTEM LOSSES pu
Real power 0.761055
Reactive power 3.446399
A. Base case
1). The load flow without TCSC: The SLD is composed of
two area networks. Load flow is performed on IEEE 24-bus
system under base case and from the power flow report the
following parameters are calculated,
Line loadings of each line
LUF (Line Utilization Factor) of each line
46
Authorized licensed use limited to: NATIONAL INSTITUTE OF TECHNOLOGY SRINAGAR. Downloaded on December 17,2024 at 06:10:36 UTC from IEEE Xplore. Restrictions apply.
is improved. Reduction in active & reactive power loss is
seen. Table III illustrates the improvement in the voltage
profile and reduction in the active & reactive power losses
between bus 2&6.
The total generation, total load, total losses of both active & Congestion itself means an abnormal condition in the
reactive power under base case with TCSC are shown in network operation. For congestion management/contingency
Table IV. analysis the heavily loaded line in the base case of system is
removed. i.e the line in between the buses 2&6 is removed
TABLE IV. TOTAL GENERATION,LOAD,LOSSES UNDER BASE CASE for congestion analysis[7-11], after taking out the line
WITH TCSC between bus 2&6, the total number of lines in the IEEE 24-
SYSTEM pu bus system came down to 32.
GENERATION 1). Load flow without TCSC: The power flow is performed
Real power 30.48
by taking IEEE 24-bus system with 32 transmission
Reactive power 10.4499 networks under contingency case. From the power flow
SYSTEM LOAD pu report the % line loadings of each line and LUF’s of each
Real power 29.86 line are calculated from the formula mentioned above & it is
observed that the voltage at bus number 8 is less and its
Reactive power 7.085
below 1pu value. And also the line between buses 7&8 is
SYSTEM LOSSES pu loaded heavily. The active power loss between bus 7&8 is
Real power 0.626357 coming high. From the calculated %line loading & LUF,
Reactive power 3.364691 observed active power loss & voltage profile at buses, the
optimal location for the placement of TCSC is figured out.
Thus the TCSC is installed between bus 7&8.
The improvement in the voltage profile of the network can
be seen by observing Fig.4. Table V shows parameters of network between bus 7&8
under contingency without TCSC
47
Authorized licensed use limited to: NATIONAL INSTITUTE OF TECHNOLOGY SRINAGAR. Downloaded on December 17,2024 at 06:10:36 UTC from IEEE Xplore. Restrictions apply.
Fig.7 Voltage profile of system under contingency case with TCSC
TABLE VII. PARAMETERS RELATED TO BUS 7 & 8 Fig.8 Percentage line loading under base case
Voltage at bus 7 1.025pu
IV. CONCLUSION
Voltage at bus 8 1.01896pu
The main aim of this work is to figure out the optimal
Active power loss 2.22E-16pu placement of TCSC in an IEEE 24-bus system which is
between bus 7&8 performed on MATLAB software under both base &
Reactive power loss 0.013717pu contingency cases. The optimal placement is determined
between bus 7&8 using different factors such %line loading, LUF, voltage
profile, losses at different buses. An algorithm is presented to
figure out the optimal location for placing TCSC. The
The total system losses after installing TCSC can be reactance model of TCSC is considered to hike the power
observed from the Table VIII. capabilities of the line. It is observed that the total system
losses under considered cases i.e. base case and contingency
case are reduced. Under base case condition the percentage
TABLE VIII. TOTAL POWER LOSSES AFTER INSTALLING TCSC reduction in real power losses after installing TCSC is
17.69% & reactive power losses is 2.37%. Under
TOTAL LOSSES pu
contingency case the reduction in real power loss after
installing TCSC is 3.53% & reactive power losses reduced
Real power 0.610415 by 2.66%. Apart from reduction in system losses the overall
voltage profile is improved with improvement in power
Reactive power 3.109922 quality.
REFERENCES
The improvement in the voltage profile can be seen by
observing Fig.7. [1] K.Satyanarayana, B.K.V. Prasad, G.Devanand, N.Siva Prasad,
“Optimal Location of TCSC with Minimum Installation Cost using
PSO”, IJCST Vol. 2, SP 1,pp 156-160, 2011.
[2] Ibrahem Totonchi , Ibrahem Totonchi et. al.,“Sensitivity Analysis for
the IEEE 30 Bus System using Load-Flow Studies” , 3rd International
Conference on Electric Power and Energy Conversion Systems
(EPECS), 2-4 Oct. 2013.
48
Authorized licensed use limited to: NATIONAL INSTITUTE OF TECHNOLOGY SRINAGAR. Downloaded on December 17,2024 at 06:10:36 UTC from IEEE Xplore. Restrictions apply.
[3] Sriparna Roy Ghatak, Debarghya Basu, Parimal Acharjee, “Voltage International Conference on Control, Instrumentation, Energy and
Profile Improvement and Loss Reduction Using Optimal Allocation Communication, pp 417-420, 2014.
of SVC”, India Conference (INDICON), 17-20 Dec. 2015. [8] Kanwardeep Singh1, Vinod K. Yadav, Arvind Dhingra ,“Congestion
[4] L. N. Mrunalini Devi1 & A. Surya Prakash Rao, “Optimal Placement Management Using Optimal Placement of TCSC in Deregulated
Of TCSC For Reactive Power reserve Management With Reactive Power System”, International Journal on Electrical Engineering and
Power Loss minimization Using Hybrid Psogsa” , International Informatics, Volume 4, Number 4, pp 620-632, 2012.
Journal of Power Systems & Microelectronics (TJPRC: IJPSM) Vol. [9] Anwar S. Siddiqui, Manisha Rani ,“Enhancing the Power System
1, Issue 1,pp 61-72, 2016. Load ability Using TCSC: Improved Gravitational Search
[5] Manasarani Mandala and C. P. Gupta,“ Transmission Congestion Algorithm”, International Journal of Innovative Research in Science,
Management with TCSC using Bacterial Foraging-Particle Swarm Engineering and Technology, Vol. 4, Issue 4, pp 1943-1950, 2015.
Optimization”, IEEE International Conference on Power Electronics, [10] Pallavi Choudekar, SK Sinha, Anwar Siddiqui, “Transmission line
Drives and Energy Systems (PEDES), 16-19 Dec. 2012 efficiency improvement and congestion management under critical
[6] Uma.V , P.Lakshmi ,J.D.Anunciya ,“Congestion Management in contingency condition by optimal placement of TCSC”, 7th India
Deregulated Power System by Fuzzy Based Optimal Location and International Conference on Power Electronics (IICPE), 2016.
Sizing of UPFC” , WSEAS Transactions On Power Systems, Volume [11] H. He, Z. Xu ,“Impacts of Transmission Congestion on Market Power
9, pp 258-266,2014. in Electricity Market”, Power Systems Conference and Exposition,
[7] Sananda Pal, Samarjit Sengupta ,“Congestion Management of a 10-13 Oct. 2004.
Multi-bus Transmission System using Distributed Smart Wires” ,
49
Authorized licensed use limited to: NATIONAL INSTITUTE OF TECHNOLOGY SRINAGAR. Downloaded on December 17,2024 at 06:10:36 UTC from IEEE Xplore. Restrictions apply.