CCP certification study guide
CCP certification study guide
8
Chapter 1 – Cost Elements
Frank D. Postula, PE CCP FAACE AACE Hon. Life
Introduction/Learning Objectives
Cost is one of the three fundamental attributes associated with performing an activity or the acquisition
of an asset. These are: price (cost), features (performance), and availability (schedule). The key learning
objectives are:
Understand what makes up cost – i.e., the basic resources (material, labor, etc.) that are needed
to perform an activity or create an asset.
Understand the distinction between cost elements that are directly applied to an asset and
those that are indirectly applied.
Relate the cost elements to the life cycle of the asset: acquisition, use and disposal.
Use the understanding of cost elements to further understand how cost is measured, applied,
and recorded to arrive at the total activity and/or asset cost.
Apply the knowledge gained to solve problems related to cost element source and definition.
Terms to Know
Activity
Asset
Cost
Cost categories
Cost elements
Cost objectives
Direct costs
Fixed costs
Indirect costs
Project
Resources
Variable costs
Work breakdown structure (WBS)
Concepts
o Cost engineering is the application of scientific principles and techniques.
o What are the key activities that generate cost when they are performed or that define plans and
processes that cause (or influence) cost to be generated in other activities and/or assets?
o What are the elements that make up cost?
o How are these cost elements categorized and how do they relate to one another?
o Why is it important to collect and account for costs as they relate to specific activities and
assets?
9
o How to apply these cost elements and categories to the insight for managing activities and
assets?
Cost Definition
o Cost is the value of an activity or asset.
o Resources used are categorized as material, labor, and “other.”
o The value of the asset may also include the cost elements of scrap material or manufacturing
spares, construction form-work and expendable safety items, as well as the cost of transporting
the material to the work site.
Material
o Material is the physical composition of the asset. However, the value of the asset may also
include the cost elements of scrap material or manufacturing spares, construction form work
and expendable safety items, and the cost of transporting the material to the work site.
Labor
o Labor as the value of the work needed to complete the activity or asset.
Other
o The “other” cost category is resources that are needed to support the activity and/or asset.
Cost Structure
o It is important to further structure the cost elements within the material, labor, and other
resource categories in order to understand how they influence the total cost of the activity or
asset and to get a better understanding of how they can be controlled.
Grouping
The cost elements can be grouped into direct costs, indirect costs, fixed costs, and variable costs.
o Direct costs are those resources that are expended solely to complete the activity or an asset. In
other words, any cost that is specifically identified with a particular final cost objective, but not
necessarily limited to items that are incorporated in the end product as material or labor is
considered direct cost.
o Indirect costs are those resources that need to be expended to support the activity or asset, but
are also associated with other activities and assets. In other words, any cost not directly
10
identified with a single final cost objective, but identified with two or more final cost objectives.
Indirect costs may also be referred to as “overhead costs” or “burden costs.” Indirect costs are
general administrative activities associated with operating the business, costs for providing and
maintaining field equipment or a manufacturing facility, and expenses for utilities, taxes, legal
services, etc.
o Fixed costs are those cost elements that must be provided independent of the volume of work
activity or asset production that they support. These can be either direct or indirect costs.
o Variable costs are those cost elements that must be provided and are dependent on the volume
of work activity or asset production that they support. Again, these can be either direct or
indirect costs.
o Grouping examples can be found in Chapter 1, Skills and Knowledge of Cost Engineering, 6th
Edition, Tables 1.2 and 1.4.
Cost Management
The four common methods for providing cost information as they apply to cost management are as
follows:
o Cost Estimating: This is the prediction of the quantity and cost of resources needed to
accomplish an activity or create an asset.
o Cost Trending: Cost trends are established from historical cost accounting information. Cost
management questions may focus on how expenditures are trending relative to physical
accomplishments.
o Cost Forecasting: Forecasts are much like estimates. Whereas an estimate is always for future
activities and assets, forecasts are prediction of the cost at completion for cost elements that
are in progress.
o Life-Cycle Costing: Life-cycle costs (LCC) are associated with an asset and extend the cost
management information beyond the acquisition (creation) of the asset to the use and disposal
of the asset.
11
Check on Learning
1. ______________ are those cost elements that must be provided and dependent on the volume of
work activity or asset production that they support.
A. Direct Costs
B. Indirect Costs
C. Fixed Costs
D. Variable Costs
A. Code of Accounts
B. Summary Level Accounts
C. Activity Based Costing
D. Work Breakdown Structure
3. _______________ are those cost elements that must be provided independent of the volume of
work activity or asset production that they support.
A. Direct Costs
B. Indirect Costs
C. Fixed Costs
D. Variable Costs
4. _______________ are those resources that are expended solely to complete the activity or asset.
A. Direct Costs
B. Indirect Costs
C. Fixed Costs
D. Variable Costs
5. _______________ are associated with an asset and extend the cost management information
beyond the acquisition (creation) of the asset to the use and disposal of the asset.
12
6. ______________ are those cost elements that must be provided and difficult to appropriate as a
direct cost on specific assets that they support.
A. Direct Costs
B. Indirect Costs
C. Fixed Costs
D. Variable Costs
7. The work breakdown structure (WBS) can be an effective aid for which type of communications?
A. Team
B. Company
C. Customer
D. All of the above
8. Which of the following is a key reason to use a work breakdown structure (WBS)?
A. Size
B. Shape
C. Stamping tool
D. Weight
13
Solutions
1. D Variable Costs
Refer to Chapter 1, “Cost Structuring” topic
3. C Fixed Cost
Refer to Chapter 1, “Cost Structuring” topic
4. A Direct Cost
Refer to Chapter 1, “Cost Structuring” topic
6. B Indirect Cost
Refer to Chapter 1, “Cost Structuring” topic
9. C Stamping tool
Refer to Chapter 1, “Cost Structuring” topic
14
Chapter 2 – Pricing and Costing
Rohit (Roy) Singh, P.Eng. M.Ed., CCP
Introduction/Learning Objectives
This chapter highlights the difference between pricing and costing. It is very important to distinguish
between the terms “price” and “cost.” There is a very fine difference between them, which is why
people often tend to use them interchangeably. This chapter discusses the concepts of pricing and
costing of a project, illustrates the differences and helps the reader to identify the inputs, transforming
mechanisms and outputs related to the costing and pricing process. The key learning objectives are:
Terms to Know
Cash flow
Competitive advantage
Cost
Financial management
Inputs
Opportunity cost
Outputs
Price
Profit
Return on assets (ROA)
Return on investment (ROI)
Transforming mechanism
Budgeting process
o Activity cost estimates
o Scope baseline
o Project schedule
o Contracts
Forecasting
o Applying earned value method
o Using Cost Performance Index (CPI) to calculate Estimate at Complete (EAC)
o Early prediction of overrun when EAC is higher than Budget at Completion (BAC)
Financial management
o Return on investment (ROI)
o Return on assets (ROA)
o Net profit margin
16
Check on Learning
A. Inputs
B. Transforming mechanisms (Tools & Techniques)
C. Outputs
D. Bid award
A. Project Estimate
B. Project acquisition
C. Business decision
D. Resource loaded CPM schedule
A. Labor
B. Material
C. Site overhead
D. Equipment
4. Historical records for costing and pricing a project does not include:
A. Quantity take-offs
B. Cost reports
C. Competitor pricing
D. Bid breakdowns
A. Scope of work
B. Historical records
C. Vendor quotations
D. Sales forecasts
17
7. Which financial management tool is best for comparing projects in the same industry?
8. In regards to the difference between price and cost, which statement is incorrect?
18
Solutions
1. D Bid Award
Refer to Chapter 2, “Cost-Pricing Process” topic & Figure 2.2
4. C Competitor pricing
Refer to Chapter 2, “Historical Records” topic
5. D Sales Forecasts
Refer to Chapter 2, “Inputs” topic & Figure 2.2
7. B Return on Assets
Refer to Chapter 2, “Financial Management” topic
19
Chapter 3 – Materials
Neil D. Opfer, CCP CEP PSP FAACE
Introduction/Learning Objectives
Materials are the key resource in most of the projects and production endeavors. Materials are
purchased by those using them, rather than being manufactured by the subject entity. Materials range
from the simplest of raw materials to the most complex fabricated materials with a large range in
between. This chapter provides a basic understanding of the use of raw and finished materials (as a
resource) in projects and production/manufacturing processes. The key learning objectives are:
Terms to Know
Bulk material
Competing characteristics
Engineered materials
Fabricated material
Handling, raw material
Procurement
Safety stock
Surplus
Waste
Materials Competition
o Economical and market forces often drive the selection of a particular material to use in the
finished product/project.
o Balancing best possible use/material type with risk, selling economics, safety and intended use is
necessary.
20
o Material movement should be over the shortest distance possible
o Terminal time should be in the shortest time possible
o Eliminate manual material handling when mechanized methods are feasible
o Avoid partial transport loads
o Materials should be readily identifiable and retrievable
EOQ = [√2𝑥𝐷𝑥𝑃/𝑆]
where:
D = annual demand; P = purchase order costs; S = storage/carrying costs
where:
RP = reorder point; O = order time; R = production rate; I = minimum inventory level or safety stock
Future Developments
o The use and continued advancement in computerized techniques and 3D printing.
22
Check on Learning
A. Poor material handling can result in damage to raw materials or the finished product
B. Efficient material handling can slow production operations
C. Material handling has no significant issues
D. Material handling in not a requirement; as inefficiencies are labor based
A. Material to be handled
B. Employee type
C. Production system type
D. Material handling costs
3. Which one of the following represents the four basic material categories?
4. Which one of the following represents the three general areas affecting the production materials
purchased and management?
A. Annual demand
B. Production rate
C. Purchase order costs
D. Storage/carrying costs
A. Order time
B. Sales
C. Production rate
D. Safety stock
23
7. US Resource Conservation and Recovery Act (RCRA) does not regulate the following category:
A. Pipelines
B. Generators
C. Transporters
D. Owners and operators of TSD facilities
8. The Globally Harmonized System (GHS) of Classification and Labeling of Chemicals, is a system for
standardizing and harmonizing the classification and labeling of chemicals. It addresses the
following:
24
Solutions
1. A Poor Material handling can result in damage to raw materials or the finished product
Refer to Chapter 3, “Material Handling Decision Factors” topic
2. B Employee type
Refer to Chapter 3, “Material Handling Decision Factors” topic
5. B Production rate
Refer to Chapter 3, “Economic Order Quantity” topic
6. B Sales
Refer to Chapter 3, “Economic Order Quantity” topic
7. A Pipelines
Refer to Chapter 3, “Environmental regulations” topic
25
Chapter 4 – Labor
Morris E. Fleishman, PE CCP FAACE
Introduction/Learning Objectives
Labor is one of the most important resources for a project. An owner, employer, or a project manager of
any industry needs to have a complete understanding of how the labor force works. This chapter
provides an overview of the different classifications of labor, the different types of labor wages and
benefits and also indirect and overhead labor and other costs. This chapter also illustrates the
methodology of determining realistic value of labor cost. The key learning objectives are:
Identify different classifications of labor and how each contributes to the final completed
project.
Develop labor rates for estimating.
Develop and use weighted average rates/composite crew rates.
Include indirect and overhead labor and other costs.
Estimate work hours for a given work scope at a given location.
Use labor hours to monitor work progress.
Terms to Know
Direct labor
Indirect labor
Labor rates
Labor wage
Overhead labor
Performance monitoring
Labor classifications
o Direct labor
o Indirect labor
o Overhead labor
Basic Wage:
o Sources of basic wages data may include:
Data bases from previous projects
Labor contracts
Unit rates supplied by contracting and engineering firms
Local chamber of commerce data
Government labor statistics
Published labor data bases
Standardized estimating publications such as Means and Aspen
26
Fringe Benefits
o Paid time off
o Medical and life insurance benefits
o Government mandated benefits
Overtime Wages
o Premium wage paid for work in excess of regular working hours
o Some benefits are not added to overtime hours
o Social Security and Medicare are calculated as a percentage added to overtime rate
Performance Monitoring
o Earned value computations (SPI and CPI)
SPI = BCWP (EV)/ BCWS (PV)
CPI = BCWP (EV)/ ACWP (AC)
o Understanding how to use graphical presentation of earned value data
Work Sampling
o Method to determine production or unit rates for specific work activities
o Used in setting up a company database, or determining the relationship between work at an
individual site and labor standards, which have been or may be used for estimating projects in
the future
o Comparisons can then be made against existing experience or databases to determine the most
reasonable data to use as the standard
o Used for estimating projects in the future
o The data can be used to determine how the actual work is deviating from the standard
27
Check on Learning
1. In a 40-hour per week work year, how many hours would a machinist work given the following:
A. 2040 hours
B. 1960 hours
C. 1880 hours
D. 1920 hours
2. You have the following crew mix. Calculate the composite direct crew hourly wage.
A. $11.67
B. $25.00
C. $16.67
D. $20.00
3. The following personnel are assigned to a construction project. Classify them into indirect and
overhead personnel and calculate the per hour cost added per direct work hour for each
classification. The total direct work-hours are 10,000 for the month.
28
4. Given the standard labor cost for 100 LF of footing 8 inches by 12 inches = $125.00, if the jobsite
conditions are:
A. $161.25
B. $170.00
C. $153.13
D. $165.00
5. You are given the following information for a five-day work activity:
Calculate the cumulative hours earned and determine the CPI and the SPI.
29
6. You are 10 weeks into a project and the following information is in your weekly project status
report:
CPI = 1.02
SPI = 0.98
7. Which of the following are U.S. and State government mandated labor benefits?
8. One of the most important items affecting the learning curve is the productivity improvement that
results from a crew performing __________ type operations.
A. Non-repetitive
B. Repetitive
C. Skill of the Craft
D. Machining
9. One common way to compute Estimate at Completion (EAC) is to take the Budget at Completion
(BAC) and:
A. Divide by SPI
B. Multiply by SPI
C. Multiply by CPI
D. Divide by CPI
30
Solutions
1. C
52 weeks x 5 days per week x 8 hours per day = 2,080 hours
Less: Sick time @ 5 days x 8 hours = -40 hours
Vacation @ 10 days x 8 hours = -80 hours
Holidays @ 10 days x 8 hours = -80 hours
S/T = -200 hours
Answer = 1,880 hours
Refer to Chapter 4, “Fringe Benefits” topic
2. C
1 x $25.00 = $25.00
2 x $18.00 = $36.00
2 x $12.00 = $24.00
1 x $15.00 = $15.00
6 $100.00
Composite crew hourly wage = $100/6 = $16.67
Refer to Chapter 4, “Developing Labor Rates” topic
3. B
Indirects No. Hrs./Mth. Wages/Hr. Total
Construction Management 3 172 $60 3x172x60 = $30,960
Plant Cost and Scheduling 3 172 $45 3x172x45 = $23,220
Payroll Personnel 3 172 $35 2x172x35 = $12,040
= $66,220
Indirect Allocation = $66,220/10,000 direct work hours = $6.62 per work hour
4. B
Adders
Jobsite conditions Average +7%
Worker skill Poor +15.5%
Temperature 80°F +0%
Work week 50 hours +13.5%
Total adders +36%
Unit Rate = $125.00 x 1.36 = $170.00
Refer to Chapter 4, “Developing Labor Rates” topic
31
5. C
Day 1 earned = .15 x 215 = 32.25
Day 2 earned = .28 x 215 = 60.20
Day 3 earned = .57 x 215 = 122.55
CPI = earned/expended = 122.5/144 = 0.85
SPI = earned/planned = 122.5/136 = 0.90
Refer to Chapter 4, “Performance Monitoring” topic
8. B Repetitive
Refer to Chapter 4, “Learning curve” Topic
9. D Divide by CPI
Refer to Chapter 4, “Performance Monitoring” topic
32
Chapter 5 – Engineering Role and Project Success
Neil D. Opfer, CCP CEP PSP FAACE
Introduction/Learning Objectives
Provide a basic understanding of the systems and their associated cost and schedule issues that lead to
efficient and effective engineering efforts. The key learning objectives are:
Identify engineering issues involved in product, project, and process development, including
research, the use of CAD/CAE/CAM, product liability, patents, trade secrets, and developing
prototypes.
Understand product and process design and production issues, including process selection,
standardization, manufacturability, constructability, and "make" or "buy" issues.
Identify production health and safety issues.
Identify issues involved in planning facility layout.
Design assembly and flow process charts.
Understand other engineering production/construction concepts, such as reengineering, and
relate engineering decisions on product selection to their impact on process selection.
Terms to Know
Engineering Production/Construction
o Production health and safety
o Facility layout
o Assembly and flow process charts
o Quantitative analysis in facility layout
o Reengineering
34
Check on Learning
1. Research that attempts to develop a usable product or new feature to an existing product is:
A. Pure research
B. Applied research
C. Market research
D. Competitive research
2. Since June 1995 in the US and generally in all industrialized countries, a patent’s duration is ____?
A. 20 years
B. 15 years
C. 17 years
D. 10 years
A. Petro-chemical plant
B. Machine shop
C. Power plant
D. Automotive manufacturer
6. Continuous production method systems are less expensive in the long run because ______?
35
7. Slight changes in design that do not affect the product, but instead promote ease of assembly of the
product, are referred to as __________?
A. Constructability
B. Process selection
C. Manufacturability
D. Continuous production
9. Which approach can reduce field labor content by allowing work to off site in a controlled
environment?
A. Constructability
B. Process selection
C. Manufacturability
D. Continuous production
36
Solutions
1. B Applied research
Refer to Chapter 5, “Pure and Applied Research” topic
2. A 20 years
Refer to Chapter 5, “Patents and Trade Secrets” topic
4. B Machine shop
Refer to Chapter 5, “Process Selection” topic
6. D Both A and C
Refer to Chapter 5, “Process Selection” topic
7. C Manufacturability
Refer to Chapter 5, “Manufacturability” topic
9. A Constructability
Refer to Chapter 5, “Constructability” topic
37
Chapter 6 – Machinery, Equipment, and Tools
Dr. Carl C. Chrappa
Introduction/Learning Objectives
This chapter illustrates the management of machinery, equipment, and tools related to a project and
their impact on the project schedule and the costs. An overview of how to establish an equipment
valuation database and identify the different categories and subcategories of the equipment value is
provided. This chapter will also discuss equipment price and cost information and the current and
residual values for new and used equipment. The key learning objectives are:
Establish an equipment valuation database and identify the different equipment value
categories and subcategories.
Research equipment price and cost information.
Understand the factors that affect current and residual values for new and used equipment.
Terms to Know
o Market value (used equipment, secondary market value). Subcategories are ranked in
decreasing order of monetary value:
Fair market value-in-place
Fair market value-in-exchange
Orderly liquidation value
Forced liquidation value
Salvage value/part-out value
Scrap value
38
Equipment Condition Terms & Definitions
o Example 1:
Very Good
Good
Fair
Poor
Scrap
o Example 2:
Excellent
Good
Average
Fair
Poor
Data Filing
o By standard industry classification (SIC)
o By equipment class and type
o By industry category
o By equipment manufacturer’s name
Inflation Factor
o Use “machine-specific” instead of “industry-specific” inflation indices to improve reliability.
40
Check on Learning
1. When using market value method to assess equipment value, which one of the following will have
the highest value?
2. Cost adjustments are applied to normalize used equipment value. Which one of the following is not
generally applied to add or deduct from the used equipment sales data?
3. Owner/leasing companies routinely apply an inflation factor to analyze residual value. Which one of
the following inflation factor generally yields the highest reliability?
4. Equipment value category-Replacement Cost New has three subcategories, what are the three
subcategories?
5. The “normal” residual value curve of long-lived equipment usually follows an L-shaped curve. The
high-tech equipment, such as a computer, exhibits what type of curve shape?
A. Normal
B. Regulation change
C. High obsolescence
D. High inflation
41
6. Residual analysis formats differ from company to company, but should contain the same basic
elements. Of the two more popular formats used in the industry, which item below is not an
element of either format type?
A. Manufacturer
B. Equipment description
C. Life expectancy
D. Equipment serial number
7. Generally speaking, there are 12 items that should be considered in estimating residual values;
which list best describes those items?
A. Initial cost, maintenance, location of equipment, and use, wear and tear
B. Population, age, legislation and regulation, and economy
C. Changes in technology, foreign exchange, tax laws, and method of sales
D. All of the above
8. From a practical standpoint in determining residual values, the _________ is oftentimes believed to
be the most accurate estimating methodology, because of its reliance on sales and trade data.
A. Market approach
B. Cost approach
C. Income approach
D. Vendor inquiry approach
9. The two major categories of equipment values that are used to establish an equipment valuation
database are?
10. Based on available information during a 1980’s study, it was found that guarantee companies
annually experienced losses (on their guarantees) in the area of only ___ percent of the total values
guaranteed.
A. 2.5
B. 1.5
C. 1.0
D. 2.0
42
Solutions
3. C The machine-specific indices tailor to each type of equipment and have the
highest reliability
Refer to Chapter 6, “Calculating Residual Values” topic
5. C High Obsolescence - The high-tech equipment has a short life and follows the
high obsolescence type curve shape
Refer to Chapter 6, “Residual Value Curves” topic
8. A Market Approach
Refer to Chapter 6, “Determining Residual Value Methodology” topic
9. D Both A and B
Refer to Chapter 6, “Conclusion” topic
10. B 1.5
Refer to Chapter 6, “Calculating Residual Values” topic
43
Chapter 7 – Economic Cost
Neil D. Opfer, CCP CEP PSP FAACE
Introduction/Learning Objectives
Facing the heightened global competition, cost professionals need to sharpen their knowledge and skills
of economic costs. Making the right decision to pursue a project, product or service requires a sound
understanding of the time value of money, tax impact, depreciation, and economic analysis techniques.
The key learning objectives are:
Evaluate, on an economic analysis basis, the differences between two or more alternative
courses of action.
Understand such concepts and techniques as depreciation methods, net present value, annual
cash flow analysis, rate-of-return, benefit-cost analysis, and payback periods.
Terms to Know
Benefit-cost ratio
Depletion
Depreciation
Discount Rate
Economic Analysis
Economic Life
Equivalent uniform annual benefit (EUAB)
Equivalent uniform annual cost (EUAC)
Future Value
Net present value
Opportunity Costs
Payback periods
Present Value
Rate of return
Taxes
Time value of money
Types of Costs
o Opportunity costs
o Sunk costs
o Book costs
o Incremental costs
Changes in Costs
o Inflation
44
Money supply
Exchange rates
Demand-pull inflation
Cost-push inflation
o Deflation
o Escalation
o Currency variation
45
Check on Learning
1. ______________ represents the foregone benefit by choosing one alternative over another.
A. Book costs
B. Sunk costs
C. Opportunity costs
D. Incremental costs
2. A cost that represents funds already spent by virtue of past decisions is:
A. Opportunity cost
B. Sunk cost
C. Book cost
D. Inflation
4. The rise in the price level of a good or service or market basket of goods and/or services is called
________________.
A. Currency variation
B. Deflation
C. Escalation
D. Inflation
A. Taxes
B. Escalation
C. Investment tax credits
D. Depreciation
6. ABC Construction Company owns a crane with an original cost of $500,000 and an estimated salvage
value of $200,000. Its life is estimated to be 15 years. Using straight-line (SL) method, calculate the
depreciation of this asset.
A. $20,000
B. $33,333
C. $13,500
D. $50,000
46
7. ABC Construction Company owns a small tractor with an original cost of $10,000 and an estimated
salvage value of $2,000. Its life is estimated to be 5 years. Using double-declining balance (DDB), in
what year will the small tractor be fully depreciated?
A. 5
B. 4
C. 2
D. 1
8. A cross-country highway is built for $200,000,000 and will have maintenance costs of $500,000 per
year. At 10 percent interest, what is the capitalized cost of perpetual service?
A. $550,000,000
B. $205,000,000
C. $220,000,000
D. $500,000,000
9. Two new highway systems are being considered for construction. Project West has a NPV (net
present value) of benefits $30,000,000 and NPV of costs is $20,000,000. Project Southwest has a
NPV of benefits $55,000,000 and NPV of costs is $45,000,000.
Using the benefit-cost ratio analysis method, which highway system should be built?
10. As a cost professional, you are requested to perform project screening in ten minutes. Which one of
following projects is worthy of further review?
47
Solutions
1. C Opportunity costs
Refer to Chapter 7, “Opportunity Costs” topic
2. B Sunk costs
Refer to Chapter 7, “Sunk Costs” topic
4. D Inflation
Refer to Chapter 7, “Inflation” topic
5. B Escalation
Refer to Chapter 7, “Escalation” topic
6. A
D = depreciation charge
C = asset original cost
S = salvage value
N = asset depreciable life (years)
D = (C – S) / N
D = (500,000 – 200,000) / 15
D = 300,000/15
D = $20,000
Refer to Chapter 7, “Straight-line Depreciation” topic
7. B
D = depreciation charge
C = asset original cost
BV r = book value of asset at end of rth year
BV 0 = book value at beginning of year 1 = C
N = asset depreciable life (years)
D = (2 / N) (BV r-1)
48
Because the small tractor cannot be depreciated below its salvage value of $2,000, Year 4 will see a
reduced allowable depreciation of the small tractor.
* Note: An asset cannot be depreciated below its salvage value. Thus the depreciation for year 4 is
limited to only $160 to claim the maximum cumulative depreciation allowance of $8,000 ($10,000 -
$2,000). Year 5 has no depreciation allowance.
Refer to Chapter 7, “Sum-of-years Digit Depreciation” topic
8. B
Capitalized Cost= $200,000,000 + ($ 500,000 / 0.10)
= $200,000,000 + ($5,000,000)
= $205,000,000
Refer to Chapter 7, “Capitalized cost” topic
9. A
Project West
Project Southwest
On the basis of the B/C analysis, both projects have B/C ratios greater than 1, and pass
the initial screening test. The next step is performing incremental B/C ratio tests by
evaluating the increased cost of Project Southwest against Project West.
The incremental B/C of 1 indicates a break even situation. In this situation, Project West
is preferred because of the lower investment cost.
Refer to Chapter 7, “Benefit-cost Ratio Analysis Method” topic
10. B
Based on the limited information and tight time constraint, using payback period
method is the only viable economic analysis technique.
Project B has the shortest payback period indicating fastest recovery of the capital
investment.
Refer to Chapter 7, “Payback Period Method” topic
49
Chapter 8 – Activity-Based Cost Management
Gary Cokins
Introduction/Learning Objectives
The general ledger uses a chart of accounts, whereas Activity-Based Cost Management (ABC/M) uses a
chart of activities. Expenses occur at the point of acquisition with third parties. This is when money (or
obligation) exits the company. From the expenses, all costs calculated are representations of how those
expenses flow through work activities and into outputs of the work. ABC/M ties each cost element to an
activity and makes cost structure transparent. Low and non-value contributing activities can be reduced
or eliminated to improve cost efficiency. The key learning objectives are:
Understand why managers and employees are misled by arbitrary cost allocations with broad
averages that violate the costing cause-and-effect principle.
Understand how Activity-Based Cost Management (ABC/M) transforms spending expenses on
resources (e.g., salaries) into calculated costs of processes, and their work activities that belong
to them, and then into products, service-lines, channels and customers.
Identify how cost drivers cause costs to occur.
Understand how attributes are tags or scores that are attached to activities to suggest actions
Understand how ABC/M is used in addition to strategic purposes, such as profit margin analysis,
for cost management, productivity, and asset use.
Terms to Know
50
Introduction of greater variation and diversity creates complexity results that require more
overhead
The shift to overhead displacing direct labor reveals complexity. ABC/M points out where
the complexity is and where it comes from
Activities are expressed with action verbs and trace expenses to outputs
o Difference between ABC/M and the General Ledger and traditional cost allocations
ABC/M describes activities using an action-verb-adjective-noun grammar convention, such
as inspect defective products
ABC/M uses a chart of activities
ABC/M describes what it was spent for
ABC/M is work-centric
General Ledger uses a chart of accounts
Chart of Accounts is inaccurate for reporting business process
General Ledger is organized around separate departments or cost centers
General Ledger uses mapping to its hierarchical organization chart
General Ledger describes what was spent
General Ledger is transaction-centric
52
Check on Learning
1. Why have the indirect expenses (i.e., overhead) of most organizations been displacing the direct
expenses as a relative portion of its cost structure?
4. What are the ultimate final cost objects of a cost measurement system?
53
6. All the following statements are correct except:
A. Expenses and costs are the same depending on the perspective of contractors or owners
B. In ABC/M system, all costs are calculated representations of how expenses flow through
work activities and into outputs of work
C. The general ledger uses a chart of accounts
D. ABC/M uses a chart of activities
A. Those that are critical steps that cannot be eliminated in a business process
B. Those that are performed to resolve or eliminate quality problems
C. Those that are performed as a result of a request or expectation of a satisfied customer
D. Those that are performed to monitor quality problems
A. Remove waste
B. Remove low-value adding activities
C. Seek a better way to manage unused capacity
D. All of the above
54
Solutions
1. C The expansion in diverse product lines and types of sales and distribution
channels has caused complexity requiring more indirect costs to manage the
complexity
Refer to Chapter 8, “Impact of Diversity in Products, Service Lines, Channels, and
Customers” topic
2. D Expenses are when cash is paid out by the organization, and costs are the
calculated usage of the expense spending
Refer to Chapter 8, “Activities Are Expressed With Action Verbs and Trace
Expenses to Outputs” topic
6. A Expenses and costs are the same depending on the perspective of contractors or
owners
Refer to Chapter 8, “Activities Are Expressed With Action Verbs and Trace
Expenses to Outputs” topic
55