Waste Risk Assessment

The document is a risk assessment for waste management at project ABC, issued on January 1, 2025, with a next assessment due on January 1, 2026. It identifies various hazards associated with waste activities, such as lithium batteries and cleaning agents, and outlines existing risk control measures along with their residual risks. The assessment includes a risk matrix to evaluate the severity and likelihood of adverse events, categorizing risks as extreme, high, medium, low, or negligible.

Uploaded by

Sazzadul Hossain
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
8 views4 pages

Waste Risk Assessment

The document is a risk assessment for waste management at project ABC, issued on January 1, 2025, with a next assessment due on January 1, 2026. It identifies various hazards associated with waste activities, such as lithium batteries and cleaning agents, and outlines existing risk control measures along with their residual risks. The assessment includes a risk matrix to evaluate the severity and likelihood of adverse events, categorizing risks as extreme, high, medium, low, or negligible.

Uploaded by

Sazzadul Hossain
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 4

Document No: QHSE-RA-W-HSE-00-F

RISK ASSESSMENT Date of issue: 01-01-2025


Revision: 00
(Waste)
Page 1 of 4

PROJECT / LOCATION: DATE OF ASSESSMENT: DATE OF NEXT ASSESSMENT


ABC 01-01-2025 01-01-2026

TASK / ACTIVITY
Waste

SR. Risk Level Residual Risk


Hazards Hazards Effects (If the hazard is released) Existing Risk Control Measures Remarks
L S RR L S RR
 Training on proper use and maintenance of
lithium batteries.
 Lithium Batteries shall be discharged, taped,
Lithium Battery Resource segregated, labelled, and transferred to a
1. Fire, Explosion, Emission to atmosphere 3 4 M 1 5 L
Consumption licensed waste management facility and
stored on rigid wooden pallets.
 Lith-X Fire extinguisher to be made available
in workshop and all units. PPE.
 Refer to COSHH assessment for chemical
Use of Lubricants / management. Clean empty drums; lubricant
2. Creation of Lubricant Land contamination 3 4 M 1 5 L
containers are to be placed in the general
Waste (Container)
waste skip.
Use and Creation of Paper  Paper reduction awareness posters.
3. Land contamination 3 4 M 1 5 L
Waste Recycling of paper.
 Turn off all appliances while not in use,
4. Use of Electricity Use of Energy 3 4 M cleaner turn off all lights, AC units at the end 1 5 L
of the day.
Use and disposal of  Purchase (where practicable)
Skin irritation, burns, water contamination,
5. cleaning agents 3 4 M 1 5 L
land contamination environmentally friendly cleaning agents.
(Domestic)
Use and disposal of  All toner/print cartridges are to be
6. Land contamination 3 4 M 1 5 L
Toner/ Print Cartridges segregated and placed in the 'Toner' bin.
7. Disposal of bottled Land contamination 3 4 M  Purchase only Specific water which they 1 5 L
drinking water have dedicated recycling system.

HSE DOCUMENTS-WASTE RISK ASSESSMENT


Document No: QHSE-RA-W-HSE-00-F
RISK ASSESSMENT Date of issue: 01-01-2025
Revision: 00
(Waste)
Page 2 of 4

 All plastic bottles are to be placed in the bin


provided in the designated areas.
Creation & disposal of oily  Ensure disposal only in the wash bay yard
8. Water contamination 3 4 M 1 5 L
waste with dedicated facilities.
Creation & disposal of oily  Place all oily rags/gloves in a designated
9. Land contamination 3 4 M 1 5 L
rags/gloves hazardous waste skip
 All scrape metal as a result of maintaining
10. Creation & disposal of equipment shall be placed in the scrap metal
Land contamination 3 4 M 1 5 L
scrap metal bin which shall be clearly highlighted and
segregated from other waste
 Dispose of waste following local guidelines
11. Creation & disposal of
Water contamination, waste handling 3 4 M  Dispose of sewage safely in the designated 1 5 L
sewage
facility.
 Use proper equipment and adhere to
12. Creation of HGV & LGV disposal protocols
Emission to air 3 4 M 1 5 L
Exhaust  Reduce unnecessary trips and optimize
routes.

HSE DOCUMENTS-WASTE RISK ASSESSMENT


Document No: QHSE-RA-W-HSE-00-F
RISK ASSESSMENT Date of issue: 01-01-2025
Revision: 00
(Waste)
Page 3 of 4

Risk Matrix
SEVERITY Consequences:
Insignificant Minor Moderate Serious Major Catastrophic 6 – Catastrophic – Multiple fatalities
1 1 2 3 4 5 6
5 – Major - Single Fatality
LIKELIHOOD

2 2 4 6 8 10 12
4 – Serious – Permanent disability
3 3 6 9 12 15 18
3 – Moderate – Lost Time Injury
4 4 8 12 16 20 24
2 – Minor – Medical Treatment
5 5 10 15 20 25 30
1 – Insignificant – First Aid Case
6 6 12 18 24 30 36

24 - 36 Extreme Immediate action required, Activity should not to proceed in current form
Prompt action required, including interim actions. Activity should be modified to include remedial
15 - 20 High
action and planning.
Schedule action including any interim countermeasures e.g. implement safe work procedures,
8 - 12 Medium
signage, instructions
4-6 Low Activity can operate subject to management and or modification,
Very Low/
1-3 Risk almost certainly acceptable, no action required unless escalation of risk is possible
Negligible

Likely Frequency:

HSE DOCUMENTS-WASTE RISK ASSESSMENT


Document No: QHSE-RA-W-HSE-00-F
RISK ASSESSMENT Date of issue: 01-01-2025
Revision: 00
(Waste)
Page 4 of 4

Likelihood (of Adverse Event Occurring)


Description Health & safety Environmental
6 Almost certain or imminent Occurs all the time Continuous or will happen frequently
5 Highly likely Common occurrence, Occurs multiple times in a year Happens 5 – 10 times per year
4 Likely or could occur Know to occur in the last 12 months 1 – 5 times per Year
3 Not likely, but possible Has occurred in an industry worldwide Once every 5 years
2 Unlikely Has not occurred in over 10 years of the same activity Not happened in over 10 years
1 Rare Theoretically possible, but not expected to occur theoretically possible, but not expected to occur

Prepared by: HSE Engineer


Reviewed by: HSE Manager Approved by:
Sign: Date: Sign: Date: Sign: Date:

HSE DOCUMENTS-WASTE RISK ASSESSMENT