Integration testing is a logical extension of unit testing. In its simplest form, two units that have already been tested
are combined into a component and the interface between them is tested. A component, in this sense, refers to an
integrated aggregate of more than one unit. In a realistic scenario, many units are combined into components, which
are in turn aggregated into even larger parts of the program. The idea is to test combinations of pieces and eventually
expand the process to test your modules with those of other groups. Eventually all the modules making up a process
are tested together. Beyond that, if the program is composed of more than one process, they should be tested in
pairs rather than all at once.
Integration testing identifies problems that occur when units are combined. By using a test plan that requires you to
test each unit and ensure the viability of each before combining units, you know that any errors discovered when
combining units are likely related to the interface between units. This method reduces the number of possibilities to a
far simpler level of analysis.
Test Framework
Class A
Integration
Integration
Class B Class C
Integration
Class D
FIGURE 1
Top-Down: The top-down approach to integration testing requires the highest-level modules be test and
integrated first. This allows high-level logic and data flow to be tested early in the process and it tends to
minimize the need for drivers. However, the need for stubs complicates test management and low-level utilities
are tested relatively late in the development cycle. Another disadvantage of top-down integration testing is its
poor support for early release of limited functionality.
Bottom-Up: The bottom-up approach requires the lowest-level units be tested and integrated first. These units
are frequently referred to as utility modules. By using this approach, utility modules are tested early in the
development process and the need for stubs is minimized. The downside, however, is that the need for drivers
complicates test management and high-level logic and data flow are tested late. Like the top-down approach,
the bottom-up approach also provides poor support for early release of limited functionality.
Sandwich Testing: Also referred to as Hybrid Integration Testing, requires testing along functional data and
control-flow paths. First, the inputs for functions are integrated in the bottom-up pattern discussed above. The
outputs for each function are then integrated in the top-down manner. The primary advantage of this approach is
the degree of support for early release of limited functionality. It also helps minimize the need for stubs and
drivers. The potential weaknesses of this approach are significant, however, in that it can be less systematic than
the other two approaches, leading to the need for more regression testing.
Big band integration approach: In big bang approach most or all of the developed modules are coupled
together to form a complete system and then used for integration testing. Big Bang Integration Testing is an
integration testing strategy wherein all units are linked at once, resulting in a complete system. When this type of
testing strategy is adopted, it is difficult to isolate any errors found, because attention is not paid to verifying the
interfaces across individual units.
Stubs are dummy modules that are always distinguish as "called programs", or you can say that is handle in
integration testing (top down approach), it used when sub programs are under construction. Stubs are considered as
the dummy modules that always simulate the low level modules.
For Example we have 3 modules login, home, and user module. Login module is ready and need to test it, but we call
functions from home and user (which is not ready). To test at a selective module we write a short dummy piece of a
code which simulates home and user, which will return values for Login, this piece of dummy code is always
called Stubs and it is used in a top down integration.
Considering the same Example above: If we have Home and User modules get ready and Login module is not ready,
and we need to test Home and User modules Which return values from Login module, So to extract the values
from Login module We write a Short Piece of Dummy code for login which returns value for home and user, So these
pieces of code is always called Drivers and it is used in Bottom Up Integration.
The replacement for the 'called' modules is known as 'Stubs' and is also used when the software needs to interact
with an external system.
Test Framework
Class A
Class B Class C
Stub Class D
FIGURE 2
FIGURE 3
The above diagrams clearly states that Modules 1, 2 and 3 are available for integration, whereas, below modules are
still under development that cannot be integrated at this point of time. Hence, Stubs are used to test the modules.
The order of Integration will be:
1,2 -> 1,3 -> 2,Stub 1 -> 2,Stub 2 -> 3,Stub 3 -> 3,Stub 4
Testing Approach:
Advantages:
- Advantageous if major flaws occur toward the top of the program.
- Once the I/O functions are added, representation of test cases is easier.
- Early skeletal Program allows demonstrations and boosts morale.
Disadvantages:
- Stub modules must be produced
- Stub Modules are often more complicated than they first appear to be.
- Before the I/O functions are added, representation of test cases in stubs can be difficult.
- Test conditions may be impossible, or very difficult, to create.
- Observation of test output is more difficult.
- Allows one to think that design and testing can be overlapped.
- Induces one to defer completion of the testing of certain modules.
Test Framework
Class A
Integration Integration
Under test
Class B Class C
FIGURE 4
FIGURE 5
4,2 -> 5,2 -> 6,3 -> 7,3 -> 2,1 -> 3,1
+ Test 2 such that it calls 4 and 5 separately. If an error occurs we know that the problem is in one of the
modules.
+ Test 1 such that it calls 3 and If an error occurs we know that the problem is in 3 or in the interface
between 1 and 3
Advantages:
Disadvantages:
Sandwich testing is also known as Hybrid approach in Integration testing. This approach is the combination of
bottom-up & Top-Down Approach. In this approach the usage of Stubs (Called Program) and Drivers (Calling
Program) are used where ever the programs are incomplete
In Sandwich testing / Hybrid Integration Testing, we exploit the advantages of Top-down and Bottom-up approaches.
As the name suggests, we make use of both the Integration techniques.
FIGURE 6
It is viewed as three layers; - The Main Target Layer, a layer above the target layer and a layer below the target layer.
Testing is mainly focused for the middle level target layer and is selected on the basis of system characteristics and
the structure of the code.
Hybrid Integration testing can be adopted if the customer wants to work on a working version of the application as
soon as possible aimed at producing a basic working system in the earlier stages of the development cycle.
In big bang Integration testing, individual modules of the programs are not integrated until everything is ready. This
approach is seen mostly in inexperienced programmers who rely on 'Run it and see' approach. In this approach, the
program is integrated without any formal integration testing, and then run to ensures that all the components are
working properly.
Testing is done as a last phase of development life cycle in form of system testing, time for writing test case and
defining test data at unit level may be saved.
No Stubs/Drivers is required to be designed and coded in this approach. the cost involved is very less as it does
not involved much creation of test artifacts.
Big Bang approach is very fast. It may not give adequate confidence to users as all permutations and
combinations cannot be tested in this testing. Even test log may not be maintained
Problem found in this approach are hard to debug, Many times defects found in random testing cannot be reproduced
as one may not remember all steps followed in testing.
It is difficult to say system interface are working correctly and will work in all cases.
Location of defect may not be found easily. In this event if we can reproduce the defect, it can be very difficult to
locate problematic areas for correcting them.
Testers conduct testing based on few test cases by historic approach and certify whether the system works/ do not
work.
Testing techniques Top-down Bottom-up approach Sandwich approach Big Bang approach
approach
Characteristics
5 CASE STUDIES
Case study is done for Banking Integration for Account Management and Bank analyzer
The Transactional banking system (Accounts Management System) application component is responsible for the
management and processing of the statutory reporting figures. It provides information about the receivables and
payables between a bank and third parties. The accounts, balances, and payment items are managed in the Account
Management system
Analytical system (Bank Analyzer) supports overall bank controlling by calculating, evaluating, and analyzing
financial products. Bank Analyzer provides a consistent view of a bank's operational data and enables you to process
data promptly so that you are always in a position to provide current financial and risk information
This Integration enables application components to communicate with each other by means of a proxy and to send
information about account contracts the account-managing system provides account contract master data, posting
data, settlement items, and accrual items. Using an appropriate method it calls the proxy to send the data to the
connected analytical system
This integration scenario supports the "checking account", "deposit account'", and "loan" financial transactions, and
the "payment", "settlement date", and "accruals and deferrals" business transactions.
According to Top-Down testing the product will be testing assuming that bottom part is not integrated, we will
test Transactional Banking system assuming Analytical system as Stub and not yet integrated.
Testing same scenario via Top-Down Testing technique:
In Bottom-Up approach the top part will be considered as driver and not yet integrated, so we will assume
Transactional Banking system as Driver and testing will be done in Analytical system. Test case for Testing same
scenario via Bottom-up Testing technique:
In Big-Bang testing technique come in picture when all systems are integrated and working, So here we will test
Scenario assuming Transactional Banking system is integrated with Analytical system. Test case of scenario with
Big-bang testing:
6 SUMMARY
The integration of multiple applications is increasingly common and with it come new challenges to creating reliable
products. It is no longer sufficient to simply test the application you have created, now we must test the way that
application interacts with other applications that may be used alongside it. Integration testing is actually composed
of different types of tests, but its objective is to ensure that the interaction of two or more components produces
results that satisfy functional testing requirements. Integration Testing resembles actual usage more than Unit
Tests do therefore, functional deficiencies are more likely to be detected at this level of testing than they are with Unit
Testing. Here Unit is defined as the smallest testable part of an application. Integration testing can expose problems
with the interfaces among program components before trouble occurs in real-world program execution. In a
comprehensive software development environment, bottom-up testing is usually done first, followed by top-down
testing. The process concludes with multiple tests of the complete application.
additional warranty.