RSG-DC-FRM-0001
Transmitted via
☐ Hand Delivery ☒ Registered Mail ☐ Courier
Status
☒ For Approval ☐ For Information ☐ Returned for Corrections
☐ For Your Use ☐ Approved as Submitted ☐ Returned Corrected Prints
☐ For Review and Comment ☐ Approved as Noted Others (Please specify):
☐
☐ As Requested ☐ Resubmit Copies for Approval
Remarks
Acknowledgement
RSG-DC-FRM-0001
Document No.
Status IFR
Rev. C1 Contract: R02I16C31 Page 1 of 7
PROJECT:
CLIENT:
CONTRACTOR:
SAAD ALI AL ESSA GROUP
P.O Box 126, Abqaiq 31992, KSA
Tel: (013)5662858, Fax: (013)5662622
13/3/2025 R02-I16C31-SAD-ITP-ME-0004 C1
Document No.
Status IFR
Rev. C1 Contract: R02I16C31 Page 2 of 7
Revision Record
Version Date Section Page Description of Modification & Basis
CLIENT RED SEA DEVELOPMENT COMPANY ITP NO: R02-I16C31-SAD-ITP-ME-0004 REV NO: C1
1 Document / Submittals
R02-I16C31-SAD-MR-GF-SDW-ME-10101 R02-
IFC/Design
1.1 Shop Drawing Approval Approval of Mechanical shop drawings I16C31-SAD-MR-M1-SDW-ME-10101 R02- Once, Prior to Start H R SDW
Drawings
I16C31-SAD-MR-RF-SDW-ME-10101.
R02-I16D01-WSU-SPC-CS-0001-PDF[04] Division
23 (SECTION 238219)
Approved
1.2 Material Submittal Approval Approval of FCU Materials. and approved vendor Once, Prior to Start H R MAT
Submittal
List ( HVA-139 LG (SouthKorea))
R02-I16C31-SAD-MAT-ME-0014
R02-I16D01-WSU-SPC-CS-0001-PDF[04] Division
Approval of FCU installation Method of Project
1.3 Method of statment Approval 23 (SECTION 238219), Once, Prior to Start H R MTS
statment/Testing procedures. Specifications
R02-I16C31-SAD-MTS-ME-0006
R02-I16D01-WSU-SPC-CS-0001-PDF[04] Division
Material Receiving, Storage and Approval of Material received, deliver to storge Approved
2.1 23 (SECTION 238219) and For each delivery H H MIR,DN
delivery and site Submittal
R02-I16C31-SAD-MIR-ME-0001
3 Installation
4 Testing
General Notes
Employer: An authorized employee who represents RSG and is empowered to take action in the activity. This role can be filled by a Quality Supervisor, Quality Manager, Technical Engineer, or Construction Engineer as defined in the
1
Method Statement and PQP.
2 Review Point: Employer shall review the task results before moving on.
3 Surveillance Point: Monitoring work in progress, which does not require a written notification. A surveillance report may be issued to document the activity.
4 Witness Point: The Employer shall be notified in advance, in writing, about the timing of inspections or tests. However, if there is no written approval or presence from the Employer, the inspection or test shall proceed as scheduled.
5 Hold Point: The Employer shall be notified in advance, in writing, about the timing of inspections or tests. Subsequent activities should not be carried out without written approval from the Employer.
LEGEND
Surveillance
H Hold Point W Witness Point S R Review Point
Point
I Inspection
Signature
Date 3/13/2025 3/13/2025 3/13/2025
Document No
R02-I16C31-SAD-ITP-ME-0004
REV C1
PAGE
Description
Drawing No.
Location
section 1 Preparation
1.1 Shop drawing for Duct Network is approved.
section 2 Installation
2.1 Installation of Hangers and supports for FCU as per approved shop drawings.
FCUs are installed in correct location as per approved shop drawings, equipment
2.2
schedule and manufacturers recommendations.
FCUs are installed with approved vibration isolation from the structure on which they
2.3
are mounted and with approved isolation from the duct work connected to it.
Condensate pipe installation & insulation done as per approved shop drawing,methed
2.6
statement & project Specifications
At the Condensate discharge points right drains shall be installed as per approved shop
2.7
drawing.
Check the Condensate pipework slope towards drain, proper trap management as per
2.8
approved shop drawing and specification.
Ensure Gravity condense pipework shall be laid to fall at a gradient of not less than 1 in
2.9
100
3.2 Functional Test is done for operation as per approved shop drawings.