1.Method Statement format (1)
1.Method Statement format (1)
EMPLOYER
Project No.21SWCG00056
REPLACEMENT OF TECHNOLOGIES AND ENDED LIFETIME
PROJECT
ASSETS OF AL JUBAIL DESALINATION PLANT, PHASE-2
Contract No. 7576
OWNER’S
ENGINEER
CONSORTIUM OF:
INTEGRATED BY
CONTRACTOR’S
ENGINEER METITO
METHOD STATEMENT FOR BUBBLE TESTING OF LIMESTONE FILTER WATER DISTRIBUTION NOZZLES
REVISION INDEX
TABLE OF CONTENTS
Page 2 of 8
REPLACEMENT OF TECHNOLOGIES AN ENDED LIFETIME ASSETS OF AL JUBAIL DESALINATION PLANT, PHASE-2
METHOD STATEMENT FOR BUBBLE TESTING OF LIMESTONE FILTER WATER DISTRIBUTION NOZZLES
1. SCOPE………………………………………………………………………………………………………………………04
2. PURPOSE………………………………………………………………………………………………………………….04
3. RESPONSIBLITIES………………………………………………………………………………………………………04
04
6. PRECAUTIONS………………………………………………………………………………………………………….05
7. TESTING……………………………………………………………………………………………………………………05
8. SAFETY ISSUES………………………………………………………………………………………………………….06
Page 3 of 8
REPLACEMENT OF TECHNOLOGIES AN ENDED LIFETIME ASSETS OF AL JUBAIL DESALINATION PLANT, PHASE-2
METHOD STATEMENT FOR BUBBLE TESTING OF LIMESTONE FILTER WATER DISTRIBUTION NOZZLES
1. SCOPE
The Method statement is to provide a guideline and establish the requirement for Testing of the
Bubble water test in Limestone filter building for the project Replacement of Technologies and
Ended Lifetime Assets of Al-Jubail Desalination Plant Phase-2.
2. PURPOSE
The purpose of this Method statement is to establish guidelines for the proper testing of the
Bubble water test in Limestone filter building to prevent damage caused by hydrodynamic
forces, internal pressures, and trapped air during testing and initial start-up.
3. RESPONSIBLITIES
Air Testing
Water – adequately supply of clean disinfected water
Pumps – 2 Nos. duty, Capacity 4,575 m³/h each, DOL driven
Temporary Blowers – 2 Nos. duty, Capacity 6,405 m³/h, DOL driven
Piping – to connect with the Blower and pump air through the flume inlet pipe
Valves – as required to operate and control the blower
Relief and venting systems for Blowers
Vent pipe in the flume
Stopwatch or timer
METHOD STATEMENT FOR BUBBLE TESTING OF LIMESTONE FILTER WATER DISTRIBUTION NOZZLES
Verify that all flow control loops are tested, calibrated, and functional.
Confirm that all air release and vacuum check valves are operational and functional.
Check that the blower, along with its relief and venting systems, is fully operational.
6. PRECAUTIONS
7. TESTING
Before placing the support Calcite media, it is essential to test the Intake water manifold to
ensure proper installation. All systems must be tested using water, and systems that incorporate
air in the backwash cycle must also undergo air testing.
Page 5 of 8
REPLACEMENT OF TECHNOLOGIES AN ENDED LIFETIME ASSETS OF AL JUBAIL DESALINATION PLANT, PHASE-2
METHOD STATEMENT FOR BUBBLE TESTING OF LIMESTONE FILTER WATER DISTRIBUTION NOZZLES
Fill with water the cell until half height of the calcite bed. Once water achieves that
height, close the inlet valve of the cell.
Open air inlet valve.
Allow entry of air flow (75 Nm3/m2/h) through intake manifold and visually verify
that the air bubble distribution is homogeneous. If the air bubble distribution is not
homogeneous empty the cell and check that the filter nozzle are clean or any
trapped particle.
Once the issue is Rectified, Repeat the Steps again unless and until the Air Bubble
distribution are homogeneous.
8. SAFETY ISSUES
Control Measures
Toolbox Meeting: Conduct a toolbox meeting before work begins to discuss the
importance of fall protection and correct rigging procedures.
Weather Conditions: No erection activities allowed during harsh weather, such as
wind exceeding 32 km/h, thick fog, heavy sandstorms, rain, etc.
Tag Lines: Use a minimum of two tag lines to control the load.
Restricted Area: The area affected by erection activities will be a restricted zone, with
barriers and notices to prohibit entry of non-erection personnel.
Simultaneous Activities: No simultaneous activities will be allowed below any
erection work. Enforce a strict 100% tie-off policy.
Scaffolds: Scaffolds must be erected by trained personnel, inspected for safety, and
have proper access provided.
Work Permit System: Ensure the Work Permit System is in place and maintained.
Emergency Contacts: Post emergency contact numbers at work areas.
Temporary Systems: Display Temporary Amended System Route plans, ensuring
clean and clear access and ingress to work areas without obstructions.
Page 6 of 8
REPLACEMENT OF TECHNOLOGIES AN ENDED LIFETIME ASSETS OF AL JUBAIL DESALINATION PLANT, PHASE-2
METHOD STATEMENT FOR BUBBLE TESTING OF LIMESTONE FILTER WATER DISTRIBUTION NOZZLES
The Safety Supervisor will be responsible for overall coordination, information dissemination,
and continuous monitoring to ensure compliance with the method statement. Prior to the
execution of works, the Construction Supervisor will thoroughly review the plan and proceed
with the work as outlined. Additionally, the Construction Manager will play an integral role in
assisting with the monitoring process to ensure that all safety and construction procedures are
being followed in accordance with the established guidelines.
Page 7 of 8
REPLACEMENT OF TECHNOLOGIES AN ENDED LIFETIME ASSETS OF AL JUBAIL DESALINATION PLANT, PHASE-2
METHOD STATEMENT FOR BUBBLE TESTING OF LIMESTONE FILTER WATER DISTRIBUTION NOZZLES
RISK ASSESSMENT
Page 8 of 8