Construction Management Final project
Construction Management Final project
Fall 2018
Computerized Scheduling Assignment
Please work on groups of two on this project. No extra credit is given for individual teams.
In this assignment the objective is to develop a computerized precedence network for a project
consisting of the construction of 5 miles of 8" diameter pipeline. The project is a classic example
of operations where repetition plays an important role. Major activities have been identified as
locate and clear, excavate, string pipe, lay pipe, test, and backfill. The contractor wants to
proceed with most of these basic tasks concurrently.
Please note that while there are instructions in this assignment that helps the student in using MS
Project software, you are not limited to any project management software program. As an
example, some students may choose to use Primavera for doing this assignment.
Page 1 of 8
The contractor has subcontracted the stringing and testing operations and will perform clearing,
excavating, pipe laying, and backfilling with his own forces. Stringing is done by SurveyBoston
Corp. and testing is performed by GeotechMass Inc.
1.1. Prepare a Network Diagram for the whole project fitted in one sheet of paper.
1.2. Prepare a schedule report with activities sorted according to the descending TF and then
earliest ES.
1.3. Prepare a barchart (Gantt Chart) for the project with ES and EF dates appearing on the
left and right hand side of bars sorted by Task IDs. In the table include just Task ID and
Name.
1.4. Prepare a schedule report where activities are arranged by responsibility. So each group
should be identified by the subcontractor's name or the general contractor. Use
GENERAL to identify activities performed by the general contractor. This means that
you have to tell the software who is responsible for each activity (SurveyBoston Corp.,
GeotechMass Inc., or GENERAL).
1.5. Generate a schedule report containing only backfilling activities and sorted according to
earliest LS.
1.6. Generate a Gantt chart containing only subcontractors' activities (i.e. string and test).
2. Resource Loading
The objective is to load the diagram developed in the step above with manpower and equipment
requirements. Consider labor and equipment use for activities excavate, lay pipe, and backfill.
Use productivity data provided in the following tables to estimate manpower and equipment
requirements for these activities. Use Fig. (2) to estimate the volume of excavation and backfill.
Load each relevant activity with equipment and labor requirements. Use crew configurations that
result in activity durations close to durations given in Table 1. Use uniform crew configurations.
Resources Used: Assume that the excavation is performed by a 0.5 cy loader/backhoe. The pipe
is laid at the bottom of the trench and tested. It is an 8", mechanical joint construction. The pipe
is backfilled and the trench is completely filled in 8" layers. Each layer is compacted by 3 passes
of an 11"x13" rammer tamper.
2.1. Include work quantity and crew size calculations. Note that these calculations are done
outside the software.
The following outputs should come from the software.
2.2. Develop histogram and cumulative resource graphs for laborer and crane.
Page 2 of 8
the reasons for any schedule delay. You should be specific. For example, you should mention
which activities' delay caused total network delay and why? Generate any report or graph that
you think is necessary to support your reasoning.
3.1. In addition to any reports that you deem necessary, submit a schedule report of the
whole network with activities sorted according to their criticality.
Page 3 of 8
Activity Actual Start Date Actual Finish Date
Locate & clear, mile 1 3/5 3/5
Locate & clear, mile 2 3/7 3/13
Locate & clear, mile 3 3/14 3/14
Locate & clear, mile 4 3/15 3/19
Locate & clear, mile 5 3/20 3/20
Excavate, mile 1 3/13 3/ 18
Excavate, mile 2 3/20 90% complete
String pipe, mile 1 3/13 3/15
String pipe, mile 2 3/20 3/21
Lay pipe, mile 1 3/22 30% complete
Procedure: In order to perform an update for the network, first set up a baseline for the original
network. You can do this by choosing "Project" tab, then clicking on "Set Baseline". Change the
“Status date” to Mar 22, 2019. Then update each activity by entering actual dates and percent
completions using “Tracking: Table” under “View” tab. You now have a revised schedule.
Prepare the following reports:
5.1. Prepare a report of the revised schedule in comparison with Baseline schedule by
choosing/creating proper table. Remember to include Baseline Start/Finish, Actual
Start/Finish, ES, and EF.
5.2. Prepare a barchart (Gantt Chart) sorted by Task IDs of the revised schedule as compared
with Baseline schedule. Make sure ES and EF dates are showing for Tracking Gantt
bars.
You can do this using “Gantt Chart” view and changing the kind of information that you
want to display in the Gantt Chart. To specify the kind of information, right click on the
time-scaled section, select “Gantt Chart wizard”, then choose “Baseline”.
5.3. Briefly explain the reasons that caused delay in project completion date.
Please note:
The project should be organized in a professional way. Separate the reports according to the
breakdown such as Phase I, 1.1, 1.2, etc. You should have a Cover Page and a Table of Contents
with page numbers. As producing reports with sequential page numbering in MSP may be time
consuming, you can remove the page number and then add it by hand. Make sure all your
reports have proper title. All the required discussions should be typed. You will be graded
according to the quality of your presentation!
Page 4 of 8
TABLE 1 - Activity Durations
Activity Duration in days per mile
Locate and clear 1
String pipe 2
Excavation 5
Lay pipe 8
Testing 1
Backfill 3
Page 5 of 8
Page 6 of 8
Page 7 of 8
CIVE 7220 – Computer Project Grade Sheet
Fall 2018
Name(s): ____________________________________
Total 60
Page 8 of 8