rashed 1 (1)
rashed 1 (1)
School of Engineering
Civil Engineering Department
D = 2000 / 2* 0.20
D = 5,000
Profit = TR – TC
Then, by discussing the derivative of he
profit fu nction, we can maximize cot
As a result, we require revenue as a function
of d emand and cost as a function of demand
for maxi mum profit.
The second derivative must be
negative for optimum profit .
Problem 2
Six years ago, an 80-kW diesel-electric set
cost $145,000. The cost index for this
class of equipment six years ago was 187 and
is now 194. The plant engineering staff was
considering a
120-kW unit of the same general design to
power a small isolated plant that would
have cost
$200,145
Based on the information above the plant
engineering staff is considering a 100-
kW unit of the same general design to power a
small isolated plant. Assume we
want to add a pre- compressor, which (when
isolated and estimated separately)
currently costs $10,000. Determine the total
cost of the 100-kW unit.
Solution:
Cn +145000*(194/187)=$150428
150428=200145*(80/120)^x so x=0.70
For 100-Kw , 150428*(100/80)^0.7= $175859
Total cost= 10000+175859 = $ 185859
Problem 3
The structural engineering design section
within the engineering department of a
regional
electrical utility corporation has developed
several standard designs for a group of similar
transmission line towers. The detailed design
for each tower is based on one of the standard
designs. A transmission line project involving
50 towers has been approved. The estimated
number of engineering hours needed to
accomplish the first detailed tower design is
126.
Assuming a 95% learning curve.
What is your estimate of the number of
engineering hours needed to design the
eighth tower and to design the last tower in
the project?