0% found this document useful (0 votes)
8 views7 pages

STP snag IBS

The document lists various equipment abnormalities and required maintenance actions, including issues with pumps, meters, and tanks. It highlights the need for proper operator training, documentation, and rectification of multiple system failures. Additionally, it provides vendor remarks and status updates on the resolution of these issues.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
8 views7 pages

STP snag IBS

The document lists various equipment abnormalities and required maintenance actions, including issues with pumps, meters, and tanks. It highlights the need for proper operator training, documentation, and rectification of multiple system failures. Additionally, it provides vendor remarks and status updates on the resolution of these issues.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 7

SL No Equipment/Part Abnormality

1 CCT Tank CCT Pump # 1 termination is not proper.

2 Oil skimmer Oil skimmer belt is damaged

Roto meter disconnected due to faulty operation and line


3 Roto meter
bypassed, need to fix it with new meter.

UF out flow meter not working and not showing reading for
4 UF out flow meter
few months.

5 All tank junction boxes Junction boxes are not covered properly.

6 Plumbing line Plumbing pipes flow direction marking needs to be done

Oil replacement, belt tightness and air filter cleaning need to


7 Air blower
be done

8 Equalisation tank EQT manhole chamber cover needs to be closed

9 CCT,TWT,SDC Tank CCT,TWT and final tank cleaning needs to be done

10 CCT Tank level sensor Level sensor for CCT pumps is not working.

Insects and worms’ presence identified in sullage tank, and


11 Sullage chamber
which does not happen normally.
Mosquito larvae filled with in the water, its crucial to keep the
12 TWT Tank
tank like that.

None of the dosing system is working, all the dosing pumps


13 Dosing system
are under breakdown for past few days.

Media found in flocculation tank but not in MBBR. Also


14 Flocculation tank
wastes are accumulated in tanks from MBBR to CCT.

15 MBBR & TWT Water is clear in MBBR than TWT, bacteria presence is low.

16 Water seepage Water leakages identified near lime dosing tank.

17 Air blower Leakage of air identified in NRV side of both air blower.

None of the check sheet matching with actual condition of


18 Check sheets and validation operation, and this is not validated by OEM supervisors
during the monthly visit.

The operator having lack of knowledge to operate the STP


19 Operator issues
plant.

20 Filter valves Multi pot valves not supported properly.


IBS Remarks

Cable directly connected to pump without using junction


box. Please use proper ways.

As per last communication, the belt replacement has


been done due to the improper alignment the oil
collection is not efficient.

Currently roto meter had been replaced still not identified


the RCA for the core issue which affecting/ reducing the
water flow from CCT to UF.

Concerns were raised during the DLP period; hence the


replacement can be done as a part of DLP services.
Requesting expected closure date

Water entry possible and which will damage the box as


well it is unsafe for operator.

Flow directions need to reduce the confusions when


tracing the lines.

Air Blower # 2 taken out for services on 7th March - not


yet received

Tanks need to close for reducing insects and safe


environment.

All tanks having sledge and wastes inside.

Need to replace the float switch (with level sensor) which


is connected as temporary solution. Also, the same need
to cover in DLP.

Proper chemicals add on will reduce the insects and


worms.
Tanks need to close for reducing insects and safe
environment.

Necessary rectification needs to done. Currently the


dosing system not operational

Purpose of MBBR and FT not met.

Purpose of MBBR and FT not met.

Need identify the leak and clear it

Need to check the proper working.

Actual operations need to document and tracked. STP


water test reports needs to be shared

Necessary training needs to be provided to improve the


operator efficiency.

Multi-pot valves required additional mechanical support


while operating.
Expected
Vendor remarks Status
closure date

For clearing the termination, we installed new cables , but tile


removing and hole drilling is pending, once it is completed, we can OPEN
finish the work.

CLOSED

CLOSED

It is installaed, one earthing is pending 30.04.25 CLOSED

For clearing the termination, we installed new cables , but tile


removing and hole drilling is pending, once it is completed, we can OPEN
finish the work.

OPEN

Previous complaints rectified and the motor issue occurred later, its
30.04.25 CLOSED
serviced and will reinstall immediately

It’s a heavey Manhole and we request several times to change the


manhole with light duty type. Operator need to check the flow, tank
levels and aeration pattern several times in a day and manhole CLOSED
opening is not possible with a single person. Either do
arranagement for lifting or change it to light weight

CLOSED

DLP is only with one year and its not coverd now. OPEN

CLOSED
CLOSED

It is in progress and will complete it immediately 30.04.25 OPEN

CLOSED

CLOSED

CLOSED

CLOSED

CLOSED

CLOSED

Filtration system installation is as per the GA submitted during the


project time. This is the standard installation . If you required any CLOSED
additional supports, we can do it as extra .
OPEN 5

CLOSED 15

Total 20

You might also like