MHI Erection Procedure of Generator of Gas Turbine GTG
MHI Erection Procedure of Generator of Gas Turbine GTG
……………………………………………………40~
1. INSTALLATION FLOW CHART
The working sequence of major items of generator installation as shown in the flow chart below.
This flow chart is provided as a standard, and minor changes may be made depending upon the
working sequence.
1) Level check
1 Set up the leveling block QC sheet No.H2-1102, 1105, 1111-1
1) Contact check
2 Installation of Stator
QC sheet No.H2-1112,1111-2
1) Visual check
Leak check of Hydrogen Coolers
2) Leak test
QC sheet No.H2-0201~2
1) Visual check
4 Assembly of High Voltage Bushing
1
1) Seal Ring gap check
8 Clearance Check of Sealring
QC sheet No.H2-0421
1) Visual check
12 Assembly of outer Deflector
QC sheet No.H2-0710
Temporarily Installation of
Brush Gear
1) Centering check
14 Centering for TB and Generator
QC sheet No.H2-1503-1~2
2
15 Assembly of coupling bolts (Performed by Turbine team)
18 Grouting
20 Painting
3
2. GENERAL NOTES AND INSPECTION
This chapter introduce the general notes and inspection items at receiving parts and
equipments, and during erection work.
The interior of the Hydrogen cooled generators cannot be inspected when assembly is
completed. Accordingly, it is necessary that inspection be made in detail in the process of
assembly.
However, it is difficult to hold clean room perfectly, because there are many times of lifting
work of parts by overhead crane during the construction.
Still the field coils of Generator are not insulating completely, there is possibility to occur any
serious problem caused by entered electrical foreign material
(Example: small wire, humidified dust etc.).
(1) When the Generator Rotor is assembling into Stator, take overalls wear which has no
pocket and clean shoes for working at Stator inside.
(2) When the erectors perform some assembly works on Stator inside and around the Bearing
Bracket, take clean shoes. Specially, sole of shoes are kept clean perfectly and do not
bring any things; writing materials, change purse, un-usable things for work, etc., in your
pockets of working wears.
(3) The center portion which are installed electrical coils of Generator Rotor, are wrapping with
plastic (polyethylene) sheet to prevent entering foreign material until insetting to Stator.
(4) Close the opening on both end of Stator and manholes with canvas sheet or plastic
(polyethylene) sheet without working time and it is to prohibit using grinder rotating wire
brush, welder near the Rotor and openings of the Stator.
4
2.2 General information for Generator parts
2.2.1 Stator
(1) Check insulation resistance with 1000 V Megger when stator is unloaded at site.
(2) Keep the transportation covers which are fixing to the stator frame until starting assembly
work for stator.
After open the transportation covers of stator, close the opening portion (ex. Both ends of
stator frame and manholes) with canvas sheets or vinyl sheets.
(3) When the covers are opened, make inspection the inside of Stator as following points;
a) appearance of rust in the frame, especially around the ends of the lamination core
b) presence of foreign matters in the frame
(4) Check insulation resistance of the stator coil at sometimes with 1000 V Megger during
erection term.
If the insulation resistance will come down, make a drying the stator inside by blowing in dry air
or apply setting temporary heater on the bottom of the stator frame.
5
2.2.2 Rotor
(1) Check insulation resistance with 500v Megger when rotor is unloaded at site.
(2) Check insulation resistance of the rotor coil at sometimes with 500 V Megger during
erection term.2.2.3 Bearings
(1) Carefully inspect the insulation of the shaft.
If the shaft insulation is in complete, it may cause bearing damage in the form of burn
marks.
(2) Consequently, the bearing and the seal casing on the collector ring side of the generator
are insulated. Inspection of the insulation shall be made of the following points.
※ Between inner bearing ring outer bearing ring
※ Between outer bearing ring and end bracket.
※ Between seal casing and end bracket.
Measurement shall be taken at these points with a 500V Megger, and a resistance of 20kΩ or
more should be obtained.
(2) Keep all parts on the storage area with each packages and tags.
(3) We are shipping all machining surface of parts with coating anti-rust.
Remove this anti-rust coating with volatile solvent (ex. acetone etc.) before using these
parts.
6
3. SETTING OF LEVELING BLOCK AND SOLE PLATES
Curing of mortar
Removal
7
3.1 Working procedure for leveling block
(1) Chipping of foundation concrete Chipping is to be performed to depth of 25mm from the
surface of foundation concrete.
In the same way as the conventional method, chip the concrete so that floor level of the
turbine generator can be properly obtained.
(4) 24hours prior to pouring the mortar, fully moisten the foundation concrete by covering with
damp cloth, or by sprinkling with water. During this period, prior to pouring the mortar, keep
the temperature of the concrete surface, within the range of 10 to 35゚C.
This can be achieved by using flood -lights.
8
(5) Curing of mortar
After filling the mortar, cure the mortar for 2 days by keeping the environment temperature
of the mortar and concrete as a whole including pads within the range from 10 to 35゚C.
During this period of time, keep the exposed surface moistened by sprinkling water and
covering those surfaces with cloth.
9
(9) Adjustment of elevation and level for Sole Plates
Elevation of Sole Plates of generator and Brush Gear base shall be adjusted to 0 to 1mm
lower to drawing or Turbine Sole Plates of turning gear casing.
Adjust the top face of Sole Plates so that the top face accuracy become to 0.05mm/m or
less with precision water level and straight edge.
For the surface of the Sole Plates, carefully check that rust is not caused and take attention
to prevent rust.
If rust is caused, completely remove it with fine sandpaper
10
4. INSTALLATION OF STATOR
4.1 Stator on Base and Correction of Foot Faces
Place Generator Frame on the sole plates with coating contact inspect-able paint on
undersurface of stator feet. For contact check between Sole Plates and stator foot.
The contact status shall be obtained more than 75% at every Sole Plate.
11
4.2 Installing Thrust Keys for Stator Frame Feet on Collector Ring end
(1) Insert initial shim between stator foot and soleplate.
Lap and insert of key between soleplate and stator foot.
Soleplate
Leveling block Stator foot
Key groove Initial shim
Stator foot
Bolt
Shim
Stopper Stopper
Key Soleplate Key
When the key is inserted tighten the retaining bolt without fail and lock the bolt afterward.
(2) Coat grease thinly over the key surfaces and insert the key into groove on the foot and the
soleplate.
(3) Insert the key to just make contact by tapping hammer.
Not to be excessive tightening as the stator easily lengthen to horizontally.
12
5 Installation of Current Transformers for High Voltage Bushing
(1) Handling carefully so as to no damage current transformers which are molding products.
(2) Assembly of High Voltage Bushing.
Nylon Sling
Stat Bolt
Special tool
Wooden block
② Rotate 90 degrees.
13
③ Rotate 90 degrees. (Special tool side upper)
④ Insert HVB.
Prepare protectivr cover
14
(2) Retighten mounting bolts for high voltage bushing, and lock these bolts with the lock
washers, before assembling bushing current transformers.
1.Preparation ;
Make the clean-up and clear the working area where is below the generator terminal box.
Make the scaffolding under the terminal box, for assembling bushing current transformers.
2.Making up the number of installation parts ;
Prepare the all assembly parts for bushing current transformer which on the drawings.
3.Positioning the current transformers ;
Check the positioning label which is indicated on the side face of current transformers.
Sort out all current transformers and divide them into each phase
(Neutral: U1,V1,W1, Line: U2,V2,W2).
4. Assembly of current transformers;
Assembly four current transformers to each high voltage bushing and keep design space
between each transformer with setting of nut, spring washer, flat washer and two Insulated
washers.
5. Termination of current transformers;
Connect the secondary lead wires for current transformers in accordance with the wiring
drawing.
Fig.5-1: CT installation
15
6. ASSEMBLY OF HYDROGEN COOLERS
6.1 Leak check of Hydrogen Coolers
This inspection for checking no leakage under pressured coolers with hydraulic or gas, as
confirming damaged tubes due to transportation, before assemble into stator frame, in the
following;
(2) Tool to be used (All part for this test is will be prepared by contractor)
1) Hydraulic pump or N2 gas cylinder
2) Pressure gauge
3) Flexible tube
4) Valve
5) Flange
16
(5) Leak test
The water or N2gas pressure will be increased in stages.
At each stage no abnormalities shall be confirmed, before the specified test pressure is
attained.
(6) The work after hydraulic or N2 gas leak test of hydrogen coolers;
1) Dewatering or exhaust N2 gas inside coolers and the system
2) Internal cleanliness preservation.
17
6.2 Assembly of Hydrogen Coolers
・1st step
・2nd step
(3) Mount eye bolt top of cooler and attach wire rope to the eye bolt
(4) One chain block loose and pull in the cooler by using chain block
as shown in fig.6-2
・3rd step
(5) Remove wire and pull in the cooler by using chain block as shown in fig.6-3
18
Fig: 6-3 Assembly of Hydrogen cooler 3rd step
(1) This instruction covers on site connection and insulation of the rectangular terminals between
the High Voltage Bushing and Stator Winding. (Refer to figure 7-1)
(2) Normally the standoff insulator connection and high voltage bushing are taped in the factory
before shipment.
(3) After the assembly of the lower frame extension, the rectangular terminal leads should be
(1) Carefully check all parts and materials that were shipped
(2) All parts and materials shall be arranged in good condition, especially insulation materials and
varnishes (which should be stored in a dark, cool and ventilated place) and kept about five
yards away from any fire and electrical sparks to avoid danger.
(1) Check if any damage exists on the surface of connection faces of coupler and rectangular
terminal. Any surface abnormalities should bring to a smooth finish by using a file.
(2) Prior to coupler assembly, clean all surfaces of contact point of the coupler and rectangular
terminal leads.
19
(3) Assemble leads and coupler according to the drawing.
(4) When bolting, all clamping bolts and nuts for the terminals should be tightened according to
the following specified torques. (Tightening conductor stainless steel bolt torque: =77.6Nm
7.4 Insulation
(1) Assembly ventilation tube and the covers in the joint, and hold them in place with the
insulation tape
(2) Apply seven half-lapped layers of tape between layers except over the flexible portion of joint.
(3) The entire insulated jointed to be covered with one half-lapped layer of scotch tape.
(4) Coat the varnish “MOLTON#809 WH” on the insulated joint.
20
Stator lead
connection
7.7 Cleaning
(1) When the above works are completed, clean the connection portion and inside the lower
frame extension.
(2) No tools should be left inside the lower frame extension
21
8. CENTERING BETWEEN TURBINE AND GENERATOR
(1) Because centering work involves both the turbine and generator, the work shall be
accomplished under close coordination.
When performing centering, the dial indicator shall be installed utilizing the teeth of turning gear
of the low-pressure turbine rotor coupling.
(2) Provide a stopper (square timber) so that the generator rotor does not move toward
turbine side or collector ring side.
The rotor tends to move toward turbine side because in general the collector ring side is slightly
higher.
(3) Lock the lower bearings before turning the rotor (Both turbine side and collector ring
side)
(5) Supply turbine oil. (Check for shortage of oil during centering).
(6) Centering of the turbine generator is performed with the turbine and generator rotor
turned together.
When turning them together do not fit pins into the coupling bolt holes, but fit pins of a diameter
that is thinner than bolt hole diameter by 0.5mm, and fit wire so that the rotor can be turned.
(7) Make sure to protect the coupling and rotor shaft with pressboards from damage due to
wire.
(8) Vertical and horizontal adjustment shall be made with jacks fitted at fore places.
22
(10) Precautions when matching generator coupling:
The following marks are punched on the external periphery of the coupling: N, S, U, O, G,
P, Position the coupling so that G mark is located in the position directly opposite to the turbine
coupling.
(11) Turn the rotor by using a crane. When reading the dial indicator, assure that wires are
loosened. Make sure to record as “generator down”, “up open” or “down open”.
(12) Take measurement of face by using a cylinder gauge (inside micrometer with dial gauge).
Turn the rotor by 90° each time and take measurement at four points, that is top, bottom,
right, left, and takes average value.
(13) Adjustment with liners shall be made between sole plates and leveling block.
When inserting liners between sole plates and leveling block, loosen the generator anchor bolts.
A shims adjstament does generator one side.(left-side or right-side)
a
× y
Adjusting amount a =
d
y
Where y means face difference between TOP
and BOTTOM reading
Lift up by crane
Jack up
23
"0"
"U
"U "U
"U
24
9. ADJUSTMENT AND ASSEMBLY OF ALIGNMENT KEYS
After centering of turbine generator is completed, adjust alignment keys at the following
Position:
(1) Between low-pressure turbine casing and generator bearing bracket
(2) Turbine end of generator stator frame
(3) Between bearing bracket on collector ring end and brush gear base’s soleplate
Take measurement of dimension (upper and lower) by using a cylinder gauge Micrometer
The key shall be made to size slightly thicker than dimension
.
TB end CL.R end
25
10. ASSEEMBLY OF SEAL CASE
10.1 Preparation of seal case assembly
Temporary disassemble bearing and bearing rings for seal case assembly.
Screw Right side and Left side jacking bolts alternately into rotor support #1 to lift the shaft up
Liner
Dial indicator
Rotor support
Jacking bolt
Rotor support
26
10.2 Installing Seal Case
measuring point A
Seal ring
Gap gauge 0.05 Gap gauge 0.05
Rubber strap
Seal ring match marks
(2) Match the marks and assemble on the gauge and tighten the ring by bolts and push up the
ring .
(3) The ring is split into 2 pieces. Assure that no gap exist at any of 2 matching points and then
(4) Install the spring on the seal case after measurement of gaps.
27
(6) Mount the lower seal case on the shaft. Install the support.
(7) Then seal case turn in the direction shown by the arrow used by two chain block.
28
11. FILLING SEAL COMPOUND
Prepare grease pump and fill seal compound, in the following sequence by referring to the
figure below.
4) Close A and B (or C) fills from C (or B) until compound come out from D
5) Close A and C (or B) fills from B (or C) until compound come out from D
Filling holes A and D are locate along the external periphery of the Bearing Bracket, and B and
Bearing Bracket D
B C
Inlet position of
Seal compound
29
12. BEARING ASSEMBLY
(1) Bearing on Turbine side and Collector side shall be reinstalled upon completion of flushing
operation.
(3) Tighten bolts to the specified torque, and lock bolts completely.
When installing the bearing cap on Collector side take measurement of insulation resistance by
using 500V megger, and assure that a resistance value of 20kΩ or more is obtained.
(5) Check to make sure metal caps on Turbine side and Collector side are mounted with bearing
locking device.
(6) Lift the caps by using hooks and gently fit those over bearings exercising care not to cause
(7) Install external outside oil deflector and make gap adjustment.(With Three Bond applied)
Photp.12-1: Assembly of Collector side bearing Photo.12-2: Meggering of Collector side seal case
30
13. AIR LEAK TEST
The hydrogen cooled Generator is filled with hydrogen.
The pressure of hydrogen in the generator is higher than the atmospheric pressure, and hydrogen
is lighter than air.
Accordingly, hydrogen gas readily leaks. Therefore, stator frame gas piping and other gas control
equipment should provide sufficient air tightness.
If any leakage from any of these equipment hydrogen consumption increases, and there is a
danger of an occurrence of explosion if a large amount of hydrogen leaks.
Leak test is carried out to check the air tightness.
Leak test carry out fill the generator with compressed air and apply soap water on the exterior, but
if there is conspicuous pressure decay found by pressure calculation method to find leak point
include a small amount of helium gas in compressed air and to use leak detectors for detection of
gas.
31
(c) Operate the seal oil equipment and adjust the automatic oil pressure regulator valve and set
the differential pressure of seal oil to 0.55bar.
The set pressure may exceed a little from this range.
(2) Fill dry compressed air through the air blow in valve of the gas dryer.
Control the internal pressure shall be within the maximum working pressure of the generator.
(3) While the increasing of the internal pressure the following care should be exercised with the
seal oil device.
(a) Seal oil pressure increases with almost constant difference to the internal pressure as the
internal pressure rises.
It shows that the operation of the automatic oil pressure regulator valve is in good condition.
(b) When the internal pressure reaches about 0.2bar the float valve in the float trap closes and
the oil level in the sight flow come to the middle.
The oil level should never drop below this point.
If the oil level does not rise or if it drops to the bottom of the oil level gauge, there is a
problem with the float valve.
The float valve is kept closed with the former case and it is kept opened with the latter case,
whichever the internal pressure shall be reduced once and the hydrogen trap shall be
disassembled and inspected.
(4) Also carefully check for rise in oil level in seal drain oil dump trouble with seal oil device and
excessive leakage of gas.
The operator is not busy while the internal pressure is increasing. consequently, carefully observe
the generator and hydrogen gas control device in the meantime and correct the condition before
the internal pressure reaches the specified value if excessive leakage is identified.
If very large leakage occurs, the area around the leaking point is filled with helium gas and it
becomes difficult to pin point the source of leakage.
If necessary measurements are taken before the internal pressure reaches the specified value,
it will shorten the time required for the leak test.
32
13.2 Detection of leakage
When the internal pressure reaches the specified value, stop the supply of compressed air and
immediately start detection. The points to be inspected are as follow.
(1) Bearing bracket, fitting to casing, bolt, knock part, end bracket fitting.
(2) Hydrogen cooler mount.
(3) Seal ring case mount, bolt knocks fitting.
(4) Bushing internal mount.
(5) Manhole.
(6) Rotor slip ring.
(7) Search coil lead and relay lead.
(8) Gas dryer, oil level rise alarm transmitter, water leakage alarm transmitter, float pressure
gauges.
(9) Transmitter in hydrogen control panel, dryer, pressure gauge, valves.
(10) Piping flanges, welded parts, valves flanges, gland.
Inspect these points and the condition is satisfactory unless the pointer of the meter reach
maximum position. Very often, leak test around seal ring case of continuous scavenging type
cannot be performed completely due to helium that dissolves into-oil.
In such a case take seal oil with an appropriate container and check if leak detector senses
leakage gas with the oil.
It is wise to perform leak test around the seal at the beginning in order to avoid such difficulties.
With Helium test in general it is easy to locate the area around the leaking point, but it is not
possible to correctly locate the leak point.
In such a case, use soap water to correctly locate the leaking point.
Check during leak test for unevenly clamped packing and loose bolts, and even if no leakage
occurs, such points that appear to be defective should be corrected.
If leaking points are identified, take corrective measures one after another. Those points which
cannot be remedied unless compressed air is discharged, shall be marked and remedied
afterward.
Leak test shall be performed again after all the leaking points are remedied and the generator
is refilled with compressed air. If there is any point that cannot be readily remedied (collector
ring, bushing, cooler, etc.), promptly notify MHPS T/A so that necessary measures can be
taken early.
33
13.3 Leakage test
Check various points of the generator with leak detector, and when all the leakage is remedied
perform leakage test and take measurement of leak rate. The result of leakage test is computed by
the pressure change and casing temperature change, 24 hours later. Calculate by the following
equation, and if leak rate exceeds 1.0 m³/day, there would be leakage points. Recheck leakage
with leak detector, make necessary correction and reduce the leak quantity to1.0 m³/day or less.
L=( ⑧ )
{ ( ① )+ ( ② )
-
( ④ )+ ( ⑤ ) } × 273 + 20 ×
24
273 + ( ③ ) 273 + ( ⑥ ) 0.1013 ( ⑦ )
Note: When gas pressure and barometric pressure are measured in kg/cm2, convert the values into
34
22
20
18
Calculation formula:
QH : Soluble quantity
35
Example of recording sheet
“ 1
“ 2
“ 3
“ 4
21
“ 22
“ 23
36
14. ASSEMBLY OF STUB SHAFT (3rd BEARING)
(1) Bearing and bearing ring contact check
(2) Bearing insulation resistance check at bearing ring (Measured by 500V megger)
(3) Measuring oil gap between journal (Measured by φ0.5mm plumb line)
37
15. INSTALLATION OF BRUSH GEAR
After the position of the generator is decided and the guide key on the collector ring is mounted,
arrange a foundation plate and set a collector ring device at the position as shown on the drawing.
15.1 Mounting
In mounting the collector ring device, wind a protective pressboard surrounding the collector ring
so as not to damage the collector ring.
As for axial direction take care that the collector ring position changes when the generator is at
shutdown and operation (due to elongation of the rotor).
When doing the centering as for right and left, upper and lower directions, then do the centering.
15.2 Adjustment
(1) Adjust gap between the collector ring surface and the brush holder to be 4.8 ±1.0 mm.
(2) During assembly measure insulation resistance at each step and precede the work, checking
the grounding.
Carefully tighten conductive portions. Forgetting to tighten and insufficient tightening will result in
heating and an accident.
38
16. GROUTING
After the completion of centering proceed to grout. Wet grouting surface 12 hours before grouting
and let it absorb moisture. When the surface is very dry it shall be watered every 3 to 4hours.
Fill material to every corner with a bamboo pole.
Mixing of non-shrink grout
39
Site Inspection and Test Plan for Generator
Record
Reference CONSTRUCTOR MHPS CUSTOMER
NO Inspection and Test Item sheet No. Remarks
document
Type Signature Date Type Signature Date Type Signature Date
Construction drawing
1 Stator & Rotor Coil insulation resistance test record H2-1114 Ⅱ RR/H P
and Erection Procedure
Construction drawing
2 Stator inspection H2-1121 Ⅱ RR/H P
and Erection Procedure
Construction drawing
3 Foundation bolt dimension record H2-1102 Ⅱ RR/H P
and Erection Procedure
Construction drawing
4 Leveling bolck dimension record H2-1106-1~3 Ⅱ RR/H P
and Erection Procedure
Construction drawing H2-1107-1
5 Leveling bolck elevation record H2-1107-2
Ⅱ RR/H P
and Erection Procedure
Construction drawing H2-1108-1
6 Sole plate dimension record H2-1108-2
Ⅱ RR/H P
and Erection Procedure
Construction drawing H2-1109-1
7 Sole plate elevation record H2-1109-2
Ⅱ RR/H P
and Erection Procedure
Construction drawing
8 Stator inspection H2-1122 Ⅱ RR/H P
and Erection Procedure
Construction drawing H2-1105-1
9 Sole Plate record H2-1105-2
Ⅱ RR/H P
and Erection Procedure
Construction drawing H2-1111-1~2
10 Stator setting H2-1112
Ⅱ RR/H P
and Erection Procedure
Construction drawing
11 Hydrogen Cooler inspection H2-0201 Ⅱ RR/H P
and Erection Procedure
Hydrogen Cooler leak check Construction drawing
12 (before assembly at site) H2-0202 Ⅱ RR/H P
and Erection Procedure
Inspection items for connection Construction drawing
13 of Terminal Leads H2-1141 Ⅱ RR/H P
and Erection Procedure
Construction drawing
14 Bearing Bracket inspection and installation H2-0301 Ⅱ RR/H P
and Erection Procedure
Installation shim record between sole plate and Construction drawing
15 leveling block H2-1353 Ⅱ RR/H P
and Erection Procedure
Construction drawing
16 Rotor inspection H2-1411-1~2 Ⅱ RR/H P
and Erection Procedure
Construction drawing
17 Record of Inner Oil Deflector and Erection Procedure
H2-0434 Ⅱ RR/H P
Construction drawing
18 Record of centering and Erection Procedure
H2-1503-1~2 Ⅱ RR/H P
40
Site Inspection and Test Plan for Generator
Record
Reference CONSTRUCTOR MHPS CUSTOMER
NO Inspection and Test Item sheet No. Remarks
document
Type Signature Date Type Signature Date Type Signature Date
Construction drawing
19 Record of Inner Oil Deflector H2-0434 Ⅱ RR/H P
and Erection Procedure
Construction drawing
20 Record of centering and Erection Procedure
H2-1503-1~2 Ⅱ RR/H P
Construction drawing
21 Assembly of Seal Casing and Erection Procedure
H2-0442~3 Ⅱ RR/H P
Construction drawing
23 Confirmation items for assembly around Bearings and Erection Procedure
H2-0701 Ⅱ RR/H P
Construction drawing
25 Record of Outer Oil Deflector and Erection Procedure
H2-0710 Ⅱ RR/H P
Construction drawing
27 Record of Brush Gear assembly H2-0751~2 Ⅱ RR/H P
and Erection Procedure
Record of measuring run out prior to T-G test Construction drawing
28 operation H2-0902-1~2 Ⅱ RR/H P
and Erection Procedure
Note:Inspection type
Ⅱ : Internal inspection (take records) RS : Record submission RR : Record review and retained P : QA documentation
W : Witness point H : Hold point
41
QC-sheet H2-1114
Mfg. No. Year
Customer Stator & Rotor Coil insulation resistance test record Working date
Name Checked by MHPS
MΩ MΩ MΩ MΩ MΩ
MΩ MΩ MΩ MΩ MΩ
MΩ MΩ MΩ MΩ MΩ
MΩ MΩ MΩ MΩ MΩ
MΩ MΩ MΩ MΩ MΩ
MΩ MΩ MΩ MΩ MΩ
MΩ MΩ MΩ MΩ MΩ
42
QC-sheet H2-1121
Mfg. No. Year
Customer Stator inspection Working date
Name Checked by MHPS
MΩ
4 Check insulation resistance of stator coil.
at 1000V Megger
43
QC-sheet H2-1102
Mfg. No. Year
Customer Foundation bolt dimension record Working date
Name Checked by MHPS
1400
440 315 315
490 490 490 490 3870 490 490 490 490 (Sole Plate for Brush Gear)
0 ~ -1mm notes :
Negative (-) mean Generator's sole plates are lower
than Turbine's ones.
44
QC-sheet H2-1106-1
Mfg. No. Year
Customer Leveling block(Right) dimension record Working date
Capacity Checked by MHPS
150
h
g
H
G
⑬ ⑮ ⑰
⑭ ⑳ ㉒ ㉔
Left ⑯ ⑱ ⑲ ㉑ ㉓
(Sole Plate for Brush Gear)
Unit:mm Tolerance:Design±1mm
A B C D E F G H a b c d e f g h
Design 1632 2155 2645 3135 3715 4298 2090 2450 1632 2205 2695 3185 3765 4348 2090 2450
Actual
45
QC-sheet H2-1106-2
Mfg. No. Year
Customer Leveling block(Left) dimension record Working date
Capacity Checked by MHPS
150
h
g
H
G
⑬ ⑮ ⑰
⑭ ⑳ ㉒ ㉔
Left ⑯ ⑱ ⑲ ㉑ ㉓
(Sole Plate for Brush Gear)
Unit:mm Tolerance:Design±1mm
A B C D E F G H a b c d e f g h
Design 1632 2155 2645 3135 3715 4298 2090 2450 1632 2205 2695 3185 3765 4348 2090 2450
Actual
46
QC-sheet H2-1106-3
Mfg. No. Year
Leveling block dimension record
Customer Working date
Capacity (Collector base) Checked by MHPS
E
D
C
℄Generator
F
G H
B
g h
f
c
d
e
Unit:mm Tolerance:Design±1mm
A B C D E F G H a c d e f g h
Design 5003 5208 5433 5768 6358 850 600 675 5003 5433 5768 6358 850 600 675
Actual
47
QC-sheet H2-1107-1
Mfg. No. Year
Customer Leveling block elevation record Working date
Name Checked by MHPS
① ② ③ ④ ⑤ ⑥ ⑦ ⑧ ⑨ ⑩ ⑪ ⑫
Target 3971mm
① ② ③ ④ ⑤ ⑥ ⑦ ⑧ ⑨ ⑩ ⑪ ⑫
⑬ ⑭ ⑮ ⑯ ⑰ ⑱ ⑲ ⑳ ㉑ ㉒ ㉓ ㉔
MHPS-J Factory site
Approved by Checked by Approved by Checked by Measured by
48
QC-sheet H2-1107-2
Mfg. No. Year
Leveling block elevation record
Customer Working date
Capacity (Collector base) Checked by MHPS
℄Generator ⑤ ⑥
⑧ ⑨
③
⑦
49
QC-sheet H2-1108-1
Mfg. No. Year
Customer Sole plate dimension record Working date
Name Checked by MHPS
B C
① ② ③ ④
H
F
E
h
g
e
⑤ ⑥ ⑦ ⑧
b c
a d
Dimension
A B C D E F G H Unit: mm
Design 3479 2056 2081 3529 2270 2270 2270 2270
Actual
a b c d e f g h MHPS-J Factory site
Design 3479 2056 2081 3529 2270 2270 2270 2270 Approved by Checked by Approved by Checked by Measured by
Actual
50
QC-sheet H2-1108-2
Mfg. No. Year
Customer Sole plate dimension record(Collector base) Working date
Name Checked by MHPS
A B
H
G
E
C D
Dimension
A B C D E F G H Unit: 1/100mm
Design 5193 755 5193 755 850 850 725 725
Actual
MHPS-J Factory site
Approved by Checked by Approved by Checked by Measured by
51
QC-sheet H2-1109-1
Mfg. No. Year
Customer Sole plate elevation record Working date
Name Checked by MHPS
① ② ③ ④
⑤ ⑥ ⑦ ⑧
Actual
52
QC-sheet H2-1109-2
Mfg. No. Year
Customer Sole plate elevation record(Collector base) Working date
Name Checked by MHPS
Actual
53
QC-sheet H2-1105-1
Mfg. No. Year
Customer Sole plate level record Working date
Name Checked by MHPS
Unit: 1/100mm
54
QC-sheet H2-1105-2
Mfg. No. Year
Customer Sole plate level record Working date
Capacity Checked by MHPS
Unit: 1/100mm
55
QC-sheet H2-1111-1
Mfg. No. Year
Customer Stator setting(1/2) Working date
Name Checked by MHPS
6 Contact check stator foot and sole plate, if it less than 75% adjustment
7 Apply "MOLYKOTE" for the face of stator foot and sole plates It applies oiliness "MOLYKOTE "
Set the shim liners that drawing thickness, on the sole plates. Drawing thickness :8mm
8
(Certainly set maximum thickness of shim liners)
56
QC-sheet H2-1111-2
Mfg. No. Year
Customer Stator setting(2/2) Working date
Name Checked by MHPS
⑤ ⑥ ⑦ ⑧
No. Thickness x QTY's No. Thickness x QTY's No. Thickness x QTY's No. Thickness x QTY's
MHPS-J Factory
① ② ③ ④ Approved by Checked by
site
⑤ ⑥ ⑦ ⑧ Approved by Checked by Measured by
57
QC-sheet H2-1112
Mfg. No. Year
Customer Stator feet and Sole Plate contact check Working date
Name Checked by MHPS
58
QC-sheet H2-0201
Mfg. No. Year
Customer Hydrogen Cooler inspection Working date
Name Checked by MHPS
59
QC-sheet H2-0202
Mfg. No. Year
Hydrogen Cooler leak check
Customer Working date
Name (before assembly at site) Checked by MHPS
2. Test result
Duration of time shall be more than 15 minutes
No. Item Cooler A Cooler B Cooler C Cooler D Remarks
Pressure actually
1
applied. bar bar bar bar
2 Duration of time
Min Min Min Min
Leakage
3 Found ・None Found ・None Found ・None Found ・None Circle either one
(1st time)
4 Leaked portion
Remedies taken
5
against leakage
6 Final result
60
QC-sheet H2-1141
Mfg. No. Year
Inspection items for connection
Customer Working date
Name of Terminal Leads Checked by MHPS
Result
No. Inspection Item Date Remarks
61
QC-sheet H2-0301
Mfg. No. Year
Customer Bearing Bracket inspection and installation Working date
Name Checked by MHPS
Result of inspection
No. Inspection Item Remarks
Turbine side Collector Ring side
62
QC-sheet H2-1353
Mfg. No. Year
Installation shim record between sole plate
Customer Working date
Name and leveling block Checked by MHPS
No. Thickness×QTY's Total No. Thickness×QTY's Total No. Thickness×QTY's Total No. Thickness×QTY's Total
No. Thickness×QTY's Total No. Thickness×QTY's Total No. Thickness×QTY's Total No. Thickness×QTY's Total
5 6 7 8
No. Thickness×QTY's Total No. Thickness×QTY's Total No. Thickness×QTY's Total No. Thickness×QTY's Total
9 10 11 12
No. Thickness×QTY's Total No. Thickness×QTY's Total No. Thickness×QTY's Total No. Thickness×QTY's Total
13 14 15 16
No. Thickness×QTY's Total No. Thickness×QTY's Total No. Thickness×QTY's Total No. Thickness×QTY's Total
17 18 19 20
No. Thickness×QTY's Total No. Thickness×QTY's Total No. Thickness×QTY's Total No. Thickness×QTY's Total
21 22 23 24
1 2 3 4 5 6 7 8 9 10 11 12
13 14 15 16 17 18 19 20 21 22 23 24
63
QC-sheet H2-1411-1
Mfg. No. Year
Customer Rotor inspection (1/2) Working date
Name Checked by MHPS
Inspection of rotor shall be carried out at least one week before insertion.
64
QC-sheet H2-1411-2
Mfg. No. Year
Customer Rotor inspection (2/2) Working date
Name Checked by MHPS
65
QC-sheet H2-0434
Mfg. No. Year
Customer Record of Inner Oil Deflector Working date
Name Checked by MHPS
Tolerance Tolerance
(Turbine side) (Collector Ring side)
0.50~0.84 0.50~0.84
0.09~0.15 0.09~0.15
Result
No. Inspection item Remarks
Turbine side Collector Ring side
1 Assure that there is no gap at joint.
Assure that mounting bolts are suitably tightened
2
and locked.
66
QC-sheet H2-1503-1
Mfg. No. Year
Customer Record of centering (1/2) Working date
Name Checked by MHPS
1. Measuring 1. Unit: mm
67
QC-sheet H2-1503-2
Mfg. No. Year
Customer Record of centering (2/2) Working date
Name Checked by MHPS
4. Result
Unit : mm
Generator ( ) Generator ( )
( ) ( )
Conditions :
68
QC-sheet H2-0442
Mfg. No. Year
Customer Assembly of Seal Casing Working date
Name Checked by MHPS
Unit : mm
1. Record of seal ring gap.
Temperature [ ℃ ] ℃ ℃ ℃ ℃
2
【K】:Correction value
Refer to H2-0443
K=Φ x R
【B】:Diameter of tool
- Diameter of rotor journal
Calculated gap at 20 ℃ This values shall be
3
【A】 + 【B】 + 【K】 within design
-5
R : 0.7 x 10 x ( measurement temperature - 20)
69
QC-sheet H2-0443
Mfg. No. Year
Temperature correction value when
Customer Working date
Name measuring Seal Rings Checked by MHPS
Φ : Diameter 429.14 mm
-0.02 Temperature : ℃
K:429.14x R mm
0 5 10 15 20 25 30 35 40
0
℃ -5
R : 0.7 x 10 x ( measurement temperature - 20)
0.02
0.04
0.06 TB side
CL.R side
0.08
MHPS-J Factory site
Approved by Checked by Approved by Checked by Measured by
70
QC-sheet H2-0601-1
Mfg. No. Year
Customer Confirmation items for leak test (1/2) Working date
Name Checked by MHPS
71
QC-sheet H2-0601-2
Mfg. No. Year
Customer Confirmation items for air leak test (2/2) Working date
Name Checked by MHPS
22 Others
72
QC-sheet H2-0602
Mfg. No. Year
Customer
Record of air leak test Working date
Name (calculation for soluble quantity of hydrogen gas) Checked by MHPS
0.12 Air
p q Vo
0.10
QH = 1/2 x 14.7 x x x H2
0.08
= 3
(m /day)
0.06
0.04
0.02
0.00
10 20 30 40 50 60 70 80 90 100
Oil temperature ( ℃ )
MHPS-J Factory site
Approved by Checked by Approved by Checked by Measured by
73
QC-sheet H2-0603-1
Mfg. No. Year
Customer Record of air leak test (1/2) Working date
Name Checked by MHPS
( 1 ) Generator gas pressure 【bar/10】, ( 2 ) Barometric pressure 【bar/10】, ( 3 ) Generator gas temperature, 【℃】
= (m3/day)
74
QC-sheet H2-0603-2
Mfg. No. Year
Customer Record of leak test (2/2) Working date
Name Checked by MHPS
1 14
2 15
3 16
4 17
5 18
6 19
7 20
8 21
9 22
10 23
(7) (4) (5) (6)
11 24
12
75
QC-sheet H2-0701
Mfg. No. Year
Customer Confirmation items for assembly around Bearings Working date
Name Checked by MHPS
76
QC-sheet H2-0707-2
Mfg. No. Year
Customer Record of Bearing assembly (2/2) Working date
Name Checked by MHPS
2. Insulation resistance for Bearing and Bearing Ring Bearing ring ⇔ Bearing
Bearing ⇔ Bearing bracket
bracket
Use a 500V Megger/20KΩ or more
Turbine side Ω Ω
Collector side Ω Ω
77
QC-sheet H2-0707-1
Mfg. No. Year
Customer Record of Bearing assembly (1/2) Working date
Name Checked by MHPS
Parallelism
・Parallelism=(B-A)-(D-C)
MHPS-J Factory site
-4 Inner diameter of the bearing Approved by Checked by Approved by Checked by Measured by
・Standard value = 10 x
2
78
QC-sheet H2-0710
Mfg. No. Year
Customer Record of Outer Oil Deflector Working date
Name Checked by MHPS
1. Record of oil deflector gap (Indicate viewed from Collector side.) Unit : mm
Tolerance Tolerance
(Turbine side) (Collector Ring side)
0.50~0.84 0.50~0.84
0.09 0.09
~0.15 ~0.15
Result
No. Inspection item Remarks
Turbine side Collector Ring side
1 Assure that there is no gap at joint.
Assure that mounting bolts are suitably tightened
2
and locked.
79
QC-sheet H2-0731-1
Mfg. No. Year
Customer Steady Bearing assembly (1/2) Working date
Name Checked by MHPS
1 It is checked that fit assembly mark which Generator shaft and Steady shaft. Punch mark 【U】 is incused
Tolerance
Shaft Journal : ≦ 3/100mm
2 Run out check of steady shaft with over hang condition to Generator shaft.
Coupling : ≦ 5/100mm
80
QC-sheet H2-0731-2
Mfg. No. Year
Customer Steady Bearing assembly (1/2) Working date
Name Checked by MHPS
pedestal cap
81
QC-sheet H2-0732-1
Mfg. No. Year
Customer Record of Steady Bearing (1/3) Working date
Name Checked by MHPS
1 2 3 4
1. Record of steady shaft run out
1 U 2 U 3 U 4 U
82
QC-sheet H2-0732-2
Mfg. No. Year
Customer Record of Steady Bearing (2/3) Working date
Name Checked by MHPS
× ×
The difference of same thickness gap gauge insertion
depth is within 5mm
A B
Generator end side |A-B|≦ 5 mm
Generator side |C-D|≦ 5 mm
Must be satisfied.
|A-C|≦ 5 mm
C D |B-D|≦ 5 mm
83
QC-sheet H2-0732-3
Mfg. No. Year
Customer Record of Steady Bearing (3/3) Working date
Name Checked by MHPS
84
QC-sheet H2-0751
Mfg. No. Year
Customer Confirmation items for Brush Gear assembly Working date
Name Checked by MHPS
2 Check the gap between collector ring and brush holder to be 4.8 ±1 mm
85
QC-sheet H2-0752-1
Mfg. No. Year
Customer Record of Brush Gear assembly(1/2) Working date
Name Checked by MHPS
① ② ③
ASM ASM ASM
2.65~4.15 1.25~2.65
1.25~2.65
MHPS-J Factory
3. Relative dimension between collector ring and carbon axial direction : Approved by Checked by
Right side
Design value 23.16 20.16 26.56 16.76 site
Approved by Checked by Measured by
Left side
86
QC-sheet H2-0752-2
Mfg. No. Year
Customer Record of Brush Gear assembly (2/2) Working date
Name Checked by MHPS
3.80 3.80
~5.80 ~5.80
Tolerance
1.26~1.96
1.26~ 0.36~
1.96 0.50 MHPS-J Factory site
Approved by Checked by Approved by Checked by Measured by
0.36~0.50
87
QC-sheet H2-0902-1
Mfg. No. Year
Record of measuring run out prior to
Customer Working date
Name T-G test operation (1/2) Checked by MHPS
Unit: mm
88
QC-sheet H2-0902-2
Mfg. No. Year
Record of measuring run out prior to
Customer Working date
Name T-G test operation (2/2) Checked by MHPS
D E F
Prior to steaming
(On turning)
TB A B C
89
GAP & ALIGNMENT CONTROL DIAGRAM for GENERATOR
A B I J K
L M N O
E G
F
D H
1. RADIAL CLEARANCE
TB SIDE TB SIDE OIL GAP TB SIDE BEARING TB SIDE CL.R SIDE CL.R SIDE BEARING
NAME OF PARTS OUTER OIL (Clearance between bearing TB SIDE AXIAL FAN GAP AIR GAP CL.R SIDE AXIAL FAN GAP
SPHERICAL GAP INNER OIL DEFLECTOR INNER OIL DEFLECTOR SPHERICAL GAP
DEFLECTOR GAP and Journal)
LOCATION A B C D E F G H I
NOMINAL VALUE 0.5 0.66~0.76 0~0.05 0.5 1.80 92.75 1.80 0.38 0~0.05
TOLERANCE
0.18~0.25 0 1.48~1.72 89.9~95.5 1.48~1.72 0.09~0.15 0
0 0.18~0.25
CL.R SIDE OIL GAP CL.R SIDE STEADY SHAFT OIL GAP unit: mm
CL.R HOUSING AIR
NAME OF PARTS (Clearance between bearing OUTER OIL COLLECTOR FAN GAP BRUSH HOLDER GAP (Clearance between bearing
DEFLECTOR GAP
and Journal) DEFLECTOR GAP and Journal)
LOCATION J K L M N O
NOMINAL VALUE 0.58~0.68 0.38 0.75 1.50 4.80 0.208~0.258
0.58~0.68 0.208~0.258
0.50~0.84 0.95~1.35 1.90~2.90 3.80~5.80
DISTRIBUTION OF
TOP- BOTTOM 0.50 0.09 0.95 0.30 1.90 0.50 3.80 3.80
RIGHT-LEFT ~0.84 ~0.15 ~1.35 ~0.40 ~2.90 ~1.20 ~5.80 ~5.80
TOLERANCE
0 0.09~0.15 0.30~0.40 0.50~1.20 0
90
Generator each parts tightening Torque list
Shows below standard torque for generator assembly work
NOTES;
The bolts used for assembling the generator are almost made of special steel.
So, almost tightening torque are applied Standard 1.5 times torque.
91