0% found this document useful (0 votes)
7 views

METHOD STATEMENT FOR EXCAVATION WORK

This method statement outlines the procedures and safety protocols for excavation work at the Mixed Development Project in Kottawa, focusing on pile foundations. It details site access, machinery, responsibilities, and environmental considerations, as well as health and safety measures. The document emphasizes quality assurance and compliance with technical specifications throughout the excavation process.

Uploaded by

en91418
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
7 views

METHOD STATEMENT FOR EXCAVATION WORK

This method statement outlines the procedures and safety protocols for excavation work at the Mixed Development Project in Kottawa, focusing on pile foundations. It details site access, machinery, responsibilities, and environmental considerations, as well as health and safety measures. The document emphasizes quality assurance and compliance with technical specifications throughout the excavation process.

Uploaded by

en91418
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 4

METHOD STATEMENT FOR EXCAVATION WORK

Project: Mixed Development Project – Kottawa


Prepared by: [Your Name]
Date: [Insert Date]

1. OBJECTIVE

The objective of this method statement is to outline the procedures, equipment, safety protocols,
and quality assurance measures associated with the excavation work for the Mixed Development
Project in Kottawa. This includes excavation for pile caps, foundations, and related substructure
elements.

2. INTRODUCTION

The project site is located in a densely developed urban area in Kottawa. Excavation is necessary
to prepare for the installation of pile caps and ground beams, forming the base of a pile
foundation system. Due to the urban setting, precautions will be taken to manage site access,
environmental impacts, and worker safety.

3. PROPOSED FOUNDATION TYPE

The project utilizes a pile foundation system to address the anticipated low bearing capacity of
the shallow soil layers and to accommodate the structural loads associated with the mixed-use
development.

4. SITE TERRAIN AND ACCESS

Although specific site terrain data is currently unavailable, the area is urbanized and likely to be
relatively level. The site access plan includes:

 Establishment of a temporary access road for machinery and material delivery.


 Coordination with local authorities to avoid disruptions.
 Ensuring adequate space for excavation equipment to maneuver safely.

[Insert Sketch: Site Layout with Access Road and Excavation Zones]
5. MATERIALS, MACHINERY & EQUIPMENT

Machinery and Equipment:

 Long-arm Excavator
 Dump Trucks
 Mini Backhoe Loader
 Submersible Pumps (standby)
 Vibro Compactor (if required)

Materials:

 Timber or Metal Shoring


 Safety Signage and Barriers
 Geotextile (if required)

[Insert Sketch: Typical Equipment Layout on Site]

6. RESPONSIBILITIES

 Project Engineer: Oversee compliance with technical specifications.


 Site Supervisor: Manage day-to-day excavation operations.
 HSE Officer: Monitor safety and environmental compliance.
 Operators and Laborers: Execute the excavation under supervision.

7. EXCAVATION PROCEDURE

 Perform setting out using survey equipment and benchmarks.


 Conduct a Pre-Construction Survey to record existing conditions.
 Begin excavation using mechanical means based on approved drawings.
 Excavate to the specified depths for pile caps and other substructure components.
 Stockpile excavated soil for reuse where appropriate or arrange for proper disposal.
 Stabilize excavation faces with appropriate sloping or shoring techniques where depth
exceeds 1.5 meters.

[Insert Sketch: Typical Excavation Section with Depths and Safety Slope]

8. DEWATERING PROCEDURE (IF APPLICABLE)

 Identify potential groundwater presence during excavation.


 Install sump pits at strategic locations within the excavation area.
 Direct water via shallow trenches to the pits.
 Use submersible pumps to discharge water to an approved location via a sedimentation
basin.

[Insert Sketch: Dewatering Layout with Trenches, Sump Pits, and Pumps]

9. SHORING AND SAFETY MEASURES

 Provide timber or metal shoring for excavation faces prone to collapse.


 Erect safety barriers and warning signs around open excavations.
 Ensure safe entry/exit paths and maintain stability of adjacent structures.

[Insert Sketch: Shoring System for Deep Excavation]

10. ENVIRONMENTAL CONSIDERATIONS

 Control dust with periodic water spraying.


 Restrict noise-generating activities to daytime hours.
 Manage runoff and prevent contamination of nearby water bodies.
 Reuse excavated soil for backfilling where feasible; otherwise, dispose responsibly.

11. HEALTH, SAFETY & ENVIRONMENTAL (HSE) PLAN

 Mandatory PPE: Helmets, gloves, safety boots, reflective vests.


 Only trained personnel permitted to operate machinery.
 First aid kits and fire extinguishers available on-site.
 Night work to include adequate lighting.
 Emergency evacuation procedures to be displayed on-site.

[Insert Sketch: Site Safety Signage and Emergency Exit Plan]

12. QUALITY ASSURANCE PLAN

 Daily inspection of excavation depth and alignment.


 Verification and approval of formation level before placing blinding.
 Maintain photographic and written documentation of progress.
 Record and report deviations or obstructions encountered during excavation.
13. REFERENCES

 Structural and Architectural Drawings


 Project Technical Specifications
 SLS Standards and Guidelines
 Company HSE Manual

Prepared By:
[Your Name]
Signature:
Date:

Approved By:
[Project Engineer / Supervisor]
Signature:
Date:

You might also like