The document outlines the ongoing rehabilitation project of the Molo Substation in Iloilo City, detailing various activities, equipment, materials, manpower, and their current statuses. Several tasks are marked as 'not yet started,' while others are ongoing, with specific remarks about material shortages and dependencies. The project includes extensive electrical installations, grounding work, and testing procedures across different voltage levels.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
4 views

MOLO_Remaining Works (Sept 25,2024)

The document outlines the ongoing rehabilitation project of the Molo Substation in Iloilo City, detailing various activities, equipment, materials, manpower, and their current statuses. Several tasks are marked as 'not yet started,' while others are ongoing, with specific remarks about material shortages and dependencies. The project includes extensive electrical installations, grounding work, and testing procedures across different voltage levels.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

Project: Rehabilitation of Molo Substation

Location: Molo, Iloilo City

Item No. Activity Equipment/Materials Manpower Entity Status Remarks/ Concerns


69kV
1 Alignment of DS & ES Hand tools 2 5S On-going With lacking materials for linkage of ES (OSM)
2 Welding of Tee Connectors Hand tools, welding machine, basket truck 3 5S On-going
3 Measurement and installation of OHGW (69kV gantry to 13.8kV gantry to outside utility pole) Hand tools 3 5S Not yet started Delivered OHGW last 9/24/24, Lacking strain clamp
4 Measurement and installation of 795MCM ACSR for 2-69kV lines Hand tools 3 5S Not yet started
5 Stringing of 2-69kV lines Hand tools, basket truck 3 5S Not yet started
6 Termination of control cables in PT marshalling box Hand tools 2 5S/EEIPC Not yet started PT box is already mounted, lacking terminal blocks
7 Tapping of 795MCM from 510DS4 to SA to PXF BCT (H1,H2,H3) Hand tools 2 5S On-going
8 Installation of GCB SF6 transmitter Hand tools 2 EEIPC/JEDD On-going Ongoing procurement of 5 pin female plug
9 Installation of bare copper wire on 6-columns from lightning rod down to grounding grid Hand tools 3 5S Not yet started, done with measurement of cable length
10 Installation of grounding wire on 512DS3 down to grounding grid Hand tools 2 5S Not yet started
11 Installation of grounding wire on 512DS1 down to grounding grid Hand tools 2 5S Not yet started
12 Installation of grounding wire on 511DS3 down to grounding grid Hand tools 2 5S Not yet started
13 Installation of grounding wire on 511DS1 down to grounding grid Hand tools 2 5S Not yet started
14 Installation of grounding wire on 510DS1 down to grounding grid Hand tools 2 5S Not yet started
15 Installation of grounding wire on 510DS4 down to grounding grid Hand tools 2 5S Not yet started
16 Installation of grounding wire on 512ES3 down to grounding grid Hand tools 2 5S Not yet started
17 Installation of grounding wire on 511ES3 down to grounding grid Hand tools 2 5S Not yet started
18 Installation of grounding wire on 9-surge arresters down to 9-surge counters Hand tools 2 5S Not yet started
19 Installation of grounding wire on 9-surge counters down to grounding grid Hand tools 2 5S Not yet started
20 Installation of grounding wire on DS and ES linkage and control box Hand tools 2 5S Not yet started
21 Installation of grounding wire on PT marshalling box Hand tools 2 5S/EEIPC Not yet started
22 Installation of grounding wire on 8-gantry column Hand tools 2 5S Not yet started, with holes already
23 Formworks, concrete pouring and finishing of 8-gantry pedestal Hand tools, concrete mixer 3 5S Not yet started, done with grout application
24 Installation of SEIL labels and circuit names Hand tools 2 5S Not yet started Labels are for layout & printing
25 Cleaning of gantry and final torque/ tightening Hand tools 5 5S On-going
26 Grounding resistance test Test equipment 3 EEIPC/5S Not yet started
27 PCIT Test equipment 3 EEIPC/JEDD Not yet started Dependent on the completion of PT cable works
28 Functional test - 3 EEIPC/JEDD Not yet started
29 Commissioning - 3 EEIPC/JEDD
13.8kV
1 Installation of 2-795MCM (insulated) from PXF BCT (X1,X2,X3) to insulator to 210DS4 Hand tools 2 5S Not yet started
2 Installation of 2-795MCM (insulated) from 210DS4 to 210CB Hand tools 2 5S On-going
3 Installation of 2-795MCM (insulated) from 210CB to 210DS1 Hand tools 2 5S On-going
4 Installation of 2-795MCM (insulated) from 210DS1 to CT-P1 Hand tools 2 5S On-going
5 Installation of 2-795MCM (insulated) from CT-P2 to middle bus Hand tools 2 5S Not yet started
6 Installation of 2-336MCM (insulated) from top bus to LBS3 Hand tools 2 5S Not yet started
7 Installation of 2-336MCM (insulated) from top bus to LBS2 Hand tools 2 5S Not yet started
8 Installation of 2-336MCM (insulated) from top bus to SA to Feeder 1 Hand tools 2 5S Not yet started
9 Installation of 2-336MCM (insulated) from top bus to post insulators to CT-P2 Hand tools 2 5S Not yet started
10 Installation of 2-336MCM (insulated) from CT-P1 to 211DS5 Hand tools 2 5S On-going
11 Installation of 2-336MCM (insulated) from 211DS5 to 211CB Hand tools 2 5S On-going
12 Installation of 2-336MCM (insulated) from 211CB to 211DS1 Hand tools 2 5S On-going
13 Installation of 2-336MCM (insulated) from 211DS1 to middle bus Hand tools 2 5S Not yet started
14 Installation of 2-336MCM (insulated) from top bus to LBS1 Hand tools 2 5S Not yet started
15 Installation of 2-336MCM (insulated) from top bus to SA to Feeder 5 Hand tools 2 5S Not yet started
16 Installation of 2-336MCM (insulated) from top bus to post insulators to CT-P2 Hand tools 2 5S On-going
17 Installation of 2-336MCM (insulated) from CT-P1 to 215DS5 Hand tools 2 5S On-going
18 Installation of 2-336MCM (insulated) from 215DS5 to 215CB Hand tools 2 5S On-going
19 Installation of 2-336MCM (insulated) from 215CB to 215DS1 Hand tools 2 5S On-going
20 Installation of 2-336MCM (insulated) from 215DS1 to middle bus Hand tools 2 5S Not yet started
21 Installation of 2-336MCM (insulated) from middle bus to 212DS1 Hand tools 2 5S Not yet started
22 Installation of 2-336MCM (insulated) from 212DS1 to 212CB Hand tools 2 5S On-going
23 Installation of 2-336MCM (insulated) from 212CB to 212DS5 Hand tools 2 5S On-going
24 Installation of 2-336MCM (insulated) from 212DS5 to CT-P1 Hand tools 2 5S On-going
25 Installation of 2-336MCM (insulated) from CT-P2 to insulator to Feeder 2 Hand tools 2 5S Not yet started
26 Installation of 2-336MCM (insulated) from CT-P2 to insulator to LBS 3 Hand tools 2 5S Not yet started
27 Installation of 2-336MCM (insulated) from SA to Feeder 2 Hand tools 2 5S Not yet started
28 Installation of 2-336MCM (insulated) from middle bus to 213DS1 Hand tools 2 5S Not yet started
29 Installation of 2-336MCM (insulated) from 213DS1 to 213CB Hand tools 2 5S On-going
30 Installation of 2-336MCM (insulated) from 213CB to 213DS5 Hand tools 2 5S On-going
31 Installation of 2-336MCM (insulated) from 213DS5 to CT-P1 Hand tools 2 5S On-going
32 Installation of 2-336MCM (insulated) from CT-P2 to insulator to Feeder 3 Hand tools 2 5S Not yet started
33 Installation of 2-336MCM (insulated) from CT-P2 to insulator to LBS 2 Hand tools 2 5S Not yet started
34 Installation of 2-336MCM (insulated) from SA to Feeder 3 Hand tools 2 5S Not yet started
35 Installation of 2-336MCM (insulated) from middle bus to 214DS1 Hand tools 2 5S Not yet started
36 Installation of 2-336MCM (insulated) from 214DS1 to 214CB Hand tools 2 5S On-going
37 Installation of 2-336MCM (insulated) from 214CB to 214DS5 Hand tools 2 5S On-going
38 Installation of 2-336MCM (insulated) from 214DS5 to CT-P1 Hand tools 2 5S On-going
39 Installation of 2-336MCM (insulated) from CT-P2 to insulator to Feeder 3 Hand tools 2 5S Not yet started
40 Installation of 2-336MCM (insulated) from CT-P2 to insulator to LBS 2 Hand tools 2 5S Not yet started
41 Installation of 2-336MCM (insulated) from SA to Feeder 3 Hand tools 2 5S Not yet started
42 Installation of heat shrinkable tube on aluminum bus (18 horizontal & 9 vertical) Hand tools 2 5S On-going
43 Welding of vertical aluminum bus (9 vertical, up and down welding joint) Hand tools, welding machine, basket truck 2 5S Not yet started
44 Installation of fuse cut-out w/ LA Hand tools 2 5S Not yet started
45 Cable termination for SST Hand tools 2 5S/EEIPC Not yet started
46 Mounting of SST breaker Hand tools 2 5S/EEIPC Not yet started
47 Installation of 3-CT donut-type Hand tools 2 5S/EEIPC Not yet started
48 Termination of CT and PT cables Hand tools 2 5S/EEIPC/JEDD Not yet started PT/CT box is already mounted, lacking terminal blocks
49 Cable termination for LBS 1,2,3 Hand tools 2 5S/EEIPC/JEDD Not yet started
50 Measurement and installation of 336MCM for feeder 1,2,3,4,5 Hand tools 2 5S Not yet started
51 Stringing of 5 feeder lines Hand tools, basket truck 2 5S Not yet started
52 Installation of grounding wire on 210DS4 down to grounding grid Hand tools 2 5S Not yet started
53 Installation of grounding wire on 210DS1 down to grounding grid Hand tools 2 5S Not yet started
54 Installation of grounding wire on 211DS1 down to grounding grid Hand tools 2 5S Not yet started
55 Installation of grounding wire on 211DS5 down to grounding grid Hand tools 2 5S Not yet started
56 Installation of grounding wire on 212DS1 down to grounding grid Hand tools 2 5S Not yet started
57 Installation of grounding wire on 212DS5 down to grounding grid Hand tools 2 5S Not yet started
58 Installation of grounding wire on 213DS1 down to grounding grid Hand tools 2 5S Not yet started
59 Installation of grounding wire on 213DS5 down to grounding grid Hand tools 2 5S Not yet started
60 Installation of grounding wire on 214DS1 down to grounding grid Hand tools 2 5S Not yet started
61 Installation of grounding wire on 214DS5 down to grounding grid Hand tools 2 5S Not yet started
62 Installation of grounding wire on 215DS1 down to grounding grid Hand tools 2 5S Not yet started
63 Installation of grounding wire on 215DS5 down to grounding grid Hand tools 2 5S Not yet started
64 Installation of grounding wire on 18-CT's down to grounding grid Hand tools 2 5S Not yet started
65 Installation of grounding wire on 3-LBS down to grounding grid Hand tools 2 5S Not yet started
66 Installation of grounding wire on CT & PT marshalling box down to grounding grid Hand tools 2 5S Not yet started
67 Installation of grounding wire on 8-gantry column Hand tools 2 5S Not yet started
68 Formworks, concrete pouring and finishing of 8-gantry pedestal Hand tools, concrete mixer 2 5S Not yet started
69 Installation of SEIL labels and circuit names Hand tools 2 5S Not yet started Labels are for layout & printing
70 Cleaning of gantry and final torque/ tightening Hand tools 2 5S On-going
71 Grounding resistance test Test equipment 3 EEIPC/5S Not yet started
72 Contact Resistance of LBS Test equipment 3 EEIPC/5S Not yet started
73 IR Test of Bus Test equipment 3 EEIPC/5S Not yet started
74 DC Hipot of Bus Test equipment 3 EEIPC/5S Not yet started
75 PCIT Test equipment 3 EEIPC/JEDD Not yet started Dependent on the completion of CT/PT cable works
76 Functional test - 3 EEIPC/JEDD Not yet started
77 Commissioning - 3 EEIPC/JEDD

General:
1 Gravel Filling Hand tools 4 5S Not yet started
2 Installation of seclusion fence Hand tools 4 5S Not yet started
3 Punchlist works in control bldg Hand tools 3 5S Not yet started