Pavan Report Inernship
Pavan Report Inernship
BATCHELOR OF ENGINEERING IN
CIVIL ENGINEERING
Submitted by
PAVANKUMAR
1BI21CV440
Under the guidance of
CERTIFICATE
I consider it is my privilege to express my heartier gratitude to all, who have extended their
valuable support and have been immensely helpful during the course.
I sincerely thank my technical seminar guide Mr. KRISHNE GOWDA P.H, Assistant
Professor, Department of Civil Engineering, Bangalore Institute of Technology, Bengaluru,
for providing encouragement and advice through the work.
I thank sincerely all the faculty members for providing encouragement and advice
throughout the work. I would like to thank one and all, who supported directly or indirectly
to complete this technical seminar work.
PAVANKUMAR
(1BI21CV440)
DECLARATION
CONTENT
SL.NO. & PARTICULARS PAGE
CONTENTS NO.
1. INTRODUCTION 3
2. SAFETY 4
PERSONAL PROTECTIVE 4
EQUIPMENTS(PPE)
PREVENTATION ON 5
CONSTRUCTION SITES
3. SLABS 10
TYPES OF SLABS 10
CHAIRS 10
COVERS 11
RAMP 11
4. FOUNDATION 13
ISOLATED FOOTING 13
COMBINED FOOTING 14
ELEMENTS OF FOOTING 14
5. BEAMS 16
BEAM CATEGORIES 16
OBSERVATION ON SITES 17
BEAM REINFORCEMENTS 18
SIMPLY SUPPORTED 19
FIXED BEAMS 19
CONCRETING OF BEAMS AND 19
SLABS
CURING AND STRIPPING OF 20
FORMWORK
6. COLUMS 21
COLUMNS REINFORCEMENTS 22
FRAME WORK FOR COLUMNS 23
PLUMB CHECK 23
CONCRETING AND STRIPPING OF 24
FORMWORKS
BEAM-COLUMN JUNCTION 24
7. PROBLEMS ON 25
FIELD
HONEYCOMB FORMATION 25
OFFSET PROBLEM 26
SLUMP PROTECTION 26
SHRINKAGE CRAKS IN SLAB 27
8. PHOTOGRAPHY
1.0 INTRODUCTION
Area - 1acer (approx.)
Number of towers - 2
Total number of 1BHK Flats - 27
Total number of 2BHK Flats - 36
Total number of Flats - 63
Initial Survey – Ravi C
Survey number - 102/2
Architect –C. J. Designs
Structural consultant - Design ventures
Services - Leeds
Contractor –VG Construction PVT LTD.
Rmc plant - RDC concrete products PVT LTD.
Concrete grade used - M5 TO M45
Steel grade used - FE500
Reinforcement given - 8mm Ø to 25mm Ø
Towers/ A B
Specification
Number of 4 4
units(per
floor)
Appartment 2BHK 1BHK
Type
2.0 SAFETY
2.1 PERSONAL PROTECTIVE EQUIPMENT’S (PPE)
Helmet
Construction worker or not, if you are even walking through a site while the work
is in progress – you have to wear a hard hat. This is the most important and
fundamental requirement for any
Construction site. At construction sites, there is always a risk of objects falling
from heights, and causing serious injury to your head. The hard hat is a vital gear
that shields workers or visitors from falling object and/or direct contact with any
harmful material. These hats are also useful for a protection from rain, direct sun
rays, and electric shock.
Protective footwear's
Unfortunate but true! Many of the death hazards at construction sites take place
because of tripping, slipping, and falling accidents. These accidents usually occur
due to unsafe ladders or scaffolds. Unsafe footwear’s are also one of the major
reasons behind such events. Therefore, it is critical for construction workers to
wear shoes that have slip proof and puncture resistant soles.
Eye and Face Safety Equipment
The eyes and face are most sensitive parts of the body and hence they need utmost
precaution at construction sites. Majority of eye injuries take place due to foreign
particles, gasses or objects that get into the eyes while welding, cutting, grinding,
nailing, working with concrete etc. Working at sites with extreme winds, sparks,
smoke, or dangerous chemicals also requires high precautions and safety
equipment.
Hand and arm protection
Potential hazards to hands and arms include skin absorption of harmful
substances, chemical or thermal burns, electrical dangers, bruises, abrasions, cuts,
punctures, fractures or amputations. Protective equipment includes gloves, finger
guards and arm coverings.
Ear Protection
When an employee’s noise exposure cannot be reduced to safe levels, then
hearingprotection must be worn. There are several options for hearing protection
available that include ear plugs, ear muffs, and hearing bands, which are also
known as canal caps. Each should be carefully considered for the noise reduction
they will provide, as well as for comfort and fit. EHS assists departments with
hearing protection selection to ensure that these variables are properly addressed.
See the Noise and Hearing Conservation page for more information about our
Hearing Conservation Program.
Industrial Safety Belt and Safety Net
Fall from height is a primitive hazard when a worker working at height. The
provision of a suitable working platform, safe access and egress, as well as proper
fencing to a dangerous place are the primary safety measures that the local safety
regulations have asked for. The use of safety nets and safety belts are only the last
resort when it is impracticable to provide such platforms, access and egress and
safe place of work.
Rope
Plaited rope is made by braiding twisted strands, and is also called square braid
this type of rope (often specified as cable to make the difference between a
braided or twined construction) has the advantage of having no construction
stretch as is the case with constructions.
OSHA
The law requires that employers provide their employees with working
conditions that are free of known dangers. The Act created the Occupational
Safety and Health Administration (OSHA), which sets and enforces protective
workplace safety and health standards. Request OSHA to inspect their
workplace.
OSAH standards are implemented on our site.
3.0 SLAB
A concrete slab is a common structural element of modern buildings. Different
thickness of slabs observed on the site are 125mm.150mm, 175mm.
3.2 CHAIR
Chair is provided because,
1. They hold the reinforcement in position.
2. They maintain the distance between top reinforcement and bottom reinforcement.
3. They hold reinforcements such that concrete may surround the reinforcement
from all directions (from bottom also).
4. They keep the reinforcement in place in case of vibration and jerk due to machine
or when labourers walk on the tied reinforcements.
5. They maintain the tidiness of work and mess-up is hence avoided.
3.3 Cover
Slab is provided with 25mm cover.
If the ramp work has to be stopped for any purpose it must be done at the point
of contra flexure. For a ramp point of contra flexure is at L/3.
Curtailment in slabs
This reduction of reinforcement bars wherever possible technically is called
curtailment of bars. Curtailment is a way of reducing the area of tensile
reinforcement at points/areas (either on a beam/slab) where bending moment is
minimum or zero for the purpose of achieving an economic design.
Reinforcements in slab
Reinforcement spacing are marked by chalk piece, based on design given.
4.0 FOUNDATION
A foundation (or, more commonly, base) is the element of an architectural
structure which connects it to the ground, and transfers loads from the structure
to the ground. Foundations are generally considered either shallow or deep.
Foundation engineering is the application of soil mechanics and rock mechanics
(Geotechnical engineering) in the design of foundation elements of structures.
Grade of concrete used is M30.
Types of footing used on the field is
4.1 Isolated footing
It is circular, square or rectangular slab of uniform thickness. Sometimes, it is
stepped to spread the load over a larger area. When footing is provided to
support an individual column, it is called isolated footing.
Footing
Isolated footing is constructed by the required reinforcement given.
PEDESTAL
A concrete pedestal is a compression element provided to carry the loads from
supported elements like columns, statues etc. to footing below the ground. It is
generally provided below the metal columns. In general pedestal width is
greater than its height.
5.0 BEAMS
Beams are the flexural members which carry transverse loads.
5.1 Beam Categories
1. Under reinforced beam sections: Reinforced concrete beam sections in which
the failure strain in concrete is reached earlier than the yield strain of steel is
reached, are called over-reinforced sections.
2. Balanced reinforced sections: Reinforced concrete beam sections in which
the tension steel also reaches yield strain simultaneously as the concrete reaches
the failure strain in bending are called balanced sections.
3. Over reinforced beam sections: Reinforced concrete beam sections in which
the failure strain in concrete is reached earlier than the yield strain of steel is
reached, are called over-reinforced sections.
5.2 Observations on beams on site
1. All exposed corners of beams shall have straight edges and chamfered
according to the structural drawings.
Formwork or shuttering works holes are filled with GP2 chemical without
effecting the strength of the beam.
Form Work layout
The material used for form work is plywood which is of 12mm thick.
Form works are done according to the drawings given. They are checked by site
engineer.
Form work releasing oil is smeared on the form work and marks are made with
chalk piece for reinforcement as shown in the drawings.
According to the IS-456 tolerance on the c/s of beam and columns is +12mm
and - 6mm.
Form work is constructed so as to remain sufficiently rigid while placing and
compacting of the concrete and so as to avoid the loss of the slurry.
Whenever beam depth crosses 750mm then side face reinforcement is given to
avoid propagation of cracks and to avoid buckling of beams.
Side reinforcement in beam schedule for beams greater than 750mm,
Width of beam Side reinforcement
200 Y12-250
300 Y12-200
400 Y12-150
500 or greater than 500 Y12-200
Cubes of 150x150x150 mm are prepared for the testing for 7 days, 28 days’
strength.
Thickness of the slab seen this project are 125mm, 150mm, 175mm.
6.0 Columns
Columns are the vertical compression members which carries vertical loads and
transferred to the footing.
Concrete Floor
M45 from footing top
to 3rd floor
(BEAM-COLUMN JUNCTION)
DEPARTMENT OF CIVIL ENGINEERING, SVVIT Page 24
RESIDENTIAL BUILDING CONSTRUCTION
Solution:
Keep mixing concrete according to the retention time of the concrete.
Add cement and water maintaining same water to cement ratio.
PHOTOGRAPHY
MARKING
EXCAVATION
PCC
ERECTION OF COLUMN
PLINTH BEAM