Sukup-Bucket-Elevator-Operation-Manual
Sukup-Bucket-Elevator-Operation-Manual
Assembly
and
Owner’s Manual
Table of Contents
Introduction-------------------------------------------------------------------------------------------------------------- 3
Receiving and Inspection -------------------------------------------------------------------------------------------- 3
Equipment Information ----------------------------------------------------------------------------------------------- 3
Limited Warranty------------------------------------------------------------------------------------------------------- 4
Safety--------------------------------------------------------------------------------------------------------------------- 5
Safety Decal Placement----------------------------------------------------------------------------------------- 12
Electrical Wire Clearances ------------------------------------------------------------------------------------- 13
Bolt Identification and Torque Ratings ---------------------------------------------------------------------------- 14
Component Identification -------------------------------------------------------------------------------------------- 15
Dimensions-------------------------------------------------------------------------------------------------------------- 16
Pre-Installation Information ------------------------------------------------------------------------------------------ 21
Elevator Location ------------------------------------------------------------------------------------------------- 21
Electrical Requirements ----------------------------------------------------------------------------------------- 21
Foundation --------------------------------------------------------------------------------------------------------- 21
Boot Footing Loads ---------------------------------------------------------------------------------------------- 22
Guy Wires and Anchors ---------------------------------------------------------------------------------------------- 22
Guy Wire Loading ----------------------------------------------------------------------------------------------------- 23
General Installation Procedures------------------------------------------------------------------------------------ 24
Boot Installation -------------------------------------------------------------------------------------------------------- 24
Boot Inlet Location ---------------------------------------------------------------------------------------------------- 26
Shovel Pocket Hopper------------------------------------------------------------------------------------------------ 27
Leg Trunking Stacking Guidelines --------------------------------------------------------------------------------- 28
Trunking for 16” to 36” Pulley Elevator ---------------------------------------------------------------------- 29
Trunking for 42” & 48” Pulley Elevator ----------------------------------------------------------------------- 33
Trunking Assembly ---------------------------------------------------------------------------------------------------- 36
Cable Lengths ---------------------------------------------------------------------------------------------------------- 43
Attaching Head Section ---------------------------------------------------------------------------------------------- 44
Belt & Buckets Installation Overview ------------------------------------------------------------------------------ 46
Attaching Buckets ----------------------------------------------------------------------------------------------------- 47
Belt Installation --------------------------------------------------------------------------------------------------------- 48
Attaching Hood --------------------------------------------------------------------------------------------------------- 51
Drive Installation ------------------------------------------------------------------------------------------------------- 52
Adjusting V-Belt Tension--------------------------------------------------------------------------------------------- 57
Reducer Oil ------------------------------------------------------------------------------------------------------------- 58
Final Check ------------------------------------------------------------------------------------------------------------- 58
Initial Test Run --------------------------------------------------------------------------------------------------------- 58
Maintenance ------------------------------------------------------------------------------------------------------------ 59
Bearing Lubrication --------------------------------------------------------------------------------------------------- 61
Pressure Relief Vent Closure Replacement--------------------------------------------------------------------- 63
Troubleshooting -------------------------------------------------------------------------------------------------------- 64
Dodge Torque Arm II Speed Reducers -------------------------------------------------------------------------- 69
Contact Information --------------------------------------------------------------------------------------------------- 76
2
Introduction
Introduction
This bucket elevator was carefully designed to give years of dependable service and was manufactured
with the finest materials available. This manual includes information relating to safety, installation,
maintenance and troubleshooting, and should be thoroughly read prior to installation of bucket elevator.
Due to the scope of projects involving material handling equipment and the wide variety of situations, this
manual cannot cover all aspects. Qualified civil engineers and contractors should be relied upon for site
design, layout and construction. This manual is to be used as a guide only. The reliability, safety and
good service life of this equipment depends to a very large extent on level of care taken in installing and
preparing this equipment for its intended use.
Equipment Information
Record bucket elevator information in space provided below and keep it on file. This information will help
identify equipment should you need to contact your dealer with any questions.
3
Limited Warranty
Limited Warranty 4
Safety
Read manual before installing or using product. Failure to follow instructions and safety precautions in
manual can result in death or serious injury. Keep manual in a safe location for future reference.
GRAIN BIN SAFETY
On safety decals, this symbol and the Owners/operators are responsible for developing
signal words Danger, Warning, Caution site-specific confined space entry procedures.
and Notice draw your attention to OSHA’s confined space entry procedures (29CFR
important instructions regarding safety. 1910.146) can be found at www.osha.gov.
They indicate potential hazards and levels of intensity.
If you must enter bin for repair or maintenance:
RED - DANGER indicates an Use a safety harness, safety line and respirator
imminently hazardous
situation which, if not avoided, will result in death or Station another person outside of bin
serious injury. Avoid the center of the bin
ORANGE - WARNING Wear appropriate personal protective equipment
indicates a potentially Keep clear of all augers and moving parts
hazardous situation which, if not avoided, could result
in death or serious injury. DANGER: Never enter bin unless all power is
YELLOW - CAUTION locked out and another person is present.
indicates a potentially
hazardous situation which, if not avoided, may result Rotating augers
in minor or moderate injury. can kill or
dismember!
BLUE - NOTICE alerts you to
practices unrelated to personal
injury, such as messages related to property damage.
NEVER enter bin when augers are running!
IMPORTANT: To prevent serious injury or death to When bin is nearly empty, sweep auger will travel at an
you or your family, it is essential that safety decals increasingly fast speed. Keep away from sweep and
are clearly visible, in good condition, and applied to sump augers to avoid entanglement.
the appropriate equipment.
5
Safety
To avoid electric shock or electrocution, all WARNING: Metal is slippery when wet. To
equipment must be properly wired and grounded avoid falls, never carry items if climbing on
according to electrical codes. Have unit wired by bin. Maintain secure hand and foothold if
qualified electrician. climbing on bin. Failure to do so could result in death
or serious injury.
6
Safety
IMPORTANT – A bucket elevator is generally used to move grain for storage in grain bins. Be aware of
dangers inherent in grain bins. Do not enter a bin if grain has stopped flowing normally or has bridged, as
shown in Fig. 1. Grain can collapse without warning and trap, bury and cause suffocation.
Each worker must have his/her own lock and the only key to that lock.
Make sure elevator is not operating before turning off power.
Notify all affected employees that elevator will be locked out for service.
Authorized employee shall refer to the facility procedure referencing the power source for the
elevator.
Shut down bucket elevator in a normal manner.
All energy sources that could activate elevator must be de-activated.
Each person who will be working on bucket elevator must put a lock on all energy sources that
could provide any power to elevator.
Confirm that power has been deactivated by trying to re-start elevator.
Turn all controls for elevator back to “off” position.
NO ONE is to return power to bucket elevator until all work on it has been completed and all locks
have been removed.
Facility management needs to proactively train employees to ensure use of proper lockout procedures
while working on bucket elevator. Management also needs to inspect unit for any covers or guards not in
their proper place. It is everyone’s responsibility to report any missing grates, guards, equipment failures
or failures of others to lock out. Make certain that no cover is removed unless power is locked out.
7
Safety
Recognizing this hazard, Sukup Manufacturing Co. believes that we all need to work together to prevent
grain dust explosions in order to protect lives, jobs, property and profits. Preventive measures should be
taken to reduce the likelihood of an explosion. Following are some suggestions.
CONTROL DUST
8
Safety
WARNING: Do not repeatedly start and stop elevator to remove obstruction. Doing so
could overheat belt or head pulley, possibly causing an explosion resulting in death or
serious injury.
Myth: There are only two (2) explosions that occur, a primary and a secondary.
FACT: Up to thirteen (13) explosions have been documented during one (1) single incident.
Remember: Good housekeeping practices and correct safety procedures will help protect lives,
jobs, property and profits.
IMPORTANT: When changing head pulley assembly or motor, do not set on platform if total weight on
platform will exceed 500 lbs. Total weight on any platform cannot exceed 500 lbs. unless otherwise noted.
9
Safety
Order replacement safety decals or shields free of charge by contacting Sukup Manufacturing Co. by
mail at PO Box 677, Sheffield, Iowa 50475; by phone at 641-892-4222; or by e-mail at [email protected].
Please specify decal number. Use drawing on Page 12 to determine location of decal(s) if replacement is
necessary.
10
Safety
11
Safety
L02612 – On head
air vent (if used)
L0114
L0164 L0917
L0281
L0113
L01135
L0284
L02612
Belt Guard
Decals
L0284 – Moving
parts (outside)
Fig. 2 – Safety
decal placement
L02612
L0284
12
Safety
13
Bolt Identification and Torque Ratings
14
Component Identification
Component Identification
15
C
Dimensions
Dimensions
** See Table 3A on next page for boot inlet height based on inlet design – Standard, Flared or 45°.
CASING
PULLEY DIA. BPH Range A B C D E H J K N P Q R T
FxG
16” 1000-2000 53-7/16 45-5/16 18-13/16 26-1/2 21-1/2 11 x 8 14 30 60 11 10 23-3/4 15 21-3/16
24" 1500-5000 68-1/2 60 26-3/4 33-1/4 21-1/2 13 x 10 23 43 60 13 9 23-5/8 17-1/4 23-3/16
30" 4000-7500 85-3/8 75-1/4 33-1/2 41-3/4 32-5/8 18 x 12 28 52 60 17-5/8 12 28-5/8 22-1/4 30-5/16
36" 6000-10000 98-3/8 87-3/8 37 50-3/8 32-5/8 18 x 12 34 58 60 17-5/8 19 28-5/8 22-1/4 30-5/16
42" 8000-17000 110-3/4 101-1/8 41-1/8 60 32-5/8 22 x 14 40 68 72 22 18 32-3/4 26 38-5/16
48" 15,000-20,000 122-15/16 107-1/2 47-1/2 60 32-13/16 22 x 14 46 74 72 22 24 32-3/4 26 38-5/16
All dimensions are in inches.
16
C
Dimensions
Dimensions
1’
PULLEY TRUNKING F G H J K L M N
*For peanut SIZE WIDTH
elevators 16 11 12 7-3/8 6 10 13 22 25 22-1/2
24 13 11 8-3/8 8 12 15 24 27 30
18 11 11-7/8 13 16 19 32 35 38
22 * 11 11-7/8 17 20 23 36 39 38
30 32 * 11 11-7/8 27 30 33 46 49 38
40 * 11 11-7/8 35 38 41 54 57 38
44 * 11 11-7/8 39 42 45 58 61 38
36 18 11 11-7/8 13 16 19 32 35 41
22 11 14-7/8 15-1/2 22 25 40 43 49
42 32 11 14-7/8 25 32 35 50 53 49
40 11 14-7/8 33 40 43 58 61 49
22 11 14-7/8 15-1/2 22 25 40 43 52
48 32 11 14-7/8 25 32 35 50 53 52
40 11 14-7/8 33 40 43 58 61 52
17
C
Dimensions
See Fig. 8 and Tables 4 and 5 for dimensions of square flanges on inlets.
18
C
Dimensions
See Fig. 9 and Tables 6 and 7 for dimensions of rectangular flanges on inlets.
Pulley Hole
Casing A B C D E F G H I J K
(in) Qty.
16 11X8 21-3/4 9-3/4 1-11/16 13-1/8 12 25-1/8 24 4 4 3-15/16 4-11/32 18
24 13X10 23-3/4 11-3/4 1-11/16 15-1/8 14 27-1/8 26 4-21/32 4-21/32 4-11/32 4-11/32 18
30 18X12 31-3/4 15-3/4 1-11/16 19-1/8 18 35-1/8 34 4-1/2 4-1/2 5-21/32 5-21/32 20
36 18X12 31-3/4 15-3/4 1-11/16 19-1/8 18 35-1/8 34 4-1/2 4-1/2 5-21/32 5-21/32 20
42 22X14 39-3/4 21-3/4 1-11/16 25-1/8 24 43-1/8 42 4 4 5-1/4 5-1/4 28
48 22X14 39-3/4 21-3/4 1-11/16 25-1/8 24 43-1/8 42 4 4 5-1/4 5-1/4 28
Table 6 – Dimensions for flared inlet rectangular flange
Pulley Hole
Casing A B C D E F
(in) Qty.
18X12 15-25/32 11-7/16 1-11/16 14-13/16 13-11/16 19-5/32 16
22X14 19-3/4 11-13/32 1-11/16 14-25/32 13-21/32 23-1/8 14
30 32X14 29-3/4 11-13/32 1-11/16 14-25/32 13-21/32 33-1/8 18
40X14 37-3/4 11-13/32 1-11/16 14-25/32 13-21/32 41-1/8 22
44X14 41-3/4 11-13/32 1-11/16 14-25/32 13-21/32 45-1/8 22
36 18X12 15-25/32 11-7/16 1-11/16 14-13/16 13-11/16 19-5/32 16
42 22X14 21-3/4 17-5/8 1-11/16 21 19-7/8 25-1/8 22
48 22X14 21-3/4 17-5/8 1-11/16 21 19-7/8 25-1/8 22
Table 7A – Dimensions A-F for 45° inlet rectangular flange
Pulley Hole
Casing G H I J K
(in) Qty.
18X12 18-1/32 4-9/16 4-9/16 4-1/2 4-1/2 16
22X14 22 4-9/16 4-9/16 5-1/2 5-1/2 14
30 32X14 32 4-9/16 4-9/16 5-11/32 5-5/16 18
40X14 40 4-9/16 4-9/16 5 5 22
44X14 44 4-9/16 4-9/16 5-1/2 5-1/2 22
36 18X12 18-1/32 4-9/16 4-9/16 4-1/2 4-1/2 16
42 22X14 24 3-31/32 3-31/32 4 4 22
48 22X14 24 3-31/32 3-31/32 4 4 22
Table 7B – Dimensions G-K for 45° inlet rectangular flange
19
Dimensions
Discharge Dimensions
See Fig. 10 and Table 8 for bolt hole pattern of head discharge based on size of leg casing.
Fig. 10 & Table 8 – Head discharge bolt hole patterns, quantities & spacing
Sizes of square flanges that fit elevators are as follows: 11” for elevator with 16” head pulley (11” x 8” leg
casing); 13” for elevator with 24” head pulley (13” x 10” leg casing); 18” for elevator with 30” or 36” head
pulley (18” x 12” leg casing); 22” for elevator with 42” or 48” head pulley (22” x 14” leg casing).
20
C
Pre-Installation Information
Pre-Installation Information
Bucket Elevators are designed to be vertically self-supporting when erected, but must be supported
against wind loads. This elevator has not been designed to support other equipment such as cleaners,
distributors, spouting, etc. Separate structures must be provided to support any accessory equipment.
Sukup Manufacturing Co. is the provider of this elevator and has supplied certain optional accessories
only, and does not assume responsibility for the installation. Installation recommendations in this manual
are general guidelines only. It is the responsibility of user and/or installer to consult a civil or structural
engineer regarding installation, including but not limited to construction, supervision, foundation, guying
or bracing for specific site.
NOTE: The MOST IMPORTANT preparations are retaining a licensed engineer to plan installation and a
qualified millwright or contractor to erect elevator and accompanying equipment and structures.
Elevator Location
Elevator must be properly located to receive incoming material and discharge it at desired location. This
requires an exact location for boot section. Determine whether boot is to be fed from down or up side, or
from both sides of elevator. The down-leg side is recommended for light material that tends to dust, such
as flour or feeds. The up-leg side is recommended for heavier materials such as whole grains. Check
planned locations for boot, head, spouting, guy cables or support tower for clearance from other
structures. Driveways, overhead power lines and buildings can present special hazards and obstructions
and will need to be considered. See Fig. 3 for electrical wire clearance requirements.
Electrical Requirements
A qualified electrician should make all electrical connections. Check local codes before installation.
A lockable external line disconnect switch, in compliance with local codes, must be provided and located
as close as possible to elevator. When elevator is connected to other machinery, electrical interlock
priorities should be maintained so that if any other equipment fails, all preceding equipment would stop.
NOTE: Local authority with jurisdiction should be contacted prior to and during planning and installation.
NOTE: If a dual-drive system is used, additional equipment may be needed to balance load between
motors. It is customer’s responsibility to identify this situation and supply such equipment. Customers
can contact Sukup Manufacturing Co. for load-balancing options if a dual-drive system is required.
Foundation
DISCLAIMER: It shall be the sole responsibility of the customer to obtain actual foundation drawings
designed by and constructed to the specifications of a licensed professional structural engineer with
knowledge of the actual soil and load specific to the project and location. Consideration should also
include, but not be limited to, live loads, dead loads, wind loads, soil bearing loads, seismic zone, proper
moisture run-off on top of base, and types of aeration applied for the project.
Sukup Manufacturing Co. will not be responsible for any damage to a product, including, but not limited
to, any damage that results from poor soil conditions or inadequate concrete type, grade, bearing
strength, and construction method. Soil bearing tests must be performed by a competent, independent,
engineering firm. Concrete foundation construction must be done by a competent concrete contractor.
If boot is installed in a pit or other Estimated boot footing load (lbs.)
structure, adequate clearance must be 60 12,251
provided to service elevator. Enough 80 14,589 Table 9 – Footing loads
clearance should be provided to remove 100 17,366 for elevator supported
boot pulley and to fully remove clean-out by tower
120 19,846
slides, as well as perform all other forms of
140 22,409
maintenance. On outdoor installations, pit
160 24,889
will require a sump pump or drain.
180 27,368
21
Pre-Installation Information
22
Guy Wire Loading
23
General Instructions
There are many methods for erecting bucket elevators and they will vary depending on conditions at job
site, kind of hoisting equipment available, crew experience, personal preference and, of course, size and
rigidity of elevator casing. However, Sukup Manufacturing Co. suggests the following procedure:
Boot Installation
NOTE: If boot has spiral wing or herringbone wing pulley, confirm that pulley will rotate in proper
direction before boot installation. See sticker on pulley that indicates rotation direction.
Boot of an elevator must be set on a firm and level foundation. A boot that is not level makes elevator
very difficult to plumb. Shim and grout as required to level boot section. Use a carpenter’s level on
flanges to verify that boot is level and plumb. When this has been accomplished – and only then – secure
boot by tightening down anchor bolts. Care must be exercised not to disturb alignment of boot section.
One of two methods may be used to anchor boot to foundation. In the first, holes in frame are used. In
the second option, a clamp plate (not supplied by Sukup Manufacturing Co.) is used to hold down boot.
Anchor bolt size should be 1/2" diameter minimum.
After boot is positioned and leveled, it must be anchored to prevent shifting. Recheck boot level after
tightening bolts and nuts securely. BOOT MUST BE LEVEL AND PLUMB. A boot that is 1/16” per foot
out of level will cause 6” deviation from plumb at 100’ elevation. Boot base dimension information is
provided on next page for use in setting anchor bolts.
24
General Instructions
25
General Instructions
Once boot is installed, inlet hopper can be attached on either upside (high position) or downside (low
position) of boot. Most free-flowing materials such as grain are best fed into boot on up-leg side in a high
position. Feeds or light materials that tend to dust can be fed on down-leg side in a low position.
Sometimes this will help obtain maximum fill level of buckets. When mounting hopper on up leg in high
position, bottom of hopper should be no lower than centerline of pulley in its highest position. If hopper is
mounted on downside low position, hopper inlet should be no lower than centerline of pulley in its lowest
position. Boot hoppers are shipped separately and need to be installed to boot end panels.
26
General Instructions
Proper positioning and size of inlet hopper is critical to performance of bucket elevator. Loss of elevator
capacity will occur if buckets are not properly fed with incoming material. If inlet is too small, material
must be fed into boot at excessive speed. Excess velocity of incoming material causes damage. Buckets
do not fill properly and material backs up in boot, clogging inlet. Grinding and churning in boot area will
damage product and excessive power will be required to operate system.
When feeding on up-leg side, device that feeds elevator (auger, belt conveyor, spout, hopper, etc.) must
feed material into boot ABOVE centerline of pulley. Every effort should be made when designing feeding
equipment or spouting that direction of flowing material is perpendicular to buckets. This will reduce or
eliminate any off-center loading of buckets. Achieving bucket elevator’s rated capacity cannot happen
without even and consistent bucket fill.
Before cutting hole into backside of boot for inlet hopper, use a marker to trace inside dimensions of inlet
hopper onto boot. This will help ensure inlet’s inside walls are flush with hole where inlet will be mounted,
preventing blockage to incoming grain.
On left side of boot, on both sides, is an area that has been designed for field installation of an optional
shovel pocket hopper. The cover, attached at factory, should not be removed if a shovel pocket hopper is
not installed. The same is true for factory-attached covers over areas designed for optional rub block.
27
Leg Trunking Stacking
28
Trunking for 16” - 36” Pulley Elevator
Only 12-gauge sheet metal is used for 10-ft. trunking sections used for 16” pulley bucket elevators, which
use 11” x 8” trunking.
Two gauges of sheet metal are used for 10-ft. trunking sections used for 24” pulley bucket elevators,
which use 13” x 10” trunking. A maximum of 26 pieces of 12-gauge (0.108” thickness) trunking can be
used. As height of bucket elevator increases, up to an additional 12 pieces of 10-ft. trunking sections
made of 10-gauge sheet metal can be added. Ten-foot trunking sections made of 12-gauge sheet
metal are always placed above 10-ft. trunking sections made of 10-gauge sheet metal. See
exception noted on Page 28.
Two gauges of sheet metal are used for 10-ft. trunking sections used for 30” and 36” pulley bucket
elevators, both of which use 18” x 12” trunking. A maximum of 26 pieces of 10-ft. trunking made of 12-
gauge sheet metal (0.108”) can be used. As height of bucket elevator increases, up to an additional 12
pieces of 10-ft. trunking sections made of 10-gauge sheet metal can be added. Ten-foot trunking
sections made of 12-gauge sheet metal are always placed above 10-ft. trunking sections made of
10-gauge sheet metal. See exception noted on Page 28.
29
Trunking for 16” - 36” Pulley Elevator
Table 16 shows general trunking stacking arrangement for ground level installations of 16” pulley bucket
elevators with 11” x 8” trunking, 24” pulley bucket elevators with 13” x 10” trunking, and 30” and 36”
pulley bucket elevators with 18” x 12” trunking.
TRUNKING & BRACING WITH BOOT AT GROUND LEVEL
HEAD
|
1 2 3 4 5 6 7 8 9 10
Sections
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
from 20’
Ht. to Head
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
Section
|
|
1 2 3 4 5 6 7 8 9 10 * * * * * * * * * *
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|
To reach
5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5
20'
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
Inspection
Section (ft) 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10
|
|
Boot Ht (ft) 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5
Discharge
20' 21' 22' 23' 24' 25' 26' 27' 28' 29' 30' 31' … 220'
Height (ft)
NOTE: Single tie angle at top of section just below head section is for ladder connection only.
NOTE: Single tie angle at bottom of inspection section is for ladder connection only.
30
Trunking for 16” - 36” Pulley Elevator
16”, 24”, 30” & 36” Dia. Pulley Bucket Elevator Trunking - Below Ground Level Installations
Tables 17-18 apply to 16”, 24”, 30” and 36” dia. pulley bucket elevators in pits, sumps, and other below-ground-level installations. NOTE: If
ground-level deck over 15’ or 25’ pit is planned but a joint between trunking sections would interfere, install 5’ section before 10’ section.
Use this table to stack elevator from boot to ground level. See Table 18 for stacking from Inspection Section to Head Section
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
Section 3 1 2 3 4 5 6 7 8 9 10
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
Section 2 1 2 3 4 5 6 7 8 9 10 10 10 10 10 10 10 10 10 10 10
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
Section 1 1 2 3 4 5 6 7 8 9 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10
|
|
Boot (ft) 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5
Pit
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
Depth (ft)
NOTE: Single tie angle at bottom of Section 1 is for ladder connection only.
Table 17 – Pit trunking (boot to bottom of inspection section)
31
Trunking for 16” - 36” Pulley Elevator
Once trunking is above top of pit structure, stacking sequence needs to follow Table 18.
Stacking sequence shown in Table 18 is based on bottom of inspection section being 5 ft. above grade for optimum visibility of, and access to,
elevator belting and cups. Any adjustment to inspection section height will require changes to stacking arrangement shown .
TRUNKING & BRACING ABOVE PIT
HEAD
|
1 2 3 4 5 6 7 8 9 10
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
Sections from 20’ Ht. to Head Section
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|
|
1 2 3 4 5 6 7 8 9 10 * * * * * * * * * *
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|
To reach
5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5
20'
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
Inspection
10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10
Section (ft.)
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
Elevation Above Grade
20' 21' 22' 23' 24' 25' 26' 27' 28' 29' 30' 31' … 220'
(Discharge Height minus Pit Depth)
NOTE: Single tie angle at top of section just below head section is for ladder connection only.
Table 18 – Trunking above pit from inspection section to discharge
32
Trunking for 42” - 48” Pulley Elevator
Two gauges of sheet metal are used for 10-ft. trunking sections used for 42” and 48” pulley bucket
elevators, which use 22” x 14” trunking. A maximum of 26 pieces of 10-ft. trunking made of 12-gauge
sheet metal (0.108” thickness) can be used. As height of bucket elevator increases, an additional 22
pieces of 10-gauge (0.138” thickness) trunking can be added. Ten-foot trunking sections made of 12-
gauge sheet metal are always placed above trunking sections made of 10-gauge sheet metal. See
exception noted on Page 28.
Table 19 shows general trunking stacking arrangement for ground level installations of 42” and 48”
pulley bucket elevators using 22” x 14” trunking.
HEAD
|
1 2 3 4 5 6 7 8 9 10
Sections
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
from 20’
Ht. to Head
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
Section
|
1 2 3 4 5 6 7 8 9 10 * * * * * * * * * *
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|
To reach
4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
20'
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
Inspection
Section (ft) 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10
|
|
Boot Ht (ft) 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6
Discharge
20' 21' 22' 23' 24' 25' 26' 27' 28' 29' 30' 31' … 220'
Height (ft.)
NOTE: Single tie angle at top of section just below head section is for ladder connection only.
NOTE: Single tie angle at bottom of inspection section is for ladder connection only.
33
Trunking for 42” - 48” Pulley Elevator
42” & 48” Dia. Pulley Bucket Elevator Trunking - Below Ground Level Installation
Tables 20-21 apply to 42” and 48” pulley bucket elevators in pits, sumps, and other below-ground-level installations. NOTE: If ground-level deck
over 16’ or 26’ pit is planned but a joint between trunking sections would interfere, install 6’ section before 10’ section.
Use this table to stack elevator from boot to ground level. See Table 21 for stacking from Inspection Section to Head Section
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
Section 3 1 2 3 4 5 6 7 8 9 10
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
Section 2 1 2 3 4 5 6 7 8 9 10 10 10 10 10 10 10 10 10 10 10
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
Section 1 1 2 3 4 5 6 7 8 9 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10
|
|
Boot (ft.) 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6
Pit
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
Depth (ft.)
NOTE: Single tie angle at bottom of Section 1 is for ladder connection only.
34
Trunking for 42” - 48” Pulley Elevator
Once trunking is above top of pit structure, stacking sequence needs to follow Table 21.
Stacking sequence shown in Table 21 is based on bottom of inspection section being 6 ft. above grade for optimum visibility of, and access to,
elevator belting and cups. Any adjustment to inspection section height will require changes to stacking arrangement shown .
|
1 2 3 4 5 6 7 8 9 10
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
Sections from 20’ Ht. to Head Section
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|
|
1 2 3 4 5 6 7 8 9 10 * * * * * * * * * *
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|
To reach
4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
20'
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
Inspection
10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10
Section (ft.)
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
|x|
Elevation Above Grade
20' 21' 22' 23' 24' 25' 26' 27' 28' 29' 30' 31' … 220'
(Discharge Height minus Pit Depth)
NOTE: Single tie angle at top of section just below head section is for ladder connection only.
Table 21 – Trunking above pit from inspection section to discharge
35
General Instructions
Bolted flanges on trunking should be on outsides of assembled elevator legs as shown in Fig. 16.
36
General Instructions
3/8 X 1”
FLANGE
BOLTS
(J0611) &
3/8” NUTS
(J1017)
3/8 X 1” BOLT
(J0606) & 3/8”
NUT (J1017)
Image 1 – Positioning 10’ trunking sections & bolting flanges Image 2 – Bolting tie angle to flanges
Adjust 10’ section so bolt holes in tie angle will line up with bolt holes of flanges in both leg sections. Bolt
tie angle to flanges. See Image 2. NOTE: Standard 3/8” hex-head cap screws (J0606) and 3/8” nuts
(J1017) are used to connect angles to trunking. This provides clearance for socket.
3/8 X 1” FLANGE
BOLTS (J0611) &
3/8” NUTS (J1017)
Image 3 – Bolting flanges of second leg together Image 4 – Bolting tie angles to flanges
37
General Instructions
Use fork lift to position sections as shown in Image 5. Tightly bolt together flanges that were inaccessible
when trunking was lying down. See Image 6.
3/8 X 1”
FLANGE
BOLTS (J0611)
& 3/8” NUTS
(J1017)
Images 7-10 – Attaching tie angles, squaring plates & alignment pins
Attach tie angles to ends as in Image 7 and at flange connections as shown in Image 8. Use J0606 bolts.
Attach squaring plates as shown in Images 8 & 9 using J0611 bolts. NOTE: Bolts should be inserted so
their heads will be on top side of flanges when section is stacked.
3/8 X 1”
FLANGE
BOLTS
(J0611) & 3/8”
NUTS (J1017)
Attach alignment pins using one nut above and one below squaring plate. See Images 11 & 12. Attach
pins to bottom squaring plate of 30’ section as shown in Image 13 to ease stacking later.
38
General Instructions
Use string and look through trunking to check alignment. If needed, loosen tie bar and squaring plate
bolts and realign. Retighten bolts and recheck.
Stacking Procedure
Attach crane to top end of bottom section assembly and lift it into position on boot. When lifting a section
assembly, do NOT drag free end on ground. Use a telehandler or loader to lift other end. See Fig. 17 for
proper lifting of assembled 30’ trunking sections.
NOTE: Bottom section will be the one needed to stack up to 20’ of elevation. Be sure inspection door is
positioned properly to view cups on up-leg side.
39
General Instructions
As each trunking section is lowered onto one below, align pins with matching holes of squaring plate on
lower section of trunking. Once upper section is in place and aligned, bolt the two sections together.
DANGER: Only an experienced aerial worker using an approved fall restraint system
should bolt assembled sections together. Never detach crane until trunking section is
secure and completely supported. Fall will result in death or serious injury.
ALIGNMENT PINS IN SQUARING
PLATE ON UPPER 30’ SECTION
OF TRUNKING
Fig. 19 – Assembled
trunking sections
Install flange bolts at lower connection and tighten. Leave crane attached and plumb section assembly at
top. Do this by pulling trunking with a strap from support tower or using guy cables. Once trunking is
plumb, tighten all bolts using torque specifications provided in this manual.
NOTE: Hardware for tie angles and squaring plates may need to be loosened at top and intermediate
seams to allow trunking to be plumbed. DO NOT remove any hardware; only loosen if needed to allow
for slip between components.
Lift and install remaining assembled sections. Plumb and secure each section as it is assembled using
method specified above.
40
General Instructions
Unless elevator will be supported by a support tower (See note on Page 23), guy wire brackets should be
located every 20’ in height, starting approximately 20’ above grade. Except for uppermost brackets, all
should be positioned above a tie angle as shown in Fig. 20.
DISCLAIMER: It shall not be the responsibility of Sukup Manufacturing Co. to determine suitable guying
and/or bracing methods and materials. Customer (or its retained engineer or construction supervisor) is
responsible and should give consideration to include the following, but not be limited to, live loads, dead
loads, wind loads, soil bearing loads, seismic zone, and moisture run-off on top of base.
Sukup Manufacturing Co. will not be responsible for any damage to a product, including, but not limited
to, any damage that results from inadequate or improper guying and/or bracing methods and materials.
41
General Instructions
Uppermost guy wire brackets must be field-welded to trunking as shown in Fig. 21.
Attach guy wires to elevator only by means of four-wire bolt-on brackets shown in Figs. 20 and 21.
Follow sequence shown in Fig. 22 for proper clamping of guy wires. Both clamps must be positioned as
shown.
42
General Instructions
Drawings in Fig. 23 give proper guying arrangement at various heights. Cable lengths shown are
straight-line lengths from ground level to connecting point on guy wire bracket. No allowance in length is
made for sag, cable clamping, turnbuckles or off-level anchors.
Cable Lengths
SWBE0003
05/03/2017 DDM
44
General Instructions
Attach discharge hopper and uppermost leg sections. If elevator has a work/service platform and/or a
distributor platform, they should be installed at this time. See instructions in Platform and Ladder manual,
L25005. Lift completed head assembly onto top elevator section. DO NOT install hood at this time. After
head assembly is attached to elevator and guy wires are installed, or elevator is secured to support tower,
double check that entire unit is plumb with a laser, transit (taking several measurements) or a plumb line.
Fig. 25 illustrates plumb line method. Maximum out-of-plumb tolerance should not exceed 1/4".
NOTE: Depending on lifting equipment and platforms, it may be best to attach drive components such as
speed reducer and motor before head section is lifted onto top of elevator. See Drive Installation
instructions beginning on Page 52.
45
General Instructions
46
General Instructions
12. Trim front lip of cups at splice section. (This is not required when using a mechanical splice.) Trim
off an amount equal to belt thickness.
13. Adjust throat wipe (Fig. 30) so there is approximately 1/8” to 1/4” distance between lip of cup and
edge of wiper.
14. Attach hood to head section (See Page 51) and attach drive belts (See Page 57).
Attaching Buckets
Figs. 26-29 show attachment of buckets. They can be attached either before or after belt is installed (See
Fig. 31) depending on height of elevator and lifting equipment (crane) availability. In either case, be sure
to position fanged bolts as shown in Fig. 27. Tighten bolts from center of bucket and work toward ends,
alternating sides as shown in Fig. 27. This will help keep bucket centered on belt and ensure proper belt
tracking. Nuts should be torqued to 4 ft. lbs. for 1/4" bolts and 6 ft. lbs. for 5/16” bolts. Belt comes pre-
punched as determined at time of order. Contact Sukup Manufacturing Co. if belt was supplied by others.
IMPORTANT: Review Belt & Buckets Installation Overview beginning on previous page before attaching.
4 2 1 3
FANGED BOLT
Fig. 30 – Adjusting
Fig. 29 – Staggered buckets
throat wipe
47
General Instructions
Belt Installation
There are two basic methods of installing belt in an elevator (with cups attached or without) depending
on height of elevator and lifting equipment (crane) available. See Fig. 31.
Any of three styles of belt splice can be selected. See Fig. 32. IMPORTANT: Review Belt & Buckets
Installation Overview beginning on Page 46 before starting installation.
IMPORTANT: Let belt hang for at least 24 hours before splicing ends.
NOTE: Contact dealer/installer and/or see instructions on Page 50 for belt-tightening weight
specifications.
WARNING: End panels should never be removed from a boot section after erection of
elevator. Removal could cause elevator to collapse, resulting in death or serious injury.
INSTALLING BELT WITH BUCKETS ATTACHED INSTALLING BELT ONLY (FOR 100’-PLUS
(ONLY FOR ELEVATOR UNDER 100’ DISCHARGE ELEVATOR DISCHARGE HEIGHT)
HEIGHT UNLESS USING CRANE)
Fig. 31 – Installing belt with cups (left) or without cups attached (right)
NOTE: If installing rub blocks to shut down elevator in case of incorrect tracking of belt, see Assembly
Instructions document L1888.
48
General Instructions
NOTE: Lap and butt splice specifications are for legs up to 249’. If discharge height is 250’ or more,
increase to seven-bucket overlap.
49
General Instructions
NOTE: If using automatic take-up, this formula can be used to estimate how much weight to put in box to
keep belt tracking properly: (HP Constant ÷ Belt Speed) – Gravity Constant. See Tables 22-24. This is
the suggested weight to keep belt tracking properly. Be sure to evenly distribute weight in weight box.
HP ELEVATOR GRAVITY
HP
CONSTANT MODEL CONSTANT
2 33000 PD16 120
3 49500 PD24 676
5 82500 PD25 676
7-1/2 123750 PD30 894
10 165000 PD31 894
15 247500 PD32 1071
20 330000 PD33 1263
25 412500 PD34 1396
30 495000 PD35 1541
40 660000 PD36 1022
50 825000 PD42 1300
60 990000 PD46 1725
75 1237500 PD48 1422
100 1650000 PD50 1767
125 2062500 PD53 2609
150 2475000
200 3300000
BELT SPEED
PULLEY DIAMETER
RPM 16" 24" 30" 36" 42" 48"
RV40 168 251 314 377 440 503
RV50 209 314 393 471 550 628
RV60 251 377 471 565 660 754
RV70 293 440 550 660 770 880
RV80 335 503 628 754 880 1005
RV90 377 565 707 848 990 1131
NOTICE: Overtightening belt can result in damage to elevator. Tighten only until belt conforms to crowns
of pulleys and tension is sufficient for proper belt tracking.
50
General Instructions
Attaching Hood
See Fig. 33 for attachment of hood to head section. Ensure shaft seals are in place on outside of each
side of hood and are held in place by seal retainers.
Use fixed and adjustable hood clamps on top of hood flanges to secure hood to head section with 3/8”
hardware. Use corresponding holes in top of head section base angles.
51
General Instructions
Drive Installation
While head section is still on ground (ideally, depending on lifting equipment), remove hood sub-
assembly if necessary and install drive assembly. See Dodge speed reducer installation instructions on
Page 69.
NOTICE: Reducer is shipped without oil. Prior to operation, oil must be added. See Pages 58 and 72.
Attach motor using mounting holes provided. Align with reducer shaft using adjustment slots.
NOTICE: On all drive systems, smaller diameter pulley (sheave) must be mounted to motor drive shaft
and larger pulley to reducer shaft. Failure to mount in this manner will cause capacity issues, increased
wear and increased risk of gear reducer failure.
Fig. 34 – Right-hand
drive on 16” – 36”
pulley head section
Bracket at end of torque arm (turnbuckle) must mount to reducer so angle formed by torque arm and
imaginary line from end of torque arm through output shaft on reducer is close to 90 degrees. See Figs.
34 and 35. Bracket mounting position is usually at lower right of reducer for most right-hand drive
models, as shown in Fig. 34, but bracket can be mounted using other adjacent holes on lower portion of
reducer. NOTE: See Fig. 41 for attachment of torque arm bracket V013270 on 42” or 48” pulley head.
Fig. 35 – Left-hand
drive on 16” – 36”
pulley head section
For left-hand mounting, note angle of reducer needed for 90-degree orientation and mount reducer and
bracket accordingly. See Fig. 35.
52
General Instructions
As shown in Fig. 36, support bracket that goes under belt shield bracket may need to be field-shortened
to adjust for smaller drive packages.
Fig. 37 – Field-cutting
UHMW seals to
accommodate shafts.
Note tilted angle of reducer on left-hand drive in Fig. 38. As described previously, mount torque arm so
angle formed by torque arm and imaginary line from end of torque arm through output shaft on reducer is
close to 90 degrees. Ensure torque arm rod does not hit bottom of reducer. Drive belt(s) will be installed
later.
53
General Instructions
NOTE: Belt shield mounting bracket for 30” head pulley assembly using TA1107 or TA2115 gear reducer
may need to be trimmed as shown in Fig. 39 so it will fit on support bracket.
Fig. 39 – Trimming belt shield mounting bracket for 30” pulley head w/ TA1107 or TA2115 reducer
Belt shield used on elevator with 16” head pulley is mounted as shown in Fig. 40.
On elevator with 42” or 48” head pulley, attach torque arm bracket V013270 as shown in Fig. 41.
Belt shield used on elevator with 42” or 48” head pulley is mounted as shown in Fig. 42. Remove belt
shield shipping brackets first, if present. See next page for location and removal.
SWBE0049
09/03/2020 TSR
SHEET 1
Fig. 42 & Table 25 – Belt shield for 42” or 48” head pulley motor & reducer
55
General Instructions
For 42" or 48” pulley elevators without factory-installed drive, brackets V013493 and V013494 (both used
to hold shield in place during shipping) must be removed to allow correct installation of speed reducer.
Detail A of Fig. 43 shows view from behind shield. Detail B shows brackets to be removed after removal
of shield.
DETAIL A
SWBE0049
09/03/2020 TSR
SHEET 2
DETAIL B
Fig. 43 – Belt shield shipping brackets removal for 42” or 48” pulley drive
After removal of brackets V013493 and V013494 and installation of reducer and motor, re-attach back of
shield as shown in Fig. 43. Front panel of shield should be left off until after attachment of belts.
56
General Instructions
Place belt(s) in pulley grooves and tighten by adjusting motor mount. Follow these steps to tension belt.
1. Measure span length. See Fig. 44.
2. At center of span, apply enough force to deflect belt 1/64” for every 1” of belt span. If span is 32”,
deflection amount should be 32/64”, or 1/2”.
3. Use Table 26 to determine pounds of force to apply to gauge proper deflection per belt.
Smallest Belt Deflection Setting
Belt Deflection = 1/64 of belt span
Pulley RPM Range
Cross Uncogged Single V-Belts & Cogged V-Belts &
Diameter
Section Uncogged Banded V-Belts Cogged Banded V-Belts
Range
Used Belt New Belt Used Belt New Belt
1,000 – 2,500 3.6 5.4 4.0 6.0
3.0 – 3.6”
2,501 – 4,000 2.8 4.1 3.3 4.9
1,000 – 2,500 4.4 6.6 4.9 7.3
A, AX 3.8 – 4.8”
2,501 – 4,000 3.7 5.7 4.3 6.4
1,000 – 2,500 5.3 7.8 5.7 9.2
5.0 – 7.0”
2,501 – 4,000 4.6 6.8 5.1 7.6
860 – 2,500 --- --- 4.8 7.2
3.4 – 4.2”
2,501 – 4,000 --- --- 4.1 6.2
860 – 2,500 5.2 7.9 7.1 10.5
B, BX 4.4 – 5.6”
2,501 – 4,000 4.5 6.6 7.1 9.1
860 – 2,500 6.2 9.4 8.4 12.4
5.8 – 8.6”
2,501 – 4,000 6.0 6.8 7.3 10.7
500 – 1,749 --- --- 10 15.2
4.4 – 6.7” 1,750 – 3,000 --- --- 8.9 13.2
3001 – 4000 --- --- 5.6 8.5
5V, 5VX 7.1 – 10.9”
500 – 1,740 12.6 18.9 14.8 22.1
1,741 – 3,000 11.2 16.5 13.7 20.1
500 – 1,740 15.5 23.4 17.1 25.5
11.8 – 16.0”
1,741 – 3,000 14.5 21.8 16.8 25
Sukup products use belts made by Bestorq. Sukup recommends using a Bestorq tension meter to
measure belt deflection. Go to www.bestorq.com or call (402) 423-3077 for more information.
After adjusting tension to desired level by adjusting motor mount, remove any foreign material from inside
of belt guard. Check that all fasteners are tightly secured. Close and latch belt guard.
Fig. 44 – Adjusting
belt tension
IMPORTANT: Check and adjust belt tension after first five (5) and 24 hours of operation, then during
regular maintenance (at least twice yearly).
57
General Instructions
Reducer Oil
Gear reducers are shipped without oil. Use high-grade petroleum-based, rust- and oxidation-inhibiting (R
& O) gear oil. See oil recommendations in Dodge Torque Arm II Speed Reducers section to determine
correct viscosity of oil for reducer. Follow instructions on reducer nameplate, warning tags and in
installation instructions attached to reducer. Oil should be changed after an initial operation of about two
weeks. After initial break-in period, lubricant should be drained, magnetic drain plug cleaned, and gear
case flushed and refilled every 2,500 hours of operation. Change oil every one to three months when
operating in conditions of extreme dirt and temperature.
Before filling reducer with oil, install magnetic drain plug in hole closest to bottom of reducer (as mounted
on elevator). Remove tape covering filter/ventilation plug in shipment and install plug in topmost hole. Of
two remaining plugs on sides of reducer; lower one is the minimum oil level plug; upper one is the level
to which oil should be filled.
NOTICE: Proper amount of oil must be added to reducer prior to running elevator. Too much oil will
cause overheating and too little will result in gear failure. Check oil level regularly.
Final Check
Check all parts to ensure no foreign objects or tools have been left in elevator. All guards, inspections
doors and removable plates should be checked for proper placement. Check for loose or missing
buckets. Drive should be turned by hand to check for proper rotation and clearance. Rotate belt a full
rotation to check for any obstructions. Make any necessary adjustments. Check all setscrews and pulley
hub bolts to ensure they are tightened.
IMPORTANT: Do not operate bucket elevator until all bolts are fully tightened.
Elevator should be run without load for approximately eight hours. During this time, particular
attention should be given to:
1. Loud or unusual noise – Check for loose buckets, an improperly adjusted throat wiper, or trash
materials/tools inside elevator.
2. Excess vibration – Drive equipment may not be adequately braced or elevator may not be plumb.
3. Bearings overheating – Check bearing lubrication; check for extreme shaft misalignment at head
and boot shafts, for a severe overhung load condition at the drive, or that take-ups are too tight.
4. Drive unit over-heating – Reducer is shipped without oil. It must be filled prior to operation.
Check belt alignment. Motor may be improperly wired or there may be incorrect voltage going to
motor.
5. Evidence of belt not tracking in center of pulleys – Check that elevator is plumb, that pulley shafts
are level, take-ups are properly adjusted, and head bearings are shimmed appropriately.
Once material is run through elevator, belt tracking needs to be checked again. Make sure material is
flowing properly into boot. Improperly flowing material can push belt to one side and make it very difficult
to properly track the belt. Final tensioning of belt will be done under load.
58
Maintenance
Maintenance
Belt will stretch after installation and may need further adjustment. Fig. 45 – Take-up screws
Expect some stretching during first few weeks of operation. On
manual take-up boots, belt tension should be maintained by turning
boot take-up screws (Fig. 45) slowly and evenly to maintain proper
tracking. When screw adjustment is completely used, belt will have to
be re-spliced. Good belt tension is critical for proper traction on head
pulley and optimum performance. Refer to Fig. 46 to ensure proper
belt tracking.
NOTE: Contact dealer/installer and/or see instructions on Page 50 for
belt-tightening specifications if using automatic take-up.
NOTICE: Overtightening belt can result in damage to elevator.
Tighten only until belt conforms to crowns of pulleys and tension is
sufficient for proper belt tracking.
Belt Tracking
Rubbing pulleys are a serious condition and should be corrected immediately. Follow steps shown below
to make any minor adjustments. A qualified millwright should correct serious defects.
If remedies above do not correct misalignment issue, look for these conditions as well:
Loose hub screws allowing pulley to move laterally on shaft
Loose bearings or bearing supports
Weak or bent head pulley shaft
Grain entering boot at an angle – pushing belt to one side
Head or boot pulley not plumb
59
Maintenance
Regularly scheduled maintenance can greatly increase equipment life and reduce downtime. A good
maintenance program includes general housekeeping, regular lubrication and regular inspection. Check
bucket elevator immediately if any unusual noise or vibration is observed.
WARNING: Never remove or loosen one or more cables or connection to support tower
without providing other means of support to elevator leg. Failure to heed this warning
could result in collapse of elevator, causing death or serious injury.
1. Check belt frequently to make certain it is running in center of leg. Check belt alignment every
hour for first 10 hours and daily thereafter. A rubbing belt could quickly cut a hole in side of leg or
cause sparks.
2. Check bucket bolts for tightness after 10, 30, and 100 hours of operation and every 200 hours
thereafter.
3. Bearings are greased at factory and do not need to be greased prior to start-up. Grease all
bearings every 800 to 1,000 hours after start-up. While unit is running, use only enough grease
so fresh grease can be seen at seals. If bearings cannot be lubricated while unit is running, do it
immediately upon shutdown while bearing is still warm. See bearing lubrication information on
next two pages.
4. Be certain to maintain reducer as specified by manufacturer. Follow manufacturer’s instructions
for regular oil level inspection and oil changes. See Dodge speed reducer and lubrication
information beginning on Page 72.
5. Check head pulley and V-belt drive assembly after 10, 30, 100 and every 300 hours, or twice
yearly thereafter. The best belt tension for a V-belt drive is the lowest tension at which belts will
not slip under the highest load condition. See belt adjusting instructions on Page 57.
6. Oil motor every 1,000 hours or once yearly if equipped with oil holes or grease unit if zerks are
available.
7. Check guy cables, turnbuckles and cable clips every three months for damage or loosening. If
elevator is supported by a tower, check connections between tower and elevator every six
months for damage or loosening. NOTE: Any change in cable tensions or support tower
connections may cause leg to go out of plumb, resulting in belt not running straight or even in
structural damage to leg.
8. Check for deterioration or looseness of any bolts or fasteners and for secure attachment of all
ladders. Tighten any loose fasteners.
9. Check for damaged or missing cups.
10. Check belt for frays, tears or cracks, as well as for damage from bolts or oil. Also check for
glazing of belt, which could lead to slippage and overheating.
60
Maintenance
BEARING LUBRICATION
NOTE: Following are instructions from Dodge on lubrication of bearings used in Sukup elevators.
61
Maintenance
62
Maintenance
DOOR ASSY. DOOR DOOR PULLEY DIA./ SCREW QTY. PER WASHER
PART # FRAME PANEL TRUNKING SIZE PART # DOOR COLOR
V01537 V01538 V01539 16” J8920 1 Green
V00080 V00079 V00077 24” J8920 1 Green
V00086 V00087 V00088 30-36” J89201 1 Tan
V00019 V00034 V00033 42-48” J89201 1 Tan
V00121 V00123 V00122 13x10” J89201 1 Tan
V00039 V00072 V00049 18x12” J89201 1 Tan
V00039S V00072S V00049S 18x12” J89201 1 Tan
V00135 V00134 V00133 22x14” J89201 2 Tan
V80001 V70003 V70002 27x14” J89201 2 Tan
63
Troubleshooting
Troubleshooting, General
64
Troubleshooting
Troubleshooting, General
65
Troubleshooting
Troubleshooting, General
Troubleshooting, Electrical
66
Troubleshooting
67
Troubleshooting
68
Dodge Torque Arm II Speed Reducers
NOTE: Information on this and following pages is from Dodge Torque-Arm II Speed Reducers manual
MN1601, dated 02/2022. It can be found at www.dodgeindustrial.com
For speed reducer warranty information, call Dodge Industrial at 864-297-4800.
69
Dodge Torque Arm II Speed Reducers
70
Dodge Torque Arm II Speed Reducers
71
Dodge Torque Arm II Speed Reducers
72
Dodge Torque Arm II Speed Reducers
73
Dodge Torque Arm II Speed Reducers
74
Dodge Torque Arm II Speed Reducers
75
Contact Information
Contact Information
Owner’s manuals are available from Sukup and additional copies can be requested at the address,
phone number, or e-mail address shown below. Please indicate manual number L2500 when requesting
the Bucket Elevator Assembly and Owner’s Manual.
Address: ______________________________
Fax: __________________________________
76