Draft 2024-2025 IDP
Draft 2024-2025 IDP
SC/11.1/03/2024
1
NO TABLE OF CONTENTS PAGE NO
2.1 Introduction 13
2
3.3 KPA 2:Basic service delivery and infrastructure 140
development analysis
3
3.4.2. Primary sector 276
4
3.6.2. Stakeholders participation 316
5
5. Chapter 5:Projects Phase 360
6
LIST OF ACRONYMS
AC Audit Committee
AG Auditor General
CS Community Survey
DG Disability Grant
7
DWS Department of Water and Sanitation
IT Information Technology
8
LG-MTEC Local Government Medium Term Expenditure Committee
OA Old age
9
PSO Provincial Strategic Objective
UN United Nation
10
CHAPTER 1: OVERVIEW AND VISION AND MISSION
1.1 CONTEXT AND OVERVIEW
The new administration has engaged in a full evaluation of the functioning of every aspect
affecting the lives of communities in Makhuduthamaga. Our constitution requires us as local
government to be developmental – a responsibility to structure and manage the administrative,
budgeting and planning processes that will give expression and priority to the basic needs of
communities and to promote their social and economic development. Hence our IDP sets out a
vision for the future of local government in Makhuduthamaga, in line with legislation and the
constitution.
Our vision points to democratic local government in which the needs of all, but especially the
poor and vulnerable communities, are met with efficiency and effectiveness. This will ensure
that we are accountable, viable, and capable of delivering sustainable services that meet the
diverse needs of our communities
11
1.2. VISION AND MISSION
1.2.1 VISION
1.2.2. MISSION
o to ensure efficient and effective consultation and communication with all municipal
stakeholders
1.2.3. VALUES
12
CHAPTER 2: EXECUTIVE SUMMARY
2.1. Introduction
The Legislative and Policy mandates that influence the activities of Local Government are
numerous, encompassing international, national, provincial and regional influences. It is
important that there is a direct linkage between the activities at a Local Government level and
the broader strategic policy and legislative environment in order that a common vision for the
development of South Africans and Makhuduthamaga Local Municipality residents can be
achieved
The Integrated Development Plan (IDP) is the principal strategic planning instrument which
guides and informs all planning, budgeting, management and decision making processes in the
municipality. The purpose of the IDP is to ensure the effective use of scarce resources; helps to
speed up delivery and attract additional funds from all the spheres of government and the
private sector; helps to overcome the legacy of apartheid by lobbying for integrated rural and
urban areas and to extend services to the poor and lastly promotes co-ordination between local,
provincial and national government
o A municipality has executive authority and has the right to administer local government
matters listed in Part B of Schedule 4 and Part B of Schedule 5, among which is
Municipal Planning and
o Any other matter assigned to it by national or provincial government.
o Constitution: Bill of Rights (fundamental rights of citizens): Sections 24-27 & 29
o Constitution: section 152 -153: Objects of Local government
o DFA 67/ 1995: Community involvement
o Powers and Functions as per the Notice of establishment of the Makhuduthamaga
Local Municipality and Municipal Structures Act
The formulation of the IDP was guided by various pieces of legislation; amongst others are the
following:
The Constitution of the Republic of South Africa 1996, stipulates that the local sphere of
government consists of municipalities which were established for the whole of the territory of
South Africa – the so called wall-to-wall municipalities.
13
The Objects of Local Government are set out in Section 152 of the Constitution.
The Municipal Structures Act (Act 117 of 1998) provides for the following:
It regulates the IDP. It requires the municipality to undertake developmental oriented planning
so as to ensure that it strives to achieve the objectives of local government set out in Section
152 and 153 of the Constitution of the Republic of South Africa. Section 25(1) requires the
municipal council within a prescribed period after the start of its elected term, to adopt a single,
inclusive and strategic plan for the development of the municipality.
Chapter 5, Section 26 of the MSA indicates the core components of an IDP and that such an
IDP must reflect the following:
o The municipal council’s vision for the long term development of the municipality with
special emphasis on the municipality’s most critical development and internal
transformation needs
o An assessment of the existing level of development in the municipality, which must
include an identification of communities which do not have access to basic municipal
services
14
o The council’s development priorities and objectives for its elected term, including its
Local Economic Development and internal transformation needs
o The council’s development strategies which must be aligned with any national and
provincial sectoral plans and planning requirements that are binding on the municipality
in terms of legislation
o A Spatial Development Framework which must include the provision of basic guidelines
for a Land Use Management System for the municipality
o The council’s operational strategies
o Applicable Disaster Management Plans
o A Financial Plan, which must include a budget projection for at least the next three years
o The Key Performance Indicators and Performance Targets determined in terms of
Section 41 of the MSA
The MFMA was promulgated to sustain the finances of both the Municipalities and other
Spheres of Government. The Act also gives mandatory obligations on Performance
Management System. Section 2 of the Act’s objectives is to secure sound and sustainable
management of the financial affairs of the Local Government institutions to which this Act
applies by establishing norms and standards.
The Makhuduthamaga Local Municipality budget process endeavors to comply to the provision
of the MFMA.It is pertinent that the development of the IDP and the budget process are
integrated and aligned as per Legislation
The Municipal Property Rates Act of 2004 aims to regulate the power of a municipality to
impose Rates on Property; to exclude certain properties from rating in the national interest; to
make provision for municipalities to implement a transparent and fair system of exemptions,
reductions and rebates through their rating policies to make provision for an objections and
appeals process.
The Municipal Planning and Performance Management Regulations (R796 of 2001) set out
further requirements for an IDP:
• An Institutional Framework is required for implementation of the IDP and to address the
municipality’s internal transformation;
• Investment initiatives;
• Development initiatives including infrastructure, physical, social and institutional
development; and
• All known projects, plans and programmes to be implemented within the municipality by
any Organ of State
15
Intergovernmental Relations Framework Act No 13 of 2005
Intergovernmental Relations Framework Act No 13 of 2005 provides clarity on how all the three
spheres of government must work together. The Act is a response to the limited successes in
the alignment efforts among the three spheres of government. It creates a framework to support
intergovernmental cooperation and coordination as required by the Constitution in its definition
of “cooperative governance”. It provides for the obligation of all spheres to participate in the
planning processes of the municipality and in turn allow their own planning processes to be
influenced by the municipal IDP’s. The Act establishes structures and processes that enhance
inter – governmental planning and monitoring processes for local, provincial and national
spheres of governance
The following are the four characteristics of this Developmental Local Government;
• Municipal powers and functions are exercised in a manner which maximises their impact
on social and economic growth
• Playing an integrating and coordinating role to ensure alignment between all government
spheres and private sector investment within the municipal area
• Democratising development
• Building social capital through providing community leadership and vision and seeking to
empower marginalised and excluded groups within the community
The Act provides a framework for Spatial Planning and Land Use Management. It provides
inclusive, developmental, equitable and efficient spatial planning at different spheres of
government. It promotes greater consistency and uniformity in the application procedures and
decision making by authorities responsible for land use decisions and development applications.
It provides for the establishment, functions and operations of Municipal Planning Tribunals
The EPWP is a programme that seeks to ensure that public bodies like municipalities formulate
plans and budgets that will draw significant numbers of the unemployed into productive work
while provide them with training. Makhuduthamaga Local Municipality is using the opportunity of
labour intensive construction method to carry out Infrastructure, Environment and Community
Works’s Programme under LED projects
16
Sustainable Development Goals (SDGs)
The 2030 Agenda on Sustainable Development was adopted by UN (United Nations) member
states in September 2015.The SDGs are a new universal set of goals, targets and indicators
that UN member states will be expected to use to frame their agendas and political policies over
the next 15 years i.e. 2015 to 2030.The Agenda consists of altogether 17 goals, 169 targets and
231 indicators.
• The SDGs take into account different national realities, capacities & levels of
development, and respect national policies & priorities
• Build on the foundation laid by the MDGs
• Seek to complete the unfinished business of the MDGs & respond to new challenges
• The framework will retain goals, targets & indicators format of the MDGs
• Will address four dimensions: Economic development, Social inclusion, Environmental
sustainability and Good Governance
In 2015 the Millennium Development Goals (MDGs) came to the end of their term, and the
Sustainable Development Goals were introduced as the post 2015 agenda comprising 17
Sustainable Development Goals, 169 targets and 229 indicators took their place. The SDG’s re
based on the moral principle of the Millennium Development Goals which strived to ensure that
no one or one country should be left behind and that each country has a common responsibility
in delivering on the global vision. The goals set out a holistic framework to help set the world on
a path towards sustainable development, by addressing all three dimensions of Economic
Development, Social inclusion, and Environmental sustainability. During the development of the
5 year IDP efforts were made to ensure that integration and institutionalization of the SDG in the
planning processes of the municipality is achieved.
There are three fundamental differences between the 2030 Development Agenda and the
Millennium Development Goals:
o The SDGs are broader and more ambitious than the MDGs.They go beyond social
development and include all three dimensions of Sustainable Development, Social.
Economic and Environmental
o The SDGs are complex and integrated, with the integrated approach implying the need
to manage trade-offs and maximise synergies across targets
o The SDGs are universal while the MDGs were not, implying that the goals and targets
are relevant to all countries and all stakeholders within the countries. The SDGs should
benefit all –eradicating poverty and reducing inequalities.
17
Millennium Development Goals Sustainable Development Goals
Goals 08 17
Targets 21 169
Indicators 60 230
Reporting Obligations
18
Alignment for integrated implementation
19
GOAL 2 End hunger,
achieve food security and Outcome 2. Long and healthy life
improved nutrition and Outcome 7. Comprehensive rural
Goal 5: Modern Agriculture for Chapter 6 An
promote sustainable development
increased productivity and integrated and
agriculture Outcome 10. Environmental
production inclusive rural
protection
economy
GOAL 12 Ensure Outcome 13. Inclusive social
sustainable consumption protection system
and production patterns
The South African Government has through the Minister of Planning Monitoring and Evaluation
published the National Development Plan. The plan aims to eliminate poverty and reduce
inequality by 2030. The plan has a target of developing peoples’ capabilities to improve their
lives through Education and Skills Development, Health care, better access to Public Transport,
jobs, Social Protection, rising incomes, Housing and Basic services and Safety.
o Expanding infrastructure
Municipalities are the first point of interaction between the communities and government and
therefore stand to benefit from the drive towards radical transformation of the economy.
20
Figure 1: National Development Plan
At the core of the plan is to eliminate poverty and reduce inequality, promotion of gender equity
and addressing the pressing needs of youth.
It is imperative for Makhuduthamaga to take these issues into consideration when reviewing the
Integrated Development Plan.
21
Limpopo Development Plan
The Limpopo Development Plan (LDP) is a 5-year overarching Growth and Development Plan
that outlines the contribution of the province to the National Development Plan (NDP) Vision
2030 imperatives and the execution of the 5-year NDP Implementation Plan and Medium Term
Strategic Framework (MTSF) priorities and targets of the current Term of Administration. The
2020-2025 Limpopo Development Plan (LDP) builds on the achievements and lessons learned
from the implementation of the 2014-2019 LDP.
The LDP is designed to marshal resources from all sectors, both public and private, towards
addressing economic growth and integrated development in Limpopo. It thus creates a platform
for the constructive and active participation of the private sector, civil society and organised
labour towards the achievement of provincial growth and development objectives to promote
higher standards of living for citizens of Limpopo.
The LDP seeks to ensure that government resources, efforts and energy are channeled towards
creating an enabling environment, offering opportunities to the people of the Limpopo Province
to be active beneficiaries of sustainable growth and development, which can improve their
quality of life.
Equally, the LDP serves as a blueprint and framework for Strategic Plans and Annual
Performance Plans of provincial departments, District-wide IDPs or One Plans and Integrated
Development Plans of districts and local municipalities, as it delineates the provincial
contribution towards the implementation of goals and targets spelled out in national strategies
and sector plans
The purpose of the LDP 2020-2025 is to outline the contribution of the Limpopo Province to the
NDP, provide a framework for the strategic plans of provincial government departments and
municipalities, and to create a structure for the constructive participation of private-sector
business and organised labour and citizens towards the achievement of the provincial growth
and development objectives
The 2020-2025 LDP is an integrated socio-economic planning and delivery document for the
province. It encapsulates the realities and the aspiration of the provincial citizens. The plan aims
to transform the productive potential of the province while addressing the inherent socio-
economic challenges with the aim of ensuring sustainable livelihoods.
Effective implementation of the LDP will be guided by the Integrated Planning Framework.
Departments, municipalities and SOEs will have to align their planning documents to the LDP.
Periodic reporting will be done to the Executive Council in line with the applicable LDP
implementation plan. Monitoring and evaluation of the LDP will serve before EXCO on a bi-
annual basis. M&E will produce a LDP midterm review for consideration by EXCO. Close out
report will be produced to guide the ensuing planning cycle towards the end of the 6th Term of
Administration. There will be a communication plan to support the process to update the
stakeholders with implementation of the LDP
22
Alignment of LDP and NDP Targets
The Limpopo Development Plan (2020-2025) is the second iteration towards the National
Development Plan (2030). The table below depicts the LDP (2020-2025) targets and how they
relate to the 2030 targets per the indicators. The LDP economic targets for period the 2020-
2025 are as follows:
Employment Number of 429 000 1,4 million 1,9 million 2,4 million
employed (448 000) (500 000)
23
Manufacturing Manufacturing 6% 2,3% 3% 6%
%to GGP share to total
GGP
Alignment of the NDP and LDP priorities into the municipal IDPs
The NDP highlights the need to strengthen the ability of local government to fulfil its
developmental role. It calls for Municipal Integrated Development Plans (IDPs) need to be used
more strategically to focus attention on critical priorities in the NDP that relate to the mandate of
local government such as spatial planning, infrastructure and basic services.
Like provincial planning processes, municipal IDPs should be used to focus on aspects of the
NDP that fit within a municipality’s core responsibilities. This would allow the IDP process to
become more manageable and the participation process more meaningful, thus helping to
narrow the gap between the aspirations contained in these documents and what can actually be
achieved. To do this effectively, the IDP process needs to be led by municipal staff, not
outsourced to consultants.
24
LOCAL IMPERATIVES
The IGR Framework Act (IGRFA) sets out the general principles and objects of
intergovernmental relations. The focus is primarily on the outcomes that the system must
achieve coherent government, effective provision of services, monitoring implementation of
policy and legislation as well as the realization of national priorities. The local government is the
closest sphere to communities and represents all spheres of government at local level. A
functional and developmental LG is a necessary requirement for an effective Developmental
State.
The District Development Model, as announced by the President seeks to encourage better
coordination and cooperation in government to improve coherence in planning and
implementation across all spheres of governance. The District Development Model seeks to
address silo planning at a horizontal and vertical level. It will also narrow the distance between
the people and government by strengthening the coordination role and capacities at the District
level as it is the penultimate sphere closer to the people after Ward and Local Spheres. It is
aimed at delivering Integrated Services whilst strengthening Monitoring and Evaluation and
impact at district and local levels.
The Sekhukhune District Municipality is located in the south-eastern part of Limpopo, which is
South Africa’s most Northern Province. The district was formed during the year 2000 and is one
of the five District Municipalities in the Limpopo Province. It shares boundaries with Capricorn
26 and Mopani Districts in the north, Mpumalanga in the south and east, and the Waterberg
District in the west. The District is largely rural in nature and is made-up of four Local
Municipalities, namely; Elias Motsoaledi, Ephraim Mogale, Makhuduthamaga and Fetakgomo
Tubatse. The District is made up of 117 wards with a total of 764 villages. There are 74
traditional leaderships within the district. These are mostly concentrated in Fetakgomo Tubatse,
Makhuduthamaga, the eastern extents of Ephraim Mogale and the southwestern extents of
Elias Motsoaledi municipality (the former Moutse area in KwaNdebele).
Sekhukhune District Municipality accounts for a total population of 1.2 million, or 20.4% of the
total population in the Limpopo Province, with the Vhembe District being the most populous
region in the Limpopo Province for 2018. Sekhukhune increased in importance from ranking
fourth in 2008 to third in 2018. In terms of its share the Sekhukhune District Municipality was
slightly larger in 2018 (20.4%) compared to what it was in 2008 (19. 6%).When looking at the
average annual growth rate, it is noted that Sekhukhune ranked highest (relative to its peers in
terms of growth) with an average annual growth rate of 1.4% between 2008 and 2018.
According to IHS Markit Regional eXplorer version 1750, in 2018, the population group with the
highest percentage of people living in poverty was the African population group with a total of
82.6% people living in poverty, using the upper poverty line definition. The proportion of the
African population group, living in poverty, decreased by 7.66 percentage points, as can be
seen by the change from 82.60% in 2008 to 74.93% in 2018. There has been a rise in
unemployment between 2008 and 2018. In 2018, there were a total number of 93 900 people
25
unemployed in Sekhukhune, which is an increase of 6 360 from 87 600 in 2008. The total
number of unemployed people within Sekhukhune constitutes 28.17% of the total number of
unemployed people in Limpopo Province. There are approximately 187 161 people of 20 years
or older in the district who have no schooling. Only 4 % of the population have higher education.
This will likely constrain the ability of the District to improve its socio-economic conditions
significantly in the short to medium term. This plan has utilised statistics received mainly from
the Department of Economic Development, Environment and Tourism (LEDET), which they
obtained from different sources, i.e. Stats SA, Global Insight /IHS Markit Regional Explorer,
Geoscience Councils, IEC, Universities, Internal (Record of Decision), etc. It analyses a
combination of stats obtained mainly from Stats SA and Global Insight/IHS Markit Regional
Explorer which brings together the deepest and timely intelligence at district level. LEDET
officially subscribes to Global Insight /IHS Markit Regional Explorer.
The main sectors of Sekhukhune District that contribute to the growth of economy in the district
are Agriculture, Mining and Community Services. Mining is the biggest contributor in the
economy of the district and it is forecasted to grow fastest at an average of 5.64% annually from
R 12.4 billion in Sekhukhune District Municipality to R 16.3 billion in 2023. The mining sector is
estimated to be the largest sector within the Sekhukhune District Municipality in 2023, with a
total 27 share of 53.0% of the total GVA (as measured in current prices), growing at an average
annual rate of 5.6%. The sector that is estimated to grow the slowest is the construction sector
with an average annual growth rate of 0.21%. The District Municipality remains focused and
committed to the vision “Sekhukhune District Municipality - a leader in integrated economic
development and sustainable service delivery”. The institutional projects included in the
Development Plan will be aligned to the institutional budget.
The Development Plan will include the plans/programmes which should be implemented by
different spheres of government (including Municipalities) and Private Sector to ensure that
people within Sekhukhune District experience integrated and inclusive development. Different
Stakeholders were consulted on the Socio-economic profile after its approval by Council in
February 2020. The District Development Model was officially inaugurated by the Deputy
Minister in the Department of Planning, Monitoring and Evaluation (DPME) on the 20th
November 2020 and launched by the Premier of Limpopo Province on the 23rd April 2021.
The Local Government Back to Basics Strategy (B2B) its main core services that Local
Government provides i.e. clean drinking water, sanitation, electricity, shelter, waste removal and
roads which are the basic human rights enshrined in our constitution and Bill of Rights. This
strategy comes after local government facing challenges in rendering services to the
communities and majority of municipalities in the country to account mainly in financial
management and continuous negative audit outcomes.
26
The following are Local government programmes which municipalities will work on:
o Municipalities must deliver the basic services (basic water, sanitation, electricity,
waste removal etc.) In addition to the above, municipalities must ensure that
services such as cutting grass, patching potholes, working robots and street
lights and consistent refuse removal are provided.
o Council to ensure proper maintenance and immediate addressing of outages or
maintenance issues to ensure continuity of service provision
o . Municipalities must improve mechanisms to deliver new infrastructure at a
faster pace whilst adhering to the relevant standards
o . Increase of Community Work Programme sites targeting the unemployed youth
in informal settlements to render day to day services such as cutting grass,
patching potholes, cleaning cemeteries, etc
o . Extend reach of basic services to communities living in informal settlements by
providing temporary services such as:(i) potable water, (ii)temporary sanitation
facilities, (iii)grading of gravel roads and (iv)refuse removal
2. Good governance
27
4. Sound financial management
Taking cognizance of the Political, National, Provincial and District policies and plans, the
following KPA’S were identified and adopted by the Makhuduthamaga Municipal Council:
28
Makhuduthamaga Municipal Priorities:
o To ensure efficient and effective Spatial Planning and Land Use Management systems
for sustainable development
o To reduce infrastructure and service delivery backlogs in order to improve quality of life
of the community by providing them roads and storm water, bridges, electricity, water &
sanitation and housing
o To promote social cohesion, road safety management, environmental welfare and
disaster management for the Municipality
o To stimulate economic development through SMMEs support, LED projects, private and
public sector investments
o To promote good governance, public participation, accountability, transparency,
effectiveness and efficiency
o To promote effective, efficient municipal administration, and governance through
application of credible and approved municipal systems/ processes
1.Air pollution No
7.Municipal Airport No
29
10.Municipal Public transport Yes Provide traffic control and licensing
30
29. Municipal parks and Yes Recreational areas for local
recreation communities
38. Learners and Drivers Yes Provide learners and drivers licensing
licensing
39.Disaster Management Yes Provide supports and coordinates the
disaster within the jurisdiction of
Makhuduthamaga
Section 32 (1) (a) of the Municipal Systems Act, act 32 of 2000 mandates the Municipal
Manager of a municipality to submit a copy of the Integrated Development Plan as adopted by
Council of the Municipality, and any subsequent amendment to the plan, to the MEC for Local
Government in the Province within 10 days of the adoption or amendment of the plan, for
assessment.
Analysis of MEC Opinion on Makhuduthamaga Municipality IDP over the last five years
31
2022/2023 High Partially Aligned High
The Opinion of the MEC assessment panel during 2023/2024 IDP/ Budget assessment was that
the MLM should maintain the status quo on issues that were clearly indicated in terms of all
KPAs and adhere to the process plan in the 2024/2025 IDP /Budget
Process plan
The Municipal Systems Act also provides for the development of a municipal’s IDP that must be
aligned to with and complement the development plans and strategies of other affected
municipalities and other organs of state so as to give effect to the principles of corporative
government contains in section 41 of the constitutions.
The following process was followed during the review of the 2024/2025 IDP
Drafting an IDP requires a comprehensive planning process and the involvement of a wide
range of internal and external role players. Such process has to be properly organized and
prepared. The preparation is the duty of the Municipal Manager and Senior Managers. The
preparation process will be referred to as the process plan and should contribute to the
institutional readiness to draft or review the IDP.
The elected Municipal Council is the ultimate IDP decision making authority. The role of
participatory democracy is to inform, negotiate and comment on those decisions in the course of
the planning process. In terms of the Council approved IDP and Budget process plan, Council
must approve the final IDP before the start of the financial year, that is, no later than 31 May
2024. In order for Makhuduthamaga to prepare a credible IDP, several stakeholders have to be
engaged to provide inputs and inform the final IDP.
32
IDP PROCESS PHASES
Analysis
Phase
Project
Phase
33
future development direction. MLM has not changed its
vision, mission statement. Strategies will be reviewed on how
to address all the needs of the communities, by prioritising
them and came up with draft projects. The Municipal SWOT
analysis will also be reviewed to project the status quo of the
Municipality.
Project Phase Identification of possible projects and their funding sources.
Integration Phase The MLM has integrated its capital projects as informed by
the vision, objectives and strategies developed and
resources available for the effective implementation of the
project in the IDP. That has been seen as putting more
emphasis on the implementation of the strategic meeting
resolutions.
Approval Phase The first draft 2024/2025-2025/26 IDP/Budget was adopted
for stakeholders’ consultations on the 25 March 2024
In order to manage the drafting of the IDP outputs effectively, Makhuduthamaga Local
Municipality institutionalized the participation process thereby giving affected parties access to
contribute to the decision making process. The following structures, linked to the internal
organizational arrangements have therefore been established:
• The IDP Steering committee which is chaired by the Head of Budget and Treasury and
is composed as follows: Head of Economic Development and Planning, Senior
Managers (Infrastructure Development, Corporate and Shared Services, Community
Services, Economic Development and Planning and CFO), Divisional Managers (Budget
and reporting and IDP) and Senior IDP Officer/IDP Officer
• IDP Representative Forum which is chaired by the Mayor and composed of the following
stakeholders: Councilors, Ward committees, CDWs, Traditional leaders, organized
business, Women’s organizations, Youth movements, People with Disabilities, Advocacy
Agents of unorganized groups, Sector departments, District municipality, Parastatals,
NGOs and CBOs.
34
Section 21 of the Municipal Finance Management Act no 56 of 2003 also provides the following:
(1) (b) at least 10 months before the start of the budget year, table in the municipal council a
time schedule outlining key deadlines for the preparation, tabling and approval of the annual
budget;
The roles and responsibilities of the various spheres of government and other relevant
stakeholders for IDP review process are as follow:
o The role of the National Sphere of Government is to provide a legal framework, policy
guidelines and principles for sectoral, provincial and local government planning.
o The role of the Provincial Sphere of Government is to monitor the IDP process and to
ensure vertical / sector alignment;
o District Municipality is also responsible to effect horizontal and vertical alignment of the
IDP’s of local municipalities,
o The role of the Local Municipalities is to compile a 5 year IDP aligned with other spheres
of government.
Chapter 4 of the Municipal Systems Act, 2000 section 17(2) stipulates that a municipality must
establish appropriate mechanisms, processes and procedures to enable the local community to
participate in the affairs of the municipality. Four major functions can be aligned with the public
participation process namely:
o Needs identification;
o Endorsement of appropriateness solutions;
o Community ownership and buy-in; and
o Empowerment.
35
• Municipal website
Municipal website will also be utilized to communicate and inform community. Copies of
IDP/Budget will be placed on the website for people and other stakeholders to view or
download.
Procedures for participation
The following procedures for participation were utilized:
o IDP Representative Forum (IDP Rep Forum)
The forum consists of members representing all stakeholders in the municipality. Efforts will be
made to bring additional organizations into the IDP Rep Forum and ensure their continued
participation throughout the process.
o The IDP Representative forum is the structure which institutionalizes and guarantees
representative participation in the IDP process.
04 April 2024 Schoonoord and Jane Furse 10h00 Peter Nchabeleng Makhuduthamaga
Clusters Sports Centre
05 April 2024 Masemola and Phokoane Clusters 10h00 Mogaladi Community Makhuduthamaga
Hall
05 April 2024 Special Focus Groups 10h00 Kgaola Mafiri Hall Makhuduthamaga
36
Distribution of roles and responsibilities of stakeholders in the IDP scenario
Municipal Manager • Oversee the whole IDP process and to take responsibility
therefore.
IDP Representative Forum • Represent interests of their constituents in the IDP process. -
Provide organizational mechanism for discussion, negotiation
and decisionmaking between the stakeholders. - Ensure
communication between Stakeholder representatives including
municipal government - Monitor the performance of the planning
and implementing process
Other Sector Departments • Contribute technical knowledge, ideas and sector expertise to
the formulation of municipal strategies, projects and sector
plans
• Actively participate in the various Task teams established for
IDP process
• Provide departmental operational and capital budgetary
information
37
• Issue Integrated Development Planning Guidelines
• Provide financial assistance
• Provide a National Training Framework
IGR Structures (IDP Rep • Provide inter-governmental dialogue to agree on shared
Forum, IDP Managers priorities and interventions
forum,PDPF,DDPF • Provide dialogue between sectors for holistic infrastructure
development
Community Development • Help in the generation of the required data, thereby providing
Workers requisite support to Ward committees
The 2024/2025 IDP Review and Budget process plan / time schedule was prepared in terms of
Section 21 (1) (a) and (b) of the Municipal Finance Management Act. No 56 of 2003 which
states the following;
The Mayor of a Municipality must;
(a) Co-ordinate the processes for preparing the annual budget and for reviewing the
municipality’s integrated development plan and budget-related policies to ensure that the tabled
budget and any revisions of the integrated development plan and budget-related policies are
mutually consistent and credible;
(b) At least 10 months before the start of the budget year, table in the municipal council a time
schedule outlining key deadlines for- i. The preparation, tabling and approval of the annual
38
budget; ii. The annual review of- (aa) the integrated development plan in terms of section 34 of
the Municipal Systems Act; and (bb) the budget related policies. iii. the tabling and adoption of
any amendments to the integrated development plan and the budget related policies; and iv.
any consultative processes forming part of the processes referred to in subparagraphs (i),
(ii)and (iii).
The 2024/2025 IDP and Budget preparation time schedule articulates the progressive activities
and processes which the municipality will embarked on to review its fourth-generation Integrated
Development Plan and to prepare the annual budget for the 2024/2025 financial-year. The
process plan/time schedule enhances integration and alignment between the IDP and Budget,
thereby ensuring the development of an IDP-based budget. It fulfils the role of a business plan
or an operational framework for the IDP review process outlining the manner in which the review
process will be undertaken. The IDP and Budget process plan/time schedule incorporates all
municipal planning, budgeting, performance management, performance reporting and public
and stakeholder engagement processes.
The process creates its own dynamics since it encompasses the involvement of external role
players; therefore, it requires accurate logistical planning and arrangements of engagement
sessions to ensure that the process is implemented in accordance with the time schedule
Annual revision of the IDP/Budget
According to Section 34 of the Municipal Systems Act, a municipal council;(a) must review its
integrated development plan- (i) annually in accordance with an assessment of its performance
measurements in terms of section 41; and (ii) to the extent that changing circumstances so
demand; and (b) may amend its integrated development plan in accordance with a prescribed
process.
The IDP must be reviewed annually in order to:
o Ensure its relevance as the municipality’s strategic plan;
o Inform other components of the municipal business process including institutional and
financial planning and budgeting; and
o Inform the cyclical inter-governmental planning and budgeting cycle.
For the IDP to remain relevant the municipality must assess implementation of performance and
the achievement of its targets and strategic objectives. In the light of this assessment the IDP is
reviewed to reflect the impact of successes as well as corrective measures to address
challenges. The IDP is also reviewed in the light of changing internal and external
circumstances that impact on the priority issues, outcomes and outputs of the IDP. The annual
39
review must inform the municipality’s financial and institutional planning and most importantly,
the drafting of the annual budget.
The purpose of the annual review is therefore to;
• reflect and report on progress made with respect to the strategy in the 5-year IDP;
• make adjustments to the strategy if necessitated by changing internal and external
circumstances that impact on the appropriateness of the IDP;
• determine annual targets and activities for the next financial year in line with the 5-year
strategy; and
• Inform the municipality’s financial and institutional planning and most importantly, the
drafting of the annual budget.
What the review is not
It is important to note that the Review is not a replacement or amendment of the 5-year IDP.
The Review is not meant to interfere with the 5-year strategic orientation of the municipality and
development horizon set in the mother document. Throughout the 5-year cycle any version of
the IDP Review should always be read in conjunction with the approved 5-year IDP document
Below is the Adopted Schedule for the review of IDP/Budget for the 2024-2025 f/y
PREPARATORY PHASE
ANALYSIS PHASE
40
September 2023 o Council determines strategic objectives for service September
delivery through IDP review processes and the 2023
development of the next 3-year budget (including
review of sector department plan)
o Consult provincial and national sector departments
on sector specific programmes for alignment
(libraries, schools, clinics, water, electricity, roads,
sanitation, etc.)
o Finalise ward based data compilation for
verification in December (IDP Rep forum)
STRATEGIES PHASE
October 2023 o Quarterly (1st) review of the 2023-2024 budget, October 2023
related policies, amendments (if necessary), any
related process
o Begin preliminary preparations on proposed budget
for 2024-2025 financial year
o 1st Quarter Performance Lekgotla (2023-2024)
o Submission of 2023-2024 1st quarter performance
report to council
o mSCOA Steering Committee meeting
Month Activity Target date
PROJECTS PHASE
November 2023 o Confirm IDP Projects with District and Sector November 2023
departments
o Review and effect changes on the initial IDP draft
Month Activity Target date
INTEGRATION PHASE
December 2023 o Review budget performance and prepare for 2023- December 2023
2024 budget adjustment
o Consolidated Analysis Phase in Place
o IDP/Budget Steering committee
o IDP Representative Forum
o Update Council Structures on updated data
o mSCOA Steering Committee meeting
January 2024 o Table Draft 2022-2023 Annual Report to Council January 2024
o Submit Draft Annual Report to AG, PT and
Coghsta
o Publish Draft Annual Report in the Municipal
jurisdiction (website etc.)
o Prepare Oversight Report for 2022-2023 financial
year
o Mid-Year Performance Lekgotla
41
o Table Mid-Year Performance assessment report to
council and submit to National Treasury, Provincial
Treasury, Coghsta and Mayor
o IDP/Budget Steering committee
o Strategic Planning Session (Review of IDP/Budget,
related policies)
Month Activity Target date
February 2024 o Table 2023-2024 Budget Adjustment (if necessary) February 2024
o Download of the latest mSCOA template
o Capturing the IDP projects and Budget figures onto
the Municipal Planning and Budget Module(MPBM)
and approved to the Financial System.
o Uploading of mSCOA data strings for the
Adjustment budget onto the National Treasury’s
GoMuni portal.
o Submission of Draft IDP/Budget for 2024-2025 to
Management, relevant stakeholders and structures
o Table adjusted SDBIP
o Conduct Mid-Year Performance assessment for
Municipal Manager and all Senior Managers for
2023-2024 financial Year.
o Submit and Present Mid-Year performance
assessment report and adjustment budget to
Provincial Treasury.
o mSCOA Steering Committee meeting
March 2024 o Council considers the 2024-2025 Draft IDP/Budget March 2024
/SDBIP
o Adoption of Oversight Report for 2022-2023
APPROVAL PHASE
April 2024 o Publish the 2024-2025 IDP/Budget for public April 2024
comments.
o Submit 2024-2025 Draft IDP/Budget to the National
Treasury, Provincial Treasury, Coghsta and SDM
in both printed and electronic formats
o Community consultation and with key stakeholders
o Strategic Risk Assessment for 2023-2024
o 3rd Quarter Performance Lekgotla (2023-2024)
o Submission of 3rd quarter performance report to
council
o mSCOA Steering Committee meeting
May 2024 o IDP/Budget steering committee meeting May 2024
o Submission of Draft IDP/Budget for 2024-2025 with
incorporated comments from stakeholders
’consultation to council for approval
o Download of the latest mSCOA template
o Capturing the IDP projects and Budget figures onto
the Municipal Planning and Budget Module(MPBM)
and approved to the Financial System.
42
o Uploading of mSCOA data strings for the Adopted
budget onto the National Treasury’s GoMuni portal.
o Submit final annual procurement plan to Mayor,
Provincial Treasury and National Treasury.
o Table Municipal policies and By-Laws to council for
approval.
o Prepare SDBIP for 2024-2025
o Prepare operational Risk assessment for 2024-
2025
June 2024 o Publish the approved 2024-2025 IDP/Budget June 2024
o Submission of the SDBIP to the Mayor for
approval.
o Develop Performance Agreements (Performance
Plans) of MM and Senior Managers for 2024-2025
Performance year
o Submission of approved IDP/Budget and SDBIP to
MEC for Coghsta / National and Provincial
Treasury and to SDM
o mSCOA Steering Committee meeting
The review process for the development of this IDP was conducted as follows:
o Council approval of the review process plan was done on 30th May 2023
o Ward to Ward data base collection / analysis phase review from 02nd August to 06th
December 2023
o Status quo report for 2024/2025 served in the IDP Representative forum on the 06th
December 2023
o Status quo report for 2024/2025 served in the IDP/Budget Steering Committee meeting
on the 29th January 2024
o District IDP engagement session whereby sector departments presented strategies and
draft projects for 2024 financial year from 08th to 09th February 2024
o Municipal Strategic Planning Session held from the 19th to 21st February 2024
o Draft 2024/2025 IDP/Budget was adopted for stakeholders’ consultations on the 25th
March 2024
43
Implementation of the IDP
The IDP drives the strategic development of Makhuduthamaga Municipality. The Municipality’s
budget is influenced by the strategic objectives identified in the IDP. The Service Delivery and
Budget Implementation Plan (SDBIP) ensure that the municipality implements programmes and
projects based on the IDP targets and associated targets. The performance of the municipality
is reported in its annual report. In addition to the above, Risk management forms an integral part
of the internal processes of a municipality. It is a systematic process to identify, evaluate, and
address risks on a continuous basis before such risks can impact negatively on the service
delivery capacity of the Makhuduthamaga Municipality. When properly implemented, risk
management provides reasonable assurance that the institution will be successful in achieving
its goals and objectives
MLM engaged in an intensive community consultation that was done at ward level in line with
the Community Based Planning approach (02.08.2023-06.12.2023). The municipality employed
the community based planning approach to stimulate participatory governance by awarding
community members a fair opportunity to deliberate on issues affecting them in their respective
wards.
Furthermore, this approach was implemented to inevitably include the local community in
decision making, planning and generally allowing them to play an active part in their own
development
44
o Electricity post connections (100)
o Transformer not in good order (always trapping)
o Skip bins (6)
o Mast lights (4)
o Secondary school for the new village
o Paving of our internal streets
o Building of library
o Education –TVET college needed
o Livestock dam
o Illegal dumping of waste
o Bridge at Ga-Masango
o Clinic
2 1.Phokoane and Toishi o Tarring of roads: Phokoane clinic to Maloka road, Piekie’s
corner to Leshalabe Primary school, Toishi to Greenside
road, Toishi to Dihlwadieme cemetery, Lekhehla to
45
Leshalabe school, Moshate to Tribal Office, Toishi to
Mabintane
o Education: allocation of bursaries, training and
Learnerships on SMMEs, technical college, multipurpose
centre
o 05 High mast lights (Ga Mashifane, Toishi, Dutch church,
Seven, Mshongo)
o 01 Sports complex
o 01 Old age centre
o CWP and EPWP provision (55)
o Funding of SMMEs (08)
o Regravelling of internal streets
o Grading of sports ground (05)-Tholesen, Slavery, Young
Birds, Juventus and Razors)
o Electricity post connections (404)
o No Water provision
o Skip bin (3)-Toishi, Ka Seven, Mmakgape
o RDP houses (1000)
o VIP toilets (714)
46
o Mast lights (02)-Renten sports ground, Mogudi Garden)
o Sports complex
o No Water provision
o Drilling of boreholes (03) and tanks provision (Jojo tanks
03)
o Recreational Park
o Electricity post connections (115)
o CWPs and EPWP provision (30)
o SMMEs support with funding and training
o Regravelling and blading of internal streets
o VIP toilets in the new stands (195)
o RDP houses (462)
47
o Water infrastructure needed
o Mobile clinic needed
o RDP houses (51)
o Skip bins at Motorsgate Makoshala and spares
o Skip bins at Thotoaneng and Petloane
o Stromwater at Lehwelere school to Makoshala cemetery
o Skip bin between Makoshala corner cemetery and Mogudi
o Stormwater from Thotoaneng to Nebo Police Station
o Waste collections (household)
o Incomplete fencing of cemetery
o Regravelling and blading of roads
o VIP toilets (10)
48
o VIP toilets (05)
6.Phatametsane o Tarring of main road from Doctor Ebrahim main road via
Lekwankwa at Phatametsane school to main road ZCC
church
o Tarring of main road library to nebo phokoane police
station road and stadium
o Storm water drainage corner Phatametsane school to
Boipusho Dam
o Phatametsane bridge between Lekwankwa and
Phatametsane school
o RDP houses (55)
o Tarring of main road- Phatametsane corner via ZCC to
main road to Phokoane tribal office
o Need of two (2) bridges between Phatametsane and tribal
office and Boipusho dam to assist learners to school
o Electricity post connections (07)
49
7.Masioneng /Skotiphola o Tarring of St Engenase Church main road
o Tarring of road from Masioneng to Skotiphola main road to
Skotiphola access bridge
o Storm water drainage on main street of Skotiphola
o Storm water drainage on Skotiphola Roman Catholic
Church
o RDP houses (06+04)
o Tarring of road from Masioneng to Skotiphola main road to
Skotiphola access bridge to Malatji via Dr Mohlala main
road
o VIP toilets (09)
o Electricity post connections (09)
50
o Water provision Phase 2
o Electricity post connection (1200)
o Sports ground
o Paving of road to cemetery
o Paving of internal streets
o Toilets in cemeteries
4.Vierfontein E o Electricity
(Mashemong section) o Water reticulation
o Street paving
o RDP
o Toilets
51
o Mobile clinic
o Mast lights
o Fencing of cemetery
o Community Hall
o Electricity post connections (04)
52
2.Patantshoane B o Sports facility
o Community hall
o Fencing of graveyard at Mabalane
o Bridge between Patantshwane A and B next to Maretele
Secondary school
o Tarring of road from Patantshwane A to Rietfontein (phase
3 of Rietfontein to Eensaam road)
o Bridge at Patantshwane old road to Rietfontein
o RDP houses (59)
o Streets paving
o Pedestrians bridge at Sekhukhuseng
o Electricity post connection(20)
53
6.Ga-Mmaboki o Tarring of road from the main road to Mahlaba secondary
o Fencing of graveyard
o VIP toilets
o RDP houses (15)
o Electricity post connection
7 1.Thoto o Clinic
o Tarring of road from main road to Thoto Tribal Office
o Phase two (2) water reticulation
o Tarring of road from Glen Cowie via Malaka to Thoto
o Community service centre
o RDP houses (110)
o Fencing of cemetery
o Seopo School be demolished
o Electricity post connection (50)
o VIP toilets (720)
54
o Extension of water pipeline and erection of reservoir
o Electricity post connections (13)
o VIP toilets (60)
55
o Tarring of road from main road to Setebong Tribal Office
o Maintenance of Setebong road
o Skip bin
o RDP houses (70)
o Electricity post connection (30)
56
o VIP toilets (784)
o Wifi connection
57
o Waste collection
58
5.Mpumalanga o Water reticulation
o Paving of road to cemetery
o Electricity post connections (78)
o Toilets in the cemetery
o Clinic
o RDP houses (13)
o Community hall
o Street lights
o Mast lights
o Sports facilitieis
o Paypoint
o VIP toilets (1986)
o Regravelling of road from water plant to Photo
59
4.Ngwanamatlang o Water supply
o Access roads need maintenance
o Electricity post connection (09)
o VIP toilets (1857)
o 3 bridges (pedestrians) link Ngwanamatlang and
Mahlomola
o High mast light next to ZCC Mahlomola
60
7.Lehwelereng o No water at all
o VIP toilets (1200)
o Mast lights (04)
o Electricity post connection (30)
o Fencing of Lehwelereng cemetery
o RDP houses (15)
o CWP and EPWP work opportunities for youth
o Waste management program
61
12 1.Moretsele o Water-the whole village and extension (illegal connections
and tampering with stand pipes or transformers)
o Roads- tarring of road from Kgagara bricks to Moshate
o Electricity post connection - Leruleng New stands (1080)
phase 2 and 3
o Tribal Office –Ga- Moretsele
o Clinic-at Ga-Moretsele
o RDP houses (30)
o VIP toilets (1080) phase 2 and 3
o Fencing of cemetery
o Shortage of water
o Additional classes at Moretsele Primary
o Bridge at Leruleng Phase 1,2 and 3
62
5.Senamela o Bridge- from Moshate to Ga-Magaba
o Roads tarring from Moshate to Ga-Magaba
o Tribal Office at Senamela
o Mobile clinic
o Community hall
o Skip bins
o VIP toilets (03)
3.Mogashoa o Bridge
Dithlakaneng o VIP Toilets (694)
o RDP houses (200)
o Capion wall next to St Engenase ZCC
o Shortage of water
o Electricity post connections(28)
4.Phase Four o Tarring of road and storm water control from Mnisi Cross
to Mountain view
o Electricity post connection (39)
o Secondary school needed
o RDP houses (48) and incomplete (10)
o VIP toilets (2129)
o Shortage of water- a borehole needed
o Regravelling of Samabethela via Malapela to Sehlatsi
roads
63
5.Mabonyane o RDP houses (38) and incomplete (17)
o VIP Toilets (496)
o Two bridges needed
o Shortage of water
o Electricity post connection (07)
64
o Additional water taps at Matulwaneng B
o Bridges needed (link bridge between Maloma village and
Dingwane)
o Additional classrooms at Makatane High School
o Sports facilities
o VIP toilets
o Funding of SMME and Cooperatives
o Mast lights
o Tarring of road from Maloma cemetery to Kgopane
Primary school
65
o EPWP opportunities
66
o Tarring of road D4230 from Hoepakrans via Mohlake and
Mohlakaneng is needed
o Urgent Mantenance and upgrading of D4230 from
Hoepakrans via Mohlake and Mohlakaneng
o Road to cemetery (25)
o VIP toilets
o Poor network coverage
o Regravelling of Access road to Tswele
o RDP houses (Mohlakaneng 02, Tswele 08)
o Mast lights
o Skip bins
o Paypoints be reinstated
o Tourism sites be taken care of
67
o Fencing of cemetery
o RDP houses (70)
o VIP toilets (05)
o ECD building
o Fencing of wetlands (02)
o Mast light
o Poor network coverage
o Market for maize, sorghum, beans and etc
o Skip bins
o Leaners transport to Lobamba Combined school
hampered by lack of road
68
o 06 jojo tanks and boreholes equipment and upgrading of
electricity
69
o Electric water pumping machine and 8 jojo tanks
o Incomplete RDP houses (72) and backlog (04)
o Electricity post connections (02)
70
2.Ramphelane o Electricity post connection
o VIP toilets (237 including Kgolane)
o Water supply
o RDP houses
o Access roads
o Mast lights
o Skip bins
o Work opportunities e.g. CWP and EPWP
o Fencing of cemetery and toilets
o Building of a primary school
o Access road from Manganeng main road to Madibong via
clinic
o Community hall
o Community library
o Sport complex
71
o Health centre
o Internal Access roads
o VIP toilets (28)
o Fencing of cemetery and toilets
o Mast lights
o Skip bins
o Work opportunities e.g. CWP and EPWP
o Building of crèches :Dihobolong and Sepeke crèches
18 1.Jane Furse RDP o Access road from Jane Furse Comprehensive School to
Jane Furse RDP
o Maintenance of mast lights
o RDP Primary School (Emis no 996606203) as approved in
2010
o Regravelling of Gwede Mantashe road
o Regravelling of internal roads
o Maintenance of sewerage system
o Issuing of title deeds
o RDP cemetery
o Mobile clinic
o Development of RDP recreational park
o Upgrading of water treatment plant
o RDP houses to cover those who occupied other people
houses (2000)
72
3.Dicheoung o Kgapamadi bridge that links Moraba, Moretsele and
Dichoeung village with clinic, Matsebong High and Eskom
sub station
o Moletsi bridge that link Dichoeung village with clinic,
Matsebong High
o Maintenance of mast lights at Jane Furse taxi rank
o Access road from Bafedi Primary to Eskom substation
o Access road from Mohloba Driving School to join Bafedi to
Jane Furse Eskom Sub-station
o Tarring of road from Rakgoadi Bakery to new Municipal
Offices (Kgaola Mafiri Municipal Offices)
o Access roads be paved or tarred
o Water crisis in portions of all zones
o Mast lights
o Fencing of cemeteries (02 existing and 01 new)
o Tarring of road to the cemetery
o RDP houses needed (798)
o VIP toilets
o Community hall
o Road from Bogopa shop to old Ratseke shop be tarred
o Electricity post connection (295)
73
o Sekhutlong section: Water, electricity post connection,
access roads, RDP houses (05) and skip
o Maswiolong section: water, access roads, mast lights,
RDP houses (20) VIP toilets (06), electricity post
connections (12) and skip
o Tarring of road from Maswielong to Mokwale café
o Tarring of road from Magaseng section to Malaeneng
o Tarring of road from Maswielong section to Kgoloko High
School
o Tarring of road from Tsogang Marota Creche to
Malaeneng Section
74
o Mast lights (02)- Mampuru Tuckshop and Sebaka shop
o Skip bins (01) Sebaka shop
o EPWP &CWP work opportunities (farming in general)
o Fencing of cemetery at Manyeleti
o Tarring of roads from R579 to cemetery (Seraki shop to
Manyeleti cemetery, Malapela shop to Manyeleti)
o Tarring of road from CJC church to Moshate (Rantho)
o Rantho and Magolaneng Multi-purpose centre
75
21 1.Mamone- Matsoke o High mast lights
o VIP toilets (93)
o Electricity post connection (03)
o RDP houses (24)
o Skip bin
o Stromwater drainage control between Matsoke graveyard
passing Tenyane High School and Motlokwe Primary
School
o Extension of pipelines and community water taps
o Fencing of Matsoke graveyard
o Work opportunities e.g CWP and EPWP
o Access bridge between Matsoke to Ntswelemotse
o FBE (334)
76
4.Mamone –A3 (Ga- o Water supply
Manyaka) o VIP toilets (1318)
o Internal roads maintenance
o Electricity post connection (95)
o RDP houses (128)
o Work opportunities
o Clinic /mobile
o Fencing of Kgomogoroga graveyard
o Build water reservoir next to steel tank
o Waste collection
o FBE (448)
77
o Fencing of cemetery
78
6.Madibaneng o RDP houses (300)
(Matolokwaneng) o Electricity post connection (375)
o Bridge – Matolokwaneng to Madibaneng
o Secondary school
o VIP toilets (500)
o Clinic (helath centre)
o Tarring/paving of road from Matolokwaneng to Lehlabile
o Water reticulation
o EPWP work opportunities
o Mast light
o Community hall
o EPWP work opportunities
o Fencing of cemetery
o Reservouir
o Skip bins
23 1.Maila Segolo o Access Road from Maila Segolo via Dinotji to Mathibeng
be tarrred
o Clinic
o Renovation of Maila Primary and Mphele Secondary
School
o RDP houses (130)
o Fencing of cemetery
o High mast light at taxi rank/Dinotji cross
o Water pump machine with enough capacity and reservoir
79
o Renewal of tribal office
o Sports facilities e.g. tennis court
o Community hall
o ECD building
o Skip Bins
o Electricity post connection new stands (500)
o Access road to Sebitlole village
o Bridge from Maila to Dinotji be improved
o Shortage of water due to illegal connections
o VIP toilets (300)
o Education: multi-purpose centre community library
o Acknowledgement of heritage sites
o Storm water drainage at Taxi rank
o Disabled and Drop centre
o Livestock dam at Leseleseleng site
o Funding of SMME and corporatives
80
o Crush pen
o Animal water catchment dam
o Pensioners pay-point
o VIP toilets (200)
o Windmill operated borehole
o High mast lights
o Water reticulation to new stands
o Electricity post connection (80)
o Clinic
o Access road to Sebitlole
o RDP houses (70)
o New water reservoir
o Community hall
o Work opportunities e.g. EPWP
o Recreational facilities
o Illegal connection from main pipeline
81
o Boreholes with enough water to supply nearby villages
that lacks water
o A bridge on the road to Mpilo Secondary School
o Regraveling of Marulaneng main street (starts from
Matsepane to Monoge)
82
7.Madibong o Water reticulation to new stands
(Mokgwatsane Section) o Electricity post connections for new stands (210)
o Access roads
o Mast light
o RDP houses (61)
o VIP toilets (50)
o Jojo tanks (04)
o Skip bins
83
3.Masehlaneng o Roofing of community hall
o Water supply
o Fencing of cemetery
o Electricity post connections
o RDP houses (25)
o VIP toilets (300)
o Mobile clinic
o Tarring of road from Masehlaneng to Vlaka
o Skip bin
o Mast lights
o EPWP opportunities
84
6.Porome o Electricity post connection (30)
o VIP toilets (60)
o Mast lights
o Regravelling of road from main road to the river and
primary school
o Work opportunities e.g EPWP and CWP
o Food parcels
o FBE
o RDP houses (10)
85
o Water to households in all villages
o VIP toilets
o Regravelling of Kgari road
o Community hall
o Drilling of new borehole
o Small bridge between Legabeng and Ntopi
o Kgari bridge is needed to join new stands to Marei
86
5.Ga Selepe o VIP toilets
o Water supply
o Road from Mamone via Selepe all the way to Talane need
tar
o ECD centre
o Sports complex
o Community hall
o Road from Selepe to Mashabela need tarring
o RDP houses
o Electrification of borehole
o Tarring of road from Selepe to Mamone
87
9.Magabaneng o Community hall
o Extension of pipes to Modipadi new stands and
Maretlwaneng
o New reservoiur is needed to subside the current one
o VIP toilets (400)
88
o Fencing og cattle and goats dip
89
o RDP houses (68)
o Road from Moshidi Bottle store to Moshate needs
regravelling
o Grading and regravelling of internal roads
o VIP toilets
o Electricity post connection at Mandela section
o Relieve communal water tanks
o Network tower
o Skip bins
o Speedhumps from Makataneng to Apel cross
o Sports complex
90
o Tarring of road from Marutleng to Mohloding
o Bridge from Marutleng to Maripana
o Legalise illegal connections
o Regravelling of internal roads
o Fencing of new cemetery
o 06 Skip bins (Moshate, Mohloding and Manare)
o Building of new classrooms at Mahwetse Secondary
o Construction of additional reservoiur at Thabeng storage
plant
91
o Three small bridges at Tswetleng
o Electrification of borehole
92
o RDP houses (30)
o VIP toilets (38)
93
o Irrigation scheme funding
o Water reticulation in Malope new stands
o Electricity post connection in new stands
o Street blading
o Tarring of internal road Malope station via Primary school
to main road
o Mast lights (03)
94
o Sushu Primary School need new building
o Electricity post connections (13)
o VIP toilets (40)
o Water drainage system (storm water drainage)
o Mast lights (02)
o Skip bin needed
95
9.Makgwabe o Electricity post connections (41)
o Shortage of water
o Clinic
o RDP houses (47)
o Fencing of camp
o Maphadime High School need new building
o VIP toilets (350)
o Fencing of cemetery
o Steel tanks for water storage
o Mast lights (03)
96
o Electricity post connections (02)
o VIP toilets (01)
97
o Incomplete RDP houses (02)
98
o Small bridge from Mapurunyane (Lebesane
bridge)between Motoaneng and Masakeng
99
o Tarring of road from Mampane Tribal Office to Sehuswane
T junction
o Work opportunities e.g. CWP and EPWP
o Regravelling of internal roads
o Livestock dam
o Drilling water borehole
100
o Water reticulation at Semahlakole and Sehuswane
o Electricity post connection (20)
101
CHAPTER 3: SITUATIONAL ANALYSIS
3.1 Introduction
This chapter provides a situational analysis of the existing trends and conditions in
Makhuduthamaga Municipality, in accordance with the requirements of the Municipal Systems
Act in developing an IDP.
The Makhuduthamaga Local Municipality is bordered by the Capricorn District in the north, Elias
Motsoaledi Local Municipality in the south, Fetakgomo Tubatse Local Municipality in the east,
and Ephraim Mogale Local Municipality in the west. It accounts for 16% of the district
geographical area and comprises of the central extents of the SDM.
102
Makhuduthamaga Local Municipality registered voters per wards as at 23 February 2024
94703001 05 4 033
94703002 05 4 233
94703003 05 4 285
94703004 06 4 620
94703005 05 3 987
94703006 08 3 489
94703007 08 3 489
94703008 07 4 791
94703009 05 5 055
94703010 07 3 771
94703011 06 4 519
94703012 06 4 586
94703013 04 4 410
94703014 05 4 216
94703015 09 3 589
94703016 06 4 562
94703017 06 3 820
94703018 05 4 107
94703019 06 4 943
94703020 06 3 483
94703021 05 3 794
94703022 06 4 372
94703023 08 3 864
103
94703024 08 4 100
94703025 08 4 160
94703026 07 3 904
94703027 05 3 667
94703028 08 4 090
94703029 07 3 724
94703030 07 3 617
94703031 08 3 674
MLM Registered Voters Demographic by Age Group and Gender as at 23 February 2024
104
80+ Male 1 533 1%
Makhuduthamaga: Literally means “executives”, this was a term used to denote members of the
Fetakgomo movement in the 1950s.
105
Makhuduthamaga Regional Locality Map
106
Makhuduthamaga Local Municipality Geographic Location
According to Census 2022 figures, the MLM has a fairly young population, with 34.7% being
younger than 15 years, 57.3% between 15 and 64 years of age, and only 8% being older than
65. This age spread in the population means that the dependency ratio in the MLM is fairly low,
with 74.4% dependents per 100 economically active people. The area population growth was
274 358 in Census 2011 and increased to 283 956 in the Community Survey 2016 and then
increased to 340 328 in the Census 2022. However, the number of households have increased
from 65 320 households in 2011 to 78 497 households in 2022. This trend is partly due to a
decrease in household size (i.e. it could be a sign of households splitting up, resulting in a
higher number of households despite very low total population growth). The average household
size has increased from 4.2 in 2011 to 4.3 in 2022.A growth in household numbers is significant
for planning purposes as each household has needs such as housing and basic services.
107
Levels of education in the MLM community
Migration
There is significant out-migration of people from Makhuduthamaga to urban areas for reasons,
inter alia: access to better opportunities such as jobs, access to better social amenities and
facilities in urban areas such as higher educational facilities, universities, schools, hospitals
(better health care services), good roads, water etc.
108
45-49 6 535 1.9 9 576 2.8
Male Female
Table: Population growth rates – Census 2011 ,2016 (CS) and Census 2022
109
Employment and unemployment profile for Makhuduthamaga
Employed 14 847
Unemployed 66.7%
R 76 R 153 R 614
R 19 R 38 R 307 R 1 228
R1- R 4801 R 9601 401 - 801 - 001 - R2
No 601 - 201 - 601 - R 801 - R
R -R -R R R R1 457 601
income R R 614 40 2
4800 9600 19 600 153 80 307 60 228 8 or more
38 200 76 400 0 457 600
Wards 0 0 00
1 206 195 387 597 530 189 115 102 50 12 5 2
2 74 109 227 534 499 153 41 25 5 1 0 0
3 226 194 308 637 587 216 208 139 39 9 4 1
4 255 156 386 452 395 102 41 25 6 1 0 0
5 346 128 284 532 480 154 116 69 23 1 1 3
6 204 131 278 489 502 134 36 16 5 0 1 0
7 185 111 206 386 370 69 35 18 13 2 0 0
8 519 264 517 704 624 257 224 143 50 10 6 5
9 477 177 429 495 429 168 163 145 37 12 4 1
10 275 148 322 374 313 82 50 57 19 0 0 1
11 190 68 182 343 356 149 120 78 27 1 2 2
12 192 142 277 542 557 231 61 30 15 1 2 2
13 321 180 451 633 561 229 121 66 19 5 1 1
14 149 87 181 362 389 138 129 60 22 4 5 3
15 190 88 222 367 412 105 36 34 8 1 0 1
16 219 124 245 412 388 129 61 29 13 0 1 0
17 238 166 386 569 552 120 51 38 17 2 5 2
18 528 197 429 630 593 296 197 110 29 11 1 1
19 208 121 310 569 586 151 63 41 12 1 2 2
20 295 143 206 600 610 176 88 52 24 7 0 3
21 281 157 383 558 540 213 175 134 50 12 6 5
22 268 153 229 445 450 119 40 39 7 3 4 3
23 209 254 333 709 675 151 98 38 20 4 2 4
24 316 120 245 574 468 111 45 44 11 0 2 0
25 252 173 347 610 638 145 63 41 7 4 1 0
26 301 118 261 632 526 146 145 123 48 7 2 9
27 316 153 251 554 529 106 78 51 18 2 2 0
28 493 216 423 755 644 142 105 51 21 2 0 1
29 290 170 251 473 365 72 60 29 12 1 2 2
30 314 132 261 525 472 142 70 35 15 1 2 1
31 232 179 212 573 440 106 26 31 11 0 0 1
Source: Census 2011
110
People with Disabilities
There are six categories: seeing, hearing, self-care, communication, walking and remembering
1. Seeing
Cannot yet
Some A lot of Cannot do at
No difficulty Do not know be Grand
difficulty difficulty all
Age determined Total
Group M F M F M F M F M F M F
00 – 04 10925 10892 201 140 35 37 187 170 60 59 7230 6929 36866
05 – 09 16080 16178 355 253 51 38 18 15 4 9 - - 33001
10 – 14 15645 14664 349 299 57 37 18 11 3 2 - - 31085
15 – 19 15855 15284 327 331 36 39 11 5 2 - - - 31890
20 – 24 10476 11684 242 290 41 36 7 14 6 1 - - 22796
25 – 29 6701 9930 174 313 17 26 5 6 1 2 - - 17174
30 – 34 4900 8216 139 303 22 38 9 10 1 1 - - 13639
35 – 39 4216 7422 149 324 21 33 8 12 - 3 - - 12187
40 – 44 3720 6440 197 463 24 50 8 3 2 - - - 10908
45 – 49 3120 5833 296 767 39 89 11 4 1 1 - - 10160
50 – 54 2689 4690 358 850 53 98 10 13 - 6 - - 8767
55 – 59 2553 4338 427 760 58 111 9 6 1 2 - - 8265
60 – 64 2254 4025 422 749 74 95 12 16 - 4 - - 7651
65 – 69 1546 3758 374 870 62 129 17 17 2 2 - - 6777
70 – 74 1554 2461 423 792 90 169 19 27 1 3 - - 5540
75 – 79 727 1586 249 696 68 162 21 29 - 4 - - 3542
80 – 84 471 1237 226 653 67 168 18 44 2 4 - - 2890
85+ 342 1064 205 622 64 235 26 74 2 9 - - 2643
10377
Total
2 129700 5114 9474 881 1589 411 476 90 114 7230 6929 265781
2. Hearing
Cannot yet
Some A lot of Cannot do at
No difficulty Do not know be Grand
difficulty difficulty all
Age determined Total
Group M F M F M F M F M F M F
00 – 04 10749 10742 327 284 73 72 288 225 90 76 7102 6861 36890
05 – 09 16182 16154 285 275 50 41 20 13 6 7 - - 33034
10 – 14 15820 14837 188 173 34 24 17 6 5 2 - - 31108
15 – 19 16009 15393 181 202 22 29 11 10 1 2 - - 31859
20 – 24 10662 11882 115 130 17 23 5 8 - 4 - - 22846
25 – 29 6795 10143 82 117 8 24 3 12 1 1 - - 17188
30 – 34 4981 8433 70 126 13 19 5 6 1 - - - 13653
35 – 39 4295 7639 84 125 18 19 4 5 - 2 - - 12191
40 – 44 3831 6787 87 125 18 22 7 1 1 - - - 10877
45 – 49 3330 6493 87 177 14 27 2 3 - - - - 10133
50 – 54 3000 5392 93 203 15 33 2 10 - 1 - - 8749
55 – 59 2917 4935 106 228 22 37 7 4 - 1 - - 8258
60 – 64 2623 4585 113 273 18 27 2 3 - - - - 7645
111
65 – 69 1858 4319 122 413 19 51 4 5 - - - - 6792
70 – 74 1864 2975 177 392 35 81 10 14 - 3 - - 5550
75 – 79 927 1960 105 399 30 93 5 11 - 1 - - 3531
80 – 84 632 1562 119 421 29 115 3 15 1 1 - - 2898
85+ 467 1306 136 488 39 173 3 27 1 5 - - 2646
Grand 10694
Total 3 135538 2477 4551 474 910 399 377 108 108 7102 6861 265848
3. Self-care
4. Communication
112
40 – 44 3867 6893 33 22 11 12 8 8 3 1 - - 10858
45 – 49 3383 6627 36 32 19 20 6 9 - 1 - - 10134
50 – 54 3056 5553 27 39 13 19 13 7 - - - - 8727
55 – 59 2995 5145 22 44 14 13 4 3 - 1 - - 8241
60 – 64 2700 4802 39 62 7 14 4 3 - - - - 7632
65 – 69 1955 4673 30 77 3 18 3 6 - 1 - - 6766
70 – 74 2028 3291 39 119 10 23 5 16 1 4 - - 5537
75 – 79 1026 2315 31 122 5 17 3 10 - 3 - - 3532
80 – 84 731 1931 34 124 9 41 1 5 - 1 - - 2878
85+ 577 1739 49 198 12 47 3 15 - 6 - - 2646
Grand 10385
Total 9 134388 2895 3339 1215 1251 1450 1444 371 396 7554 7243 265404
5. Walking
6. Remembering / Concentration
113
20 – 24 10676 11946 65 66 38 17 16 16 3 2 - - 22843
25 – 29 6830 10207 59 63 27 29 10 10 3 - - - 17240
30 – 34 4978 8491 48 59 37 28 17 13 2 3 - - 13676
35 – 39 4286 7688 70 70 35 24 12 11 1 2 - - 12200
40 – 44 3841 6843 54 70 23 13 9 14 3 - - - 10871
45 – 49 3357 6538 70 110 28 26 2 5 - 4 - - 10139
50 – 54 3021 5500 60 120 22 31 12 5 - - - - 8771
55 – 59 2952 5040 71 154 20 29 7 10 3 2 - - 8288
60 – 64 2651 4638 87 200 13 35 2 6 2 2 - - 7637
65 – 69 1908 4467 87 247 12 45 3 13 1 2 - - 6784
70 – 74 1941 3100 117 283 22 65 6 12 - 4 - - 5551
75 – 79 963 2082 78 302 18 76 4 16 - 2 - - 3541
80 – 84 669 1661 83 314 27 113 3 22 - 4 - - 2896
85+ 516 1369 95 398 31 185 6 38 1 10 - - 2648
Grand 10026 26637
Total 6 129608 4602 5914 2194 2473 1975 2005 461 482 8335 8060 4
Land ownership is predominantly under the South African Development Trust but under the
custodianship of local traditional authorities. The land under traditional leadership totals 176 393
ha which accounts for 83% of all land in the municipality. The municipality own hectors of land
where Jane Furse and Moji RDP houses were built since 1996.
114
Map showing Traditional authorities land per Municipality in the District
Land use within Makhuduthamaga is characterized by a mixed use of subsistence farming and
residential uses. The land issue is potentially a source of tension in the area. There is a latent
tension between the traditional (tribal council) and modern (legalized) land use management
systems. There is also a number of competing land claims in the area, which have not been
resolved by the Department of Rural Development and Land Reform as yet. Land restitution has
the potential to alter the spatial pattern and to contribute significantly in agriculture development
and job creation. Many people would obtain access to land that could result in improved living
standards and quality of life.
115
The Makhuduthamaga villages are characterized by poor accessibility, low density and large
distances between settlements. This makes it challenging for the municipality to provide the
required infrastructure and basic services. Lack of coordination between the Municipality,
traditional authorities and the provincial Department of Cooperative, Human Settlement and
Traditional Affairs (COGHSTA) has resulted in unplanned residential development taking place
in the area.
Some of the key challenges facing the municipality include, inter alia:
o Uncertainty about the status of land ownership especially with reference to state and
tribal land prohibits future development and investments.
o Unresolved and competing land claims in the area threaten to destabilize future
development.
o Competing land uses (i.e. mining and agriculture, commercial, etc.) may cause spatial,
social, environmental and economic constraints in future.
o Lack of environmental management
o Communal land use management
o Sprawled development
o Lack of adequate water to supply all settlements
116
Map showing the Spatial Perspective of the municipality
Game farms 0
Nature Reserves 0
117
Settlement/Towns 29228
Other 0
Total 209695
The Municipality does not have a Zoning Scheme. A process has been embarked upon to
develop an integrated zoning policy. The first phase will consist of the Jane Furse regeneration
and the development of a zoning mapping system.
118
3.2.3 Growth/ Nodal points and hierarchy of settlement
Settlement Growth
Settlement Settlements Description Development
type
First order Ga-Marishane, Ga- This is the cluster of Growth: The settlements abutting
settlements Masemola, Ga-Moloi, Ga- settlements located the Jane Furse node will come
and housing Phaahla, Ga-Ra-Ntobeng, around the main node of under increased pressure for
focus areas Glen Cowie, Jane Jane Furse. This is one of development with growth direction
Furse,Kopjeng,Malaita,Malet the most accessible areas probably along the D2219, D4828
se,Maserumole,Matlakatle, in the MLM due to its close and D4190.These areas need to be
Mohlarekoma,Mohwelere, location to the R579 and formalised to ensure sustainable
Mokwete,Nebo,Ngwaritsi, three district routes, and growth. Intensification, infill and
Phatametsane,Phokwane, has the largest densification should occur within
Sekwati, Takataka concentration of services the Jane Furse nodal boundary.
and facilities. One of the The growth abutting the R579
main population ought to be managed in terms of
concentrations. Identified the planning for the R579 corridor,
as the municipal growth the Growth focus area and the Apel
point in District planning, Cross and Glen Cowie nodes.
the highest order node in
the MLM Accessibility: Provide public
transport facilities along the D2219,
D4828, and D4190 routes. This
include pedestrian amenities at
stops e.g. shade or shelters,
lighting, sidewalks etc.
119
settlements preferably at or close
to transport facilities. Existing
school sites can also be used to
cluster community facilities. This
clustering will also assist with the
accommodation of markets or
sales points (e.g. pension day
markets) at accessible points.
Second order Ga-Mashegwana, Ga- These areas are clustered Growth: Growth of these
settlements Mogashoa, Manganeng, around the D4226 and settlements will be stable with no
and housing Schoonord,Tsatane D4241 routes. It is served economic activity to drive
infill and by Magnet heights and migration. The economic base is
consolidation Schoonoord services very narrow and the sprawl of
area nodes settlements need to be prohibited
in order to support in fill and
densification as means of creating
economies of scale for the two
service nodes. The escarpment
area to the east should be
protected against further intrusion
of residential development.
120
community facilities. This clustering
will also assist with the
accommodation of markets or
sales points (e.g. pension day
markets)at accessible points
121
The table below identifies the nodal points and hierarchy of settlements
Nodal Points and Hierarchy of Settlements
Classification Function
122
MLM Map showing Growth / Nodal points / Hierarchy of Settlement
123
Land Capability in Makhuduthamaga
Land Capability in Makhuduthamaga is divided into three parts which are shown below
Grains: The area has Irrigation schemes Sorghum is produced in these areas
higher rainfall and is along Oliphant's river which include the low lying areas of
most suitable for rain (though none of them is Schoonoord, Ga Masemola and
fed maize production. operational currently) Diphagane, Phaahla towards Mamone
These includes all the Vegetable crops Ga and Madibong, Moretsele, Makgane.
villages in Leolo and Masemola and around
the villages along the Schoonoord
NEBO maize belt
Source: Department of Agriculture and Rural Development 2023
124
Map showing areas used for Agricultural Purposes within Makhuduthamaga
125
3.2.4 Current land claims in Makhuduthamaga municipal area
A total of 622 565 ha of land is subject to land claims in Sekhukhune.i.e. (1897 claims lodged)
126
127
MLM tenure status and population group of head of household
Other 2983 2 - 1 1
11. Kgarethuthu Ext 1 405 Erven + 9 Parks = 414 October 2006 &June 2007
128
16. Mohlarekoma Ext 500 2015/16-2016/17
Challenge Interventions
129
3.2.6 Environmental analysis
Climate
Biodiversity
Biodiversity describes the variety of life in an area including the number of different species, the
genetic wealth within each species, the interrelationships between them and the natural areas in
which they occur. Sensitive vegetation and watercourses should be maintained for both the
conservation of biodiversity and for their ecological functioning in water quality improvement and
flood control.
130
The Makhuduthamaga Municipality is rich in biodiversity. The region is rich in ultramafic-
induced endemic plant species, which make it a treasure house for biodiversity (e.g. lewang and
protea found in the Leolo mountains).
The role of biodiversity in agricultural and natural ecosystems is to ensure food security and
sustainable agricultural production through direct or indirect provision of food for humans and
their livestock, provision of raw materials and services, such as fiber, fuel and pharmaceuticals
and the maintenance of ecosystem functions. Any agricultural plan must therefore take the
biodiversity of the region into consideration
Topography
The topography of the MLM is defined by a series of ridges and river valleys. The most
prominent ridge is in the eastern part of the area. Villages are mostly located in valley and in the
foothills of ridges. The more even topography of the western part of the area resulted in a
higher settlement density.
Hydrology
Closely related to the topography, the rivers in the MLM run along the valleys between the
ridges. Together with the ridges, the rivers are the main physical feature determining settlement
patterns and access in the area. The Olifants River forms the northern boundary of the MLM.
Various tributaries run from the hills of the MLM towards the Olifants River. The most prominent
are the Grass Valley, Ngwaritsi and Lepellane Rivers. The De Hoop Dam in the Olifants River,
although not located in the MLM, will be a water source to the MLM.
Geology
The soil types include dolomite, limestone, iron formation, shale and quartzite. Various water
sources transverse the municipal area. They flow during rainy seasons and dry out when it does
not rain.
Climate change
Changes in climate patterns are natural phenomena. However, there is increasing concern
about the impact of climate change that has been brought as a result of human activities (such
as burning fossil fuels of energy, use of motor vehicles, etc) Human induced changes in climate
have acknowledge as a current global reality and are the subject of significant global attention.
Global changes in climate have already been observed that are generally consistent with model
projects and are likely to continue to occur for many decades to come even if mitigation efforts
are successful due to lays and inertia in the global biosphere response.
South Africa is a country of extraordinary natural beauty, outdoor lifestyle and activities, warm
weather and diversity in terms of culture and is known as an affordable destination. The broad
range of tourism activities, including ecotourism, cultural sporting activities, historical and
geological attractions and business tourism make it a premier destination for domestic and local
tourism.
131
Climate Change implications
No Sector Implications
• Water borne and communicable diseases (especially bilharzia)
• Vector and Rodent-Borne Diseases
• Increased air pollution
1 Human Health
• Change in grain (maize, wheat & barley) production
• Change in deciduous fruit production
• Change in other crop production areas
• Increased exposure to pests such as eldana, chilo and codling
moth
• Increased risks to livestock (cattle and pigs)
2 Agriculture • Reduced food security Increased heat stress
• Decreased quality of drinking water
• Decreased water quality in ecosystem due to increased
Water concentrations of effluent and salt concentrations
3 • Increased impacts of flooding from litter blocking sewer system
Biodiversity and
4 Environment • Loss of Grasslands
5 Human Settlements • Increased isolation of rural communities and displacement
Pollution
Air pollution in the area emanates from the use of fire wood for energy purpose, burning of
refuses and dust from gravel roads. Water pollution is caused by the cumulative impact of the
insufficient solid waste removal, lack of sanitation infrastructure, sewerage effluent, etc.
132
Water resources
Various water sources transverse the municipal area. They flow during rainy seasons and dry
out when it does not rain. Nonetheless, the area suffers from a water scarcity, which constraints
both economic and social activities. This challenge is further exacerbated by insufficient and
variable rainfall, inequitable water resources management and the absence of drinking water,
and the lack of bulk water and irrigation infrastructure
The Municipality has identified wards and villages that have wetlands that need to be preserved.
133
134
List of wetlands fenced in the past four years
Water scarcity
Water scarcity is a huge developmental challenge within the Sekhukhune
Distric/Makhuduthamaga, and constraints both economic and social activities in the area. The
issue is a manifestation of climate variability. However; it is also the result of a number of other
factors, which include insufficient and variable rainfall, inequitable water resources management
and the absence of drinking water, bulk water and irrigation infrastructure that would aid the
distribution of water to rural villages. Water scarcity affects a range of other developmental
issues in Makhuduthamaga municipal service delivery, subsistence farming activities and
commercial agriculture.
Environmental management
As part of environmental management the MLM has a licensed authorized landfill site, Jane
Furse landfill site. However, livestock management and control is a key problem within
MLM.The is a lack of fences in some crop farming areas and along main roads, which results in
wandering livestock. These livestock damage crops and cause vehicle accidents along
Makhuduthamaga main roads. To worsen the challenge is that some of the communities
destroy or steal fence in areas that was erected. The Municipality has a promulgated Waste
Management By-law. The municipality has also adopted the Integrated Waste Management
Plan (IWMP) in the 2019/20 financial year.
135
Environmental impact management
Challenges Interventions
Environment
Urban greening • The Department of Public Works has launched the concept of Greening
Sekhukhune District. There are also greenery programmes that are
initiated by Dept. Of Agriculture that target governmental issues.
Alien Plant Spices • Depleted water from the water sources. The National Department of
environment is managing the programme of eradication of alien vegetation
in the municipal area.
136
make livestock grazing space smaller. The indigenous plants get slowly
depleted.
Pollution
Air Pollution • Air pollution resulting from the use of fire wood for energy purpose, burning
of refuses and dust from gravel roads are environmental problems.
Water pollution • Water pollution is the result of the calmative impact of the insufficient solid
waste removal, lack of sanitation infrastructure, sewerage effluent etc.
Conservation
Deforestation • There is uncontrolled massive cutting of trees for sale, creating loss of vital
trees and vegetation. This adds to the problem of soil erosion and inability
of remaining poor soil to preserve water. Water simply just runs off. This
worsens the aridity more.
Overharvesting of • Some plants like aloes, dagga and ’lewang” and others are overharvested
medicinal vegetation by people from other areas for medicinal purposes.
Over utilization • Overgrazing resulting from too many livestock units per area of land is a
/overgrazing problem
• One of the major environment problems in the area is incorrect agriculture
methods, which leads to overgrazing, and denuding of trees.
Cultural Heritage • The tourism potential of the Makhuduthamaga Municipality relates directly
to the cultural heritage assets.
Waste • There is formal waste collection at Jane Furse which covers Jane Furse,
Phokoane and Schoonoord. The MLM has one waste recycling centre at
Madibong.
Medical waste • Two hospitals and about 21 clinics are found within the MLM. Currently,
the Local and District Municipality conduct no medical waste collection. No
facility for the management and disposal of medical waste exist. However,
a private company, Buhle Waste Limpopo collects from all health
137
institutions within the Municipality. Private surgeries have private
companies to collect and dispose medical waste
The MLM has installed a Geographic Information System (GIS) located within the Economic
Development Planning Department. Complimentary to the System, the municipality has
developed GIS Policy as a guiding mechanism for the effective running of the system.The policy
was approved in the 2018/19 financila year.The municipality has employed an official during the
2022/2023 financial year.
Integrating with the everyday business database, GIS can represent inter alia;
STRENGTHS • The department has its legal legislations which are approved by
Council such as SPLUM bylaw, Spatial Development Framework,
Building Control Policy, land Use Scheme, LED & Tourism
Strategy(ies) etc
• Committed and competent staff
• Functional JDMPT
• Precinct plans developed to guide development in identified nodes
• Declared as Business Registration & Licensing Centre
• Several strategically located economic hubs/nodes identified and
studied
• Good relationship between MLM and traditional authorities within
its jurisdiction
• Piloting of the Farmers support programme (Eensaam, Leolo )
138
WEAKNESSES • Shortage of staff (Building Control)
• SPLUM Bylaw due for review
• Limited Office Space
• Enforcement of By-laws (Absence of Peace Officers)
• No By- laws to regulate Business Registration & Licensing within
MLM
• No Memorandum of Understanding (MoU) between the
Municipality and the Traditional Authorities on development matters
• Combination of the Town Planning & LED Units
• Misplacement of the IDP unit in the EDP directorate
• Insufficient support to SMMEs
• No Municipal land ownership to attract potential investors.
• No Appeal Authority
139
Spatial challenges within Makhuduthamaga
5.Traditional authorities are the custodians of higher proportion of land within MLM
Due to the lack of human capacity within Sekhukhune District Municipality, an SLA was signed
with Lepelle Northern Water (LNW) for the supply of water from Flag boshielo WTW,
Olifantspoort WTW and to operate Nkadimeng WTW
140
Ground water availability in Makhuduthamaga
Total Utilisable
Annual Available
Local Municipality Groundwater Exploitation
Abstraction (Ml/d) Groundwater (Ml/d)
Potential (Ml/d)
WTW (Water Treatment Works) in the clusters that are currently in operations
NAME CAPACITY
3.3.1.1. Status quo on bulk water supply schemes that supply Makhuduthamaga
141
Flag Boshielo Water Scheme
142
Lnw Plant has
been upgraded
02 Phokwane (Mogudi, Insufficient water Severe Water is
Phatametsane, supply from Flag breakdowns at currently
Boshielo WTW
Mokgeretli, Ga Maloka, Flag Boshielo supplied on an
Ga Boshielo) and WTW rotational basis
Mabintwane
03 Phokwane (Makoshala, Water supply Constant
Mokgapaneng, program not engagement
Mapaing) adhered to with Lepelle
05 Mohlarekoma Rotation takes Northern Water
Six weeks to to improve the
cover all the supply in the
areas. affected
Brooklyn No ground water communities.
08
potential
Source: Infrastructure and Water Services (IWS) Sekhukhune District 2023
143
Malekane to
Janefurse
11 Mokwete, Vergelegen Insufficient water Severe Water is
A, Molepane supply mechanical currently
breakdowns at supplied on an
the WTW rotational basis
18 Dichueung, Moraba, Demand higher Electro-
Vergelegen B, than the supply mechanical
Janefurse RDP section in a
process to
refurbish raw
and clear water
pumps.
19 Vergelegen C, Unauthorized Removal of
Madibong
connections on illegal
the rising main connections
Fast-track the
completion of
Malekane to
Janefurse
Source: Infrastructure and Water Services (IWS) Sekhukhune District 2023
144
Areas receiving water through Tswaing package plant
No of boreholes operational 96
No of vandalised boreholes 7
Borehole
Spring
River /Stream
Water vendor
145
Water tanker
Other
Flag Boshielo dam has been raised by five meters to allow the dam to increase its supply to
communities. Construction of De Hoop dam and erection of bulk water pipe to Jane Furse is
completed and to Lobethal at an advanced stage. The two dams will improve state of water
provision in the municipality and this will boost other development opportunities in the area. The
pipe will supply water to greater parts of Makhuduthamaga which recently experience shortages
of water due to poor water sources. The District is also currently investigating the development
of a Community Water Supplies Master Plan. This will enable the District and its implementing
agents to achieve its WSDP objectives. The intention is also to investigate alternative technical
options for supplying specific areas with water and to ensure coordinated and implementation of
the water supply infrastructure. Early findings of these studies reveal that groundwater is a
major water resource for most households in Sekhukhune and will continue to do so in the
future.
146
Developmental challenges
Challenges Intervention
147
o Robust revenue collection to address
the operational matters.SDM to
transfer repair and maintenance
functions to local municipalities
o Community awareness campaigns
and implementation of bylaws
At the current rate of progress, it will take another four to five years before all households have
access to water within 200 meters.
3.3.2. Sanitation
The Sekhukhune District Municipality is responsible for sanitation provision. Access to sanitation
remains a challenge in Makhuduthamaga. Pit toilets are still the main source of sanitation.
Measures need to be taken in order to reduce the number of pit toilets as they may lead to
ground water pollution whilst many households are relying on it for daily consumption
148
4 Rietfontein VIP toilets needed
149
Brooklyn VIP toilets (784)
150
13 Mashengwaneng VIP toilets (4988)
151
Kotsiri VIP toilets (07)
Kgolane
152
Mamone A3 (Ga Manyaka) VIP toilets (1318)
153
Mashabela (Malegasane) VIP toilets needed
154
Wonderboom VIP toilets (38)
155
Mangwanyane VIP toilets (21)
156
Developmental challenges and interventions
Challenges Interventions
157
implemented during project
implementation and after completion
158
Phatametsane Electricity post connections (11)
159
Setebong Electricity post connections (30)
160
Mokwete Mast lights at Phetla street next to Segafa and
Ledimo homes, Dronkop and Makalaneng Ga
Disegwane and Ga Manong
161
Mabule No challenge nor backlog indicated
162
19 Madibong Mast lights and electricity post
(Malaeneng,Sechabeng,Sekhutlong connections(Malaeneng 160,Sechabeng
and Maswiolong) (06)Sekhutlong (05) and Maswiolong (10)
Mamone A1 Bothas (Ga Mohlala) Electricity post connections (10) and FBE (215)
Mamone A3 (Ga Manyaka) Electricity post connections (95) and FBE (448)
163
Madibaneng (Matolokwaneng) Electricity post connections (375) and mast
light
164
Ga Selepe No challenge nor backlog indicated
165
Ga Maphutha Mast lights,FBE,elewctricity post connections
(04)
Moji /Sekale/Apel cross Electricity post connections (42) and mast lights
(02)
166
Serageng Mast light
167
3.3.3.1. Makhuduthamaga local municipality electricity backlog
Coal 91 0.1%
168
Solar 9 0.0%
Other 18 0.0
None 53 0.1%
Other 49 0.1%
None 92 0.1%
Type Statistics
169
170
Eskom Sekhukhune / Makhuduthamaga Electricity Network Expansion Plan
Eskom has capacity and funding challenges in areas of Makhuduthamaga in particular Leolo
due to nature of the area. As such Eskom was unable to electrify villages of Greater Komane as
previously planned but designs for the area are completed and negotiations on additional
funding with Department of Energy are at advanced stage. There are also minor incidents of
lack of capacity from feeder lines in other areas of Makhuduthamaga and as a result some
areas were taken out of the electrification priority list. But Eskom is working on the matter by
upgrading Jane Furse substation and building 3 new substations (Mamatjekele, Uitkyk &
Tjatane) to provide capacity for growth and electrification. Makhuduthamag will also instal a 24
km of 22KV line from Mamatshekele to Moloi to improve capacity around Phokoane cluster.
171
Below is map by Eskom showing new sub-stations to strengthen capacity in Sekhukhune
/ Makhuduthamaga Municipal area
172
Developmental challenges and interventions
Challenges Interventions
18.34% of the households in MLM have access to refuse removal services from the
municipality. About 72.3% of the households in the area use their own refuse dump. There are
5.5% of the households with no access to rubbish disposal services. The municipality has no
drop-off, garden sites, transfer station, material recovery facilities and buy-back centres for
recycling.
The households without access to refuse removal poses a threat to environmental quality.
Lack of provision of refuse removal services in the rural communities is mainly driven by land
unavailability and inadequate financial resources since there is no cost recovery in these areas.
Kutupu and Extension Skip bins (07+04) and there is illegal dumping
173
Makoshala Skip bin between Makoshala corner cemetery
and Mogudi and households waste collection
needed
174
Malaka Illegal dumps and littering of waste
175
11 Molepane Waste collection program
176
Stocking No challenge nor backlog indicated
Dihlabaneng B
177
20 Tisane Skip bin next to Owen Liquor Restaurant
178
Phaahla No challenge nor backlog indicated
179
Moshate/Mokgopaneng/Maripane Skip bins ( Moshate,Mohloding,Manare)
180
Serageng littering of waste
Kutupu/Mabintane road 01
Phokoane library 01
Nebo SAPS
181
Vleischboom borrow pit 02
05 Maserumule park 01
Mohlarekoma 01
Nebo Magistrate 01
St Ritas Hospital 01
Brooklyn 01
09 Riverside 02
10 Mogorwane 01
Ga Moloi 01
11 Mokwete 01
Vergelegen A 01
13 Mogashoa T-Juntion 01
Sekhukhune SAPS 01
17 Manganeng (Sunrise) 01
182
Jane Furse RDP 04
Mathomomayo business 01
Chicken Licken 01
Home Affairs 01
Rakgoadi Bakery 01
20 Mamone super 01
25 Mphanama Cross 01
Masemola Pshiring 01
Masemola SAPS 01
29 Apel Cross 01
Malope 01
183
Table: Refuse disposal for Households within MLM
MLM Jane Fuse RDP oxidation ponds Not licensed Poorly managed
Jane Furse Old Hospital Oxidation ponds Not licensed Poorly managed
Jane Furse New Hospital Oxidation ponds Not licensed Poorly managed
184
185
Absolute Access
Disposal Permitted Operation Security Equip Cover Compacti Comments
Location
site /Not al hours availability ment material on
Permitted
1. Leolo( Office 318 of cardboard • Not licensed but has • Need to provide
Suppliers & Services registered as a storage area
cc. business entity • Need to report
• Operate within Jane quantities monthly to
169 of glass bottle Furse landfill site the Department
• No storage facilities
• Not reporting to the
Department
2. Mmashadi Recycling 1.2 of cans • Not licensed but has • Availability of electricity
trading as Jane Furse registered as a • Need to report
Recycling business entity quantities monthly to
8.9 of cardboard • Operate within Jane the Department
Furse landfill site
• Storage area
available
• Operational
equipment available
although not in use
due to non-
availability of
electricity
186
• Not reporting to the
Department
187
Refuse Removal / Waste Management Challenges and interventions
CHALLENGES INTERVENTIONS
o No cost recovery o Enhance revenue collection to households
o Provision of waste minimization facilities that receives weekly refuse removal
o Provision of new disposal sites and services. Billing waste disposal services at
transfer stations the landfill site. Flat rate billing to be
o Illegal disposal of waste e.g disposal introduced where we are collecting
nappies along rivers and roads o Establish a buy back centre
o Two new sites identified for the development
of landfill site and a transfer station
o Awareness on waste
management.Enforcement of bylaws
Ka-Mabule Only 3.6 Unpaved The only access to this village, currently
access inaccessible with a normal vehicle. Needs
immediate action
Malegase Only 3.5 Paved Roads connects on the provincial road R579, the
access road will link villages from Malegase to Mapulane
Ga-Sekele Only 3.5 Unpaved Roads connects on the provincial road R579, the
access road will link villages from Malegase to Mapulane
Emkhondweni District 3 Unpaved This road has been earmarked for upgrade by the
provincial government but it is deemed that more
immediate action is required.
188
Ga-Mokgoadi District 2.5 Unpaved Further down the road from Ga-Sekele. Situation is
the same as for the previous village.
Geluk District 4.3 Unpaved The furthest away from Schoonoord so it must be
handled after the previous two villages. Action is
required very soon though.
Sekele Only 4.3 Unpaved The road has been constructed and for the most
access part is still in very good condition, but some areas
have become eroded and almost impassable with a
normal vehicle. Also provides access to two other
villages.
Hoepakrantz Only 3.4 Unpaved Next in line from Geluk. Road situation is the same
access however and it is the only access to Hoeperkranzt
Kanaan A Only 3.3 Unpaved Last village in this road. The road is worse for this
access last section and need immediate action.
Tsopaneng Only 0.6 Paved The current road is very small and needs to be
access upgraded. Only serves a small number of the
population though.
Sopeyana District 3.5 Unpaved This is a district road but is currently not earmarked
by the provincial or district government for
upgrading even though it needs to be upgraded
urgently.
Malaka B, District 7.6 Unpaved Gets access through Tsopaneng. Some very steep
Manthenyane, areas that needs immediate attention and
Botshabelo, upgrading. Also a district road.
Ntwane
Pitsaneng District 10.3 Unpaved This is a provincial road with these villages
scattered along it. This road has not been
earmarked by any of the other authorities but it
needs action soon as it is impassable in some
places.
Maseleseleng Only 2.3 Unpaved For the most part this road is adequate for the
access amount of traffic, but some boulders are exposed
and some bad areas are present at the start of the
road.
Matlakatle B&C Only 1.3 Unpaved Access to the village from the provincial road. Small
access road that needs to be upgraded soon as erosion
are fast becoming a problem.
Maololo District 3.2 Unpaved The road is washed away between B and C but
both villages can be accessed from different
locations. This road is not earmarked for upgrade
by the other authorities.
Kanaan B Only 5.6 Unpaved Currently easily accessible but there are signs that
access the road is deteriorating. This is the only access to
this village.
Moripane District 12.4 Unpaved - This road is impassible but a bridge is busy being
Bridge constructed. Further upgrading of the road needs to
Required be done soon.
189
Phokwane District 1.4 Unpaved - The road has deteriorated so the only access is
Bridge from the D4045 road. This will however be
Required impassible during the rainy season as it crosses a
stream. Needs to be upgraded soon but it is not
earmarked by the other authorities.
Jane Furse Internal 8 Unpaved A good network of paved and unpaved roads
roads and paved currently exists. Some provision has been made to
- Good fill in the gaps. The length given is for this internal
road only.
Makgeru, Ga- Internal 22 Unpaved The situation is the same as for Phokoane. Jane
Mogashoa, roads and paved Furse and Phokoane have also been recognized by
Senkgapudi, Ga- - Good the provincial government as growth points within
and the municipal area.
Ratau,
average
Manamane
Kapaneng, Ga- Internal 12 (D Unpaved, Same as for the previous two villages. These
Marishane, Ga- roads 4.5) paved and villages have been grouped together due to their
Phahla blocks - close proximity to each other.
Good
Ga-Masemola Internal 4 Paved Paved and unpaved roads cross through these
roads villages to provide a good network of roads.
Provision has been made for filling in the gaps.
Schoonoord Internal 7 (D 6) Unpaved Once again the district roads provide a good
roads and paved network but some internal roads have been
- Good identified as being necessary. In general the roads
are in good condition.
Apel Cross LCH Roads paved - Houses further away from the paved road.
Good
Mogaladi, Internal 9 Unpaved Build mostly along the D4190 but some internal
Mogaladi Ext 3 and roads need to be upgraded to provide access to the
Klipspruit Internal 3 Unpaved The district roads cross through this village but
roads and paved additional internal roads is required to provide very
- Good good access.
Disesane Only 1.7 Unpaved The road passing through Mogaladi is paved but
access access to Ext 3 of the village need to be upgraded
as it is currently not a very good road.
Molapong Only 1.8 Unpaved A small village which gains access through Ga-
access Madiba. Upgrading this road will benefit both theses
villages. This is the only access to this village.
Ga-Magolego Only 1.8 Unpaved Final section of this road is currently being
access and under upgraded. The rest also needs to be improved as it
constructi also provides access to Molapong and Ga-
on Magolego.
Masite, Modiketsi, Only 1.5 Unpaved Also serves as an access to Ga-Magolego. Pipe
Ga-Maila access laying next to the road have narrowed the road
significantly but it is predicted that this will be
rectified as soon as construction is finished.
Semahlakole Only 2.1 Unpaved For the most part this road is a concrete path
access and leading up to the village. This footpath does
however require maintenance as it has started to
190
concrete - break up in some areas. The rest of the road is
Bad drivable.
Kome District 0.9 Unpaved This 0.9 km is in addition to the district road already
passing through these villages. The current district
road is in good condition.
Ga-Malaka District 0.7 Unpaved The road passing through this village is a lower
order district road as can be seen on the photos.
This road is the only access road to this village so
must be upgraded.
Vleeschboom Internal 10 Paved This is quite a long and narrow village so this road
roads will provide access to the entire village. Currently a
very narrow and winding road. The district road
nearby have been earmarked to be upgraded.
Glen Cowie Internal 1 (D Unpaved - The district road has been earmarked for upgrade
roads 3.8) Bridge by the higher authorities. The 1 km internal road will
Required provide greatly improved access throughout the
village.
Ga-Mokadi, Internal 1 Unpaved This village is not indicated on the map but it runs
Geluks A, roads and paved alongside the D4295 near Nebo. The proposed
Mangineng, - Good road forms a loop going through the centre of the
Madibaneng village.
Kgwaripe Internal 1.2 Unpaved Well maintained district roads running parallel to
roads each other enclose this village on two sides. The
proposed road running through the village will
provide a link between these roads.
Sephoto District 7.6 Unpaved The road is in good condition, but might need some
maintenance especially near Madibaneng. This is a
district road but no plans for upgrading of this road
by the higher authorities have been identified.
Ga-Moloi District 0.8 Paved The district road passing through the village is in
bad condition but it has been earmarked by the
provincial government for upgrading. Currently a
paved road pass near the village and this is seen
as adequate access.
Ga-Maila-Segolo Only 0.8 (D Paved The 0.8 km provides access internal to the village.
access 3) This is however not in immediate need of an
upgrade. The district road has been identified to be
in need of an upgrade by the higher authorities.
Thamaga Internal 2.4 Unpaved Situation is the same as for Glen Cowie. This road
roads will pass through the village and provide a link to
the two district roads passing close by.
Maraganeng Internal 1.8 (D Unpaved Currently the provincial road is not in good
roads 1.5) and paved condition but it has been identified as being in need
- Very bad of a upgrade. The 1.8 km internal road is important
as some of the houses are far from the provincial
road
Mapitsane Only 0.8 Unpaved Important because it is the only access to the
access village but is currently in good condition.
Mahlowaneng Only 0.6 Unpaved Village is close to the D 4260 which has been
access identified to be upgraded to a paved road. This
191
access road shows signs of erosion but it is not yet
critical.
Sebitsane, Only 0.9 Unpaved Access from the district road. Currently not a well-
Mathibeng, access constructed road but for the time being it has an
Dinotsi acceptable driving standard.
Makhutsho District 1.2 (D Unpaved Access to the village is good via Malope but the
4.6) road deteriorates in the village and is not easily
drivable and very winding pass the dam. Upgrading
of this section is not seen as critical but must be
done in the near future.
Malope District 4.7 Unpaved No action is required from the local municipality as
this road have been identified for upgrading by the
provincial government. If this action however take
too long to be implemented the state of this road
will become critical.
Riverside District 4.5 Unpaved The district road serves the entire length of the
village before ending at a reservoir at the end of the
village. The current condition is not great however
but it still provides an acceptable driving
experience.
Thoto Internal 2.4 Unpaved Close to a paved road but the internal roads need
roads to be upgraded as they are currently not in a good
condition.
Serageng Internal 2.6 upaved A paved road pass through the centre of the village
roads but good internal roads to provide access to the
furthest away houses is not existent.
Tshatane Internal 1 (D Unpaved The 1 km section of internal road pass through
roads 2.8) mountainous terrain and erosion is a problem. This
road has to be upgraded to provide access to a
school.
Polaseng District 1.6 Unpaved The district road nearby has been identified to be
upgraded by the higher authorities. Access from
that road to this village has a lot of very loose
material and erosion will become a problem.
Kgaruthuthu Internal 3 Unpaved A district road provides access to this village but
roads and under internal access roads have to be upgraded to
constructi provide the link to another adjacent district road.
on
Ga-Madiba Only 3.5 Unpaved Village is close to a main road. Road have been
access changed previously due to erosion being a problem.
Currently the road is in good condition.
Setlaboswane Only 6.5 Unpaved Road is in good condition and provides an
access acceptable driving experience.
Brooklyn Internal 1.5 Unpaved Runs along the D 1547 which is a paved road.
roads Additional access must in future be provided to
service more of the inhabitants.
Hwafeng Internal 1.6 Unpaved Adjacent to a paved road. Internal roads must be
roads constructed to provide better access to the village.
Mahlomola Internal 0.5 Unpaved Needs additional internal roads to provide complete
roads access to the village.
192
Mphanama District 3 Unpaved Road is in good condition. Some bad sections
and paved where previous efforts to pave the road have
- Very bad deteriorated to form a lot of potholes.
Nkotokwane District 0.8 (D Unpaved District road is in bad condition and must be
2.7) upgraded along with an internal section to provide
internal access to the village.
Matlakatle District 6 Unpaved Access provided by provincial road which has been
identified as one that needs to be upgraded. No
further action required by the municipality.
Ramphelane, Internal 0.8 Unpaved Close to the district road but the internal roads have
Tsatane ext 1 roads to be upgraded to provide access to and from the
district road.
Ga- Internal 1.3 (D Unpaved Close by district road have been earmarked for
Mashehlaneng roads 5.9) upgrading. An internal road will ease the access for
the further away houses.
Ga-Machacha Internal 5 Paved Village is located all along the west of road D 4190
roads but an internal road is required to run through the
centre of the village.
Patantswane, Internal 3.5 Unpaved Very rocky area. The main road is paved but is
Patantswane B, roads and paved severely deteriorated. A district road provides good
Lekorokorwaneng - Bad access to the village but internal roads is in bad
, Lehlakong, condition.
Eenzaam,
Enzaam LCH
Ga-Tisane District 4 Paved Gets access via a district road that pass through
the village. The current condition is satisfactory but
maintenance will have to be done in the future. No
additional internal roads are required.
Mohwelere District 18.5 Unpaved This is an access road to a lot of villages. It is a
district road but maintenance needs to be done
urgently to fix the couple of bad sections along this
road.
Mogodi District 1.7 Unpaved Two access via two different district roads. Some
bad sections but in general a good driving
experience.
Maseshegwane Internal 1 Unpaved Mountainous on the edge of the village. Rest of the
roads and paved roads is winding and very uneven. Paved road pass
- Good through the centre of the village.
Ga- Mashabela Internal 1 Paved Internal road will provide access to the houses
roads furthest away from the district road. This district
road has been identified as one that needs
upgrading.
Manganeng Internal 0.7 Paved Village is linked to Ga-Machacha via a small road.
roads This road needs to be upgraded to provide an
acceptable access road.
Thabeng Internal 1 Unpaved Close to a paved road. Very rocky internal roads
roads that must be upgraded to provide access to the
furthest houses.
193
Sebetha Internal 1.3 Unpaved A well maintained district road provides access to
roads most of the village. Some internal roads need to be
upgraded to provide the subserviced households.
Mampe Internal 2.6 Unpaved The district road passing close by has been
roads earmarked for upgrading by the higher authorities.
Internal access needs to be upgraded as it is
currently limited to a narrow road.
Masanteng Internal 1.5 (D Unpaved A small section of the road needs to be upgraded
roads 2.1) and paved urgently, but the rest is in good condition and need
- Good not be upgraded in the near future.
Lobethal Internal 0.3 Unpaved Only a short non critical section of road needs to be
roads upgraded to provide access for the inhabitants of
this village.
Sehuswane Internal 1.7 Unpaved On one side the village is bordered by a well
roads maintained district road. The upgrading of the ring
road currently situated within the village will provide
good access.
Ga-Mampana District 2 Paved The current access is via a district road. The road is
in good condition and no urgent upgrading or
maintenance is required.
Mmatsekele District 2.4 Unpaved Also serves as an access to Semahlakole.
Currently the road is in good condition.
Mare District 0.9 Unpaved This small section of the district road is sufficient to
provide access to the village. It is also key to
providing access for Makhutso.
Zoetvelden District 1.2 Unpaved The district road has been paved inside the village.
and paved This paved road needs maintenance as potholes
- Average are forming on the surface. The approach from
either side is in good condition.
Manotou District 2.8 Unpaved The road leading up to this village has been
earmarked for upgrade by the provincial
government so no further action is required.
Thabampshe Internal 1.1 Paved Access from the district road is in good condition.
roads Minor upkeep and maintenance required.
Mangoanyane Internal 0.9 (D Unpaved The district road has been identified by provincial
roads 3.8) government for upgrading. The internal road is not
a necessity but will provide better access
Mokwete Internal 2 (D Unpaved This village requires an upgraded internal road to
roads 5.8) provide access to some of the furthest houses.
Currently only a limited number of the inhabitants
are served by a district road.
Ga-Molepane Internal 1.8 Unpaved The internal road is almost impassible at present.
roads This road needs to be upgraded for ease of
movement but the close by district road has been
earmarked to be upgraded.
Magolapong, Ga District 3 Unpaved A very good district road that also serves Ga-
Maloa, Molepane. No immediate action required.
Phushulang
Kotupu District 4.2 Unpaved A very good district road that also serves Ga-
Molepane. No immediate action required.
194
Ngwaritsi District 11 Unpaved A very good road connecting all these villages to
the paved roads. As they are building along the
road no internal access is required.
Moomane North District 1 (D Unpaved Serviced by a paved road from Mabintwane's side.
9.6) and paved The unpaved section is also good and no further
- Good roads are required. This is a district road.
Sekwati District 4 Unpaved From the one side the road is paved and from the
other side it has been earmarked for an upgrade.
This road provides sufficient access to this village.
Krokodil Heuwel District 3.3 Unpaved The district road is still in a fairly good condition and
it has been identified as one of the roads to be
upgraded by the provincial government. No internal
access road is required at this stage.
Greenside Internal 4.5 Unpaved This village is served by a network of district roads
roads and paved passing through it. An additional 4.5 km of internal
- Good roads will fill in the gaps. This is however only
necessary for future planning.
Glen Cowie Ext 2 Internal 2.2 (D Unpaved The internal road will complete the distribution
roads 3.4) network of this village. The current district roads are
in good condition.
Molebeledi Internal 0.6 (D Unpaved The district road is of acceptable standard. The
roads 2.3) internal road has a lot of surface water running on
the road even in the dry season and special care
must be taken
to handle this water.
Maserumule Internal 1.1 Unpaved Enclosed by district roads on two sides and a very
Park, Nebo roads and paved good internal road on a third. Internal roads might
- Average need to be constructed in future.
Tikathon Internal 2.2 (D Unpaved This is a longitudinal village which has a acceptable
roads 2.5) internal road network. This road must however be
maintained to keep on providing this level of
access.
Thabanapitsi Internal 3 Unpaved Have been identified as a growth point in the area.
roads and paved A limited network of paved roads exists but it has to
- Good be completed by upgrading the internal roads.
Mmakgwabe Internal 0.8 (D Unpaved Very good district road pass through the village but
roads 2.5) an internal road is required to provide access to the
further away houses.
De Paarl Internal 1 (D Unpaved Good access provided by the district roads. A
roads 2.9) internal road will provide complete and easy access
to the entire village.
Vlakplaas A District 1.7 Unpaved Serviced by two district roads which are in good
condition. This village and De Paarl can be seen as
one village
Vlakplaas B District 1.9 Unpaved Serviced by two district roads which are in good
condition. This village and De Paarl can be seen as
one village
Tswaing Internal 1.5 Unpaved Village is close to a paved provincial road and
roads internal roads are acceptable but an improvement
will increase the living standard of inhabitants.
195
Moswanyaneng Internal 0.5 Unpaved Village is close to a paved provincial road and
roads internal roads are acceptable but an improvement
will increase the living standard of inhabitants.
Glen Cowie Ext 1 Internal 1.9 Unpaved Village is close to a paved provincial road and
roads internal roads are acceptable but an improvement
will increase the living standard of inhabitants
Marulaneng Internal 0.7 (D paved Road in good condition with scattered bad sections
roads 5.9)
Setebong Internal 2.2 Blocks - A paving block ring road exists within the village but
roads Need maintenance needs to be done as unwanted
cleaning material have ingresses from the side of the road.
Mathapisa Internal 2 (D Unpaved This village is serviced by two district roads which
roads 2.6) are in acceptable condition. Internal roads are not
critical but it will provide better access through the
village.
Phelindaba District 2.5 Unpaved One or two bad sections are present on this district
road but in general the road is in very good
condition.
Goodhope District 1.5 Unpaved This road is currently in good condition and it has
been identified to be upgraded by the higher
authorities. No action is required from the local
municipality.
Mohlarekoma Internal 1.9 Unpaved A district road which is in very good condition
roads passes through the village. An internal road has
been identified for upgrade but it is not at all critical.
Dihlabeng Only 1.6 Unpaved This village has been abandoned some time back.
access No population remains in this area. The road is only
used by people looking to gather fire wood.
TOTAL KMS 332,69 Unpaved
KMS
Source: MLM Draft Road Master Plan, 2022
196
Makhuduthamaga Local Municipality roads priority list as per District and Provincial list
Type of
Road
Road no. maintenance District Local Wards Growth point
particulars
Priority required
no:
Malope to
Upgrading from
D4260 Phokoane SDM MLM 29,31,24,03 Phokoane/Ap
gravel to tar
1 el Cross
197
Glen Cowie via
Upgrading from Thoto via
D4280 SDM MLM 09,06,07,05 Phokoane
gravel to tar Eensaam join
2 Leeukraal
Madibong to
Upgrading from
D4225 Manganeng SDM MLM 19,17,23 Schoonoord/J
gravel to tar
3 ane Furse
Mathapisa
Upgrading from road to
D4264 SDM MLM 26,24,31 Apel Cross
gravel to tar Vlakplaas to
3 Masehlaneng
Ga-Moloi to
Upgrading from
D4271 Phokoane SDM MLM 29,31,24,03 Phokoane/Ja
gravel to tar
4 ne Furse
Thabampshe
Upgrading from
D4255 cross to SDM MLM 27,28 Apel Cross
gravel to tar
5 Mahubitswane
Preventative
Access road to
D4253 Preventative Masemola SDM MLM 27,28 Apel Cross
1 Clinic
Jane
D2219 Preventative Phokoane to SDM MLM 03,05,09,0 Furse/Phoko
2 Tshehlwaneng ane
198
Phokoane to
D4295 Preventative SDM MLM 03,05,04,0 Phokoane
3 Moratiwa
Road network
The total road network in Makhuduthamaga is estimated at nearly 332.69 km which include both
provincial and local roads.
Arterial routes Primary arterial routes providing vehicular mobility with limited
off street access. These roads are generally the ring roads
Road: around districts providing external circulation but can also
D4280,D4379,DD4250,D4200,2219 traverse the district itself
199
Strategic Road Network and Description of Road Class
Hierarchy
Distributor and collector routes Miner arterial road /collector road serving as internal vehicular
circulation road within the municipal area
Roads:D4225,D4287,D4370,D4285,
D4280,D4254,D4217,D4350,D4267 o Primary arterial routes providing vehicular mobility with
limited off street access
Internal roads: Collector and streets There is currently a weak internal road hierarchy. The informal
nature of most of the villages makes it very difficult to
development an appropriate hierarchy. The SDF will provide
proposals and guidelines but detail transport and movement
studies will have to be done. At local level there are no street
names which further complicate the matter.
Challenges Interventions
200
3.3.6 Public Transport
The Department of Transport and Community Safety (LDoT) is the public transport authority.
The Sekhukhune District Municipality helps in respect of transport planning. The major public
transport services are bus and taxi operations. The bus industry is weakened as a result of
insufficient government funding and internal management capacities. The taxi industry is well
established.
The Municipality has several Taxis Associations operating within the municipal area. In the past
five years, the Department has never approved any additional trips to operators owing to
financial constraints experienced by the Department. This has resulted in high overloading
pressures in the District. Bus Operators in these areas continue to operate additional
unsubsidized trips to ease the overload burden and going forward this has a potential to
collapse the entire bus transport system should the operators decide to withdraw all the trips
whose operational costs they continue to cushion without any assistance from the government.
Additional subsidy is required in this regard as a matter of urgency to address all the gaps
identified and historical disparities.
The Great North Transport, Sekhukhune Express and Thembalethu are the only bus operators
within Makhuduthamaga municipal area with conventional fixed routes and a fixed schedule
system that provides passengers with public transport to work in the morning and back home in
the evening
The Municipality through its Community Service department facilitated the granting of Operating
Certificate to Operators of Meter Taxis to Jane Furse Maxi Taxi Association that operated in
Jane Furse.
Unregulated and influx of Mini taxis operating as metered taxis within Jane Furse area are
posing a threat to road users as majority of them are not road-worthy. The Municipality, SAPS
and the Department together with organised meter taxis in the area are doing everything in their
power to address the challenge.
Provincial roads that are found within Makhuduthamaga municipal area are R579 that runs from
Jane Furse to Stoffberg or/and Elias Motsoaledi municipal border through Nebo to Lepelle
Nkumpi municipal border and the R555 that run from Jane Furse to Burgersfort.
It is a requirement in terms of the National Land Transport Act 2009 that municipalities develop
Integrated Transport Plans (ITPs). In the absence of ITP’s, it is difficult to consider applications
for public transport operating licenses hence the Department decided to assist municipalities
with the development of ITP’s for the growth points in the province. The Makhuduthamaga local
municipality has a Draft Integrated Transport Plan which indicates that the municipality has one
mode of transport found in the area, viz, road transport. The plan will be adopted in the
2023/2024 financial year.
201
Public Transport Conflicts:
There is a high demand for new operating licenses by registered members and aspirant
operators alike resulting in an increased number of new applications for the registration of new
taxi associations. Most of the conflicts are fuelled by individuals operating without operating
licenses.
Road Safety
Speeding remains the highest contributory factor (60%) to possible causes of accidents in the
Province which poses a major challenge to the Department. For further reduction of the
accidents there will be a need to implement fixed speed enforcement cameras at certain
strategic areas.
From 2009 the number of fatalities decreased annually. Though the number of fatalities
decreases the number of road accidents increased drastically. This is linked to the increase in
vehicle population yearly.
Transport Regulation
• Nebo Traffic Station: The institution provides law enforcement and it is without
Registering Authority facility.
The municipality is providing law enforcement, registration licensing and roadworthy tests and
driving license test services, which is overseen by the District.
The SLA between the department and Municipalities provide 80/20 % share out of revenue
collection
In addition to the above, there are also 2 private vehicle testing centres in Makhuduthamaga, of
which the role of the department is to monitor.
202
TIME WHEN ACCIDENTS USUALY HAPPEN POSSIBLE CAUSES OF ACCIDENTS
Transport operations
Makhuduthamaga 8 1018
203
The Provincial and District road network is currently the responsibility of the Roads Agency
Limpopo (RAL) and the Department of Public Works, Roads and Transport (Limpopo). The RAL
utilise the Road Management System (RMS) as a tool for assisting with road network
management.
CHALLENGE INTERVENTION
o Taxis fighting for the use of o Municipality public safety must organise
certain routes meetings together with Provincial
o Regulation and control of meter Department of Transport in order to get
taxis around Jane Furse amicable solution to the conflict
o Poor roads infrastructure o Ensure proper control of meter taxis
o Traffic congestion in Jane Furse o Develop and implement road infrastructure
o No transport facilities in some maintenance plan
parts of the municipality o By-pass roads to build to reduce congestion
o Lack of public transport in some o To negotiate with taxi associations and bus
areas due to poor roads companies to provide transport
infrastructure o To engage DoRT to tar roads that belongs
to the department
The Sekhukhune District Municipality (SDM) is implementing FBW to all ward of the municipality
(31). The process began by compiling the indigent registers and development of indigent policy.
The District also had yard connections of water in some areas within MLM in order that the
households whose monthly income is beyond R4180 can pay for the services while those below
qualify for 6 kilolitres of water free of charge every month. This service, however, never took off
due to delays by authority to develop relevant by-laws. To date, all households with yard
connections regardless of their indigent status get Free Basic Water.
Sanitation service is also provided free to all households by Sekhukhune District Municipality
(31 wards)
204
14 658 households in Makhuduthamaga receive free refuse removal service through pilot
project. The programme ensures that every household within the collection area i.e. Jane Furse,
Phokoane, Glen Cowie and Schoonoord gets its refuse removed once per week without
payment. Skip bins are placed in strategic points throughout the municipality for communities
and collection is made on daily basis.
The responsibility for Housing is that of Human Settlements in the Departments of CoGHSTA.
The municipality gets allocation of houses from CoGHSTA and is only required to identify and
submit the names of beneficiaries. The Department is responsible for the implementation of the
projects. It has a Draft Housing Sector Plan and will be adopted during the 2023/2024 financial
year. All the housing stock is located within a rural setting made up of traditional authority
settlements. The character of the area is viewed as rural even where some form of settlement
formalization processes has been implemented. Informal dwelling / shacks need some attention
although it is not a major problem.
205
Phatametsane RDP houses (09)
206
Pelepele Park/Maswiakae RDP houses (50)
207
Senamela RDP houses (09)
Kgopane
208
Dlamini RDP houses (68)
Ramphelane
Kgolane
Mathibeng (Toona)
209
Mamone Centre Extension No challenge nor backlog indicated
210
Mamoshalela RDP houses
211
Police station extension RDP houses
212
Masanteng RDP houses backlog(03) and (04)
incomplete
213
Makhuduthamaga local municipality housing backlog
LIM473: MLM
Formal 1 388 2 1 0 5 0
residential
Informal 0 0 0 0 0 0
residential
Traditional 62 769 17 78 48 86 0
residential
Farms 0 0 0 0 0 0
Parks and 0 0 0 0 0 0
recreation
Collective living 86 1 3 0 0 0
quarters
Industrial 0 0 0 0 0 0
Small holdings 0 0 0 0 0 0
Vacant 731 0 0 1 0 0
Commercial 0 0 0 0 0 0
214
Table: Number of rooms by population group of head of the household
1 3 727 4 11 3 19 0
2 4 738 5 17 2 25 0
3 6 515 2 13 6 19 0
4 10 583 1 14 6 5 0
5 10 610 1 7 12 8 0
6 10 986 2 9 5 5 0
7 8 156 4 2 4 4 0
8 4 911 0 4 3 2 0
9 2 458 1 2 4 2 0
10 1 137 0 0 1 0 0
11 562 0 1 3 0 0
12 316 0 1 0 0 0
13 125 0 0 0 0 0
14 69 0 0 0 0 0
15 34 0 0 0 0 0
16 14 0 0 0 0 0
17 10 0 0 0 0 0
18 6 0 0 0 0 0
19 4 0 0 0 0 0
20 12 0 0 0 0 0
21 0 0 0 0 0 0
215
Table: MLM type of main dwelling and Population group of head of household
LIM473: MLM
Townhouse (semi-detached 16 - - - - -
house in a complex)
Semi-detached house 31 - 1 - 1 -
Caravan/tent 28 - - - 1 -
Other 222 1 2 1 -
Most houses in the municipality are situated on separate stands and this indicates potential for
future formalization and upgrading. Enormous housing backlogs building up at urban areas due
to influx of people to these areas resulting in large numbers of informal dwellings / shacks in
216
backyards and an open land. Due to envisaged development in Jane Furse proper housing
plan needs to be developed.
Makhuduthamaga 2012/13- 0
2013/14 – 0
CHALLENGES INTERVENTIONS
The pace at which RDP housing is moving coupled with incomplete and substandard quality
constructed RDP houses makes it difficult to confidently forecast that housing target can be
achieved in Makhuduthamaga by 2024.
217
3.3.9 Social grants
Planned Pay-points
Makhuduthamaga 20 20 20
The table above presents the statistics on grants beneficiaries as obtained from the South African
Social Security Agency (SASSA). The figures indicated in the table change every month due to
new approvals, births and deaths. The SASSA shows that the state resources are spend in the
form of child grants in the areas that are predominantly rural. Many of these beneficiaries are
either fostered, old aged, depended, need support one way or the other hence they receive
different forms of grants. Issues contributing to high dependency rate on grants range from
amongst others, orphans resulting from HIV/AIDS related deaths, child-headed households.
218
Infrastructure
Makhuduthamaga has 111 service points (Pay points) whereby community members can
access social grants on monthly basis. It has 6 permanents and 4 temporary offices whereby
applications for grants and other services can be made
CHALLENGES INTERVENTION
3.3.10 Education
The Municipality has established a Bursary Fund to assist youth from disadvantage families to
study at Tertiary level. The Makhuduthamaga Municipal Council during the 2009/10 financial
year resolved to fund students who will pursue their studies in Infrastructure/ Engineering
Development, Planning or Finance to address the skills gap within Makhuduthamaga.
219
Education key Challenges
d) Sanitation facilities in some schools collapsing, not user friendly and pose a health
hazard to both learners and educators
220
Sekhukhune East Malegale Ordinary Public
Pitsi Prim 1
Sekhukhune East Malegale Ordinary Public
Ramphelane Sec 1
Sekhukhune East Ordinary Public
Malegale Sebase Sec 1
Sekhukhune East Ordinary Public
Malegale Seboeng Prim 1
Sekhukhune East Ordinary Public
Malegale Seraki Sec 1
Sekhukhune East Ordinary Public
Malegale Thulare Prim 1
Sekhukhune East Ordinary Public
Malegale Tsatane Prim 1
Sekhukhune East Ordinary Public
Mmashadi Arethabeng Prim 2
Sekhukhune East Mmashadi Ordinary Public
Bafedi Prim 2
Sekhukhune East Mmashadi Ordinary Public
Baropodi Prim 2
Sekhukhune East Mmashadi Bonega Ordinary Public
Madikubung Prim 2
Sekhukhune East Mmashadi Ordinary Public
Dikgabje Prim 1
Sekhukhune East Mmashadi Ordinary Public
Freddy Mokgabudi Prim 1
Sekhukhune East Mmashadi Public
Jane Furse SNE Special
Sekhukhune East Mmashadi Jane Furse Ordinary Public
Comprehensive Combined 3
Sekhukhune East Mmashadi Ordinary Public
Kalafong Prim 2
Sekhukhune East Mmashadi Ordinary Public
Kgoloko Sec 1
Sekhukhune East Mmashadi Leap Science and Ordinary
Maths Sec Indep
Sekhukhune East Mmashadi Ordinary Public
Lehutjwana Sec 2
Sekhukhune East Mmashadi Ordinary Public
Lengama Sec 2
Sekhukhune East Mmashadi Ordinary Public
Madibong Prim 1
Sekhukhune East Mmashadi Madinoge Ordinary Public
Kgoloko Prim 1
Sekhukhune East Mmashadi Ordinary
Mashegoanyane Prim Public 1
Sekhukhune East Mmashadi Ordinary Public
Matsebong Sec 2
Sekhukhune East Mmashadi Ordinary Public
Molepane Sec 1
221
Sekhukhune East Mmashadi Ordinary Public
Monapanape Prim 1
Sekhukhune East Mmashadi Ordinary Public
Mookwane Prim 1
Sekhukhune East Mmashadi Ordinary Public
Moretsele Prim 2
Sekhukhune East Mmashadi Ordinary Public
Moripane Rim 2
Sekhukhune East Mmashadi Ordinary Public
Ngwanamatlang Sec 1
Sekhukhune East Mmashadi Ordinary Public
St. Mark's Prim 2
Sekhukhune East Mmashadi St. Mark's Ordinary Public
Comprehensive
College Sec 4
Sekhukhune East Ordinary
Ngwaabe Legapana Prim Public 1
Sekhukhune East Ngwaabe Ordinary Public
Seokgome Sec 1
Sekhukhune East Ngwaabe Steelpoort Ordinary Public
Academy Comb 5
Sekhukhune East Ordinary Public
Schoonoord Dihlabaneng Prim 1
Sekhukhune East Schoonoord Ordinary Public
Dikankatla Prim 1
Sekhukhune East Schoonoord Ordinary Public
Dlamini Prim 1
Sekhukhune East Schoonoord Ordinary Public
Kgalatlou Sec 1
Sekhukhune East Schoonoord Ordinary Public
Kgobise Prim 1
Sekhukhune East Schoonoord Ordinary Public
Lamdzandvo Sec 1
Sekhukhune East Ordinary Public
Schoonoord Legare Sec 1
Sekhukhune East Ordinary Public
Schoonoord Madikanono Prim 1
Sekhukhune East Ordinary Public
Schoonoord Makatane Sec 1
Sekhukhune East Ordinary Public
Schoonoord Makgane Prim 1
Sekhukhune East Ordinary Public
Schoonoord Malakeng-Serotele Prim 1
Sekhukhune East Ordinary Public
Schoonoord Manchakgathe Prim 1
Sekhukhune East Ordinary Public
Schoonoord Mantimo Prim 1
Sekhukhune East Ordinary Public
Schoonoord Marota makgane Prim 1
Sekhukhune East Ordinary Public
Schoonoord Maserala Prim 1
222
Sekhukhune East Ordinary Public
Schoonoord Matime Prim 1
Sekhukhune East Schoonoord Ordinary Public
Mogashoa Prim 1
Sekhukhune East Schoonoord Ordinary Public
Mokale Prim 1
Sekhukhune East Schoonoord Ordinary Public
Nokomeetse Prim 1
Sekhukhune East Schoonoord Ordinary Public
Ntshitshimale Prim 1
Sekhukhune East Schoonoord Ordinary Public
Phutlotau Sec 1
Sekhukhune East Schoonoord Ordinary Public
Schoonoord Prim 1
Sekhukhune East Schoonoord Ordinary Public
Sefogole Sepeke Sec 1
Sekhukhune East Schoonoord Ordinary Public
Semashego Prim 1
Sekhukhune East Schoonoord Ordinary Public
Tshabadietla Sec 1
Sekhukhune East Schoonoord Ordinary Public
Tshehlwaneng Sec 1
Sekhukhune Ordinary Public
South Eensaam Areikhuleng Prim 1
Sekhukhune Eensaam Ordinary Public
South
Gammalebese Prim 1
Sekhukhune Eensaam Ordinary Public
South
Kgahlanamorulana Sec 1
Sekhukhune Eensaam Ordinary Public
South
Kwenatshwene Prim 1
Sekhukhune Eensaam Ordinary Public
South
Lehlakong Prim 1
Sekhukhune Eensaam Ordinary Public
South
Leokeng Sec 1
Sekhukhune Eensaam Ordinary Public
South
Mafetatsubela Prim 1
Sekhukhune Eensaam Ordinary Public
South
Magale Sec 2
Sekhukhune Eensaam Ordinary Public
South
Mahlakanaseleng Prim 2
223
Sekhukhune Eensaam Ordinary Public
South
Maretele Sec 1
Sekhukhune Eensaam Ordinary Public
South
Mmamokgokolushi Sec 1
Sekhukhune Eensaam Ordinary Public
South
Mogalatladi Prim 1
Sekhukhune Ordinary
South
Eensaam Mohlodi Sec Public 1
Sekhukhune Ordinary Public
South
Eensaam Morulana Prim 1
Sekhukhune Ordinary Public
South
Eensaam Moteane Sec 2
Sekhukhune Eensaam Ordinary Public
South
Namudi Sec 1
Sekhukhune Eensaam Ordinary Public
South
Ntshebele Sec 1
Sekhukhune Eensaam Ordinary Public
South
Patantshwana Prim 1
Sekhukhune Eensaam Ordinary Public
South
Photohlogoana Prim 2
Sekhukhune Eensaam Ordinary Public
South
Thabong Prim 1
Sekhukhune Eensaam Ordinary Public
South
Tshwatlhakge Prim 2
Sekhukhune Comprehensive Ordinary
South Riverside
Glen cowie Technical Comb Indep
Sekhukhune Ordinary Public
South
Glen cowie Dikwetse Prim 1
Sekhukhune Public
South Guardian Angels
Glen cowie College Sec Ordinary 3
Sekhukhune Glen cowie Ordinary Public
South
Hlabje Prim 1
224
Sekhukhune Glen cowie Ordinary Public
South
Katudi Prim 1
Sekhukhune Glen cowie Ordinary Public
South
Kopanong Prim 1
Sekhukhune Glen cowie Ordinary Public
South
Legaletlwa Sec 1
Sekhukhune Glen cowie Ordinary Public
South
Mabodibeng Sec 1
Sekhukhune Glen cowie Ordinary Public
South
Manotong Prim 1
Sekhukhune Glen cowie Ordinary Public
South
Mantlhanyane Sec 1
Sekhukhune Glen cowie Ordinary Public
South
Mapalagadi Prim 1
Sekhukhune Glen cowie Ordinary Public
South
Mapogo Prim 1
Sekhukhune Glen cowie Ordinary Public
South
Matshumane Sec 2
Sekhukhune Glen cowie Ordinary Public
South
Mmakubu Prim 1
Sekhukhune Ordinary Public
South
Glen cowie Mmauwane Sec 1
Sekhukhune Glen cowie Ordinary Public
South
Mpelegeng Prim 1
Sekhukhune Glen cowie Ordinary Public
South
Mphele a Mphele Sec 1
Sekhukhune Glen cowie Ordinary Public
South
Phiriagae Sec 1
Sekhukhune Glen cowie Ordinary Public
South
Photo Prim 1
Sekhukhune Glen cowie Ordinary Public
South
Ponti Sec 1
225
Sekhukhune Glen cowie Ordinary Public
South
Rebone Sec 1
Sekhukhune Glen cowie Ordinary Public
South
Sebjaneng Prim 2
Sekhukhune Glen cowie Ordinary Public
South
Sedikwe Prim 1
Sekhukhune Glen cowie Ordinary Public
South
Sekwena Prim 1
Sekhukhune Glen cowie Ordinary Public
South
Seopo Sec 1
Sekhukhune Glen cowie Ordinary Public
South
Swike Prim 1
Sekhukhune Glen cowie
South
Thakgudi Sec Ordinary Public 1
Sekhukhune Ordinary Public
South
Glen cowie Thoto Prim 1
Sekhukhune Ordinary Public
South
Glen cowie Tlame Prim 2
Sekhukhune Ordinary Public
South Lepelle(Sekhukhune Baithudi
South) Mohlahledi Prim 1
Sekhukhune Lepelle(Sekhukhune Ordinary Public
South South)
Hopefield Prim 1
Sekhukhune Lepelle(Sekhukhune Ordinary Public
South South)
Katang Prim 1
Sekhukhune Lepelle(Sekhukhune Ordinary Public
South South)
Katisi Prim 1
Sekhukhune Lepelle(Sekhukhune Ordinary Public
South South)
Kediketse Prim 1
Sekhukhune Lepelle(Sekhukhune Ordinary Public
South South)
Lekhine Sec 1
Sekhukhune Lepelle(Sekhukhune Ordinary Public
South South)
Mafoko Prim 1
226
Sekhukhune Lepelle(Sekhukhune Ordinary Public
South South)
Makgoabe Prim 1
Sekhukhune Lepelle(Sekhukhune Ordinary Public
South South)
Malope Prim 1
Sekhukhune Lepelle(Sekhukhune Ordinary Public
South South)
Mamakgatlape Prim 1
Sekhukhune Lepelle(Sekhukhune Ordinary Public
South South)
Mampana Prim 1
Sekhukhune Lepelle(Sekhukhune Ordinary Public
South South)
Mangolwane Sec 1
Sekhukhune Lepelle(Sekhukhune Ordinary Public
South South)
Maphadime Sec 1
Sekhukhune Lepelle(Sekhukhune Ordinary Public
South South)
Mampuru Tseke Sec 1
Sekhukhune Lepelle(Sekhukhune Ordinary Public
South South)
Matshele Sec 1
Sekhukhune Lepelle(Sekhukhune Ordinary Public
South South)
Modishang Prim 1
Sekhukhune Lepelle(Sekhukhune Ordinary Public
South South)
Mokgapi Sec 1
Sekhukhune Lepelle(Sekhukhune Ordinary Public
South South)
Molwetsi Sec 1
Sekhukhune Lepelle(Sekhukhune Ordinary Public
South South)
Motsatsi Prim 1
Sekhukhune Lepelle(Sekhukhune Ordinary Public
South South)
Mphegolle Sec 1
Sekhukhune Lepelle(Sekhukhune Ordinary Public
South South)
Sepheu Moleke Sec 1
Sekhukhune Lepelle(Sekhukhune Ordinary Public
South South)
Shushu Prim 1
Sekhukhune Lepelle(Sekhukhune Ordinary Public
South South)
Thabanapitsi Prim 1
227
Sekhukhune Lepelle(Sekhukhune Ordinary Public
South South)
Thingwa Prim 1
Sekhukhune Lepelle(Sekhukhune Ordinary Public
South South)
Thutlwamakwa Prim 1
Sekhukhune Lepelle(Sekhukhune Ordinary Public
South South)
Tisana Prim 1
Sekhukhune Lepelle(Sekhukhune Ordinary Public
South South)
Tshege Sec 1
Sekhukhune Ordinary Public
South Lepelle(Sekhukhune
South) Tsoatago Prim 1
Sekhukhune Ordinary Public
South
Lobethal Bohwelabatho Prim 1
Sekhukhune Lobethal Ordinary Public
South
Lediitse Prim 1
Sekhukhune Lobethal Ordinary Public
South
Lobethal Prim 1
Sekhukhune Lobethal Ordinary Public
South
Mamorithing Prim 1
Sekhukhune Lobethal Ordinary Public
South
Mantlatle Sec 1
Sekhukhune Lobethal Ordinary Public
South
Marei Prim 1
Sekhukhune Lobethal Ordinary Public
South
Mashabela Prim 1
Sekhukhune Lobethal Ordinary Public
South
Mmakadikwe Prim 1
Sekhukhune Lobethal Ordinary Public
South
Modipadi Sec 1
Sekhukhune Lobethal Ordinary Public
South
Mogobelala Prim 1
Sekhukhune Lobethal Ordinary Public
South
Mohwelere Prim 1
228
Sekhukhune Lobethal Ordinary Public
South
Mokgoko Prim 1
Sekhukhune Lobethal Ordinary Public
South
Molebeledi Sec 1
Sekhukhune Lobethal Ordinary Public
South
Nala Prim 1
Sekhukhune Lobethal Ordinary Public
South
Nkgonyeletse Sec 1
Sekhukhune Lobethal Ordinary Public
South
Phaswane Prim 1
Sekhukhune Lobethal Ordinary Public
South
Phuti-Kwena Sec 1
Sekhukhune Lobethal Ordinary Public
South
Rantobeng Sec 1
Sekhukhune Lobethal Ordinary Public
South
Serokoloana Prim 1
Sekhukhune Ordinary Public
South
Masemola Diphale Sec 1
Sekhukhune Masemola Ordinary Public
South
Ekele Prim 1
Sekhukhune Masemola Ordinary Public
South
Kgoogo Prim 1
Sekhukhune Masemola Ordinary Public
South
Khudu Tseke Prim 1
Sekhukhune Masemola Ordinary Public
South
Lewalemolomo Sec 1
Sekhukhune Masemola Ordinary Public
South
Mabooe Prim 1
Sekhukhune Masemola Ordinary Public
South
Machelane Prim 1
Sekhukhune Masemola Ordinary Public
South
Mahlolwaneng Prim 1
229
Sekhukhune Masemola Ordinary Public
South
Mahwetse Sec 1
Sekhukhune Masemola Ordinary Public
South
Mannyetha Prim 1
Sekhukhune Masemola Ordinary Public
South
Masemola Sec 1
Sekhukhune Ordinary Public
South
Masemola Mathume Sec 1
Sekhukhune Ordinary Public
South
Masemola Matlebjoane Sec 1
Sekhukhune Ordinary Public
South
Masemola Mmakopi Sec 1
Sekhukhune Ordinary Public
South
Masemola Mogaile Prim 1
Sekhukhune Ordinary Public
South
Masemola Mokalapa Prim 1
Sekhukhune Ordinary Public
South
Masemola Molomotoatau Sec 1
Sekhukhune Ordinary Public
South
Masemola Monyaku Sec 1
Sekhukhune Ordinary Public
South
Masemola Motubatse Sec 1
Sekhukhune Ordinary Public
South
Masemola Ngwanabekane Prim 1
Sekhukhune Ordinary Public
South
Masemola Nkgari Prim 1
Sekhukhune Ordinary Public
South
Masemola Phoroane Sec 1
Sekhukhune Ordinary Public
South
Masemola Sekale Prim 1
Sekhukhune Public
South
Masemola Thabamphse Prim Ordinary 1
230
Sekhukhune Ordinary Public
South
Masemola Thabanaswana Prim 1
Sekhukhune Ordinary
South The Future
Masemola Comprehensive Comb Indep
Sekhukhune Ordinary Public
South
Masemola Tiitsane Prim 1
Sekhukhune Ordinary Public
South
Ngwaritsi Bopedi Bapedi Sec 2
Sekhukhune Ordinary Public
South
Ngwaritsi George Clifford Prim 1
Sekhukhune Ordinary Public
South
Ngwaritsi Kgaladi Prim 1
Sekhukhune Ordinary Public
South
Ngwaritsi Kgaruthuthu Prim 1
Sekhukhune Ordinary Public
South Kgoshi
Ngwaritsi Moroangoato Sec 1
Sekhukhune Ordinary Public
South
Ngwaritsi Kgotswane Sec 1
Sekhukhune Ordinary Public
South Lehlagare
Ngwaritsi Marishane Prim 1
Sekhukhune Ordinary Public
South
Ngwaritsi Lekoko Sec 1
Sekhukhune Ordinary Public
South Letebele
Ngwaritsi Marishane Sec 1
Sekhukhune Ordinary Public
South
Ngwaritsi Makgatsike Prim 1
Sekhukhune Ordinary Public
South
Ngwaritsi Makubarate Prim 1
Sekhukhune Ordinary Public
South
Ngwaritsi Malekutu Sec 1
Sekhukhune Ordinary Public
South
Ngwaritsi Marishane Prim 1
231
Sekhukhune Ordinary Public
South
Ngwaritsi Marotobale Prim 1
Sekhukhune Public
South
Ngwaritsi Matobule SNE Special
Sekhukhune Ordinary Public
South
Ngwaritsi Matobule Prim 1
Sekhukhune Ordinary Public
South
Ngwaritsi Mogaletlwa Prim 1
Sekhukhune Ordinary Public
South
Ngwaritsi Mohlahledi Prim 1
Sekhukhune Ordinary Public
South
Ngwaritsi Mokgubi Sec 1
Sekhukhune Ordinary Public
South
Ngwaritsi Motlokwe Prim 1
Sekhukhune Ordinary Public
South
Ngwaritsi Motsemogolo Prim 1
Sekhukhune Ordinary Public
South
Ngwaritsi Mpole Sec 1
Sekhukhune Ordinary Public
South
Ngwaritsi Ngwanamashile Prim 1
Sekhukhune Ordinary Public
South
Ngwaritsi Ngwanatshwane Sec 1
Sekhukhune Ordinary Public
South
Ngwaritsi Ranong Prim 1
Sekhukhune Ordinary Public
South
Ngwaritsi Sekwati Prim 1
Sekhukhune Ordinary Public
South
Ngwaritsi Teme Prim 1
Sekhukhune Ordinary Public
South
Ngwaritsi Tenyane Sec 1
Sekhukhune Ordinary Public
South
Ngwaritsi Thabadiphiri Prim 1
232
Sekhukhune Ordinary Public
south
Ngwaritsi Tholong Prim 1
Sekhukhune Ordinary Public
south
Ngwaritsi Tseke Marishane Sec 1
Sekhukhune Ordinary Public
south
Phokoane Kopjeng Prim 2
Sekhukhune Ordinary Public
south
Phokoane Lehlake Prim 1
Sekhukhune Ordinary Public
south
Phokoane Lehwelere Sec 2
Sekhukhune Ordinary Public
south
Phokoane Leshalabe Prim 1
Sekhukhune Ordinary Public
south
Phokoane Makhato Sec 2
Sekhukhune Ordinary Public
south
Phokoane Makwe Sec 2
Sekhukhune Ordinary Public
south
Phokoane Maserumule Sec 1
Sekhukhune Ordinary Public
south
Phokoane Mmeshi Prim 2
Sekhukhune Ordinary Public
south
Phokoane Mokgeretli Sec 1
Sekhukhune Ordinary Public
south Mokgoma
Phokoane Phokoane Prim 1
Sekhukhune Ordinary Public
south
Phokoane Mokgoshi Prim 2
Sekhukhune Ordinary Public
south
Phokoane Moleijane Prim 2
Sekhukhune Ordinary Public
south
Phokoane Moreko Sec 2
Sekhukhune Ordinary Public
south
Phokoane Moriti Sec 1
233
Sekhukhune Ordinary Public
south
Phokoane Petloane Prim 2
Sekhukhune Ordinary Public
south
Phokoane Phatametsane Sec 2
Sekhukhune Ordinary Public
south
Phokoane Thotaneng Prim 2
Sekhukhune
south Phokoane Tshwaane Prim Ordinary Public 1
Source: Department of Education 2024
Municipality 2019/20
Fetakgomo/ Tubatse 14
234
Ephraim Mogale 10
Elias Motsoaledi 09
Makhuduthamaga 21
Total 54
Makhuduthamaga Fair
(educators +learners)
235
Bonega Madikubung Primary Mmashadi 271 12
236
Lobambo Secondary Schoonord 226 12
237
Mashabela Primary Lobethal 384 18
238
Manyaku Secondary Masemola 217 10
239
Thakgudi Secondary Glen Cowie 380 18
LIM473: MLM
Male
Grade 0 6 331 1 6 0 3
240
Grade 6 / Std 4 5 489 1 3 5 8
N4 / NTC 4 101 0 0 2 0
N5 /NTC 5 93 0 0 1 0
N6 / NTC 6 171 0 1 0 0
241
Higher Degree Masters / PhD 115 0 1 1 0
Other 83 0 1 0 0
No schooling 10 077 1 3 3 17
Unspecified 0 0 0 0 0
Female
Grade 0 6 317 2 1 1 1
N4 / NTC 4 125 1 0 0 0
N5 /NTC 5 140 0 0 0 0
242
N6 / NTC 6 256 0 0 0 0
Other 99 0 0 0 0
No schooling 23 421 5 4 15 4
Unspecified 0 0 0 0 0
Table:MLM 2011 highest level of education grouped, gender and population group
LIM473:
Makhuduthamaga
Male
No schooling 10 077 1 3 3 17
243
Some primary 36 723 9 28 17 23
Higher 3 072 3 22 6 2
Other - - - - -
Unspecified 83 - 1 - -
Female
No schooling 23 421 5 4 15 4
Higher 4 741 3 4 4 -
Other - - - - -
Unspecified 99 - - - -
LIM473: MLM
Male
Yes 53 829 15 36 16 13 -
244
No 45 351 15 168 33 123 -
Do not know 48 - - - - -
Unspecified 1 852 - - 1 - -
Female
Yes 51 752 12 31 19 3 -
No 78 380 20 52 45 44 -
Do not know 96 - - - - -
Unspecified 2 965 - 7 3 - -
Provision of health services within Makhuduthamaga is not satisfactory. This view derives from
generally low levels of services combined with poor health infrastructure. Makhuduthamaga has
only two public hospitals i.e. Jane Furse and St Rita’s hospitals, 21 clinics and 45 mobile clinic
service points
2 21 45 0
245
Availability of mobile clinics and their frequency of visits
Municipality Backlog
Makhuduthamaga 1.Mamakgosefoka
2.Maila Mapitsane
3.Hoeperkrans
2.Madibaneng
Specific areas without health facilities and how they are being catered for
Municipality
Makhuduthamaga Madibaneng, Malegale, Hoepagrantz, Dlamini, Maila
Mapitsane, Thoto, Malaka, Kome, Goedhope and
Kgarethuthu
246
Clinics with water challenges in Makhuduthamaga
o Tshehlwaneng clinic
o Marishane clinic
o Magalies clinic
o Magalies clinic
o Klipspruit clinic
o Phokoane clinic
o Marishane clinic
o Phaahla clinic
o Probeerin clinic
o Tshehlwaneng cliunic
o Phokoane clinic
o Schonoord clinic
o Patantshwane clinic
Patantshwane 06
Rietfontein 04
Klipspruit 01
Setlaboswane 31
Magalies 21
247
Clinic earmarked for renovation in the 2024/2025 financial year in Makhuduthamaga
o Patantshwane clinic
o St Ritas Gateway
Challenges
Challenges Interventions
Lack of accessibility due to poor infrastructure e.g Request the department to complete incomplete
roads facilities and upgrade dilapidated ones
Some health facilities needs upgrading To prioritise budget allocation in the next financial
year
Long distance to access health facilities To provide mobile clinic in the remote areas
3.3.12 Libraries
The responsibility for the establishment of libraries rests within the Provincial function. However,
Makhuduthamaga Local Municipality operates four libraries within its area of jurisdiction on
behalf of the Department of Sports, Arts and Culture. There is a Service Level Agreement
between the Municipality and the Department. The rural nature of the municipality renders
accessibility ineffective. While more libraries would be needed they should be located at densely
populated areas and provided with internet access.
248
Library services: norm and Standards:
o 02 libraries
MLM Ga-Phaahla
1. Ga-Phaahla,
2.Patantswane • Access- accessible to the community.
3. Jane Furse. • Materials- Academic books are a need in the
community.
4.Phokoane
• Personnel 04
Patantshwane
• Access- accessible to the community.
• Materials- Academic books are a need in the
community.
• Personnel- 02,
Jane Furse
• Access- Not accessible to the community
• Materials- adequate materials suitable for
users’ needs.
• Personnel- 01
Phokoane
249
Challenges Intervention
The National Government initiated the Thusong Service Centre concept which seeks to provide
one stop government services and facilities to communities.
There are no Thusong centres in the municipality. The state of affair denies the community of
socializing and access to services. The establishment of Thusong Centres would assist.
Engagements with the Office of the Premier concluded that mobile/ temporary service centres
will be established while awaiting the conclusion of the acquisition of land for such. The
Thusong Service centres as envisaged by National Government are based on a 6 –Block
Service Model which seeks to integrate and provide all or most of the following services in one
community located facility: Government Social and administrative Office, Education and skills
Development, Local Economic Development, Business Services and Community Opportunities;
and Information and communication.
The Municipality has secured a land from Masemola Traditional Council and the area is now
protected or fenced together with the stadium. A budget will be set aside in the 2024/2025
financial year to kick start the project.
Public places and local amenities are issues that are often raised during public engagement
processes. The following programmes and projects have been identified to address issues
related to a clean environment:
250
Area Projects
Enhanced Healthy Environment ( CWP) Promotion of food gardens projects/ food security
The Municipality has developed a Municipal Park at Jane Furse township. The area is fenced
with palisade fence and will be developed further in the 2024/2025 financial year. The
municipality is also engaging traditional leaders and other stakeholders on earmarked areas for
municipal cemeteries per cluster.
Challenges Interventions
251
Ga- Moloi 2019/20 Complete
11 Molepane 2013/14 Complete
22
Tjatane 2014/15 Complete
Madibaneng 2022/23 Complete
23 Dinotji 2014/15 Complete
252
Maila Segolo 2017/18 Complete
Sport, Arts and Culture play an important role in the physical, psychological, social, technical
and tactical development of young and matured people. Makhuduthamaga Local Municipality
plays an advocacy role/ function whereby most of the programmes are driven by the provincial
department of Sport, Arts and Culture. The communities within the municipality participate in
various sport, arts and culture programmes that are meant to promote a healthy lifestyle in the
society
253
Sports, Arts & Culture norms and standards
254
Eensaam Stam None Yes None
255
Mosehla None None None
256
Mashegoana Tswaledi None Yes None
257
Lekgwareng None Yes None
258
27 Maripana None None None
259
31 Ntshong None Yes None
The rural nature of the municipality suggests that even sports facilities will be in short supply.
There are very few sporting and recreational facilities most of which are sub-standard. The
community is forced to share some of the facilities with schools. The main sporting codes are
football, netball and cricket. Such codes are also played under noncompetitive circumstances
due to lack of funding and the quality of the fields. There are four Sports Centres: Peter
Nchabeleng, Phokoane, Mampuru Artificial Turf and Masemola. The artificial turf was
constructed in Jane Furse with the help of SAFA and National Lottery as part of the 2010
Soccer World Cup legacy programme. SAFA further sponsored the second phase of Artificial
Turf construction that included building of change rooms, toilets and bathrooms and drilling of
water. Upgrading of Marishane Sports Centre started in the 2019/20 financial year. Maintenance
and repairs were done in Peter Nchabeleng and the other facilities (Phokoane and Glen Cowie)
will be taken care of in the coming financial years when funds permit.
There is a need to construct few standard sports fields in the municipality. The provincial
Department of Sport, Arts and Culture was contacted in this regard and the following areas were
identified for sports facilities upgrading in the coming three financial years which are
Marulaneng, RDP Park /sports complex in Jane Furse, Mamone, Rietfontein and Masanteng.
The Municipality is recently developing policy to control use of Sports Centres for their smooth
management.
There has been no specific focus on Arts Crafts and Culture from a municipal perspective
except a few observations of Heritage activities. With the current IDP review, the Municipality
plans to introduce initiatives to respond to the citizens needs for the promotion of Arts Crafts
and Culture.
260
CHALLENGES INTERVENTIONS
o Lack of sport facilities for different o Coordinate and facilitate use of facilities
sporting codes o Investigation linked to the Organisational
o Lack of clear roles and review and redesign.
responsibilities for Arts , Craft and
Culture
3.3.16 Religion
Overall statistical analysis indicates that there are many places of worship (535) within
Makhuduthamaga. The actual number may be higher than what can be estimated due to the
growing recognition and subscription to theism (belief in the existence of God). Although we did
not go at lengths to evaluate the infrastructure of these institutions, it is reported that church
leaders and senior priests/pastors cry out that government gives religious fraternity least
attention. A predominantly theist community is often peaceful and add impetus to stability. This
fraternity often plays a lead role against tendencies that signify degeneration of morality. It is
therefore a blessing to have them.
There are seven Post offices in Makhuduthamaga municipality i.e. Jane Furse, Nebo,
Masemola, Sekhukhune, Glen Cowie, Marishane, and Mamone with several villages having
lobby’s offices. Post office still plays an important role in the lives of rural people on micro
banking, post services, information communication and technology. When future Post Offices
are provided it would be cost effective to look at a set up like the Thusong Service Centres
which could be a One Stop Shop for the consumption of government services. Post Office has
also embarked on a pilot project of installing house numbers in several villages within
Makhuduthamaga.
Services provided by Post Office: Post services, Banking, payments of services like car
registrations, TV licenses, accounts and etc.
Challenges
o Street delivery
o Households numbering
261
Distribution of households with a radio, television, refrigerator, computer, cell phone,
landline / telephone and access to internet by municipality
2001 2011 2001 2011 200 201 2001 2011 2001 2011 2001 2011 2011
1 1
State of Communication (postal services, land lines, network towers, radio & TV
reception) in Makhuduthamaga
1 No No No No No Lack of services
262
13 No No No Yes No No network
tower
15 No No No No No Postal service
only in Maila.
No network in
all villages
22 No No Yes No No Poor TV
&Radio
reception
263
27 Yes No No Yes Yes Poor network at
Mohloding
village
28 No No No No No No network and
reception
29 No No No No No No network and
reception
03 02 01 01 05 Fully
03 02 01 01 02 Fully
264
Community Based Care and Support Service Centres for Older Persons
Number of Number of CBCSS How many CBCSS Overall backlog for CBCSS
CBCSS centres receiving not funded
Centres funding
07 02 05 05
Drop in Centres
09 05 04 04 2/7
02 02 0 0 NPO
The Municipality has Makgwabe, Mogaladi and Phaahla Community halls as the only places to
can be used to accommodate communities during municipal meetings / activities, but some of
the halls are in poor state and as such the municipality will set aside a budget to rehabilitate the
halls. It also relies on traditional council’s halls and schools in various villages to accommodate
communities during municipal meetings and Imbizos. In some instances, even soccer fields are
used to hold big government functions because of insufficient halls within the municipal area.
265
3.3.20 Safety, Security and liaison mandate
Monitor Police conduct, Oversee the effectiveness and efficiency of Police service delivery
including receiving reports, promote good relations between community and the police,
report to cabinet member responsible for policing matters in the province.
In 2030 “people living in South Africa feel safe and have no fear of crime. They are safe at
home, at school, at work and they enjoy an active community life free of fear. Women can
walk freely in the streets and children can play safely outside.”
Makhuduthamaga Local Municipality has two Magistrate Courts located at Nebo and
Schoonoord (Sekhukhune)
1.Jane Furse Police Station Sekhukhune Police Station Nebo Police station
According to planning standards one police station supposed to serve 25 000 people. In
Makhuduthamaga therefore there were supposed to be 11 Police Stations
• Backlog: 07
266
There are Community Policing Forums (CPFs) in all Police Stations and Community Safety
Forums (CSFs) in all local municipalities.
Department of Community Safety is currently providing stipends to CPF and CSF members.
However, there is a need for local municipalities to consider the possibility of having a funding
model for the CSF structures.
The local municipalities are also expected to establish street committees in all wards.
Crime
1.Masemola Polokwane 07 08
3.Sekhukhune Burgersfort 10 10
4.Nebo Groblersdal 12 13
5.Hlogotlou Groblersdal 7 14
Sexual offences
1.Masemola Polokwane 13 20
3.Sekhukhune Burgersfort 43 34
4.Nebo Groblersdal 76 63
5.Hlogotlou Groblersdal 60 68
Assault GBH
1.Masemola Polokwane 68 60
3.Sekhukhune Burgersfort 43 34
267
4.Nebo Groblersdal 76 63
5.Hlogotlou Groblersdal 60 68
Common Robbery
1.Masemola Polokwane 08 23
3.Sekhukhune Burgersfort 34 27
4.Nebo Groblersdal 34 41
5.Hlogotlou Groblersdal 27 32
Burglary at Residential
1.Masemola Polokwane 49 57
3.Sekhukhune Burgersfort 70 84
1.Masemola Polokwane 03 04
3.Sekhukhune Burgersfort 04 11
4.Nebo Groblersdal 07 16
268
5.Hlogotlou Groblersdal 22 17
Stock Theft
1.Masemola Polokwane 30 39
3.Sekhukhune Burgersfort 34 21
4.Nebo Groblersdal 36 70
5.Hlogotlou Groblersdal 19 18
Polokwane Jane furse Kgoloko High School Drugs, dangerous weapons and
bullying
Polokwane Jane furse Phiri ya Gae High School Drugs, dangerous weapons and
bullying
269
Groblersdal Hlogotlou Zama Zama Secondary Substance abuse
School
Development challenges:
• Establishment of additional satellite police stations in some wards
• Revival and capacitating of Community Policing Forums
• Conducting crime prevention and awareness campaigns
- Performing an agency function for the Provincial Government by testing and licensing
vehicles on an agency basis.
270
3.3.22 Social cohesion
The following factors affect the required social cohesion among communities and individuals in
the municipality namely:
271
BASIC SERVICES DELIVERY AND INFRASTRUCTURE DEVELOPMENT SWOT ANALYSIS
272
• Inadequate resources e.g., Personnel and equipment
(sports and recreation facilities and parks)
• Operation and maintenance
• Inadequate resources e.g., Personnel and equipment
• Few professional artists
• Inadequate resources
• Ownership of libraries,Operation hours,Inaccessibility
273
THREATHS • Insufficient funds to implement the projects
• Lack of provision of water services
• Unco-ordinated Spatial Development
• (Topographical location of projects leads to natural
disaster)
• Delay in implementation of RDP houses.
• Insufficient electricity capacity on ESKOM existing
network
• Not electricity Licence holder.
• Community protests that could lead to vandalism to
existing infrastructure.
• Business forums interference during projects
implementation.
• Lack of municipal registered borrow pit.
• Competition with other institutions for revenue
collection.
• Poor maintenance and continuous network failure
which affects eNaTIS system
• Illegal public transport operations
• Environmental pollution
• Limited life span of landfill site
• Non-compliance to environmental assessment
regulations
• Interferences by stakeholders (external)
• Illegal disposal of waste
• Competing with private service providers for waste
collection services
• Mushrooming of informal settlements
• Reluctance to hand over the shelters after recovery
• Climate change impacts
• Increase on substance abuse and crime
• Dilapidating sports and recreation facilities
• Substance abuse and crime
• Dysfunctional art centres e.g., Lebone and Nogana
Moretsele Arts Centres
• Relocation of arts and culture professionals
• Substance abuse and crime
• Crowding
• Load shedding
• Competition from NGOs
• Limited controls over libraries
274
CHALLENGES
• High backlog of water and sanitation within the MLM area of jurisdiction
• Insufficient clinics
275
3.4. KPA 3: Local Economic Development (LED)
Economic growth is one of the main indicators of a progressing and developing municipality.
Makhuduthamaga municipality promotes agriculture, tourism and mining as the key growth
sectors. There are a number of mining exploration exercises that are taking place within the
municipality and should mining prove feasible, it will have an added impetus on the creation of
much needed jobs in particular and the growth of the economy in general.
The local economy is dominated by the tertiary/services sector, which accounted for 85% of the
local economic output in 2015. The secondary and primary sectors, respectively contributed
9.9% and 5.1% to the local economic output.
The major contributor to the municipal economy is the government sector, which contributed
approximately 41% to the local economy in 2015. The second largest contributor is wholesale
and retail (20%), followed by finance and business services 9% and community, transport and
communication services at 8%.
Makhuduthamaga Gross Value Added stood at R4.4 billion in 2015, making municipality the
third largest economy within Sekhukhune District. The dominant municipal economy in the
district is Greater Tubatse with a GDP of R6.3 billion
The primary sector’s output has increased in nominal terms from R38 million in 1995 to R221
million in 2015. However, the sector’s contribution to the local economy has declined from 7.3%
in 1995 to 5.1% in 2015.
Agriculture’s regional value output has increased from R3 million in 1995 to R18 million in 2015
– an average growth of 11% for the period. However, the sector is a marginal contributor to the
aggregate GVA, estimated at 0.4% in 2015.
Most of the land that is under cultivation in Makhuduthamaga is used for subsistence purposes
with only a small portion of the land under commercial farming. The scarcity of water may be the
reason why agriculture is not a larger contributor to the GVA of the area. Moreover, the status of
land ownership and the fact that a significant amount of the land in Makhuduthamaga is under
land claims hampers the development of the agriculture sector. Assessing the agriculture
potential in the area could help unlock some of the factors that inhibit the full usage of land.
Unlike Tubatse / Fetakgomo Municipality, Makhuduthamaga has a low level of mining activities.
This is also depicted in the regional value add of the sector to the local economy. The mining
sector has registered a growth rate of 14% since 1995, however, its regional economic value
add has declined from 0.6% in 1995 to 0.4% in 2015.
276
3.4.3. Secondary Sectors
The secondary sector of the MLM economy includes Manufacturing, Construction and
Electricity, Gas and Water Supply. The output of the secondary sector has grown from R51
million in 1995 to R431 million in 2015 – an average of 12%.
a) Manufacturing
Makhuduthamaga does not have a strong manufacturing base. The contribution of the
Manufacturing sector to Secondary sector GVA was estimated at R15 million in 1995 and this
increased to R69 million in 2015 – an average increase of 9% over the period.
Manufacturing contribution to the local output is very marginal across many areas with the
exception of Jane Furse and surrounding areas
The most common manufacturing activities include the making of sand bricks, windows, door
and steel frames. These activities respond to local demand from infrastructure development
relating to housing projects, road rehabilitation, and agriculture and to a lesser extent, mining
activities.
There is potential for growth in manufacturing if effective links can be made to exploit
opportunities resulting from the wholesale and trade sector and public sector infrastructure
spending.
The sector contribution to the local economy increased from R20 million (3.8%) in 1995 to R206
million (4.7%) in 2015 – an average decrease of 13% over the period.
The largest GVA contribution of electricity services is concentrated in Jane Furse and the
southern part of the municipal area
c) Construction
The contribution of the Construction sector to MLM GVA increased from R16 million in 1995 to
R156 million in 2015 – an average increase of 13% for the period.
This sector is linked to development within all the other sectors of the economy such as demand
for construction of public sector infrastructure such as housing, roads, and the provision of basic
services. Most of the work is currently sourced from outside of Makhuduthamaga, which poses
the challenge for locals to become competitive enough or partner with already competitive
contractors to share in this growth.
The tertiary sector’s contribution to the total economy has increased from R433 million in 1995
to R3.7 billion in 2015 – an average annual increase of 11%.
277
a) Wholesale and Retail
The Wholesale and Retail sector is one of the dominant economic contributors (20%) in the
municipality. The sector contributed R96 million to MLM economy in 1995 and this increased to
R867 million in 2015. This means the sector grew on average by a rate of 13% per annum from
1995 to 2015. The sector responds predominantly to local markets. Growth in this sector could
be explained by increased local spending power as a result of growth in the public sector.
The growth point in the Municipality, Jane Furse is a key retail centre and where repair services
are provided. It is evident, as well, that residents from these neighborhoods do a substantial
part of their shopping in the area. While formal trade is mostly restricted to Jane Furse, informal
trade takes place throughout the rural parts of the municipality, including the numerous villages.
The transport and communication sector is becoming more and more important each day,
especially as a result of the increase in activities in other sectors. The sector contribution to
local GVA was R49 million in 1995. This figure increased by an estimated 9% to R337 million in
2015.
The anticipated increase in public sector infrastructure development also requires movement of
vast amounts of material and people and thereby offers tremendous opportunity for passenger
transport and material. Jane Furse is the centre of logistics and communications
Finance, Real Estate and Business Services contribution to GVA increased from R47 million in
1995 to R393 million in 2015 – an average increase of 12% over the period.
The financial and business services sector is an equally important economic sector, especially
in terms of its enabling qualities in support of other sectors. The majority of these services are
concentrated within the economic node of Jane Furse
Personal, Social and Personal Services contribution to local GVA was R45 million in 1995. The
contribution increased to R343 million in 2015 - recording an average increase of 11% over the
period under review.
Government services sector is the biggest contributor to the local GVA. As the Municipality
grew over time so has been the need for additional government services. Accordingly, the
sector’s contribution to local GVA increased from R196 million in 1995 to R1.8 billion in
2015.The government sector employs 24% of the total population of Makhuduthamaga and
provides public services and invests in development work. Besides the employment created,
income generated and spent in Sekhukhune, the public sector also has a key role to play in the
economy in the way decisions are taken.
278
Gross Domestic Product (GDP)
The Gross Domestic Product (GDP), an important indicator of economic performance, is used to
compare economies and economic states. Gross Domestic Product by Region (GDP-R)
represents the value of all goods and services produced within a region, over a period of one
year, plus taxes and minus subsidies.
Greater
Tubatse/Fetakgomo
49%
Elias Motsoaledi
29%
279
Poverty
Percentage of People Living in Poverty - Local Municipalities and the rest of Sekhukhune
District Municipality
LMs
Greater
Tubatse/Fetakgomo
59,3%
Makhuduthamaga 66,0%
280
In terms of the percentage of people living in poverty for each of the locals within the Sekhukhune
District Municipality, Makhuduthamaga Local Municipality has the highest percentage of people
living in poverty, using the upper poverty line definition, with a total of 79.0%. This is due to fact
that there was no formal town in the Municipal area for many years. However, with the growth of
Jane Furse as the District Growth Point and the relocation of District offices from Lebowakgomo
to Jane Furse it is expected that the economic activities will boom and job creation will benefit
local residents.
The lowest percentage of people living in poverty can be observed in the Fetakgomo Tubatse
Local Municipality with a total of 70.4% living in poverty, using the upper poverty line definition
281
EPWP jobs created in Makhuduthamaga during 2014-2018/19 financial years
3500
2894 3115
Number of Work Opportunities
3000
2500
2000 1565
1500 Target (work
1000
840 706 opportunities)
500 121 10019 Achievement
0
Infrastructure Envir & Culture Social 2014- Total Protocol
2014-2018/19 2014-2018/19 2018/19 Target 2014-
2018/19
Year
35,0%
30,0%
25,0%
20,0%
15,0%
10,0%
5,0%
0,0%
282
Source: Global Insight 2015
Employment by sector
8 000
7 000
6 000
5 000
4 000
3 000
2 000
1 000
3.4.5. Agriculture
Constraints Opportunities
Municipality is mainly rural so there are few Suitable for grain production under dryland
economic activities.No commercial farming mainly maize (Leolo. Zaaiplaas)
so few people employed by the Agric sector
Irrigation production limited by water Retailers serve as market for vegetable
scarcity.( 2 irrigation schemes & small scale farmers (Pick n pay, Spar)
vegetable production inTjatane )
Highest number of livestock 49 013 cattle on Vleeischboom FPSU located in
communal as per LDARD census 2020 Makhuduthamaga and farmers will benefit
from the services
Overstocking results in overgrazing since Opportunity exist for local private tractor
cattle are kept in communal grazing areas owners to bid for Mechanization term contract
as the area has more hectares to plant
283
No private farms/ no land reform High number of cattle serve as source of
income and create jobs for herd men
Farmers must practise intensive farming eg
piggery and poultry which require less water
Agriculture is no longer just about food security and rural livelihoods to address social policy
questions but a major contributor to economic growth
The growth aspects of agriculture are threatened by several challenges which some contributed
to the decline in production over the years
➢ Rising input costs
➢ Deteriorating infrastructure
➢ Climate changes
➢ Persistence of infectious diseases and pest's infestation
➢ Poor management of natural resources
LDARD has intervening strategies that aim to address the aspects mentioned above
Land Capability in Makhuduthamaga is divided into three parts which are shown below
Grains: The area has Irrigation schemes Sorghum is produced in these areas
higher rainfall and isalong Oliphant's river which include the low lying areas of
most suitable for rain(Setlaboswane-119 Schoonoord, Ga Masemola and
fed maize production. hactres and Kolokotela- Diphagane, Phaahla towards Mamone
These includes all the240 hactres) (though and Madibong, Moretsele, Makgane.
villages in Leolo and none of them is
the villages along theoperational currently)
NEBO maize belt Vegetable crops Ga
Masemola and around
Schoonoord
Source: Department of Agriculture and Rural Development 2023
Tomatoes cover more production land followed by other crops like cabbage, butternut,
watermelon, onions and most recently garlic.
o Villages around Ga Masemola irrigate using canals from Lepelle river. Their common
challenges are farming infrastructure including fences and irrigation infrastructure
o Villages around Schoonoord use the Psirwa river as their water source, however the
water level is not adequate to serve those who are farming further away from it and thus
their main challenge is water infrastructure, be it in the form of boreholes for those
further away and/ stronger pumps for those who can still access water from the river.
284
7 vegetable farmers received seeds, medication and fertilizers through the Letsema program
and 170 household backyard farmers received seeds and hand tools through the Food Security
program
Maize Production
High potential arable areas produce maize and intercrop with beans and groundnuts. Maize is
produced in Leolo area with very limited land but very high yields. The farmers in Leolo have
now affiliated to GrainSA to improve their skills capacity.
300 farmer received seeds, LAN fertilizers and mechanisation services through the Ilima/
Letsema program
650 farmers received seeds and mechanisation services through the Ilima/letsema program
Fall Army Worm remains the common challenging pest in maize farming and this season it has
hit Leolo area.
Invasion by birds remain the most common challenge amongst sorghum farmers and thus only
a few of the farmers are able to persevere up to harvesting.
The farmers in this low production areas were assisted with sugar bean seeds as production of
such is met with lower challenges unlike with sorghum.
Livestock Production
This is practiced throughout the municipality but higher numbers are found around the
Masemola area. The area is also the one which is most prone to draught and lots of livestock is
often lost during very dry seasons in Masemola area.
A total of 230 livestock farmers have each received 6 bags of lucerne pellets through the Ilima
Letsema program. Farmers also get subsidised with bags of fodder each year to reduce the
impact of drought on production.
Livestock watering (borehole, windmill, drinking troughs) were also erected at Mphane and
Sehuswane villages through the Drought Relief fund
285
Other Commodities
Poultry production includes broiler and layer production.3 smallholder farmers supported with
feeds for broilers and one layer producing farmer also received feeds
1 Smallholder pig farmer and 10 subsistence pig farmers also received feeds through the Ilima
Letsema program
Skills Development
Twenty-two farmers were trained in water rights through liaison with DWA
Five farmers received training on Climate Smart Agriculture.Farmers also receive training
through coordination with other institutions.
Agriculture
6,0%
5,0%
4,0%
3,0%
2,0%
1,0%
0,0%
286
Mining
50,0%
45,0%
40,0%
35,0%
30,0%
25,0%
20,0%
15,0%
10,0%
5,0%
0,0%
287
Manufacturing
4,5%
4,0%
3,5%
3,0%
2,5%
2,0%
1,5%
1,0%
0,5%
0,0%
Employed 19534
Unemployed 32780
288
MLM Population aged between 15 and 64 years by employment status – 1996, 2001 and
2011
LM unemployment rate
45,0%
40,0%
35,0%
30,0%
25,0%
20,0%
2012
15,0% 2013
10,0%
5,0%
0,0%
289
Source: MLM 2017
290
The municipality has implemented a number of temporary job creation initiatives through the
implementation of the Expanded Public Works Programme (143), The Community Works
Programme (1235), Municipal Infrastructure Grant (80) and Equitable Share (113) in the
2022/2023 financial year.
Occupation structure
The overall occupation structure of the employed population of MLM is represented in table
below. Notably, there is a relatively small proportion of people employed in the professional
occupations.
The spatial distribution of the occupation sector throughout the municipality which is dominated
by the elementary occupations closely corresponds with the dominance of the agricultural
sector.
3.4.8. MLM Occupation levels
291
Occupation Male Male (%) Female Female Total Total
(%) (%)
Life science and health associate 100 0.19 375 0.46 475 0.35
professionals
Personal and protective services 446 0.83 233 0.28 679 0.50
workers
Metal; machinery and related trades 238 0.44 21 0.03 259 0.19
workers
292
Occupation Male Male (%) Female Female Total Total
(%) (%)
Sales and services elementary 386 0.72 1266 1.54 1652 1.21
occupations
Not applicable (not economically 48263 89.43 77239 93.84 125502 92.09
active)
For Makhuduthamaga economy to grow sustainably, revenues and investment flows must
increase, preferably from external markets. Economic grows flows when businesses in local
sectors become more competitive in external and/ or local markets. The market responds to
better goods, at lower prices by increasing sales often lead to increased investment
It is therefore necessary to determine which external markets Makhuduthamaga based firms
can compete in profitably and sustainably. These markets and sectors offer the most
opportunity for self- sustained economic growth and, therefore become strategic priorities for the
municipality. Furthermore, it is important to understand the nature of competitive advantages
and disadvantages in these markets and to recognize which factors are critical to success and
which still constrain the relevant sector’s performance
Challenges Interventions
The regulation and promotion of informal Develop an economic development strategy, and
trading informal trading policies
Lack of formal economic development Identify land for Economic development initiatives
opportunities
293
Lack of informal trading infrastructure Identify informal trading areas
Effectively, rural development is an approach for economic and social development in rural
areas. It is not a service based project, but an outcome that Makhuduthamaga Municipality
together with other spheres of government wishes to achieve.
The Municipality is in the process of localizing the National Comprehensive Rural Development
Strategy and it has also been identified as a CRDP site.
294
3.4.12. Tourism
The Municipality has developed and adopted the Tourism strategy. Annually the Municipality
produces Tourism brochures to market the Municipal Tourism areas and products. Tourism
Exhibition Centre is planned for Jane Furse by the municipality.
The municipality intends to enhance and maximize its tourism potential as eco-tourism presents
the potential to be a major employer and economic driver in Makhuduthamaga.
• Develop eco-tourism and promote natural assets such as Leolo Mountain, and Manche
Masemola
Tourism has been identified as one of the major growth sectors in the Makhuduthamaga Local
Municipality
Heritage
Heritage has a key role in uplifting and positioning tourism development in economy.
295
Name of Location Significance / Current status/ Intervention
the attributes Developments needed/Developments
attraction
was brutally Makhuduthamaga • Maintenance at the grave
murdered by her Local Municipality, site
parents for refusing Local, SAHRA,
chieftaincy and local
to abandon her
community to discuss
holy beliefs in some of the
favour of traditional interventions needed
and spiritual up at the site.
bring. . Her grave
turned to be one of LEDET to erect two
the world’s tourism signage on the
main road leading to
pilgrimage centres
Manche Masemola
since 1935 when
small groups of
Christians visited
the site annually to
commemorate the
heroine who vowed
to be baptized with
her own blood.
Today the grave
site of Manche
Masemola is
visited and
celebrated yearly
on the first week of
August by
hundreds of
tourists, especially
Anglicans from all
over the World. Her
statue has been
erected in West
Abbey Ministry in
London -Great
Britain.
Kgoshi Mamone Kgosi Mampuru II, Annual National event 1. Determine the economic
Mampuru II Village who was heir to the of commemoration impact of the event on local
Heritage Bapedi throne, was held on the capture business
Site executed in public, site of King Mampuru
at the Pretoria II (Mamone Moshate)
Central Prison now to commemorate his
296
Name of Location Significance / Current status/ Intervention
the attributes Developments needed/Developments
attraction
renamed after him, resistance to colonial 2. The impact of the event on
for public violence, and apartheid the occupancy rate in local
revolt and alleged government. accommodation facilities
murder of
Sekhukhune in The statue of King 3. Ablutions facilities needed
1883 by the then Mampuru II is erected 4. Tour guides needs to be
Paul Kruger on the site at Mamone trained
administration. Moshate. 5. Link the site with Manche
President Jacob Masemola gravesite
Zuma renamed the 6. Marketing the site as an all
Pretoria Central year round tourist attraction
7. Tourism management plan
Prison after Kgosi
for the site
Mampuru II as part 8. The need for local
of government's municipalities to recognise
heritage events as tourist attractions
programme that and major contributors to
includes the economic growth
restoration of the 9. Engage planning committee
to determine the tourism
dignity of the
multiplier effect of the event
people of South 10. Tourism signage
Africa and 11. Interpretative signage onsite
upgrading and
declaration of
historic sites to
ensure a more
representative and
inclusive South
African history and
heritage. It is
commemorated
yearly during the
second or third
week of January at
Mamone Royal
Kraal.
Tisane Ga-Tisane Tisane cultural NDT initiative: SRI LEDET to play a monitoring role
Cultural heritage site which on the project pending additional
Heritage holds the history of Project uncompleted funding from NDT
Pedi culture.it has due to lack of funding.
strong walls, built in
the form of kraals
297
Name of Location Significance / Current status/ Intervention
the attributes Developments needed/Developments
attraction
and they were NDT still waiting for
constructed wisely additional funding to
by the forefathers to complete the project
defend themselves
against enemies.
Also home of the
Matjading fortress
the long passage
between boulders
that leads to a
secret cave
beneath rocks. Also
other caves of
fascinating history
that could be of
interest to tourists.
1. Eensaam tourism site The Eensaam tourism site stretches 190 hectares on the
reef of the Nebo plateau. It constitutes mainly of historical
sites and cultural heritages. Seefane “the wind tree”, view of
De hoop Dam from the peak of this mountains, the fountain
of luck, mephato “initiation schools” and lediba la pula,
which is place where traditional healers go and perform
certain rituals in order to wish for the rain.
298
Accommodation facilities within MLM
299
Mogorwane Lodge No 05 No No Mogorwane 076 778 5383
/079 916
5216
The following are some of the tourism hot spots that needed to be developed into
tourism products:
❖ Sekhukhune Centre of Plant Endemism: underlain by the Bush veld Igneous Complex
and covers areas of approximately 5,449 square km. i.e. Protea Flower and Yellow Arum
Lily flower
❖ Wetland and Protected area: Game parks and nature conservation
❖ Scenery of Leolo Mountains: Adventure, Scenery, Hiking and Trail.
CHALLENGE INTERVENTION
Accommodation facilities not graded Resuscitate the Local Tourism Association
Lack of signage Install signage where needed
Tourism information centre Establish a fully functional Tourism Information
centre
300
LOCAL ECONOMIC DEVELOPMENT SWOT ANALYSIS
STRENGTHS ▪ The department has its legal legislations which are approved
by Council such as SPLUM bylaw, Spatial Development
Framework, Building Control Policy, land Use Scheme, LED &
Tourism Strategy(ies) etc
▪ Committed and competent staff
▪ Functional JDMPT
▪ Precinct plans developed to guide development in identified
nodes
▪ Declared as Business Registration & Licensing Centre
▪ Several strategically located economic hubs/nodes identified
and studied
▪ Good relationship between MLM and traditional authorities
within its jurisdiction
▪ Piloting of the Farmers support programme (Eensaam, Leolo
)
301
▪ Lack of Willingness of the Traditional Authorities to release
the land
Challenge
o Climate change
The municipality has budgeted a total Revenue of R 516.7 million for 2024/25 financial ye,
R520.2 million and R 520.5 million for 2025/26 and 2026/27 respectively. Total revenue has
decreased by R 43.3 million for the 2024/25 financial year when compared to the 2023/24
adjusted revenue budget. For the two outer years, total revenue will increase by 0,669 per cent
and 0.055 per cent respectively. The total revenue for 2024/25 includes the grants allocations
from the national treasury to the amount of R 452.5 million and own revenue sources to the
amount of R 64.2 million. For the two outer years of the MTREF 2025/26 and 2026/27 total
grants allocations included in total revenue amounts to R 520.2 million and R 520.5 million
respectively while own revenue increases to R 68.8 million and R 74 million respectively.
Total operating expenditure for the 2024/25 financial year has been appropriated at R 417
million and translates into an operating budgeted surplus of R 99.7 million as indicated in table
1 consolidated overview above. This surplus will be used to fund capital expenditure for 2024/25
as indicated in table 1 consolidated overview above. The operating surplus for 2024/25
decreased by R 43 million as compared the 2023/24 operational surplus. The operating surplus
for the two outer years increases to R 2.9 million for 2025/26 and to R 7.9 million in 2026/27
financial year. These surpluses will be used to fund capital projects for two outer years. The
municipality will use cash backed reserves to an amount of R 56 million to fund the capital
expenditure in excess of the budgeted revenue over the MTREF. This reserves are cash
backed for vat refunds.
302
The total capital budget for 2024/25 financial year amounts to R 155.7 million. For 2025/26
and 2026/27 budget years, the capital expenditure is budgeted at R 156 million and R 169
million respectively. The municipality’s revenue enhancements strategies programme is aiming
at amongst other things to address this reduction in capital expenditure in the future budget
years.
NET INCREASE/ (DECREASE) IN CASH HELD (103 809) (42 611) (36 417) (36 417) – (28 732) (31 741) (34 682)
Cash/cash equivalents at the year begin: 2 101 007 101 007 101 007 64 590 35 858 4 117
Cash/cash equivalents at the year end: 2 (103 809) 58 396 64 590 64 590 – 35 858 4 117 (30 565)
303
Billing System
Property rates billed based on the valuation roll based on market value on monthly basis which
is performed by the professional valuer. Our first valuation roll was signed by the valuator on the
31 January 2007 and implemented during the 2009/10 financial year. MLM collect rates from
Businesses and Sector departments.MLM use a system called Accpac to perform all its financial
transactions.
The Municipality has established fully functional Budget and Treasury Department in line with
chapter 9 sections 80 of MFMA and the role of Budget and Treasury department. The
municipality has a challenge with regard to generation of own revenue since the municipality
does not offer services like water and sanitation, electricity due to limitations on powers and
functions. The municipality has always maintained positive cash flow and it does not finance its
operation through loans and overdrafts.
In terms of expenditure management, the municipality has always maintained watertight system
of internal control and at all times municipality adheres to the principle of paying creditors on
time which is 30 days’ payment period. Municipal credit control and debt collection policy has
been fully utilized to ensure that all amounts that are being owed to municipality are indeed
recovered within 60 days’ invoice period and the ultimate intention is to recoup all the accounts
receivable within 30 days’ period. Furthermore, municipality has introduced a system of internal
control as early warning mechanisms to detect unauthorized, irregular, fruitless and wasteful
expenditure as well as unfunded mandates.
For the KFAs below, we have only included the current challenges and issues.
o Optimizing and sustaining Councils o Implement credit control and focus more on
revenue consumers that have the ability to pay for
o Increasing internally generated funds Municipal Services/ rates
for funding operational and capital
expenditure
304
3.5.2 Revenue Enhancement/ Management
Challenge Intervention
Challenge Intervention
o Correct alignment of cost drivers to o Establish and comply with activity based
appropriate expenditure through costing component.
Activity Based Costing model o Prepare municipal budget in line with the cost
containment practice note issued by National
cabinet for all government departments.
Challenge Intervention
Challenges Intervention
o Late appointment of service providers o Review, update, and improve the planning
for implementation of capital projects cycle of the procurement of capital projects and
items.
o Budget & Treasury to prepare an annual
procurement plan that will guide the processes
timeously.
305
3.5.6 Supply Chain Management
Committees Function
Challenges Intervention
Challenges
None
3.5.8.1 Budgeting
Challenges Intervention
o Dependence on grant funding by o Concentrate on debtors that can afford to pay and
national and provincial government enforce the credit control and debt collection
policies with a view of enhancing Council revenue
306
the CRR with a view of cash funding the budget
from access available funds
Section 214(1) of the Constitution of the Republic of South Africa, 1996 requires an Act of
Parliament to provide for the equitable division of revenue raised nationally among the National,
Provincial and Local Spheres of Government and any other allocation to Provinces, Local
Government or Municipalities from the National Government’s share of revenue, and conditions
on which those allocations may be made.
Makhuduthamaga Local Municipality receives the following grants on yearly basis as per
Division of Revenue Act (DORA)
Conditional grants
Municipal Infrastructure Grant R74 062 000 R77 411 000 R80 902 000
(MIG)
Unconditional grants
Equitable Shares (ES) R344 706 000 R366 686 000 R 354 762 000
307
3.5.10 Existing revenue sources
Revenue Observation
Investment and tender documents The interests earned on investment and tender documents are also
revenue sources
Traffic functions(licenses and permit) The devolution of the traffic function will positively impact on
revenue generation like vehicle licensing, driver’s licenses and
traffic fines
Property rates The Municipal Property Rates Act, 2004 was promulgated with
effect from 2 July 2005.Property rates would be one of the primary
sources of revenue for the municipality. Factors that will determine
the amount that a property owner must pay to the municipality
include: the assessed value of the property, the effective
assessment rate etc.
Business registration and licensing The service was formally transferred to the municipality and the
municipality LED staff receiving training to over everything from the
Department
The MLM’s revenue sources are both internal and external. The internal sources contribute
about 18% of the total revenue of the municipality while external sources make up to 82%. The
internal sources include vehicle licensing and registration, property rates (businesses) and
interest earned on investment and tender documents. The external sources of revenue at the
disposal of MLM are grants and social donations from private sector. Some grants are often
conditional such that the municipality is not at liberty to spend otherwise despite deserving
needs.
Makhuduthamaga Local Municipality Audit opinion as per the 2022/2023 AGSA Opinion:
308
FINANCIAL VIABILITY SWOT ANALYSIS
309
THREATS ▪ Grant dependency and unsustainable budget
▪ Emerging competition on municipal (post office, pick n pay)
▪ Inadequate inter departmental intergration
▪ High demand for services with limited resources (Public expectations to
render services)
▪ Community protests (loss in public confidence)
▪ Regression in Audit opinion (once off opportunity to adjust)
▪ Introduction of material irregularity (concept by AGSA (MI)
▪ Resistance by customers to pay municipal services (writing off of debts)
▪ Inadequate access to land
▪ Grade regression
▪ Inadequate capacity from Eskom leading to poor implementation of INEP
projects
▪ Re –activeness to development leading to loss of revenue
Challenges
Section 53 of the Municipal Systems Act, Act 32 of 2000, stipulates inter alia that the respective
roles and areas of responsibilities of the political structure and each Political Office Bearer of the
Municipality and of the Municipal Manager must be defined.
310
Table 3: Makhuduthamaga Municipal Council consists of 62 Councilors and the political
party representation is as follows:
The Mayor of the Municipality Minah Maitula assisted by the Executive Committee heads the
Executive arm of Council. The Mayor is at the centre of the system of governance.
The Mayor operates in consent with the Executive committee (see table below):
311
Clr MG Machaba Deputy Head Economic Development and
Planning
The Table below indicates with their capacity and political party
312
Clr Nkadimeng KT Ward Councilor -17 ANC 076 345 8965
313
Clr Laka EL PR Councilor DA 072 878 1078
314
3.6. 1.4 Additional Committees
In addition to the above, the municipality has various committees, these include:
Section 80 Committees:
I. Corporate Services
Section 79 Committees:
X. Ward committees
315
o Prepare joint strategy
workshops with local
municipalities, provincial
and national role players
Office of the Premiere o Ensure Medium Term Inadequate
Framework and Strategic monitoring of
Plans of Sector sector
departments considers
departmental
IDPs
o Support and monitor participation in the
CoGHSTA alignment IDP/Budget
responsibilities processes
No progress
reports on
implementation of
projects
IGR Structures (IDP Rep forum, o Provide dialogue between Ineffective DDPF
IDP Managers/ Officers sectors for holistic
Forum,PDPF,DDPF) infrastructure development
o Promote inter-
governmental dialogue to
agree on shared priorities
and interventions
LEDET o Provide advice on Adhered to more
environmental, economic particularly on
development and trading environmental
issues
issues
316
Treasury o Provide support to ensure Adhered to
that the municipality
complies with MFMA and
relevant regulation
Civil society o Inform and consult various Not enough
(CBOs,NGOs,Organisations for interests of the community resources are
Youth, women and people with available to meet
disabilities, tertiary and research needs of all
institutions interests groups
317
IDP Rep Forum and Mayoral Imbizos
The Forum is functional as per approved process plan. The Mayor together with Councilors
held Imbizos whereby ordinary community members are given chance to raise their views in
terms of service delivery challenges and report to them on progress made by the
Municipality.
The Municipality has established 31 Ward Committees which assist Council in terms of
liaising with the community. They play a role as link between the Municipality and
Community and facilitate development of long term vision. Ward committees ensure that the
views of the communities are captured in the IDP by attending to public participation
meetings and submitting inputs to the Municipality. The Municipality has developed a Ward
Committee Policy to ensure the effectiveness and efficiency of system. They assist in terms
of monitoring Municipal Institutional Performance. The Ward committees’ reports get
evaluated every month for the purpose of monitoring their functionality and effectiveness.
The Municipality has 24 Community Development Workers (CDWs) deployed to 31 wards
and remain with 7 wards without CDWs. This is constituted by 15 females and 9 males. The
CDWs are linked directly with Public Participation Office which is in the Office of the
Speaker.CDWs attends all ward committee meetings duly convened by the Chairperson
(Ward councilor) of the ward committee. They serve as resource persons during the official
sittings of the ward committee
Traditional leadership
318
Marota Tanker VIP Available Tarred
Madibong
319
Phokoane Tanker VIP Available Tarred
CHALLENGES INTERVENTION
The Municipality is critically aware of the impact of risk on service delivery. As such; it has
developed extensive risk mitigation measures for both strategic and operational risks that
have been identified. The municipality has adopted an integrated approach to risk
management with the primary aim of embedding of a culture of making a correct and timely
decisions that take in to consideration associated risk exposures and opportunity.
320
Risk governance in the Municipality
The Municipality has Independent Governance Oversight and Advisory committees, namely,
Risk management Committee and the Audit Committee, which operate in accordance with
Council approved terms of reference, Corporate governance guidelines and practices (King
III). This will ensure both the reliability and quality of advisories and integrated reporting to
the council.
Some of the key strategies in the short-to-medium term to ensure successful implementation
of risk governance and enterprise risk management in Makhuduthamaga Local Municipality
are listed below:
VI. Continuous risk assessment, design and implementation of risk response and
continuous monitoring.
o Insufficient Staff
Audit Committee
The Internal audit component of the municipality was established in terms of the approved
organizational structure to ensure that the municipality has systems and processes in place
that will ensure or improve compliance to various legislative requirements, thus trying to
achieve a better audit opinion. The Audit committee was appointed through a Council
resolution. This committee reports directly to council to assist it to achieve its oversight role
efficiently and appropriately based on the expertise of the various members of the
committee.
321
Section 166(2) of the MFMA state that an Audit Committee is an independent advisory body
which must amongst others advise the Municipal council, the Political Office Bearers, the
Accounting Officer and the management staff of the municipality, on matters relating to:
In the financials under review the Audit committee also performed the Performance Audit
Function.
For the past five years the Municipality has performed well according to Auditor General’s
reports in terms of Financial Management and finance related matters.
Analysis of Audit Opinion by the Auditor General over the last five years
Anti-Corruption
• To prevent and combat fraud and corruption and related corrupt activities
322
3.6.4 Inter Governmental Relations
The main purpose of IGR in a Municipality is to coordinate, facilitate and intervene between
the various functions and responsibilities of the different spheres of government as well as
interactions with Parastatals, private sector and other stakeholders within our functional
sphere in order to influence the effective delivery of our mandate.
The municipality endeavors to ensure the full implementation of the IGR framework through
the establishment of the IGR Forum that is represented by Municipal officials as well as
sector departments within the district.
o To coordinate and align priorities, budgets, policies and activities across interrelated
functions and sectors
CHALLENGES INTERVENTION
Customer care
323
satellite offices, this enables the municipality to deal with the needs and provide feedback to
complainants. All employees were provided with new nametags in March 2023. The
municipality managed to hold Bathopele build up activities successfully on the 20th October
2022. The Customer Care personnel also helps in ensuring that clients do not wait for longer
periods of time before receiving services from our offices including DLTCs
Premier 09 12 14 18 18
Hotline
Bathopele Survey not Survey Survey not Survey not Survey not
survey conducted conducted conducted conducted Conducted
324
CHALLENGES INTERVENTION
CHALLENGES INTERVENTION
The MLM has developed and adopted Disaster Management Plan during the 2007/8
financial year and reviewed in the 2022/23 financial year. The plan is aimed at disaster
prevention, mitigation, preparedness, response, recovery and rehabilitation. It also aimed at
providing an enabling environment for disaster management in the municipal area.
325
Promote pro-active disaster management through risk reduction programmes, promote
cooperative relationships between all spheres of government in case of emergency
incidence.
The Municipality assists in terms of providing relief materials in the form of temporary
shelters, sponges and blankets.
The general priority of the law enforcement unit is to ensure that the community is adhering
to the By-laws and policies of Makhuduthamaga Municipality. This unit works hand in hand
with all municipal departments, the SAPS and other sector departments.
326
WEAKNESES o Shortage of office and variable storage space.
o No proper need analysis prior to creation of position
(Work Study)
o Inconsistent application of consequence management.
o Lack of feedback to communities (Inadequate public
participation)
o Lack of Municipal Anti Fraud and Corruption Hotline
o Shortage of service delivery oriented staff (core vs
support)
o Lack of internal audit and Risk Management Software.
o Inadequate internal communications mechanism (e.g.
intranet)
o Lack of digital strategy (paperless systems)
o Lack of integrated IT systems
CHALLENGES
327
o Lack of complaints management system
o Ineffective and inefficient implementation of training and capacity building
programmes
o No capacity and inadequate budget to fund placement of bursary holders (internship
programmes)
o Non adherence to HR policies (Leave and time management)
o Exclusion of people living with disabilities on municipal programmes
328
3.7.2 Staff compliment: 2023/2024
Office of the 12 11 7 4 1
Speaker and
Chiefwhip
Office of the MM 12 12 4 8 0
Budget and 44 44 22 22 0
Treasury
Community 81 74 46 28 7
Services
Corporate Services 22 22 11 11 0
Economic 14 12 7 5 2
Development and
Planning
Infrastructure 30 20 11 9 7
Development
Employment Equity
The staff component of the Municipality is made up of ninenty (91) women, one hundred and
eleven (114) men and one (1) disabled employee in terms of Employment Equity
representations.
329
Employment equity challenges
The Municipality is grappling with employment equity challenge of ensuring that its
structures reflect equitable representation of all groups, particularly people living with
disability. The male- female ratio stands at 84:66. The ability to retain and attract skilled staff
is limited – a situation is reflected in the number of vacancies in the Organogram.
From the adopted SDBIP the municipality abstracts Performance Contracts of the Section
57 employees which become the Departmental annual business plans. Departments report
progress on the implementation of the SDBIP to Management reviews; Exco – Makgotlas,
Executive committee and Council for adoption. The purpose of these sittings is to monitor
progress and performance in terms of the implementation of the IDP and budget and to
propose reviews where necessary. The municipality is currently developing Organisational
review and staff re-engineering to address work processes, job descriptions and to do
comparative job evaluation on the basis of TASK system.
A Midyear a report (Section 72 report) is developed from the Quarterly reports generated
during the EXCO Lekgotla sessions. Municipal annual service delivery reports are generated
from this process on annual basis which amongst others will inform the formulation of the
annual report. After the adoption of the Annual report by the Municipal Council, the
Oversight Committee scrutinizes the report and makes final recommendations to the council
for the adoption of the final Oversight report which will then be open for public consumption.
All Section 57 Managers have signed Performance Agreements for 2023/2024 financial
year.
330
Administrative Structure
Makhuduthamaga Local Municipality is divided into six departments which are interrelated:
o Corporate Services
o Community Services
o Infrastructure Services
MSA 32 of 2000 s68 (1) requires municipalities to develop their human resource capacity to
a level that enables them to perform their functions and exercise their powers in an
economical, effective, efficient and accountable way.
Municipalities are required in terms of the Skills Development Act No. 97 of 1998 to facilitate
training for capacity building in order to address skills gaps. A skills audit is conducted on an
annual basis to inform the Workplace skills plan which guides all the training to be
conducted throughout the year. The plan is developed in consultation with the staff members
and councilors. Individuals from the mentioned stakeholders’ complete questionnaires that
serve as tools to identify training needs. The training needs are further consolidated into
WSP / ATR and submitted to LG SETA after approval by the Council on time as legislated.
This should be able to address the issues of scarce skills. MLM has a training committee,
which comprises of labour, Management and council; its role is to ensure that all training
activities are done in consultation with all relevant stakeholders and are to the benefit of the
Municipality by enhancing the skills and knowledge in the individual’s functional area.
Although line managers and staff identify their skills needs as contained in their completed
skill audit plan, the alignment of such needs with their responsibilities is crucial, thus the
HRD & OD division supports them through organizing trainings, workshops, seminars and
internal bursaries.
These interventions mentioned above are being implemented to ensure individuals are able
to achieve their Perfomance Management Development System (PMDS) goals and as in
alignment with their identified capacity gaps and interventions, which are contained in the
individual staff members’ Personal Development Plans (PDPs).
It is critical to note that among others, the critical skills need within the Municipality are
Engineering, Town Planning, and Finance and Leadership skills for Councilors, which are
being targeted through the offering of municipal bursary for students from indigent families
331
3.7.5 Occupational Health and Safety (OHS)
Makhuduthamaga Local Municipality has established Occupational Health Safety Committee in
line with Occupational Health and Safety Act, Act 85 of 1993. There are seven (7) appointed
Health and Safety representative for all municipal offices including satelites. The committee
meets on a quarterly basis. Thirteen (13) OHS committee members have received training on
OHS legislation, Hazard Identification & Risk Assessmet (HIRA), incident investigation, and
HSE representative.
The Municipality has 39-trained officials for First Aid Level 3 & Basic Fire Fighting & Evacuation
Awareness. These trainings are in line with the rrequiremnts of the Act and its regulations, and
are valid for three (3) years.
The unit will perform the following functions in an effort to ensure Health and Safety
within the workplace.
• Implementation and Enforcement of Occupational Health and Safety Act and its regulations.
• Facilitation of medical surveillance assessments and follow-ups for all employees.
• Management and recording of all incidences and occupational diseases, including reporting
to Department of employment and Labour.
• Monitoring of municipal construction projects to ensure compliance with relevant
legislations.
• Conduct orientation and induction of all newly employed officials on OHS issues.
• Facilitation and provision of Personal Protective Equipment PPE (including protective
clothing)
• Conduct all administrative duties related to OHS including policy formulation, its reviewing
and report writing
• Facilitate the administration of Returns of Earnings (ROE’s) as per the COID Act 130 of
1993.
Disposal
332
Electronic Document System (Therefore)
The Municipality has installed an electronic records management system called THEREFORE.
The system assists it by giving assurance incase of fire or floods that can destroy the physical
records. Records Champions received training on the Electronic System (TEREFOR) and
monthly they upload their records on it. Other employees and sections received one-on-one
training as well. Management is updated monthly about progress made by each department
Municipal Council annually approves an Organisational Structure that has been reviewed and is
in line with the new needs/ mandates identified during its consultative engagements with its
communities.
The performance of powers and functions, and delivery of the IDP projects is dependent upon
appropriate and funded organisational structure. A model for organisational structure for Grade
four (04) municipalities was used as a base to develop the municipal organisational structure.
The powers and functions that are for the municipality were also considered in the process.
Office of the MM 12 12 4 8 0
Community Services 81 74 46 28 7
Corporate Services 22 22 11 11 0
333
Infrastructure Development 30 20 11 9 7
Flowing from Public Participation Engagement with Communities and Stakeholders within
Makhuduthamaga Local Municipality, the following issues repeatedly surfaced as overarching
needs of the community:
1. Water and sanitation: water supply to communities is highly needed. The need to fix recurring
broken water pumping machines and leakages of pipes.
2. Roads surfacing and provision of sufficient bridges and storm water drainages. Many roads
were destroyed by heavy rains and floods in some areas. Speed humps.
3. Electricity post connection and solar energy
4. RDP houses (Sufficient and fast tracking delivery of RDP houses, proper construction and the
need to complete the incomplete houses).
5.Better/tarred roads
6. High unemployment and illiteracy level.
7. Spatial issues.(releasing of land for development by traditional authorities eg government
offices,shopping malls,municipal cemetery and etc)
8. Cell phone, TV and radio reception in some areas.
9.Inadequated Childcare facilities and libraries services
10.Wifi connections
11.Waste collection
12.IGR improvement
14.Mast lights to combat crime
15.Health facilities
16.Load shedding
17.Institutions of Higher Learning e.g TVET Colleges
Source: MLM 2023
Women Empowerment
Women empowerment is a phenomenon that is high on the agenda. The municipality has
woman Mayor as part of empowering them. Women should be encouraged to partake in
developmental projects that would assist them to get out of the poverty line that they found
themselves in. This means that the resources should be channeled in the direction of women
empowerment projects in order to empower them economically and politically. The municipality
has developed a policy on how women matters can be approached and addressed.
334
Youth Empowerment
The Municipality has appointed an official to deal with youth matters. It is in this office where
issues that affect the youth are attended to. Issues that affect the youth are unemployment, lack
of housing, poverty, shortage of skills, high level of crime and violence, social and family
disintegration and other social ills like HIV/AIDS.A youth Council has been established as a
platform whereby youth discuss and agree on issues that affect youth. It is within this
background that youth development policy was developed to assist youth and young people to
deal with issues that affect them such as unemployment, skills shortage, and vulnerability and
under resourced. Resources should be biasely channeled towards the development of youth’s
projects for the upliftment of young people of the municipality to stop the escalating crime and
violence. Makhuduthamaga Youth Council was re-launched in February 2017 by the Office of
the Mayor.
Gender Equity
Gender inequalities exist in the social, economic, physical and institutional environment of the
municipality. The municipality has put in place an employment equity plan with monitoring
indicators that are gender disaggregated. Within the municipality, several initiatives have been
undertaken to advance the national gender agenda. Amongst others, a gender procurement
scoring system is in place to encourage the economic empowerment of women entrepreneurs
and companies.
Children
The Office of the Mayor through their Special Programme Division Support Rights of Children
through
▪ Annual celebration of children’s day, and participating in annual activities aimed at
promoting the rights of Children.
Aged / elderly
The Office of the Mayor through their Special Programme Division supports Aged development
programmes through:
▪ Celebration of Social development month
▪ Programmes initiated by the Makhuduthamaga Aged group
HIV/AIDS
The Municipality has developed and adopted policy on HIV/AIDS during 2008/9 financial year.
The policy was reviewed during the 2015/16 financial year.HIV/Aids Council was re-launched
during 2015/16 financial year. Mother-Children dialogue on HIV/Aids was held in collaboration
with Sekhukhune Educare Project and Image.
335
Provincial Prevalence by District
The District is the second lowest in terms of people that are living with HIV in the province. This
is also reflected on the prevalence rate 15 – 49. The table show that on a yearly basis 3800
people are infected with an incidence rate 6.33.
The Municipality has during the past year tested 73 904 patients for HIV. Total of 14 417 of
those tested were in the age group 15 – 24 years and 147 of the same age group tested HIV
positive. This resulted in 1% HIV positivity rate for 15 – 24 years.
In the PMTCT program the municipality tested 633 infants for PCR at 10 weeks and only four
babies were found to HIV positive and all would need to be initiated on ART.
There is also a problem of teenage pregnancy in the local municipality and during the past year
a total of 1 069 15 –19-year-old delivered in facilities and 12 who also delivered in facilities 10 –
14 years. This resulted in 11.8% delivery in facility rate 10 – 19 years.
336
ART TROA Cascade and 95-95-95 Estimates
Location/area 95 – 95 - 95
South Africa
Limpopo Province 92 – 69 - 92
Sekhukhune District 91 – 69 - 92
The province while is on its way to achieve the first 95, it is struggling in terms of ensuring that
patients are retained on ART treatment where there is 69% ART retention rate, the same
challenge is also seen at the district level. It should however be noted that the province and
district have achieved 92% suppression rate albeit with low levels of retention.
The Makhuduthamaga Local Municipality as at March 2023 had 15 982 patients remaining on
treatment but when assessed using the 12-month cohort analysis of patients that started
treatment during 2021, the results show that at 12 months 63% of patients are retained on ART
treatment, which means that there is a high number of patients that are lost to follow up. The
local municipality is however doing much better with regards to the suppression rate which is at
92%.
TB Treatment
Makhuduthamaga during the past financial year managed to put a total of 233 patients on TB
treatment. The cohort produces a 79% success rate, 12% Death rate and 6% of the patients
were lost to follow up and only 5 (2.1%) of the patients were lost to follow up.
Details Number
MLIP Development 1
337
Conferences TB Conference or AIDS Conference
World TB Day
HIV/AIDS Awareness 10
Developmental challenges
• Most orphaned children are not in foster care due to long procedures
Disabled Persons
Youth, women and people with disabilities have generally a broad range of interrelated needs
which therefore must be addressed in a holistic and integrated manner. The municipality has
identified major challenges that face people with disabilities such as lack of skills and career
guidance. The Municipality together with OTP (Office of the Premier) has embarked on a
programme of skilling the unemployed disabled persons whereby four people were on a one
year Learnership on Development Practice.The municipality has also employed three disabled
persons as interns previously in order for them to gain practical experience. A policy to address
and approach matters affecting people with Disabilities was developed.
Business Sector
The Municipality is in good working relations with Makhuduthamaga Chamber of Commerce
and Hawkers Associations within its area of jurisdiction. They participate actively in the affairs of
the municipality especially during IDP stakeholders’ consultations meetings where the
municipality engages stakeholders on development issues.
338
Non-Government Organizations (NGOs) and Community Based Organizations (CBOs)
NGOs and CBOs like Love life, Kgwana, Sekhukhune Educare Project (SEP) and
Makhuduthamaga Umbrella (umbrella body for Home Based Cares) are some of the important
stakeholders that the municipality takes on board on matters of development. These
organizations also have programmes on youth and HIV/AIDS that they run together with the
municipality.
The Constitution of the Republic of South Africa, 1996 reflects on the Government of the
Republic as “constituted as national, provincial and local spheres of government, which are
distinctive, inter-dependent and interrelated”. It thus establishes some principles of co-operative
and intergovernmental relations which all spheres of government all organs of state within each
sphere must adhere to.
Among such principles with an impact on the IDP of which all spheres must observe are:
339
MUNICIPAL TRANSFORMATION AND ORGANISATIONAL DEVELOPMENT SWOT
ANALYSIS
Challenges
340
CHAPTER 4: STRATEGIES PHASE
The chapter provides an overview of the Makhuduthamaga municipality’s key developmental strategies. It involves formulation of strategies to
address gaps or service delivery challenges identified in the analysis phase. The Makhuduthamaga Local Municipality has aligned its objectives
and strategic goals to that of the NDP (National Development Plan) vision 2030 as well as the LDP (Limpopo Development Plan). The Strategic
Planning Session of Makhuduthamaga was held from 19-21 February 2024.
Strategic Objective: To ensure efficient and effective Spatial Planning and Land Use Management systems for sustainable development
Spatial Rationale 1.Discrepancies in the MLM To ensure efficient and effective 1. Review of the MLM SPLUM By law
SPLUM By law Spatial Planning & Land Use
2.Poor Enforcement of Municipal Management systems for 2. Review of the organizational structure for
By laws sustainable development inclusion of Peace Officers
3.Mushrooming of unplanned 3. Implementation of Municipal By laws
developments. (SPLUM By-law, Building Control By law, Land
Use Schemes etc.)
4.Dispersed settlements and 4. Formalization of nodal points/economic hubs
uncoordinated spatial
developments
5.Traditional authorities are the 5. Foster partnership with traditional authorities
custodians of higher proportion to deal with land allocation matters(mainly
of land within MLM municipal nodal points )
341
4.2.KPA 2: Basic Service Delivery and Infrastructure Development
Strategic Objective: To reduce Infrastructure and Service Delivery backlogs in order to Improve Quality of Life of the Community by providing
them with Roads and Storm water, Bridges, Electricity and Housing
Strategic Objectives: 2. To promote social cohesion, road safety management, environmental welfare and disaster management for the
Municipality
Inadequate housing for the To facilitate the provision of low cost Adopt and implementation of Housing Chapter
needy free (RDP) to 6484 beneficiaries by
Basic service Coghsta during 2023/2025 financial Negotiate and monitor implementation of adequate low cost
delivery and year housing units with Coghsta
infrastructure
Development Shortage of portable water To facilitate provision of potable water Adopt and implementation of water and sanitation master
and reliable sources to 33312 households through SDM plan
engagement during 2023/2025 financial
year Draw up priority list to SDM and follow up roll out
programme and extension of bulk water to new areas
Poor operation and To facilitate Operation and Highlight to SDM for improved and acceptable turnaround
maintenance of water maintenance time of maintenance and operation of water infrastructure
infrastructure
Insufficient basic level To facilitate provision of VIP toilets to Adopt and implementation of water and sanitation master
sanitation services 2552 households by SDM during plan
342
2023/2025 financial year, ensure Engaged SDM for provision of sufficient sanitation units to
cleaner and hygienic lifestyle meet the national targets
Electricity post connection To facilitate provision of electricity post Adopt and implementation of the Electricity master plan
backlog and lack of capacity connection to 4440 households by
from feeder lines Eskom during 2023/2025 financial year, Engage Eskom in prioritisation of villages in line with IDP’s
to ensure access to more efficient priority list
energy for everyday use Update data on households that need post connections with
the possibility of new projects
343
Gravel impassable roads To build, (at all roads, bridges, storm Adoption and implementation of roads and storm water plan
water) infrastructure,150km (at up all
roads, bridges and storm water Construction of 150km new roads (of the 255,49km and 76
kilometres) new roads and storm water bridges backlog) and storm water infrastructure (Review
infrastructure and maintain (at up all and implementation of the road and storm water master
gravel roads kilometres) of gravel plan)
roads, during the 2023/2025 financial Maintain 200km of gravel roads
year period, to improve accessibility
Construction and maintenance of municipal roads and
Paving of roads. bridges
Construction of bridges
Mobilise resources through engagements with Department
Huge storm water drainage of Public Works, Roads and Infrastructure, SANRAL and
backlog RAL for surfacing of District, Provincial and National roads
Turnaround time for To ensure effective and efficient To engage direct service providers (Bell or cat) for
maintenance of maintenance of infrastructure plant. maintenance service level agreements.
infrastructure plants
Establish mechanical team in-house.
344
Insufficient storm water Adherence to developed road and storm water master plan
mechanisms due to
topography
Out-dated library material To provide the current and relevant Purchasing of new library material
library material that shall meet the
information needs of our community
members.
Lack of access roads To ensure accessibility of the library to To pave or tar the access roads to the libraries
the community.
Underdeveloped culture of To ensure the transformed, informed Introduction of library and information services in the remote
reading in our municipality and knowledgeable society areas of the Municipality.
Inaccessibility of Wi-Fi in To ensure to internet access to all Engagement of the DSAC in the next financial year
Jane Furse library Hall library users
Lack of sporting facilities To promote sport, arts and culture . Development of multi sports facilities to cater for all
sporting codes.
Lack of public transport To ensure that there is infrastructure for Negotiate for adequate transport (buses and taxis) and
facilities transport facilities extension of routes
Insufficient clinics To facilitate provision of clinics Lobby for partnership in favour of establishment of clinics
Inadequate educational To facilitate for provision of educational Engage Dept. of Education for building of schools and
facilities and equipments facilities and equipments general infrastructural provision and equipments at schools
within Makhuduthamaga
345
Lack of support to ECDs Lobby for partnership in favour of supporting ECDs
Inadequate safety and To enhance safety and security of the Lobby for partnership in favour of SAPS for construction of
security operations public additional police stations i.e. engage with Department of
Police
Waste management To provide sustainable waste Provision of sufficient waste management services to meet
(informal disposal of waste, management infrastructure national target
maintenance of landfill site,
cost recovering, refuse Maintenance of waste management assets
removal not covering all
Expand waste collection
villages)
Fencing of cemeteries To fence and provide sanitary facilities Identify, prioritise and construction of fence and ablution
at the cemeteries facilities
Lack of law enforcement To establish law enforcement facilities Upgrading / expansion of Drivers’ License Test Centres
facilities /services
Disaster Management To provide relieve to disaster affected Mobilisation of and provision of relief to disaster victims
households
Educate communities about Disaster management
Shortage of sector plans Develop all infrastructure related Develop / review Environmental Management Plan,
(e.g. IWMP, Integrated management plans during 2018/19,to Integrated Transport Plan, Disaster Management, Housing
Transport Plan, Housing ensure all infrastructure development Plan etc.
346
Plan, Disaster Management interventions follow effective,
Plan etc.) standardised protocols
Poor network (cell phones, To facilitate for strengthening of cell Lobby SENTECH, ICASA, Cell phone, operations and
TV and radio coverage) phone, TV and radio network coverage relevant authorities for strengthening network coverage
within Makhuduthamaga
Strategic Objective: To stimulate economic development through SMMEs support, LED projects, private and public sector investments
Local Economic 1. No By law to regulate Business To stimulate economic 1. Develop a Business Registration & Licensing
Development Operations within MLM development through SMMEs By-law in line with the Limpopo Business
support, LED projects, private Registration Act (LIBRA)
and public sector investments
2. Poor Enforcement of Municipal LED 2. Review of the organizational structure for
By laws (Street trading etc) inclusion of Peace Officers
347
5. None compliance to Municipal LED 5. Implementation of the Municipal LED By laws
By-laws by the Informal sector (i.e. Street Trading etc)
Strategic Objective: To provide sound and sustainable management of the financial affairs of Makhuduthamaga Local Municipality
Financial Limited revenue base To maximally utilize opportunities for Allocate resources to increase revenue from the following
viability revenue generation. current sources: traffic functions, licensing function, property
rates, renting of council facilities, and sourcing other
available grants
348
KPA Development Challenges Objectives Development Strategies
349
KPA Development Challenges Objectives Development Strategies
Poor collection of property To collect 95% of the total billed Review and verify credibility, completeness and reliability of
rates billed revenue. revenue for property rates from information in the municipal valuation roll.
customers.
Conduct consultative engagements with all property owners
on the municipal valuation roll.
350
KPA Development Challenges Objectives Development Strategies
Inadequate implementation To ensure all municipal departments mSCOA steering committee and project implementation
of mSCOA project. understand and operate the mSCOA team to have meetings quarterly to monitor progress and
live systems adequately. provide remedial actions for none achievement of targets.
Improved data quality and credibility Report mSCOA implementation progress in every
of reported financial and non-financial management meeting, Executive committee meeting,
information. portfolio committees, audit committee meeting and council
meetings.
351
KPA Development Challenges Objectives Development Strategies
Material audit findings on To ensure accurate recording of all Fill all vacant BTO positions and regularly capacitate (train)
municipal Annual Financial financial transactions in compliance the current staff to grow their knowledge and to be up to
Statements. with applicable GRAP standards. date with developments within their financial management
career.
To ensure adequate management and
recording of all municipal assets. Adequately review all financial transaction and segregate
duties.
To ensure compliance with SCM
regulations and municipal SCM policy. Review, approve and implement the Budget related policies.
(Asset management policy, Budget management and
virement policy, Revenue management policies, SCM
policies and Expenditure management policies.)
Poor adherence to To ensure effective and efficient Senior managers must realistically project timelines for
municipal procurement procurement system. annual targets and clearly outline how they will be achieved
plan. on a monthly basis and quarterly basis.
352
KPA Development Challenges Objectives Development Strategies
Underspending of approved To adequately implement the Implement procurement plan and report progress on its
annual budget approved IDP and annual budget implementation in every management meeting, executive
within targeted timeframes. committee meeting, and audit committee meeting and
council meeting.
353
4.5.KPA 5: Good Governance and Public Participation
Strategic Objectives: To promote good governance, public participation, accountability, transparency, effectiveness and efficiency
Good Shortage of Office space To have sufficient office To advocate for building of more office space including
governance and and variable storage space and variable storage variable storage facilities to comply with relevant legislations.
public facilities facilities.
To advocate for electronic filing system
participation
Integration of IT systems
No proper need analysis To support service delivery Compliance with the new Municipal Staff Regulations
prior to creation of position through human capital
(work study)
Non- compliance with DDM Alignment of all government Improved collaboration with all stakeholders
objectives developmental programs
Lack of feedback to To ensure community Capacitate and Intensify public participation unit
communities (Inadequate involvement through public
public participation) participation of municipal Comply with relevant legislations
programs
354
Lack of municipal anti-fraud To prevent fraud and To acquire and install municipal anti-fraud and corruption
and corruption hotline corruption hotline
7. Cyber Security To ensure a continued Develop and Implement IT Security Strategy and Plan
threats/Incidents operation during negative Implementation of business Continuity Plan
impact.
355
Exclusion of people living To ensure involvement and Review organisational structure
with disabilities on participation in municipal Train all staff e.g. on sign language and braille
municipal programmes programmes
Strategic Objectives: To promote effective, efficient municipal administration, and governance through application of credible and approved
municipal systems/ processes
Municipal Inadequate institutional To improve institutional Review and implementation of municipal planning framework,
transformation governance systems governance and administrative e.g. IDP/Budget
and systems
organizational Recruit more qualified competent and skilled personnel
development Ensure implementation of PMS
To ensure compliance with all
governance and administrative Implement Employment Equity Plan
systems Implement Human Resource Strategy
356
Mobilise for empowerment of IGR forums i.e. IDP
Representative forum, LED forum etc.
Inadequate monitoring of To ensure that there is To monitor the compliance with all municipal systems,
performance of all compliance with all approved procedures and policies
municipal systems, municipal systems, procedures
procedures and policies. and policies.
Limited powers and To advocate inter-sectoral Engage SDM, Coghsta and LEDET in sharing some of the
functions collaboration of powers and feasible powers and functions such as water provisions,
functions commensurate with maintenance and operations, business licensing
the capacity of the municipality
(MOU & SLA)
None compliance with To ensure that there is no none Develop a legal and credible SLA/Contracts
legislative guidelines, compliance with all related
directives, policies, municipal legislations including Compile a database of all legislative compliance
SLA/Contracts, by-laws monitoring of all SLA/contracts Management of litigations
None adherence to Service To improve customer care Hold Batho Pele Build up event
standards and service service for better service
delivery charter delivery Implement Customer Care Service Standards
357
Develop Municipal excellent service awards
None adherence and To ensure compliance with the Workshop Staff on code of conduct.
implementation of Labour Labour Relations policy and
relation policy and the code code conduct. Workshop Managers on the implementation of the Labour
of conduct by managers Relations Policy.
and employees. Implement Minimum Service Level Agreement
Inconsistent and Train and develop employees, Conduct workshops for all staff members.
inadequate Capacity councillors and ward committee
building (councillors, members to ensure adequate Annual Employee training through WSP (Workplace Skills
employees and ward capacity exist in the Plan)
committees) municipality’s human service Completing of Skills audit questionnaire
delivery machinery at all times
Development of PDP’s
Councillors training
358
Implement municipal File Plan
Implement PAIA
359
CHAPTER 5: PROJECTS PHASE
Strategic Objective: To ensure efficient and effective Spatial Planning and Land Use Management systems for sustainable development
SR01 EDP Land MLM To have No. of land ES 4 land R0.0 R0.00 R0.00 R0.00
acquisition municipal acquisition acquisition
land committee committee
ownership meetings meetings held
held by 30 by 30 June
June 2025 2025
SR02 EDP Spatial MLM To To review N/A SPLUM by- R0.00 R0.00 R0.00 R0.00
Planning and improve SPLUM by law `1reviewed
Land Use on spatial law by 30 by 30 June
Management planning June 2025 2025
and land
use
360
No. Directorate Project Project Measurab Key Source 2024/25 Budget
location le Performance of Annual
Objective funding Overall 2024/25(R 2025/26 2026/27
Indicator Target Budget )‘000’
(R’000’) (R)‘000’ (R)‘000’
SR 04 EDP Land Use MLM No. of Land ES 01 Land use R1 757 R560 R585 R612
Audit use audit audit
conducted conducted
within the within the
jurisdiction jurisdiction of
of MLM by
361
No. Directorate Project Project Measurab Key Source 2024/25 Budget
location le Performance of Annual
Objective funding Overall 2024/25(R 2025/26 2026/27
Indicator Target Budget )‘000’
(R’000’) (R)‘000’ (R)‘000’
30 June MLM by 30
2025 June 2025
SR05 EDP Monitoring MLM To No. of N/A 200 building R0.00 R0.00 R0.00 R0.00
and promote building inspections
implementati complianc inspections conducted by
on of building e with conducted 30 June 2025
control bylaw building by 30 June
standards 2025
362
No. Directorate Project Project Measurab Key Source 2024/25 Budget
location le Performance of Annual
Objective funding Overall 2024/25(R 2025/26 2026/27
Indicator Target Budget )‘000’
(R’000’) (R)‘000’ (R)‘000’
SR06 EDP Assessment MLM and % of building N/A. 100% of R0.00 R0.00 R0.00 R0.00
of building regulation plans building plans
plans. s received and received and
assessed by assessed by
30 June 30 June 2025
2025(total (total no of
no of building plans
building assessed/ no
plans of building
assessed / plans
no of received)
building
plans
received)
SR07 EDP Monitoring & MLM To % of N/A 100% of R0.00 R0.00 R0.00 R0.00
Maintenance integrate Geospatial Geospatial
of the GIS the updates updates
System institution performed performed on
al on the GIS the GIS
Informatio system by system by 30
n and 30 June June
improve 2025(data 2025(data
efficiency updated
363
No. Directorate Project Project Measurab Key Source 2024/25 Budget
location le Performance of Annual
Objective funding Overall 2024/25(R 2025/26 2026/27
Indicator Target Budget )‘000’
(R’000’) (R)‘000’ (R)‘000’
364
KPA: 2 BASIC SERVICE DELIVERY AND INFRASTRUCTURE DEVELOPMENT
STRATEGIC OBJECTIVE: 1 To reduce infrastructure and service delivery backlogs in order to improve quality of life of the community by
providing them with roads and storm water, bridges and electricity
2. To promote social cohesion, road safety management, environmental welfare and disaster management for the Municipality
No. Project Project Measurable Key Performance Source 2025/2025 Annual BUDGET
location Objective Indicators of targets
funding Overall Budget Budget Budget
2024/2025 2025/2026 2026/2027
Budget (R’000’) (R’000’) (R’000’)
(R’000’)
BS01 Construction of road Ward To improve No of km road from ES 5km road from R26 R16 000 R10 000 R0.00
from Mokwete to 11 accessibility of Mokwete to Mokwete to 000
Molepane Phase villages within Molepane to be Molepane to be
2(5km) Makhuduthamaga constructed up to site constructed up to
establishment by 30 base layer by 30
June 2025(5km) June 2025
BS02 Construction of Ward To improve No of km road from ES 5 km of road from R25 R25 000 R0.00 R0.00
access road from 15 accessibility of Maila Mapitsane to Maila Mapitsane to 000
Maila Mapitsane to villages within Magolego Tribal Magolego Tribal
Magolego Tribal Makhuduthamaga Office(5km) Office constructed
Office(5km) constructed by 30 by 30 June 2025
June 2025
BS03 Design for Ward To improve No of KM of access ES 3.2 KM for R 14 R 1 500 R6 500 R6 000
Construction of 19 accessibility road for construction construction of 000
of Madibong internal Madibong internal
365
Madibong internal within road by 30 June road constructed
road (3.2km) Makhuduthamaga 2025 by 30 June 2025
BS04 Design for Upgrading Ward To improve No of Km of internal ES 10 km of internal R9 000 R 2 000 R0.00 R 7 000
of Jane Furse CBD 18 accessibility roads at Jane Furse roads at Jane
within CBD upgraded up to Furse CBD
Makhuduthamaga road bed by 30 June upgraded up to
2025 road bed layer by
30 June 2025
BS05 Development of Ward To develop a hub Detailed design ES 01 Detailed design R8 500 R1 500 R0.00 R7 000
designs for Grade A 28 of government developed for Grade developed for
DLTC offices. A DLTC by 30 June Grade A DLTC
2025 developed by 30
June 2025
BS06 Contruction of access Ward To improve Design developed for ES 01 design R1 000 R1 000 R0.00 R2 000
road from Tsopaneng 14 accessibility construction of road developed for
to Moela /Kgopane within from Tsopaneng to construction of road
Makhuduthamaga Moela Kgopane by from Tsopaneng to
30 June 2025 Moela Kgopane by
30 June 2025
BS07 Construction of Ward To improve No of km of access ES 5 km of access R23 R5 000 R10 500 R8 000
Phaahla/Mamatjekele 24 accessibility road from Phaahla road from Phaahla 500
to Masehlaneng within to Masehlaneng to Masehlaneng
access road(18km) Makhuduthamaga constructed up to constructed up to
sub- base layer by sub- base layer by
30 June 2025 30 June 2025
366
BS08 Construction of Ward To improve No of km of access ES 4.5 km of access R 22 R 2 000 R 11 600 R 8 700
access road from 28 accessibility road from motor gate road from motor 300
Motor gate within Wonderboom to gate Wonderboom
Wonderboom to Makhuduthamaga R579 constructed up to R579
R579 (10km) to road bed by 30 constructed up to
June 2025 road bed by 30
June 2025
BS09 Construction of Ward To improve No of km of access ES 5 km of access R 32 R8 000 R18 000 R 6 890
access road from 24,27 accessibility road from road from 890
Molebeledi within Molebeledi Molebeledi
/Masemola moshate Makhuduthamaga /Mamatjekele to /Mamatjekele to
to Mamatjekele to Masemola Moshate Masemola Moshate
Masemola Moshate constructed up to constructed up to
(5km) selected layer by 30 selected layer by
June 2025 30 June 2025
BS10 Design for Ward To improve No of detailed ES 1 detailed design R2000 R2 000 R0.00 R0.00
Construction of 30 accessibility designs for for construction of
Masanteng access within construction of Masanteng access
road Makhuduthamaga Masanteng access road constructed by
road constructed by 30 June 2025
30 June 2025
BS11 Repair and MLM To improve No of Existing roads, ES 40 Existing roads, R69 R 20 000 R28 000 R21 276
Maintenance of accessibility of bridges and storm bridges and storm 276
roads, bridges and villages within water maintained water maintained
storm water Makhuduthamaga within MLM by 30 within MLM by 30
June 2025 June 2025
BS12 Repairs and MLM To improve No of electricity ES 15 Existing R5 694 R1 500 R 2 072 R2 122
Maintenance of lifespan of service infrastructure electricity
367
electricity delivery maintained within infrastructure
Infrastructure. infrastructure MLM by 30 June maintained within
2025 MLM by 30 June
2025
BS13 Repairs and MLM To improve No of repairs and ES 10 repairs and R 7 390 R 3 000 R2 096 R 2 195
Maintenance of other lifespan of service maintenance of other maintenance of
assets delivery assets maintained other assets
infrastructure within MLM by 30 maintained within
June 2025 MLM by 30 June
2025
BS14 Design for Ward To improve No of bridge for ES 01 bridge for R1 000 R0.00 R 1 000 R0.00
Construction of 31 accessibility Mangwanyane Mangwanyane
Mangwanyane within /Kutopo constructed /Kutopo
/Kutopo bridge Makhuduthamaga by 30 June 2025 constructed by 30
June 2026
BS15 Design of access Ward To improve Design developed for ES 01 design R21 R0.00 R2 000 R8 000
road from Moloi to 10 accessibility construction of road developed for 000
Phushulang within from Moloi to construction of road
Makhuduthamaga Phushulang by 30 from Moloi to
June 2026 Phushulang by 30
June 2026
BS16 Repair and MLM To address water No of water and SDM 20 water and R0.00 R0.00 R0.00 R0.00
maintenance of water and sanitation sanitation assets sanitation assets
and sanitation backlog repaired and repaired and
maintained by 30 maintained by 30
June 2025 June 2025
368
BS17 Construction of Kome Ward To improve No of km of access MIG 4.2 km of access R 29 R8 391 R 20 809 R0.00
internal road phase 2 31 accessibility road for Kome road for Kome 200
(4.2km) within internal street (phase Internal street
Makhuduthamaga 2) constructed up to (phase 2)
base layer by 30 constructed up to
June 2025 base layer by 30
June 2025
BS18 Construction of Ward To improve No of km of access MIG 6.5 km of access R38 R 30 000 R8 000 R 0.00
access road from 26 accessibility road from road from 000
Soetveld / Mathapisa within Soetveld/Mathapisa Soetveld/Mathapisa
to Ga-Mampane Makhuduthamaga to Ga-Mampane to Ga-Mampane
Thabeng (6.5km) Thabeng Thabeng
constructed by 30 constructed by 30
June 2025 June 2025
BS Construction of Ward To improve No of km access MIG 4.12 km of access R24 R 7 385 R 17 027 R0
19 Cabrieve Internal 08 accessibility road for Cabrieve road of Cabrieve 412
street (4.12km) within internal road internal road
Makhuduthamaga constructed up to constructed up to
base layer by 30 base layer by June
June 2025 2025
BS20 Construction of Jane Ward To improve No of Km access MIG 1.14 km of access R 10 R10 282 R0.00 R8 000
Furse RDP to 18,10 accessibility road from Jane Furse road from Jane 282
Mogorwane Phase within RDP to Mogorwane RDP to Mogorwane
02 Makhuduthamaga (phase 02) (phase 02)
Constructed by 30 constructed by 30
June 2025 June 2025
369
BS21 Construction of Ward To improve No of km of access MIG 3.2km of access R33 R2 500 R22 371 R8 350
access road from 08,03 accessibility road from Brooklyn to road from Brooklyn 221
Brooklyn to within Makoshala to Makoshala
Makoshala (3.2km) Makhuduthamaga constructed by June constructed by
2026 June 2026
BS22 Specialised Waste MLM To improve Roller compactor , MIG 3X specialised R 10 R10 800 R0.00 R0.00
vehicles (MIG) 15% effeteness of the waste truck, grader ( waste vehicles 800
landfill site 10 Ton payload procured
Refuse Compactor
Truck –R 2 503 000
Tipper Truck ( 2 098
643.45 By June 2025
BS23 Upgrading of Jane Ward To improve No of Km of internal MIG 10 km of internal R 10 R 0.00 R0.00 R 10 000
Furse CBD internal 18 accessibility roads at Jane Furse roads at Jane 000
road network(R579) within CBD network Furse CBD network
Phase 2 Makhuduthamaga upgraded up to road upgraded up to
bed by 30 June road bed layer by
2025 30 June 2027
BS24 Installation of Ward To improve No of INEP 50 Households/ R 1000 R1000 0.00 0.00
electrical 26 Access to electric Households/stands stands provided
infrastructure energy for provided with access with access to
household to electrical electrical
infrastructure at infrastructure at
Soetveld by 30 June Soetveld by 30
2025 June 2025
370
BS25 Installation of Ward To improve No of INEP 162 R 3 221 R 3 221 R0.00 R0.00
electrical 02 Access to electric Households/stands Households/stands
infrastructure energy for provided with access provided with
household to electrical access to electrical
infrastructure at infrastructure at
Mabintane by 30 Mabintane by 30
June 2025 June 2025
BS Installation of Ward To improve No of INEP 130 Households/ R 2 600 R 2 600 R0.00 R0.00
28 electrical 05 Access to electric Households/stands stands provided
infrastructure energy for provided with access with access to
household to electrical electrical
infrastructure at infrastructure at
Leeukraal by 30 June Leeukraal by 30
2025 June 2025
371
BS29 Installation of Ward To improve No of INEP 170 R 3 410 R 3 410 R0.00 R0.00
electrical 05 Access to electric Households/stands Households/stands
infrastructure energy for provided with access provided with
household to electrical access to electrical
infrastructure at infrastructure at
Mohlwarekoma by 30
June 2025
BS30 Installation of Ward To improve No of INEP 550 R0.00 R0.00 R0.00 R0.00
electrical 08 Access to electric households/stands households/stands
infrastructure energy for provided with access provided with
household to electrical access to electrical
infrastructure at Ga infrastructure at Ga
(Moloi Phase 02) by Moloi Phase 02 by
30 June 2025 30 June 2025
BS32 Design for Ward To improve No of km of access ES 3.5 km of access R6 408 R 0.00 R0.00 R6 408
Construction of Glen 8,7 accessibility road from Glen road from Glen
cowie via Setebong/ within cowie via cowie via
Dikatone to Thoto Makhuduthamaga Setebong/Dikatone Setebong/Dikatone
access road (9km) to Thoto constructed to Thoto
road bed by 30 June constructed up to
2027 road bed by 30
June 2027
372
BS33 Construction of Ward To improve No of km of access ES 9 km of access R17 R0.00 R 9 000 R 8 000
Topanama access 19, accessibility road for Topanama road for Topanama 000
road(9km) 23,17 within (9km) constructed up (9km) constructed
Makhuduthamaga to site establishment up to site
by 30 June 2025 establishment by
30 June 2026
BS34 Construction of guard To safeguard No of guardrooms ES 04 guardrooms R 800 R0.00 R0.00 R0.00
rooms in municipal municipal Assets constructed at constructed at
facilities MLM municipal facilities ( municipal facilities (
Mogaladi CH, Mogaladi CH,
Makgwabe CH, Makgwabe CH,
artificial pitch and artificial pitch and
Madibong Landfill Madibong Landfill
site) by 30 June 2026 site) by 30 June
2027
BS35 Refurbishment of Ward 8 To Improve storm No of km of storm ES 1 Km of storm R 6 000 R0.00 R0.00 R 6 000
Storm water control water control from water control system water control
from Glen Cowie to Glen Cowie to from Glen cowie to system from Glen
Cabrieve Cabrieve Cabrieve refurbished cowie to Cabrieve
by June 2027 refurbished by
June 2027
BS36 Construction of Ward To improve No sports facilities MIG 1 Sports facility at R0.00 R0.00 R 0.00 R0.00
Rietfontein 04 accessibility constructed at Rietfontein
(Ngwaritsi) sports within Rietfontein (Ngwaritsi)
facility Phase 01 Makhuduthamaga (Ngwaritsi) phase 01 constructed by 30
by 30 June 2027 June 2027
373
BS37 Development of Ward To improve No of Detailed ES 01 Detailed R 0.00 R0.00 R0.00 R0.00
detailed designs for 27 accessibility designs developed design developed
Masemola within for Masemola for Masemola
Majekaneng to Makhuduthamaga Majekaneng to Majekaneng to
Masemola Mabopane Masemola Masemola
internal road (10km) Mabopane internal Mabopane internal
road (10km) by 30 road constructed
June 2026 by June 2026
BS38 Construction of Ward To improve No of km of access MIG 4km of access R 23 R0.00 R 0.00 R23 900
Mamone Sekwati- 21 accessibility road from Mamone road from Mamone 900
Motlokwe access within Sekwati-Motlokwe Sekwati-Motlokwe
road(4km) Makhuduthamaga completed by June completed by June
2026 2026
BS Construction of Ward To improve No of km of access MIG km of access road R 22 R0.00 R 0.00 R22 000
39 Sekwati-Motlokwe 21 accessibility road from Sekwati- from Sekwati- 000
access road within Motlokwe completed Motlokwe
Makhuduthamaga by June 2027 completed by June
2027
BS Design and W 27 To improve Design and MIG 01 Design and R4 500 R0.00 R4 500 R0.00
40 construction of accessibility construction of construction of
Mabopane internal within Mabopane internal Mabopane internal
street Makhuduthamaga street completed by street completed by
30 June 2026 30 June 2026
BS41 Installation solar Ward X To improve No of solar high MIG 10 solar high mast R14 R0.00 R0.00 R14 862
high mast and street visibility within mast lights installed lights installed at 862
lights within Makhuduthamaga at Jane Furse R579 Jane Furse R579
by 30 June 2025 by 30 June 2027
374
Makhuduthamaga No of street lights MIG 10 street lights
Local Municipality installed at various installed at various
villages by 30 June villages by 30 June
2025 2027
BS42 Construction of Low Ward To improve No of low level ES 4 low level bridges R 5 000 R0.00 R 0.00 R5 000
Level Bridges at 14,15, accessibility bridges for Mokadi, constructed by
Makhuduthamaga 16 within Bodutung, Ga- June 2027
Makhuduthamaga Seopela &
Dingoane/Tsopaneng
constructed by June
2026
BS43 Construction of Ward To improve No of km for ES 5 km Construction R0.00 R0.00 R0.00 R0.00
Matsoke Stormwater 21 accessibility Construction of of Matsoke
control system within Matsoke Stormwater Stormwater control
Makhuduthamaga control system system by 30 June
2026
BS44 Construction of MLM To protect No. of registry office ES 01 registry office R0.00 R0.00 R0.00 R0.00
Registry office block Municipal records blocks constructed block constructed
up by 30 June 2026 by 30 June 2026
BS Construction of MLM To comply with No. of emergency ES 03 emergency exits R0.00 R0.00 R0.00 R0.00
45 emergency exits in building exits constructed in constructed in the
the main building regulations the main building by main building by 30
30 June 2025 June 2025
BS46 Upgrading of R579 Ward To improve No. of Km of R579 ES 7.2 Km of R579 R 0.00 R0.00 R0.00 R0.00
access road from 18 accessibility access road from access road from
RDP/Shell garage to Jane Furse 4-ways to Jane Furse 4-ways
Marangrang road Marangrang to Marangrang
375
and Old Hospital within upgraded by 30 June upgraded by 30
road Makhuduthamaga 2026 June 2026
BS47 Construction of Ward To improve No of detailed ES 1 detailed design R4000 R0.00 R0.00 R4 000
Masanteng access 30 accessibility designs for for construction of
road within construction of Masanteng access
Makhuduthamaga Masanteng access road constructed by
road constructed by 30 June 2026
30 June 2026
BS48 Construction of Ward To improve No. of Km of MIG 10 Km of access R0.00 R0.00 R 0.00 R 0.00
Molepane to 11,12 accessibility access road from road from
Makgane village within Molepane to Molepane to
Makhuduthamaga Makgane Makgane
Constructed by 30 Constructed by 30
June 2027 June 2027
BS Construction of Ward To improve No of km of access ES 3.5 km of access R 0.00 R0.00 R0.00 R0.00
49 access road from 8,3&2 accessibility of road from Glen road from Glen
Glen Cowie Old Post villages within Cowie Old Post Cowie Old Post
Office to Phokwane Makhuduthamaga Office to Phokwane Office to
Phase 2 (3.5km) constructed by 30 Phokwane
June 2027 constructed by 30
June 2027
BS50 Electrification of Ward To improve No of households INEP 700 H/H of R 0.00 R 0.00 R0.00 R0.00
Dihlabaneng 22 Access to electric electrified at households
(Ngwanakwena and energy for Dihlabaneng electrified at
Malatjane) 700 H/H household (Ngwanakwena and Dihlabaneng
Malatjane) by 30 (Ngwanakwena
June 2027
376
and Malatja) by 30
June 2027
BS51 Construction of Ga- Ward To improve No of km of access MIG 6 km of access R0.00 R0.00 R 0.00 R0.00
Selepe access road 25 accessibility road for Ga-Selepe road for Ga-Selepe
within constructed by June constructed by
Makhuduthamaga 2027 June 2027
BS52 Construction of Ward To improve No of km access ES 3.6 km of access R0.00 R0.00 R0.00 R0.00
access road from 03 accessibility road from road from
Mokgapaneng within Mokgapaneng Mokgapaneng
reservoir-Malegale Makhuduthamaga reservoir-Malegale reservoir-Malegale
cemetery (3.6km) cemetery completed cemetery
by 30 June 2027 completed by June
2027
BS53 Refurbishment of MLM To improve No. of community ES 01 community R 0.00 R0.00 R0.00 R0.00
Phaahla Community lifespan of halls refurbished at halls refurbished at
hall Municipal Facility Phaahla by June Phaahla by June
2027 2027
BS Construction of Ward To improve No of Km of access ES 3km of access road R0.00 R 0.00 R0.00 R0.00
54 access road from 04,06 accessibility road for access from Rietfontein to
Rietfontein to Mare within road from Rietfontein Mare village
village (3km) Makhuduthamaga to Mare village constructed up to
constructed up to selected layer by
selected layer by 30 June 2027
30June 2027
377
BS55 Construction of Ward To improve No of Km of access ES 0.9 Km of access R0.00 R0.00 R0.00 R0.00
Vergelegen C 19 Access to electric roads constructed at road constructed at
internal road (0.9m) energy for Vergelegen C by 30 Vergelegen C by
household June 2028 30 June 2028
BS56 Upgrading of access Ward To improve No of Km of access ES 15 km of access R0.00 R0.00 R0.00 R0.00
roads for the land 21 accessibility roads for the land roads for the land
earmarked for within earmarked municipal earmarked
Municipal offices Makhuduthamaga facilities constructed municipal facilities
by June 2028 constructed by
June 2028
BS57 Upgrading of MLM To improve No of community ES 01 community hall R0.00 R0.00 R0.00 R0.00
Mogaladi Community ward lifespan of halls upgraded by 30 upgraded by 30
hall 30 Municipal Facility June 2027 June 2028
BS58 Upgrading of access MLM To improve No of community ES 01 community hall R0.00 R0.00 R0.00 R0.00
road to Makgwabe 29 lifespan of halls upgraded by 30 upgraded by 30
community hall Municipal Facility June 2027 June 2028
BS59 Design of access MLM To improve Design of access ES 01 Design of R0.00 R0.00 R0.00 R0.00
road to Jane Furse accessibility road to Jane Furse access road to
Library.Jane furse within Library.Jane furse Jane Furse
Artificial turf and new Makhuduthamaga Artificial turf and new Library.Jane furse
District Offices District Offices by 30 Artificial turf and
June 2025 new District Offices
by 30 June 2025
BS60 Construction of Ward To improve No of km of access ES 3.2km of access R0.00 R0.00 R0.00 R0.00
Mogaladi access 30 accessibility road for Mogaladi road for Mogaladi
road (3.2km) access road
378
within constructed by June constructed by
Makhuduthamaga 2028 June 2028
BS61 Construction of Ward To improve No of km of access ES 10km of access R 10 0.00 0.00 R 10 000
Maololo road 24 accessibility road for Maololo road for Maololo 000
within access road access road
Makhuduthamaga constructed up to constructed up to
base layer by June base layer by
2029 June 2028
BS62 Kotsiri to Ward To improve No of km of access ES 3km of access road R 37 0.00 0.00 R 5 000
Dihlabaneng 14 accessibility road from Kotsiri to from Kotsiri to 000
within Dihlabaneng Dihlabaneng
Makhuduthamaga constructed up to constructed up to
base layer by June base layer by
2029 June 2028
BS Solid waste collection MLM To promote a Number of house to ES 1282 house to R44 R20 000 R17 030 R7 073
63 healthy and clean house collection with house collection 103
environment access to solid waste with access to solid
removal services by waste removal
30 June 2025 services at
Marishane, Glen
cowie new stands
and Glen cowie
Mathousands by 30
June 2025
379
31 wards by 30 June 31 villages by 30
2025 June 2025
BS64 Landfill site operation MLM To enhance Number of landfill ES 04 landfill sites R0.00 R0.00 R0.00 R0.00
landfill operation sites audit reports audit reports
compiled by 30 June compiled by 30
2025 June 2025
Construction of a ES 01 new landfill site R30 R0.00 R10 000 R20 000
new landfill site by 30 constructed by 30 000
June 2026 June 2027
BS65 Fencing of MLM To protect Number of ES 1 cluster cemetery R0.00 R0.00 R0.00
cemeteries gravestones from cemeteries fenced fenced within the
wandering within the Makhuduthamaga
R0.00
animals Makhuduthamaga Jurisdiction by 30
jurisdiction by 30 June 2025.
June 2025
BS66 Environmental care MLM To promote Number of ES 8 Environmental R940 R300 R313 R327
awareness to sustainable Environmental awareness and
communities environmental awareness and clean clean up
system and up campaigns held campaigns held
380
improve within the jurisdiction within the
community of Makhuduthamaga jurisdiction of
awareness by 30 June 2025 Makhuduthamaga
by 30 June 2025.
BS67 Library promotions MLM To promote the No of Library ES 16 Library R469 R150 R156 R163
culture of reading Awareness awareness
and learning Campaign held within campaigns held
the jurisdiction of within the
Makhuduthamaga by jurisdiction of
30 June 2025. Makhuduthamaga
by 30 June 2025
BS68 Disaster relief MLM To provide relieve Percentage (%) of ES 100% Disaster R4 627 R1 800 R1 382 R1 445
to disaster Disaster relief relief provided.(
affected H/H provided.( Disaster Disaster cases
cases attended /total attended /total
number of reported number of reported
disaster cases)by 30 disaster cases)by
June 2025 June 2025
BS69 Climate change MLM To improve Development of ES Climate change R0.00 R0.00 R0.00 R0.00
strategy awareness, climate change management
secure planet and management strategy developed
protect the future. strategy developed and approved by
and approved by 30 30 June 2025
June 2025
381
BS70 Disaster MLM To educate No of Disaster ES 8 Disaster R470 R150 R156 R163
management communities to awareness awareness
awareness respond campaigns campaigns
adequately to conducted within conducted within
disaster events jurisdiction of jurisdiction of
Makhuduthamaga by Makhuduthamaga
30June 2025 by 30 June 2025
BS71 Sports promotion MLM To promote No of Sports ES 8 Sports promotion R3 766 R1 200 R1 255 R1 311
healthy lifestyle promotion activities activities held by 30
and social held by 30 June 2025 June 2025
cohesion
BS72 Arts and culture MLM To promote and No of Arts and ES 8 Arts and culture R2 511 R800 R836 R 874
promotions sustain cultural culture promotion promotion activities
heritage activities held within held within
Makhuduthamaga Makhuduthamaga
community by 30 community by 30
June 2025 June 2025
382
BS73 Road safety MLM To promote road No of Road safety ES 12 Road safety R690 R220 R230 R240
Management safety campaigns campaigns
conducted by June conducted by June
2025 2025
BS74 Development of MLM To enhance No of integrated ES 01 integrated R2000 R2000 R0.00 R0.00
Integrated Transport mode of transport transport plan transport plan
plan for the community developed by 30June developed by 30
2025 June 2025
383
KPA3: LED
Strategic Objective: To stimulate economic development through SMMEs support, LED projects, private and public sector investments
No. Directorate Project Measurable Key Performance Source of Annual Overall BUDGET
Objective Indicators funding Target budget
Budget Budget Budget
2024/2025 2024/2025( 2025/2026 2026/2027
R’000’) (R’000’) (R’000’)
384
No. Directorate Project Measurable Key Performance Source of Annual Overall BUDGET
Objective Indicators funding Target budget
Budget Budget Budget
2024/2025 2024/2025( 2025/2026 2026/2027
R’000’) (R’000’) (R’000’)
385
No. Directorate Project Measurable Key Performance Source of Annual Overall BUDGET
Objective Indicators funding Target budget
Budget Budget Budget
2024/2025 2024/2025( 2025/2026 2026/2027
R’000’) (R’000’) (R’000’)
30 June
2025
LED05 EDP Agricultural No of Agri Expo ES 02 Agri Expo R650 R200 R300 R150
Developme conducted by 30 conducted by
nt June 2025 30 June
2025
386
No. Directorate Project Measurable Key Performance Source of Annual Overall BUDGET
Objective Indicators funding Target budget
Budget Budget Budget
2024/2025 2024/2025( 2025/2026 2026/2027
R’000’) (R’000’) (R’000’)
387
No. Directorate Project Measurable Key Performance Source of Annual Overall BUDGET
Objective Indicators funding Target budget
Budget Budget Budget
2024/2025 2024/2025( 2025/2026 2026/2027
R’000’) (R’000’) (R’000’)
LED07 Infrastructur EPWP Alleviate No of job EPWP 142 job R15 411 R4 900 R5 135 R5 376
e unemploym opportunities funding opportunities
ent and created through created
poverty EPWP by 30 June through
2025 EPWP by 30
June 2025
388
KPA 4: FINANCIAL VIABILITY MANAGEMENT
Strategic Objective: To provide sound and sustainable management of the financial affairs of Makhuduthamaga Local Municipality.
BTO 02 BTO Revenue To increase Percentage of 5% of own R 0.00 R 0.00 R 0.00 R 0.00
management own revenue own revenue revenue
and reduced increment increment
dependency on
grants.
389
No of 1 R 3 139 R 1 000 R 1 046 R 1 093.
Supplementary Supplementary
valuation rolls valuation rolls
developed and developed and
implemented by implemented
30 June 2025. done by 30
June 2025.
BTO 03 BTO Own To increase % of billed 95% of billed R0.00 R0.00 R 0.00 R 0.00
Revenue own revenue revenue revenue
collection. and reduced collected ( collected
dependency on
revenue amount (revenue
grants
collected vs amount
amount billed) by collected vs
30 June 2025 amount billed)
by 30 June
2025
BTO 04 BTO Procurement To facilitate No of Develop and R0.00 R0.00 R0.00 R0.00
management effective and Procurement implement
activities. efficient plan Developed approved
implementation
and approved for procurement
of SDBIP.
2024/2025 plan by 30
financial year by June 2025
30 June 2025
BTO 05 BTO Financial To enhance % of FMG spend 100% FMG R5 700 R1800 R1 900 R2 000
Management human by 30 June 2025 spend by 30
capacity resource June 2025
building. competency.
390
BTO 06 BTO Budget and To ensure No. of Municipal 03 Municipal R0.00 R0.00 R0.00 R0.00
reporting. Credible and Annual Budgets Annual
compliant prepared and Budgets
municipal table in council
prepared and
budgeting and for approval by
reporting. 30 June 2025 table in council
for approval
by 30 June
2025
BTO 07 BTO Expenditure To ensure % of creditors 100% of R0.00 R0.00 R0.00 R0.00
Management authorized paid within 30 creditors paid
. expenditure days period by within 30 days
and timeous
30 June 2025 period by 30
payment of
obligations. June 2025
391
and signed within prepared and
first 10 working signed within
days of every first 10 working
month by June days of every
2025 month by 30
June 2025
BTO 08 BTO Asset To manage all No. of assets 8 assets R0.00 R0.00 R0.00 R0.00
management municipal verification verification
assets. activities activities
conducted and conducted and
reported by 30 reported by 30
June 2025. June 2025.
392
(3 Traffic
vehicles
1 Waste
collection truck
1 Motor
Graders
2 Fleet
vehicles
1 Towing truck
BTO 09 BTO Unqualified To improve To obtain Obtain R5 265 R5 265 R0.00 R0.00
AGSA audit AGSA audit Unqualified audit Unqualified
opinion. opinion. opinion with no audit opinion
material finding
with no
by 30 June 2025
material
finding by 30
June 2025.
BTO 10 BTO Provision of To improve No of reports 04 reports R1 200 R1 200 R0.00 R0.00
Free Basic lives of compiled on compiled on
Electricity indigents provision of FBE provision of
to registered
FBE to
indigents by 30
June 2025 registered
indigents by
30 June 2025
393
KPA 5: Good Governance and Public Participation
Strategic Objective: To promote Good Governance, Public Participation, accountability, transparency, effectiveness and efficiency
GG01 Risk MLM To assess, No. of 1 Strategic Risk ES R0.00 R0.00 R0.00 R0.00
Assessm identify Strategic assessment
ents manage risk Risk conducted and 4
and assessment Operational Risk
uncertainty in conducted Assessments
order to and reviewed by 30
safeguard Operational June 2025
assets, Risk
enhance Assessment
productivity reviewed by
and build 30 June 2025
resilience into
GG02 Monitorin MLM operations No of 12 Physical ES R0.00 R0.00 R0.00 R0.00
g of Physical Security
physical Security Monitoring
security Monitoring conducted by 30
conducted by June 2025
30 June 2025
394
Business projects implemented by
Continuit implemented 30 June 2025
y plan by 30 June
2025
GG05 Manage MLM To ensure No. of 3 Internal Audit ES R0.00 R0.00 R0.00 R0.00
ment of proper Internal Audit policies and
Internal functionality policies and procedures
Audit of Internal procedures reviewed and
Activity Audit Activity reviewed and approved by 30
approved by June 2025
30 June 2025
395
committee by
30 June 2025
GG08 Internal MLM To ensure No of Internal 8 Internal audit ES R0.00 R0.00 R0.00 R0.00
Audit proper audit follow- follow-up reviews
Activity’s monitoring of up reviews performed by 30
AGSA audit action performed by June 2025.
and IA plans for 30 June
follow clean 2025.
396
ups administratio
reviews n
GG09 Audit MLM To ensure No. of Audit 04 Audit and ES R 2 668 R850 R889 R929
and effectiveness and Performance
performa of sound Performance Committee
nce financial Committee meetings held by
Committ Management, meetings 30 June 2025
ee Risk held by 30
support. management June 2025
and controls
,internal audit
,and
performance
management
GG10 Develop MLM To improve No. of 12 customer care ES R3 500 R 500 R1 500 R1 500
customer service customer projects
care delivery care projects implemented in
impleme through implemented line with the
ntation customer in line with approved
plan engagements the approved customer care
platforms customer plan by 30 June
care plan by 2025
30 June 2025
397
No of 01 Community ES R2 700 R900 R900 R900
community satisfaction
satisfaction survey conducted
survey by 30 June 2025
conducted
by 30 June
2025
GG12 Publicati MLM To ensure No. of 6 documents ES R4 233 R2 000 R1 092 R1 141
ons effective documents published by 30
involvement published June 2025.
and done by June
participation 2025.
of all
stakeholders.
398
performed by
30 June 2025
GG14 Capacity MLM To ensure No of 8 trainings Own R4 709 R1 500 R1 569 R1 640
building effective and trainings provided to funding
of efficient good provided to councillors and
councillo governance. councillors council
r and and council committees by 30
council committees June 2025
committe by 30 June
es 2025
GG15 Speaker MLM To promote No of 08 Speakers Own R 4 175 R 1 330 R1 391 R1 454
‘s public Speakers outreach events funding
Outreach participation outreach conducted by 30
events and events June 2025.
deepening conducted by
participatory 30 June 2025
democracy.
GG16 Council MLM To fulfill No of 4 ordinary Own R1 099 R 350 R 366 R 383
logistics legislative ordinary Council meetings funding
mandate Council held by 30 June
meetings 2025.
held by 30
June 2025.
399
No of special 8 special council
council meetings held by
meetings 30 June 2025
held by 30
June 2025
GG17 Council MLM To Improve No. of project 4 project visit ES R942 R300 R314 R328
Oversigh municipal visits conducted by 30
t on performance conducted by June 2025
service and service 30 June 2025
delivery delivery.
performa % of cases 100% cases
nce referred to referred to MPAC
MPAC from from council (
council ( total total number of
number of cases referred/
cases total number
referred/ total cases
number investigated) by
cases 30 June 2025
investigated)
by 30 June
2025
No of 1 Oversight report ES
Oversight compiled and
400
report presented to
compiled and Council by 30
presented to June 2025
Council by 30
June 2025
No. of 04 Whippery ES
Whippery reports generated
reports and submitted to
generated council by 30
and June 2025
submitted to
council by 30
June 2025
401
30 June
2025.
402
KPA 6: Municipal Transformation and Organizational Development
Strategic Objectives: To promote effective, efficient municipal administration, and governance through application of credible and approved
municipal systems/ processes
403
01 Draft R0.00 R0.00 R0.00 R0.00
No of Draft
2025/2026
2025/2026
IDP and 01
IDP and final
final
2025/2026
2025/2026
IDP tabled to N/A
IDP tabled
Council by
to Council
30 June
by 30 June
2025
2025
404
10 PMS
No of PMS
reports
reports
compiled
compiled and
and
approved by N/A
approved
30 June
by 30 June
2025
2025
405
by 30 June
2025
406
Safety all reports reports
services municipal generated by generated
employees 30 June by 30 June
each year. 2025 2025
Provision of Corporate To provide No of HRD & 4 HRD & ES R4 708 R1 500 R1 569 R1 639
Human Services skilled and organisationa organisation
Resource capable l design al design
Development work force reports reports
MTOD04 & to support generated by generated
organisationa service 30 June by 30 June
l design delivery 2025 2025
services
MTOD05 Manage Corporate To provide No. of 4 external ES R9 668 R3 080 R3 221 R 3 366
bursary funds services academic external bursary
support to bursary funds
students funds reports reports
and generated by generated
employees 30 June by 30 June
for higher 2025 2025
education
No. of 4 ES R 1 569 R500 R 523 R546
employees employees
bursary bursary
funds reports funds
generated by reports
30 June generated
2025
407
by 30 June
2025
No of 02
performance assessment
assessments s conducted
conducted by by 30 June
30 June 2025(2023/
2025(2023/2 2024
024 annual annual and
and 2024/2025
2024/2025 Mid-year)
Mid-year)
408
resource Corporate rate and as at vacant
management Services strengthen beginning of posts as at
services workforce financial year beginning of
filled in line financial
with the year filled
approved in line with
organisationa the
l structure by approved
30 June organisation
2025(total al structure
number of by 30 June
funded 2025(total
vacant number of
positions funded
filled /by no vacant
of vacant positions
positions as filled /by no
at beginning of vacant
of financial positions as
year) at beginning
of financial
year)
409
operating
procedures
MTOD08 Provide Corporate To ensure No. of LLF 4 LLF ES R0.00 R0.00 R0.00 R0.00
employee Services compliance resolution resolution
relations with reports reports
services SALGBC created by created by
collective 30 June 30 June
agreement 2025 2025
through
functional
LLF each
year.
MTOD09 Manage Corporate To ensure No. of 4 litigations ES R7 847 R2 500 R2 615 R2 732
municipal Services proper litigations cases
litigation monitoring cases reports reports
cases of legal compiled by compiled by
cases 30 June 30 June
2025 2025
MTOD10 ICT Corporate To No. of ICT 4 ICT ES R0.00 R0.00 R0.00 R0.00
Governance Services strengthen steering steering
municipal committee committee
ICT monitoring monitoring
governance reports reports
and generated by generated
systems 30 June by 30 June
2025 2025
410
MTOD11 ICT systems Corporate To enhance No. of 12 reports ES R32 893 R 12 555 R9 945 R10 393
support Services productivity reports for IT for IT
of ICT Systems Systems
Systems Supported by Supported
30 June by 30 June
2025 2025
MTOD12 Provision for Corporate To fully No of 1 System ES R 5 964 R 1 900 R 1 987 R 2 077
Automation Service Automate Automation for
(Digital) Municipal (Digital) automation
system processes systems of business
procured processes
procured
and
installed by
June 2025
411
MTOD14 Provision of Corporate Design and No of Facility 12 Facility ES R10 500 R3 500 R3 500 R3 500
facility Services developme management manageme
management nt of land reports nt reports
services scabbing at generated by generated
Nebo, 30 June by 30 June
Sekhukhun 2025 2025
e and Jane
Furse
Library)
412
CHAPTER 6: INTEGRATION PHASE
6.1. Spatial rationale
Sector plans
413
6.2 Basic service delivery and infrastructure Development
Sector plans
414
6.3 Economic and environmental analysis
Sector plans
Tourism Strategy The Municipality hasTourism Strategy that seeks to provide tourism guidelines within Makhuduthamaga municipal area.
Its main purpose is to promote tourism within the Municipality. The Strategy was adopted in the 2022/2023 financial year.
Integrated Waste The plan was adopted by MLM council in the 2019/20 financial year.The plan is under review (2023/2024 financial year)
Management Plan
Street trading by-law The municipality aims at regulating and formalising the informal street trading economic activities more especially through
the municipal CBD.
EPWP Policy The Expanded Public Works Programme (EPWP) is a nation-wide Government programme aiming at drawing significant
numbers of unemployed into productive work, so that they increase their capacity to earn an income. Job creation and
skills development remain key priorities of the South African Government. The Expanded Public Works Programme
(EPWP) is a Cabinet endorsed Programme aimed at creating work opportunities. The Programme is implemented by all
spheres of government, across four (4) defined sectors, namely the Infrastructure, Social, Non-State and Environment
and Culture sectors. The Programme’ s overall coordinator is the National Department of Public Works (DPW)
415
6.4 Financial viability and Management
Sector plans
Banking and This policy is aimed at gaining optimal return on investment, without incurring undue risks, during those periods when
Investment Policy cash revenues are not needed for capital or operational purposes. The policy was reviewed in 2022/2023 financial year.
Financial Management The MLM has at the moment the 3 years Financial Plan which addresses the financial challenges highlighted in the
Plan analysis phase. The financial priority of the municipality is viability and sustainability. The Financial Plan is aligned to the
Medium Term Revenue Expenditure Framework and caters for the income, revenue and expenditure for the year under
review as well as two outer years. This plan is under stewardship of the Finance department.
Asset Management The Municipality has approved Asset Management Policy during the 2009/10 financial year. The policy was reviewed
Policy during 202/2023 financial year.
Tariffs Policy The Municipality has adopted Tariffs Policy during 2011/12 financial year. The objective of the tariffs policy is to enables
the MLM to be self-sustainable through tariff income, enables the Council to determine tariffs in line with the applicable
legislation. All households with the exception of the indigent should pay the full cost of the services consumed. Municipal
tariffs must not be unduly a burden to local business through higher tariffs, as cost affects the sustainability and
competitiveness of such business. The plan was reviewed by council in 2022/2023 financial year.
416
Budget Policy The Budget for MLM is guided by the recently developed Budget policy. The policy aims to set budgeting principles
which the municipality should follow in preparing each annual budget, in implementing and controlling the budget during
the financial year, in adjusting the budget as directed by the MLM.The annual budget is the financial planning document
that involves all operating and expenditure decisions. In compiling the budget of the Municipality, National Budget Policy
guidelines were considered which include macroeconomic indicators as in the guidelines of the National Treasury, the
expenditure trends and revenue patterns. The policy was reviewed in the 2022/2023 financial year.
Virement policy The Municipality has recently developed and adopted the Virement policy (2010/11 financial year).The policy was
reviewed during 2022/2023 financial year.
Banking and The policy is aimed at gaining optimal return on investments, without incurring undue risks, during those periods when
investment policy cash revenues are not needed for capital or operational purpose. The policy was reviewed by council in the 2022/2023
financial year
Bad debt write off policy The municipality adopted the policy to ensure that principles and procedures for writing off irrecoverable debt are
formalised. Further to ensure that household consumers with no or lower income are not denied a reasonable service
and that the municipality is not financially burdened with non- payment of services. It provides guidance in determining
irrecoverable debts so that debtors of the municipality are not overstated in the books of the council
Property rates policy Makhuduthamaga property rates policy was reviewed by council in 2022/2023.Its purpose is to allow council to exercise
its power to impose rates within a statutory framework, with the aim to enhance certainty, uniformity and simplicity, taking
into account the historical imbalances within communities, as well as the burden of rates on the poor.
Inventory policy The policy aims to achieve the following objectives which are to: - a) Provide guidelines that employees of the
Municipality must follow in the management and control of inventory, including safeguarding and disposal of inventory. b)
Procure inventory in line with the established procurement principles contained in the Municipality’s Supply Chain
Management Policy. c) Eliminate any potential misuse of inventory and possible theft
417
6.5 Good governance and public participation
Sector plans
418
Public participation policy Public Participation Policy of Makhuduthamaga municipality was adopted by council in 2016.The purpose of
this policy is to guide and regulate public participation in Makhuduthamaga Local Municipality’s area of
jurisdiction. The main objective of this policy is to provide a broad framework through which the Municipality
can engage its stakeholders in the development of plans and the implementation of subsequent decisions or
final products. The Municipality also has an obligation to comply with statutory requirements which direct its
operations and such statutes alluding to public participation as an integral part of governance. The
incorporation of public participation in the municipal programmes is also intended to ensure legitimacy and
credibility of processes and final products.
HIV/AIDS Mainstreaming Strategy The MLM has developed and adopted the HIV/AIDS Mainstreaming Strategy during the 2007/2008 financial
for Makhuduthamaga Local year. The strategy is aimed at increasing awareness on the pandemic in the municipal area. It also
Municipality empowers councilors and employees of Makhuduthamaga Municipality to deal with HIV/AIDS matters in
service delivery
Complaints management policy The policy was developed and adopted by Makhuduthamaga council in 2016
419
6.6 Municipal Transformation and Organizational Development
Sector plans
• Address under-representation of designated groups in all occupational categories and levels in the work force
420
• Identifying and developing strategies for the achievement of numerical goals and timetables for the implementation
of affirmative action measures, taking into account the mission of the MLM
• Establishing of procedures for the monitoring and enforcement of the implementation process
• Establish procedures to address and resolve disputes regarding implementation and enforcement of EE
Human Resource It contains Recruitment, Selection and Appointment, Conditions of Service (Grievance Procedures, Discipline & Disciplinary
Policies and Procedures, Personnel Retrenchment and Personnel Replacement Policy), Basic Conditions of Employment Act, Code of
Procedure Conduct, Overtime Policy, Leave and Overtime Form
Bursary Policy The purpose of the policy is to regulate and provide a framework through which financial aid and support can be provided to
employees and members of the community for the advancement of their studies
ICT Change The purpose of this policy is to provide the Makhuduthamaga Municipality with a procedure for the change control function
Management Policy that shall be established to manage record and track all changes for Makhuduthamaga Municipality ICT environment. The
objective of this policy is to ensure that Sector Plan standardized processes are followed and adhered to accordingly. This
is to ensure that no changes take place as a quick change, with “after the fact” documentation, without any prior
authorization
421
ANNEXURE A: DRAFT BUDGET SUMMARY FOR 2024/2025- 2026/2027
REVENUE PER SOURCE Draft Budget 2024/25 Draft Budget 2025/26 Draft Budget 2026/27
Equitable Shares (ES) R363 154 000 R359 864 000 R346 801 000
Finance Management Grant (FMG) R1 800 000 R1 900 000 R2 000 000
Municipal Infrastructure Grant (MIG) R72 858 000 R76 407 000 R83 012 000
Incentive Grant: Public Works R2 348 000 R0 R0
Integrated National Electrification Grant (INEG) R12 431 000 R13 200 000 R14 327 000
Grants for Repairs and Maintenance from SDM R0 R0 R0
TOTAL R452 591 000,00 R451 371 000,00 R446 140 000,00
OWN INCOME
Property Rates R40 000 000,00 R42 000 000,00 R44 000 000,00
Licenses and Permits R6 000 000,00 R6 200 000,00 R6 300 000,00
Interest Earned-External Investments R3 500 000,00 R3 800 000,00 R4 000 000,00
Waste Management R340 000,00 R350 000,00 R360 000,00
Traffic fines R800 000,00 R900 000,00 R1 000 000,00
Interests on outstanding debtors R13 000 000,00 R15 000 000,00 RR18 000 000,00
Tender Documents R40 000,00 R45 000,00 R50 000,00
Site rental R190 000,00 R200 000,00 R250 000,00
Other Income R300 000,00 R350 000,00 R400 000,00
TOTAL R64 170 000,00 R 68 845 000,00 R74 360 000,00
TOTAL REVENUE R 516 761 000,00 R520 216 000,00 R520 500 000,00
422
ANNEXURE B: ORGANISATIONAL STRUCTURE FOR 2024/2025 FINANCIAL YEAR
423