Module 1
Module 1
Fundamentals
Module 1
CBCP_v2023.10 2
Challenges
CBCP® 5
Challenges
CBCP® 6
CBCP_v2023.10 3
Challenges
They should, but
they don’t!
CBCP® 7
Philosophy of Building Cx
• Term originated from the naval practice
• A whole building approach for quality assurance in new construction
and facility modernization
• A team effort which helps in achieving, validating and documenting
that the performance of the total building and its systems meet the
design intent and requirements of the owner
• Help restoring the existing buildings to high performance and
productivity
CBCP® 8
CBCP_v2023.10 4
Fundamentals of Building Cx
The Commissioning Process is a proven method to
consistently deliver cost effective, quality buildings and
construction projects. Its application includes:
• New buildings, facilities, and construction projects
• Identification of functional requirements and needs in existing buildings
• Retro-commissioning and commissioning existing facilities
• Building and process rehab/modification
• Sustainable/green buildings
• Energy projects
• Design-Build
• ESCO projects and Performance contracts
• LEED, BREEAM (UK), HQE(FR)
CBCP® 9
Fundamentals of Building Cx
CBCP® 10
10
CBCP_v2023.10 5
Definition of New Construction
Commissioning
11
CBCP® 12
12
CBCP_v2023.10 6
Objectives of New Building Commissioning
Building
Cx
Objectives
CBCP® 13
13
CBCP® 14
14
CBCP_v2023.10 7
New Building Commissioning : When?
Who and How ?
• Pre-design Phase
When applied • Design Phase
in buildings? • Construction Phase
• Occupancy and Operations Phase - the first year
15
Cx Process Overview
Pre-design Phase:
CBCP® 16
16
CBCP_v2023.10 8
Cx Process Overview
Design Phase:
CBCP® 17
17
Cx Process Overview
Construction Phase:
CBCP® 18
18
CBCP_v2023.10 9
Cx Process Overview
Acceptance Phase:
CBCP® 19
19
Cx Process Overview
Occupancy Phase:
CBCP® 20
20
CBCP_v2023.10 10
Definition of Existing Building
Commissioning
21
CBCP® 22
22
CBCP_v2023.10 11
Existing Buildings Commissioning Goals
Goals
• Improve building performance by saving energy and reducing operational costs
• Ensure the persistence of improvements over the building’s life
• Assist in achieving LEED certification for existing buildings
• Improve the building’s ENERGY STAR rating
• Identify and resolve building system operation, control and maintenance problems
• Verify that a facility and its systems meet the current facility requirements (CFR)
• Reduce or eliminate occupant complaints and increase tenant satisfaction
• Identify the O&M staff training needs and provide such training
• Minimize operational risk and increase asset value
• Extend equipment life-cycle
• Improve indoor environmental comfort and quality, and reduce associated liability
• Document system operation
CBCP® 23
23
Benefits
• Provides a safe and healthier facility
• Optimizes energy use
• Reduces operating costs
• Ensures adequate O&M staff orientation and
training
• Improves installed building systems documentation
CBCP® 24
24
CBCP_v2023.10 12
Retro-commissioning (RCx) : When,
Who & How?
When applied • Occupancy and Operations Phase
in buildings?
• Commissioning Authority
Performer • AEE, BCA, NEBB, ASHRAE, and other
organizations offer retro-commissioning
certification
• BCA's “Best Practices in Commissioning Existing Buildings”
• NEBB's “Procedural Standards for Retro-Commissioning of
Existing Buildings”
CBCP® 25
25
CBCP® 26
26
CBCP_v2023.10 13
RCx Process Overview
Site Investigation Phase:
• Owner’s staff training
• Initiate site investigations
• Design calculations/studies
• Building systems investigation and tests
• Perform “quick fixes”
• Update the current facility requirements
Analysis Phase:
• Define issues that are affecting the building’s performance
• Analyze issues
• Recommended problem resolution
• RCx corrective action report development
• Corrective action report presentation
CBCP® 27
27
• Approval of recommendations
• Remedial design
• Commissioning all construction and corrections made
Follow Up Phase:
• Performance verification
• Lessons learned workshop
CBCP® 28
28
CBCP_v2023.10 14
Existing Buildings Commissioning
Retro-commissioning (RCx)
Re-commissioning (Re-Cx)
CBCP® 29
29
CBCP® 30
30
CBCP_v2023.10 15
Definition of Monitoring-based Commissioning (MBCx)
CBCP® 31
31
CBCP® 32
32
CBCP_v2023.10 16
Definition of Continuous Commissioning® (CC®)
Definition:
• “An ongoing process to resolve operating problems, improve comfort,
optimize energy use, and identify retrofits for existing commercial and
institutional buildings and central plant facilities.”
FEMP Continuous Commissioning Guidebook
Purpose:
• Optimize HVAC systems operation and control for existing building
conditions
CBCP® 33
33
CC Process Overview
34
34
CBCP_v2023.10 17
Buildings Commissioning Costs
and Savings
35
Source : Eliot Crowe and All, 2020, Building commissioning costs and savings across three decades and 1,500 North American buildings
CBCP® 36
36
CBCP_v2023.10 18
Building Commissioning Costs & Savings
Source : Eliot Crowe and All, 2020, Building commissioning costs and savings across three decades and 1,500 North American buildings
CBCP® 37
37
Source : Eliot Crowe and All, 2020, Building commissioning costs and savings across three decades and 1,500 North American buildings
CBCP® 38
38
CBCP_v2023.10 19
Building Commissioning Costs & Savings
To assess the significance of non-energy benefits, 2018 survey respondents indicated the
presence or absence of up to 16 non-energy benefits that occurred as a result of a given project,
and the following seven benefits were indicated for 75 percent or more of the projects:
These non-energy benefits are highly valuable to building owners and developers.
Source : Eliot Crowe and All, 2020, Building commissioning costs and savings across three decades and 1,500 North American buildings
CBCP® 39
39
Life-Cycle Building
Commissioning (LCBCx)
40
CBCP_v2023.10 20
How Do We Transition to a More
Comprehensive Solution?
ASHRAE Guideline 0-2013
• Retro-Commissioning Process (RCx): The Commissioning Process applied to an
existing facility that was not previously commissioned. This guideline does not
specifically address retro-commissioning. However, the same basic process should
be followed from Predesign through Occupancy and Operations to optimize the
benefits of implementing the Commissioning Process philosophy and practice.
CBCP® 41
41
CBCP® 42
42
CBCP_v2023.10 21
How Do We Transition to a More
Comprehensive Solution?
• IEA ANNEX 40
• Four types of commissioning:
1) Initial Commissioning (I-Cx) is a systematic process applied to
production of a new building and/or an installation of new systems.
2) Retro-Commissioning (Retro-Cx) is the first-time commissioning is
implemented in an existing building in which a documented
commissioning process was not previously implemented.
3) Re-Commissioning (Re-Cx) is a commissioning process implemented
after I-Cx or Retro-Cx when the owner hopes to verify, improve, and
document the performance of building systems.
4) On-Going Commissioning (On-Going Cx) is a commissioning process
conducted continually for the purposes of maintaining, improving, and
optimizing the performance of building systems after I-Cx or Retro-Cx.
CBCP® 43
43
CBCP® 44
44
CBCP_v2023.10 22
ASHRAE Guidelines and
Standards for Cx Process
45
ASHRAE Guideline 1.5 – 2017 ASHRAE Guideline 1.1 – 2007 ASHRAE/NIBS Guideline 3 – 2012 (Removed)
HVAC&R Technical Requirements Technical commissioning guidelines dealing with
The Commissioning Process for
Smoke Control Systems for the Commissioning Process lighting, fire, interiors, envelopes, plumbing, etc.
CBCP® 46
46
CBCP_v2023.10 23
LEED BD+C Commissioning
47
Introduction
LEED® BD+C Energy and Atmosphere(EA) Category
• The Energy and Atmosphere (EA) category approaches energy from a holistic
perspective, addressing energy use reduction, energy-efficient design
strategies, and renewable energy sources.
• The commissioning process is critical to ensuring high-performing buildings.
CBCP® 48
48
CBCP_v2023.10 24
A Zoom on LEED BD+C
Fundamental
commissioning
and verification
Minimum energy
performance
Required
Building-level
energy metering
Fundamental
EA(up to 33 points) refrigerant
management
Enhanced
commissioning
(up to 6 points)
Extra Points( up
to 33 points)
Others
CBCP® 49
49
CBCP® 50
50
CBCP_v2023.10 25
Fundamental Commissioning & Verification
Systems to be commissioned:
Mechanical
• including HVAC&R equipment and controls
Plumbing
• including domestic hot water systems, pumps, and controls
Electrical
• including service, distribution, lighting, and controls
• including daylighting controls
Renewable energy systems
Elements of envelope commissioning (New!)
CBCP® 51
51
Envelope
Process equipment
CBCP® 52
52
CBCP_v2023.10 26
LEED® V4 Fundamental Commissioning
The commissioning authority (CxA) must do the following:
• Review the OPR, BOD, and project design.
• Develop and implement a Cx plan.
• Confirm incorporation of Cx requirements into the construction documents.
• Develop construction checklists.
• Develop a system test procedure.
• Verify system test execution.
• Maintain an issues and benefits log throughout the Cx process.
• Prepare a final Cx process report.
• Document all findings and recommendations and report directly to the owner
throughout the process.
CBCP® 53
53
By the end of the design development phase, a commissioning authority must be engaged with the following
qualifications.
• The CxA must have documented commissioning process experience on at least two building projects with a
similar scope of work. The experience must extend from early design phase through at least 10 months of
occupancy;
• The CxA may be a qualified employee of the owner, an independent consultant, or an employee of the
design or construction firm, who is not part of the project’s design or construction team, or a disinterested
subcontractor of the design or construction team.
• For projects smaller than 20,000 square feet (1 860 square meters), the CxA may be a qualified member of the
design or construction team in all cases, while the CxA must report his or her findings directly to the owner.
Project teams that intend to pursue EA Credit Enhanced Commissioning should note a difference in the CxA
qualifications: for the credit, the CxA may not be an employee of the design or construction firm, nor a
subcontractor to the construction firm.
The review of the exterior enclosure design may be performed by a qualified member of the design or
construction team (or an employee of that firm), who is not directly responsible for design of the building
envelope.
CBCP® 54
54
CBCP_v2023.10 27
LEED® V4 Fundamental Commissioning
All
Documentation
projects
CxA previous Experience X
Confirmation of OPR and BOD
X
Contents
Required List of Systems to be Commissioned X
Documentation
Verification of CxA Activities and
X
Reviews
Cx Plan X
Documentation of Testing and
X
Verification
CFR, O&M Plan X
Cx Report X
CBCP® 55
55
56
CBCP_v2023.10 28
LEED® V4 Enhanced Commissioning
Path 1 Requirements : Enhanced Commissioning (3 points)
Complete the following commissioning process (CxP) activities for mechanical, electrical, plumbing, and
renewable energy systems and assemblies in accordance with ASHRAE Guideline 0–2013 and ASHRAE
Guideline 1.1–2007 for HVAC&R systems, as they relate to energy, water, indoor environmental quality,
and durability. The commissioning authority must do the following:
Include all enhanced commissioning tasks in the OPR and BOD
Review contractor submittals
Verify inclusion of systems manual requirements in construction documents
Verify inclusion of operator and occupant training requirements in construction documents
Verify systems manual updates and delivery
Verify operator and occupant training delivery and effectiveness
Verify seasonal testing
Review building operations 10 months after substantial completion
Develop an on-going commissioning plan
CBCP® 57
57
Achieve Path 1. AND Develop monitoring-based procedures and identify points to be measured and
evaluated to assess performance of energy- and water-consuming systems. Include the procedures and
measurement points in the commissioning plan. Address the following:
roles and responsibilities;
measurement requirements (meters, points, metering systems, data access);
the points to be tracked, with frequency and duration for trend monitoring;
the limits of acceptable values for tracked points and metered values (where appropriate, predictive
algorithms may be used to compare ideal values with actual values);
the elements used to evaluate performance, including conflict between systems, out-of-sequence
operation of systems components, and energy and water usage profiles;
an action plan for identifying and correcting operational errors and deficiencies;
training to prevent errors;
planning for repairs needed to maintain performance; and
the frequency of analyses in the first year of occupancy (at least quarterly).
CBCP® 58
58
CBCP_v2023.10 29
LEED® V4 Enhanced Commissioning
Option 2 Requirements : Building Enclosure Commissioning (2 points)
The qualified independent member of the design or construction team responsible for building enclosure
commissioning must complete the following:
Review contractor submittals.
Verify inclusion of systems manual requirements in construction documents for enclosure systems.
For specialty enclosure systems with controls and automation:
Verify inclusion of operator and occupant training requirements in construction documents.
Verify systems manual updates and delivery.
Verify operator and occupant training delivery and effectiveness.
Verify seasonal testing.
Review building operations 10 months after substantial completion.
Develop an on-going enclosure commissioning plan for maintenance, renewal and revitalization cycles.
CBCP® 59
59
CBCP® 60
60
CBCP_v2023.10 30
LEED® O+M Commissioning
61
Introduction
LEED® O+M Energy and Atmosphere(EA) Category
• The Energy and Atmosphere (EA) category approaches energy from a holistic
perspective, addressing energy use reduction, energy-efficient design
strategies, and renewable energy sources.
CBCP® 62
62
CBCP_v2023.10 31
Introduction Energy efficiency
best management
practices
Minimum energy
performance
Required
Building-level
energy metering
Fundamental
refrigerant
management
EA
Existing Building
(up to 38 points) Cx Analysis
Existing Building
Extra Points( up to Commissioning (7
Cx
38 points) points)
Implementation
Others On-going Cx
CBCP® 63
63
CBCP® 64
64
CBCP_v2023.10 32
Existing Building Commissioning-Analysis
Establishment:
• Evaluate the current performance of the project building against the
performance specifications in the current facilities requirements and the
operations and maintenance plan.
• Identify the systems and components in the facility to be investigated and
analyzed as part of the existing building commissioning process. Provide a
breakdown of estimated resource use for each of these systems.
Performance
• Apply the requirements below to all direct energy-consuming or energy-
producing systems, including lighting, process loads, HVAC&R, domestic
water heating, and renewable energy.
• Update the systems and components to be addressed as part of the
existing building commissioning or energy auditing process. Provide a
breakdown of estimated resource use for each of these systems.
CBCP® 65
65
Schedule X X
Required
Documentation Energy use breakdown X X
CBCP® 66
66
CBCP_v2023.10 33
Existing Building Commissioning-Implementation
Establishment
Meet the requirements of EA Credit Existing Building
Commissioning—Analysis.
Performance
• Apply the requirements below to all direct energy-consuming or
energy-producing systems, including lighting, process loads, HVAC&R,
domestic water heating, and renewable energy.
CBCP® 67
67
Documentation All
projects
CBCP® 68
68
CBCP_v2023.10 34
Ongoing Commissioning
Establishment:
• Meet the requirements of EA Credit Existing Building Commissioning–Analysis
and EA Credit Existing Building Commissioning–Implementation.
• Establish an ongoing commissioning process that includes planning, point
monitoring, system testing, performance verification, corrective action
response, ongoing measurement, and documentation to proactively address
operating problems in the systems being commissioned.
Performance
• Apply the requirements below to all direct energy-consuming or energy-
producing systems, including lighting, process loads, HVAC&R, domestic
water heating, and renewable energy.
• Continue to update the facility’s operating and maintenance plan and current
facilities requirements to reflect actual conditions and issue annual revisions
of these documents.
• Only activities associated with ongoing commissioning completed within two
years of the LEED application may be included to show progress.
CBCP® 69
69
Ongoing Commissioning
CBCP® 70
70
CBCP_v2023.10 35
ISO Standard for Building
Commissioning
71
CBCP® 72
72
CBCP_v2023.10 36
ISO 21105-1: 2019 - Performance of buildings
— Building enclosure thermal performance
verification and commissioning
73
CBCP® 74
74
CBCP_v2023.10 37
ISO 21105-1: 2019 - Performance of buildings
— Building enclosure thermal performance
verification and commissioning
The standard identifies steps necessary to perform a building enclosure risk
analysis. The analysis will result in tasks that define the level of BECx,
commensurate with the owner's tolerance for risk associated with building
enclosure performance.
The Levels of BECx are:
Level 1: Basic - minimum
Level 2: Intermediate - medium
Level 3: Comprehensive – maximum
Each level has many fundamental tasks that are required to achieve the process.
CBCP® 75
75
CBCP® 76
76
CBCP_v2023.10 38
ISO 21105-1: 2019 - Performance of buildings
— Building enclosure thermal performance
verification and commissioning
Level 1 basic BECx would require:
one design review
monthly construction observation site visits
and witness to 25 % of performance testing during construction
CBCP® 77
77
End
78
CBCP_v2023.10 39