SSRE Manchinillabavi EOT Lettter From EE To SE
SSRE Manchinillabavi EOT Lettter From EE To SE
Sir,
Executive Engineer(R&B)
NH Division, Karimnagar
To
The Superintending Engineer(R&B)
NH Circle Nizamabad.
a) Handing Over of the Land: Project ROW length 3.037 km was handed over on the appointed date
after a delay of one month from the date of agreement. However, there are various hindrances in
the form of Trees, Municipal & Mission Bhageeratha Water Supply Lines, Electrical Lines etc., The
work got delayed due to delay in providing Tree cutting permission by Forest department.
b) Work front availability free from Hindrances:
1. Work font available is NIL as on Appointed Date as there was Hindrance due to existing 114
No.s of old Trees having girth (diameter) ranging from 2.00 m to 5.00 meters which are very
near to existing two-lane paved shoulders.
2. Shifting of Electrical power lines are also hindrance to the work.
3. The authority Engineer has applied for permission for cutting and uprooting the old trees and
for shifting of Electrical lines to the concerned Departments.
4. The Divisional Forest Officer has accorded the felling permission on 06-05-2023 vide his letter
No. R.C No. 1114/SBA/2023, Copy of letter enclosed. The cutting of trees started. The time
taken for cutting of trees and uprooting them about three (3) months i.e., 06-08-2023.
5. For shifting Electrical lines the NPDCL (Northern Power DistributionCo.Ltd) has accorded
permission subject to payment of Security Deposit of 2.5% (two and half) percent of
estimated cost of shifting of Electrical lines after lapse of 87 days vide their letter dated 16-
06-2023 copy enclosed. The Security Deposit of Rs. 65,122 /- was paid by NHAI through
online on 30-08-2023 copy of payment receipts is enclosed. Shifting of Electrical lines and
relocating commenced and simultaneously widening work was also commenced.
The above details of clearances & hindrances along road side, the Milestones to be achieved as
per Contractor Agreement, delayed by 163 days i.e., up to 30-08-2023.
As the tree cutting was completed by July-2023 and the shifting of Electrical lines started in Sep-
2023, simultaneously the widening work was also commenced. The progress of work achieved as per
Mile Stones is tabulated below.
In view of the above and taking into consideration the non-availability of work front for 163 days,
were determined as Extension of Time required for all Mile Stones. The Extension of Time for completion
of whole work i.e., Mile Stone – IV up to 18th-Sep-2024 is requested.
Hence, keeping the delays in giving hindrance free reach to the contractor as shown in Table-I, to
grant Extension of Time to each of the Mile stones and for the completion of the project as per Clause
19.11 of EPC Agreement as per the above Table-II without imposing Liquidated Damages and without
restriction on Price Adjustment.
In this regard, it is to submit that work font available is NIL as on Appointed Date as there were
Hindrances at site.
a) Approval for clearing Hindrances in 3.037 km was accorded by Forest clearance on 06-05-
2023 for tree cutting.
b) Approval for clearing hindrances in 3.037 was accorded by concluding agreement for shifting
of Electrical lines on 30-08-203
c) Hence as on 30-08-2023, the hindrances like Shifting of Electrical lines and relocating
commenced and simultaneously widening work was also commenced.
In view of the above the Extension of 1st 2nd& 3rd& 4th Mile Stones/Scheduled completion date is
requested up to 10-01-2024, 14-04-2024, 15-06-2024&18-09-2024 respectively, As the Financial Progress
achieved as on 15-06-2024 is 87.089%. The completion of work within available work front of 3.037 is
herewith recommended to 18-09-2024.
Modified summary of Extension of Time for different Milestones including completion of the
work recommended are as below.
Table-II
% OF FINANCIAL
MILESTONE/ EOT No. of
PROGRESS
Days
SL. APPOINTED MILESTONE EOT/
Description (From
No. AS PER AS PER DATE AS PER PROPOSED
Appointed
AGREEMENT ACHIEVED AGREEMEN MILESTONE
Date)
T UP TO
Due to delay in getting hindrance free Road from Trees as well as shifting of Electrical lines etc., it
is requested to grant Extension of Time for the proposed Mile Stones I, II, III&IV as mention in the above
table without imposing liquidated damages and without restriction of Price Adjustment.
In view of the above, it is requested to communicate the approval of Mile stone with respect to
granted extension of time period as above from the Competent Authority at an early date.
Yours Faithfully
OLD EOT letter
GOVERNMENT OF TELANGANA
ROADS & BUILDINGS DEPARTMENT
NATIONAL HIGHWAYS
From To
K.Manohar, The Superintending Engineer,
Executive Engineer(R&B), (R&B) NH Circle, Nizamabad.
NH Division, Karimnagar.
Sir,
Executive Engineer(R&B)
NH Division, Karimnagar