PMI-RMP-demo
PMI-RMP-demo
Exam
PMI PMI-RMP
Version Demo
https://dumpsarena.co
[email protected]
QUESTION NO: 1
You work as a project manager for BlueWell Inc. You have to communicate the causes of risk events to the stakeholders.
Which risk diagramming technique you will use to communicate the causes of risk events to project stakeholders?
C. Ishikawa diagrams
D. Influence diagrams
ANSWER: C
QUESTION NO: 2
Yolanda is the project manager of a high-profile project for her organization. This project has 124 stakeholders from across
the organization and many of the stakeholders have high demands and expectations for the project. Yolanda will need
several pieces of project information as she begins to communicate and manage the stakeholder expectations. Which of the
following inputs of the manage stakeholder expectations process directly addresses the risks that could affect the project and
which must be communicated to the project stakeholders?
A. Change log
C. Issue log
D. Stakeholder register
ANSWER: A
QUESTION NO: 3
A risk manager is confident that they have identified and quantified the risks and opportunities for a project. When presenting
their work to management, on what areas should the risk manager focus? (Choose two.)
B. Risks as they apply to the organization's overall risk management philosophy and strategic ambition
C. Huge opportunities that possibly bring an additional 30% return for 10 projects in the next year
D. Risks related to cost that will impact the major projects that are currently in the execution phase
ANSWER: A B
Explanation:
The risk manager should focus on risks that are directly tied to the success of the organization and those that align with the
organization's risk management philosophy and strategic ambition. This will ensure that management is informed about the
most relevant risks and opportunities for the project.
QUESTION NO: 4
You are the project manager for TTP project. You are in the Identify Risks process. You have to create the risk register.
Which of the following are included in the risk register? Each correct answer represents a complete solution. Choose two.
ANSWER: C D
QUESTION NO: 5
Project stakeholders identify, analyze, and plan the risk responses for a project. However, the contingency reserves are
depleted before the project is completed.
ANSWER: C
QUESTION NO: 6
ANSWER: C D
Explanation:
Lessons learned and previous project risks are valuable sources of information for creating a risk checklist. They provide
insights into potential risks that may impact the current project and help the project manager develop appropriate risk
responses. Budget variance data, project scope and cost management plans, and stakeholder analysis metrics, although
useful, are not directly related to risk identification. (Reference: Project Management Institute. A Guide to the Project
Management Body of Knowledge (PMBOK® Guide) – Sixth Edition, Section 11.2)
QUESTION NO: 7
The project manager asks the risk manager to determine the initial risk assessment for a six month initiative that is about to
kick-off. Which two artifacts will help the risk manager conduct the related analysis? (Choose two.)
D. Brainstorming
ANSWER: A E
Explanation:
The work breakdown structure (WBS) will help the risk manager in understanding the project's scope and identifying
potential risks at different levels of the project. Monte Carlo analysis is a quantitative risk analysis technique that can be used
to assess the impact of identified risks on the project's schedule and cost.
QUESTION NO: 8
A. Scope baseline
C. Risk register
ANSWER: A B D
QUESTION NO: 9
A risk manager was recently hired to assist with a mid-sized infrastructure project. The risk manager becomes aware that
they have an inexperienced project team.
What two items should the risk manager have their team review in order to prepare for an upcoming risk identification
workshop? (Choose two.)
ANSWER: A E
Explanation:
The risk manager should have their team review the scope of work and requirements to ensure they understand the project's
objectives and deliverables. Additionally, reviewing the risk management plan will help the team understand the risk
management process, roles, and responsibilities, and prepare for the risk identification workshop.
QUESTION NO: 10
Which of the following are parts of SWOT Analysis? Each correct answer represents a complete solution. Choose all that
apply.
A. Opportunities
B. Tools
C. Weaknesses
E. Strengths
F. Optimism
ANSWER: A C D E
QUESTION NO: 11
You are the project manager for the NHQ Project. This project requires that you install 140 copies of design software onto
your department's computers. The vendor offers you a twenty percent discount on the software if your company will
purchase 150 or more copies of the software. You communicate this offer with other departments in your firm to see if
anyone else would need 10 copies of the software to save your project a significant amount of funds. What is this risk
response called?
A. Exploiting
B. Avoidance
C. Sharing
D. Transference
ANSWER: C
QUESTION NO: 12
During project execution, the project team realizes that the power outlet for imported equipment is not compatible with the
current customer's electrical infrastructure. This event was originally identified as a risk during earlier stages of the project
and the associated risk response indicated a plan to purchase a new power adapter.
A. Management reserve
B. Management budget
C. Project budget
D. Contingency reserve
ANSWER: D
QUESTION NO: 13
D. Wendy can forecast deviation of the project cost and schedule for completion targets.
ANSWER: D
QUESTION NO: 14
The Project Risk Management knowledge area focuses on which of the following processes? Each correct answer
represents a complete solution. Choose all that apply.
ANSWER: A B D
QUESTION NO: 15
A mega facility development project is evaluating some options to achieve the project schedule and budget. Each option's
success is driven by multiple quantifiable factors.
What should the project manager do to evaluate and select the best option based on costs and probabilities?
ANSWER: C
Explanation:
QUESTION NO: 16
A project manager was informed that the testing of the latest component in the project's software update release was not
successful. As a result, 1he delivery timelines for the software release wifi be delayed, The project manager did not
previously capture this as a risk to the project.
D. Log the event in the issue log and update the project management plan.
ANSWER: B
Explanation:
The project manager should reassess risks by conducting a new assumptions and constraints analysis. This will help identify
any previously overlooked risks and ensure that the risk register is comprehensive and up-to-date.
QUESTION NO: 17
The project team has correctly identified, assessed, and planned responses for a project's risks. The risk manager is
required to prepare a quarterly report on the performance of managing the risks.
What are two options the risk manager should consult for the analysis? (Choose two.)
ANSWER: C E
Explanation:
QUESTION NO: 18
A regional vendor for custom manufactured steel oil derricks, is awarded a contract to design, manufacture, and install 40
offshore oil platforms. Installation of these derricks requires precision placement and stable seas for the transport and
installation ships to property install the deep water structure. There are several schedule and cost incentives for early
completion, and the project manager asks the project risk coordinator to perform an analysis, which will predict the
probability of meeting the incentive dates. While researching methods that could be used for performing this analysis, the
risk manager realizes that there are readily available spreadsheets within the organization. The risk manager is considering
performing a Method of Moments (PERT) analysis with software already owned, or the other option is to buy a commercial
risk analysis software suite that will perform Latin Hypercube Monte Carlo simulations at a cost of US$975.
What would be the best analytical option for this probability assessment?
A. Schedule based Method of Moments analysis is a time proven, highly accurate method for schedule risk and is not
impacted by Monte Carlo simulation’s limitation of summation modeling where only addition and subtraction of uncertain
values are used.
B. The commercial product that performs the Monte Carlo simulations is the best option, because a schedule risk
assessment involves summation of uncertainties added or subtracted from or to schedule dates.
C. Because a schedule risk assessment involves multiplication and division of schedule durations against specific risk
events, a spreadsheet and using a Method of Moments analysis is the best option.
D. Since a schedule risk assessment involves multiplication and division of schedule durations against specific risk events,
the Monte Carlo simulation software is the best option.
ANSWER: B
QUESTION NO: 19
Which of the following statements describe the purpose of an Issue Log? Each correct answer represents a complete
solution. Choose all that apply.
ANSWER: A B C
You are the project manager for GHY Project and are working to create a risk response for a negative risk. You and the
project team have identified the risk that the project may not complete on time, as required by the management, due to the
creation of the user guide for the software you're creating. You have elected to hire an external writer in order to satisfy the
requirements and to alleviate the risk event. What type of risk response have you elected to use in this instance?
A. Avoidance
B. Exploiting
C. Transference
D. Sharing
ANSWER: C