Punch Points list of Behiating
Punch Points list of Behiating
Report on pending issues related to 220/132kV extension portion commissioned under NERPSIP scheme at 220kV Behiating GSS, AEGCL, Khanikar, Dibrugarh as on 19/05/2025
Issues evolved from
Commissioning/during
Sl no Issue generated after charging or prior to charging which are still unresolved Present Satus Remarks Material Requirement
Defect liability period.
Issue related to battery cell and battery bank:The 48V battery bank-1 is out of service since
1 set of Battery bank has been
dtd. 04-11-2024 following mulfunctioning of 48V DC system due to excessive heating of Issue related to 48V Battery cell and
restored by replaing few
battery cells. 01 no of battery cell of 48V battery bank-2 is found to be totally defective and Battery bank was Completed on
battery cells( 4 nos). And 1 set
currently only 23 nos of battery cells are in service. Moreover Damaged battery cells (09 nos 19.05.2025.
8 battery bank replaced from the 1 set of 48V Battery
and 05nos respectively) of 48V & 220V battery banks should be replaced at the earliest.
battery supplied for FOTE. Also
Considering the last records of faulty battery cells this can be ascertained that there must be Issue related 220V Battery cell and
Battery charger voltage was
some issue with quality of the materials supplied and the number of faulty battery cells will Battery bank is pending
higher and tuned appropriately.
be increased in coming days.
Issues evolved from
Commissioning/during
Sl no Issue generated after charging or prior to charging which are still unresolved Present Satus Remarks Material Requirement
Defect liability period.
The Bay Control Unit (BCU Make: Micom, Alstom, Ds Agile, SER no: 34565494/09/18) of
Transformer CRP (Bay-108) of the 220/132kV,100MVA ICT-2 is not functioning resulting
BCU Power supply wire was
hinderances in operation/monitoring of LV side of the ICT-2 from SAS HMI and CRP. This has
10 Completed on 19.05.2025 found loosen. Now the BCU is
been scrutinized in coordination with T&C wing, AEGCL and found the issue with the BCU.
functioning satisfactorily.
The issue related to the IV (132kV) side BCU of the ICT-2 should be rectified at the earliest for
smooth operation/monitoring.
Mismatch in energy import-export data of 220/132kV portion. Export from 100MVA ICT is
11 more than the import from the 220kV Transmission lines. This results in -ve energy loss of Pending
the sub-station which should be rectified at the earliest.
Only Station service transformer-2, connected to 100MVA ICT-2 was commissioned.Station Breaker closing issue has
service transformer-1 (connected to 100MVA ICT-1) is not commissioned yet. The 400kVA resolved and LT Transformer
12 Completed on 19.05.2025
station transformer-1 should be commissioned at the earliest to avoid any station black out back charged. The transformer
at the time of failure of the station service transformer-2. is charged on 20.05.2025
DG set is installed but not commissioned yet. It should be commissioned at the earliest to
13 Pending Battery has sent for charging.
restore station power during emmergency condition.
14 Fire Hydrant system is not commissioned yet and this should be commissioned at the earliest. Completed
Air conditioners of the SPR1&2 are non functioining prior to commissioning of the
220/132kV extension portion. Considering the excessive temperature within the SPRs the
15 Pending
rectifiation/installation of new air conditioners should be done on priorty basis to avoid any
further breakdown of the protection/communication system and SAS.
Issues evolved from
Commissioning/during
Sl no Issue generated after charging or prior to charging which are still unresolved Present Satus Remarks Material Requirement
Defect liability period.
440V ACDB: The bus coupler CB(make:C&S electric,type:AHA-6N-CS,630A) is found to be The VCB was found in racked
defective since DoC. As such replacement is needed for enabling the independent mode of out condition. The breaker was
17 Completed on17.05.2025
operation from station service Tr-1&2. The issue has already been brought to notice of racked in and explained the
NECCON site engineer requesting early rectification of the issue. oeprational procedure of ACDB
and MSB to AEGCL Staffs.
21 Healthiness of RTCC panel (Spare) to be demonstrated Pending Under the scope of T&R
22 Emergency break glass to be fitted on NIFPS indoor control panel against ICT -2 Pending Under the scope of T&R
Driving mechanism issue of the Earth switch , 89 CE1(bay 203, ICT-II) should be rectified for
23 Pending
its smooth operation
24 Broken/damaged locks of all equipment JBs/MBs are to be replaced/rectified. Completed
25 The chequered plates of PLCC room, SPRs, New extension control room needs to be placed Completed
properly for safety of duty personnel and also to maintain the suitable room temperature.
Hard copies of manual for CB, CRP, charger panels, ICTs,DG, Fire hydrant system etc. and
27 drawings related to all electrical & civil works should be provided before handing over the Pending
substation.
28 Repairing of cable trenches and drain (in front of existing control room) is required. Pending
29 Supply of furniture for SAS & DR PCs and printers. Pending
30 Other remaining civil works as per BOQ should be completed at the earliest. Pending
31 Mandatory spares to be supplied as per BOQ. Pending
One power cable in the cable trench between bay 205& bay 204 is found to be punctured.
32 Closing issue with the Earth switch of line isolator of bay 204.These should be rectified at the Completed
earliest.
33 Installation of dewatering pump in the swicthyard should be completed. Completed
34 203 bay(ICT-2):Closing issue related to isolator 89B is to be attended. Completed on 17.05.2025