The document outlines a detailed construction schedule with various tasks, durations, and start and finish dates. It includes phases such as mobilization, substructure, superstructure, and finishing work, detailing specific activities and their respective time allocations. The overall timeline spans from June 5, 2013, to December 20, 2013, with various dependencies and relationships between tasks noted.

Uploaded by

tinsaekifle08
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
1 views

Exercise_Import to MS Project_2024

The document outlines a detailed construction schedule with various tasks, durations, and start and finish dates. It includes phases such as mobilization, substructure, superstructure, and finishing work, detailing specific activities and their respective time allocations. The overall timeline spans from June 5, 2013, to December 20, 2013, with various dependencies and relationships between tasks noted.

Uploaded by

tinsaekifle08
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 8

ID Name Duration Start Date Finish Date

G+3 T16 C 1 day? 9/2/2013 8:00 9/2/2013 17:00


Mobilization 20 days 9/2/2013 8:00 9/24/2013 17:00
SUB STRUCTURE 169.5 days 6/5/2013 8:00 12/20/2013 12:00
Excavation & Earth work 159.5 days 6/5/2013 8:00 12/9/2013 12:00
Site clear 3 days 6/5/2013 8:00 6/7/2013 17:00
Bulk excavation 2 days 6/8/2013 8:00 6/10/2013 17:00
Pit excavation 1 day 6/11/2013 8:00 6/11/2013 17:00
Trench excavation 5 days
Back fill using selected materialsl 13.5 days
cart away 4 days
Concret work 35 days
Lean concret 2 days
Lean Concrete Under Masonary wall 1 day
For footing Pad 1 day
For foundation column 0.5 days
For Grade beam 0.5 days
Ground floor slab 1 day
Ground floor elevation column 1 day
Stair case 0.5 days
Form work 58 days
For footing pad 1 day
For Foundation column 1 day
For grade beam 1 day
Ground floor elevation column 1 day
stair case 1 day
Props and joists for stair 3 days
Striping of props 1 day
Reinforcement 12.5 days
Footin pad and foundation column 11 days
Grade Beam 5 days
Ground floor slab 3 days
Ground floor elevation column 3 days
Stair case 1 day
Stone Work 8.5 days
Foundation wall 5 days
Hard Core 2 days
SUPER STRUCTURE 142 days
First Floor 55.7 days
Concret Work 9.2 days
Elevation column 0.5 days
Beam and Ribbed Slab 1 day
Stair Case 0.2 days
Form Work 55.7 days
Elevation Column 1 day
Intermidate Beam and slab 2 days
Side formwork for exterior beams 2 days
Stair Case 1 day
Props and joists 3 days
striping of props 3 days
Reinforcement 24.5 days
Elevation column 6 days
Beam 8 days
Ribbed Slab 7.5 days
Stair Case 1 day
Second Floor 39.2 days
Concret Work 15.5 days
Elevation column 0.5 days
beam and Ribbed Slab 1 day
Stair Case 0.2 days
Form Work 39.2 days
Elevation Column 1 day
Intermidate Beam and slab soffit 2 days
side formwork for exterior beam 2 days
Stair Case 1 day
Props and joists 3 days
striping of props 3 days
Reinforcement 24 days
Elevation column 5.5 days
Intermidate Beam 8 days
Ribbed Slab 7.5 days
Stair Case 1 day
3rd Floor 53 days
Concrete Work 23.5 days
Elevation column 1 day
Beam and Ribbed Slab 1 day
Top Tie Beam 0.5 days
Form Work 49 days
Elevation column 1.5 days
Intermidate Beam and slab soffit 2 days
Side formwork for exterior beam 1 day
Props and joists 3 days
striping of props 3 days
Top Tie Beam 2 days
props & Joists for Top tie beam 1 day
striping of props for top tie beam 1 day
Reinforcement 27 days
Elevation column 4 days
Intermidate Beam 8 days
Ribbed Slab 7.5 days
Top Tie Beam 4.5 days
Block work 47.3 days
Block work for ground floor 3 days
Block work for first floor 3 days
block work for second floor 3 days
Block work for third floor 3 days
Metal Work 77.3 days
Metal work for ground floor 2 days
Metal Windows for 1st floor 2 days
Metal Windows for 2nd floor 2 days
Metal Windows for 3rd floor 2 days
Steel Guard Rail 16 days
Roofing Work 2 days
EGA 500 1.5 days
Roofing ridge 0.5 days
Side Cladding 0.5 days
Carpentery & Joinery 13.2 days
Eucalyptus Truss 2.5 days
Zigba wooden purlin 1 day
Latice purlin 4 days
Chip wood ceiling 3.5 days
Wooden doors 6 days
Finishing Work 66.3 days
Ground floor 7 days
first coat plastering 1 day
Second coat plastering 2 days
Third coat of plastering 2 days
First floor 7 days
first coat plastering 1 day
Second coat plastering 2 days
Third coat of plastering 2 days
Second floor 7 days
first coat plastering 1 day
Second coat plastering 2 days
Third coat of plastering 2 days
Third floor 7 days
first coat plastering 1 day
Second coat plastering 2 days
Third coat of plastering 2 days
Terrazo Tile 45.3 days
For ground floor 1 day
For first floor 1 day
For second floor 1 day
For third floor 1 day
Terrazo Tile skirting 45.3 days
For ground floor 1 day
For first floor 1 day
For second floor 1 day
For third floor 1 day
window sill for ground floor 0.5 days
window sill for first floor 0.5 days
window sill for second floor 0.5 days
Window Sill for third floor 0.5 days
Glazing 2 days
Clear Glass 2 days
Painting 49.3 days
ground floor 5 days
First coat of plastic paint 1 day
second coat of plastic paint 1 day
Thired coat of plastic Painting 1 day
First floor 5 days
First coat of plastic paint 1 day
second coat of plastic paint 1 day
Thired coat of plastic Painting 1 day
Second floor 5 days
First coat of plastic paint 1 day
second coat of plastic paint 1 day
Thired coat of plastic Painting 1 day
Third floor 3 days
First coat of plastic paint 1 day
second coat of plastic paint 1 day
Thired coat of plastic Painting 1 day
Oil Paint 23.3 days
For ground floor 1 day
For first floor 1 day
For second floor 1 day
For third floor 1 day
Silling paint 1 day
Site Work 44.3 days
Concret Paving 1 day
Open Ditch 1 day
Site waste disposal 3 days
Site hand over 1 day
Relationship

5
6
9SS+1 day
15SS+7 days
5,6,7,8,171SS+1 day

7,8
8
29
22
23
31
24
25,33

12

30
32
26
17,18
19FS+21 days

21
35
36
16
30

13
9

44
46
41SS+2 days,47

51
48
53
54,27
17
41,42FS+21 days

41
45
52
52

61
63
64

68
65
70
71
41
58,59FS+21 days

58
62
69
69

78
80,71
90

87
81,59
89
74
75FS+21 days
84
78
76FS+14 days

58
79
88
83

49
66
82
85

115
119
123
127
129

107
103
103

109
107
85
108
151

92FS+2 days
114FS+1 day
115FS+1 day,139

93FS+2 days
118FS+1 day
119FS+1 day,140

94FS+2 days
122FS+1 day
123FS+1 day,141

95FS+2 days
126FS+1 day
127FS+1 day,142

149FS+1 day
153FS+1 day
157FS+1 day
161FS+1 day
130
131
132
133
115
119
123
127

153

116FS+7 days
147FS+1 day
148FS+1 day

120FS+7 days
151FS+1 day
152FS+1 day

124FS+7 days
155FS+1 day
156FS+1 day

128SS+7 days
159SS+1 day
160SS+1 day

97,111
98,111
99,111
100,111,104,105
163,164,165,166,144,110

144SS+2 days
169FS+1 day
167,170,135,136,137,138
10