Timesheet (06 to 28)

The document is a time sheet detailing the work conducted by engineer Thirumal Azagan K for SCADA commissioning at the Transrail site in April 2025. It includes dates, working hours, activities performed, and remarks on testing and observations related to 132kV and 220kV systems. The time sheet highlights various tasks such as relay testing, database updates, and configuration changes as per customer requirements.

Uploaded by

rockthiru5500
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
7 views1 page

Timesheet (06 to 28)

The document is a time sheet detailing the work conducted by engineer Thirumal Azagan K for SCADA commissioning at the Transrail site in April 2025. It includes dates, working hours, activities performed, and remarks on testing and observations related to 132kV and 220kV systems. The time sheet highlights various tasks such as relay testing, database updates, and configuration changes as per customer requirements.

Uploaded by

rockthiru5500
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

TIME SHEET FOR WORK ON SITE

JOB REFERENCE :
CUSTOMER’S REFERENCE :
CUSTOMER : TRANSRAIL
SITE : 220/132KV PGCIL NAMSAI
ENGINEER ‘S NAME : THIRUMAL AZAGAN K MONTH :APRIL YEAR : 2025
JOB UNDERTAKEN : SCADA COMMISSIONING

DATE WORKING TIME ACTIVITY REMARKS


FROM TO HOURS
132kv shutdown for ICT-3 and ICT-5 Testing with SCADA Events.
06 April 2025 09:30 20:00 10:30

07/04/2025 comb off work on Sunday

For Line-1 201 REL670 testing completed with scada events


08/04/2025 09:30 21:00 11:30

21:00 Observation changes doing for database as per customer requirements


09/04/2025 09:30 11:30
For 132kv ICT-3 P643 Relay testing completed with scada events.
10/04/2025 09:30 01:30 16:30

22:00 For 132kv ICT-4 P643 Relay testing completed with scada events..
11/04/2025 09:30 12:30
In gateway RLDC and BRLDC 104 Address Mapped in gateway and In DB
12/04/2025 09:30 00:30 15:30 observations ongoing for 220kv

13/04/2025 09:30 01:00 16:00 132kv shutdown for ICT-3 and ICT-5 Testing with SCADA Events.

For All the bay Checked the current and voltage value and scaling also
14/04/2025 09:30 01:00 16:00 changed in DB all reporting
201 P546 Relay testing completed and LED rename for all bay. Main and
15/04/2025 09:30 01:00 16:00 standby Gateway DB uploaded

For RLDC and BRLDC validation completed for 132kv ICT-3 and ICT-5
16/04/2025 09:30 01:00 16:00
132kv ICT-3 and 220kv ICT-3 Line-1 and Bus coupler Bus-1 RLDC and
17/04/2025 09:30 01:30 16:30 BRLDC validation Completed 132kv ICT-3 and 220kv ICT-3 and Line-1
Tested Charged
132kv ICT-4 and 220kv ICT-4,Line-2 ,Bus coupler and Reactor bay RLDC and
18/04/2025 09:30 01:30 16:30 BRLDC validation Completed. 132kv ICT-4 and 220kv ICT-4 and Line-2
Tested Charged
observations need to change as per RTAMC, NTAMC and BNTAMC.
19/04/2025 09:30 01:00 16:00

20/04/2025 SUNDAY

Testing completed observations for relay and scada is there need to


21/04/2025 10.00AM 01:00 16:00
complete
observation ongoing retrip signal configure for 201,206 and configure in
22/04/2025 10.00AM 01:00 16:00 scada now reporting in HMI. O/C and E/F signal also configured in scada
Already Existing bay signal configured in RLDC and BRLDC GATEWAY
23/04/2025 10.00AM 01:30 16:30 main and standby server.
For 202 and 203 LBB backtrip checked . 132kv also 103 and 105 checked.As
24/04/2025 10.00AM 12:30 15:30 per customer requirements for master trip relay created one logic 86a and
86b if any one optd logic will get high
For AR RECLOSE as per customer requirements logic has changed but logic
25/04/2025 10.00AM 01:30 16:30 is working need to be check.
Observations for 103 and 105 overflux start signal mapped in scada and LED
26/04/2025 10.00AM 21:30 13:30 also renamed for p546 and p643 relay.
201 and 206 Observations Completed And LED renamed for P546 and
27/04/2025 10.00AM 22:30 14:30 REL670 Relay.
As per observations AutoReclose Logic made in DB and Upload and checked
28/04/2025 10.00AM 00:30 15:00 in BCU.

SIGNATURE : DATE : 30/04/25 SIGNATURE : DATE : 30/04/25

ENGINEER ‘S NAME : Thirumal Azagan K CUSTOMER NAME : Dhandayuthabani

M/s. SEIL M/S.TRANSRAIL