Method Statement for Lighting Fixtures

This document outlines a comprehensive method statement for the installation of lighting fixtures, detailing necessary steps, safety measures, and equipment required for the process. It includes sections on contractor details, scope of work, management structure, and inspection plans, ensuring that all work complies with project specifications and safety standards. The document emphasizes the importance of proper installation and testing to enhance both functionality and aesthetics in the designated space.

Uploaded by

joewell01986
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
22 views5 pages

Method Statement for Lighting Fixtures

This document outlines a comprehensive method statement for the installation of lighting fixtures, detailing necessary steps, safety measures, and equipment required for the process. It includes sections on contractor details, scope of work, management structure, and inspection plans, ensuring that all work complies with project specifications and safety standards. The document emphasizes the importance of proper installation and testing to enhance both functionality and aesthetics in the designated space.

Uploaded by

joewell01986
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 5

As lighting fixtures play an essential role in enhancing the

functionality and aesthetics of any space, a well-planned and


executed installation process is essential.
A comprehensive method statement for installing lighting fixtures will ensure
that the installation process is conducted safely, efficiently, and systematically.

This method statement will outline the necessary steps and procedures
required to install lighting fixtures, including detailed instructions for handling
the fixtures, tools, and equipment needed to complete the installation and
safety measures to ensure the well-being of the installation team and other
stakeholders.

Table of Contents

 1.0- Contactor Details


 2.0- Scope of Work
 3.0- Programmed Duration of Activity
 4.0- Management Structure/Resources and Responsibilities
 5.0- Communication/Contact Details
 6.0- Method Statement for Installation of Lighting Fixtures at Main Mosque
 7.0- Inspection and Test Plan (and records to be submitted)
 8.0- Plant and Equipment
 9.0- Special Scaffold/Access Equipment
 10.0- Training and Competency of Personnel (see also 18 below)
 11.0- First Aid and Emergency Arrangements
 12.0- Advise Any Permits to Work required (e.g., Hot works; confined space;
excavation; electrical)
 13.0- Environmental Considerations
 14.0- Waste Management
 15.0- Hazardous Substances – Attach material data sheets
 16.0- Any Special Storage Requirements
 17.0- Testing and Commissioning
 18.0- Supporting Documents:
 Expert Advice:

1.0- Contactor Details


The main contractor will undertake the work.

2.0- Scope of Work


Our total scope of work for lighting Installation and testing, and commissioning
in accordance with the project specifications for the satisfaction and approval
of the Consultant.

The work shall include not only the system’s major items but all the incidental
sundry components necessary, together with the resources for the complete
execution of the works and the proper operation of the installation, whether or
not these sundry components are stated in detail.

3.0- Programmed Duration of Activity


All activities shall be done in accordance with the approved project schedule.

4.0- Management Structure/Resources and Responsibilities


All the material will be available in the store; work will be done under the
supervision of:

Name Designation Mobile

5.0- Communication/Contact Details


Name Designation Mobile

6.0- Method Statement for Installation of Lighting Fixtures at


Main Mosque
 Ensure that the entire installation is in conformance and accordance
with the design intent of the project for the electrical system approved
by the Consultant and as per approved drawings and comply with the
manufacturer’s recommendations and the following project
specifications:

16050 BASIC ELECTRICAL MATERIALS AND METHODS


16145 LIGHTING CONTROL DEVICES
16511 INTERIOR LIGHTING
16570 DIMMING CONTROLS.
 Before proceeding with the work installation, we will ensure that the
consultant approves the drawings and materials and coordinate with
other services
 The material shall be protected as per manufacturer recommendations.
 After material inspection, it will be released for site activities.
 MEP Engineer shall coordinate for any discrepancies at the site.
 Damaged material will be removed from the site after consultation and
approval from the concerned person.
 Setting out will be done on the surfaces according to the approved
drawings and shall be coordinated with other services.
 Ensure all finishing work in all related areas should be completed for the
installation area and released /cleared by the civil section to proceed
with installing lighting fixtures.
 Fixtures will be installed rigidly, and supports/hangers will be installed
where needed with consideration of manufacturer recommendations
 All lighting fixtures shall be installed below or follow as approved
drawings of all other services like (duct, pipe, tray, and trunkings).
 Light fixtures shall be installed as per approved shop drawings and
materials submittal.
 All the fixtures should be properly earthed.
 Strippers will be used to trim the wire’s insulation according to the depth
of the wiring device. When connecting two wires in the same terminal,
they will be inserted alongside without twisting together.
 The number of wires inside the conduits (PVC/EMT/RGS/GI/UPVC) will
be as per NEC standards and project specifications.
 Each circuit loop shall be connected to the Circuit Breaker/Panelboard
per the approved drawings & project specifications.
 Wires’ colors shall be in accordance with approved drawings and
project specifications.
 Install the tags /labels per project specifications and approved material
submittals.
 EMT bushing shall be added at all adaptors, and all other accessories
shall be added as per project specifications, approved shop drawings,
and Electrical standards. Then we will ensure that enclosed fixtures are
reasonably insect/dust-tight when installed.
 The site Engineer will ensure that all wiring works, labeling (including
raceways), etc. Are completed and tested with approved IR.
 Fixtures shall be installed on suitable and safe surfaces according to
specifications, manufacturer recommendations, and approved shop
drawings.
 Bulbs’ wattages, sizes, shapes, and light colors shall follow the
approved shop drawings, project specifications, manufacturer
recommendations, and approved material submittal.
 Gloves shall be used in work, and care will be taken in fixing the fittings.

7.0- Inspection and Test Plan (and records to be submitted)


 A visual inspection will be done after the installation of lighting fixtures.
 All lights shall be measured for lux level at various points where
necessary, according to the project specifications.
 Record all the correct readings as per approved formats, and take
corrective measures if the required lux level is not achieved.
 Normal operation and uniformity of lights will be verified after luminaire
installations.
 Performance tests will be done according to the project specifications.
 Inspection requests shall be raised for the consultant’s inspection.
 Inspection request formats will be submitted attached with IFC drawings
and any other required documents.
 Inspection requests will be submitted 24 hours before the inspection
date.
 If the work is unsatisfactory, the work will be rectified, and the inspection
request will be resubmitted.

8.0- Plant and Equipment


 Standard Electrical Tool Box.
 Measuring and leveling tools.
 PVC pipe bending spring.
 Hand-cutting tools.
 Markers.
 Drilling tools.
 Electrical grinder.
 Step ladder.
 Mobile scaffolding.
 Hand gloves, fall protection Equipment, and other personal equipment
(PPE) as necessary.
 All the measuring equipment, such as the Megger test, Multimeter, and
lux meter, shall have a valid calibration certificate.

9.0- Special Scaffold/Access Equipment


Normal scaffolding will be used if required.

10.0- Training and Competency of Personnel (see also 18


below)
 The work will be carried out with professional and skilled technicians.
 Truck Drivers will have KSA heavy-duty licenses.
 Mobile Crane drivers will be certified by Main Contractor Plant and
Equipment section.
 Riggers will be certified by Main Contractor Plant and Equipment
section.
 Scaffolders will be well-trained and certified.

11.0- First Aid and Emergency Arrangements


 The site team must have a first aid kit at the time of work.
 The site clinic is also operational as necessary.

12.0- Advise Any Permits to Work required (e.g., Hot works;


confined space; excavation; electrical)
To be assessed at the time of work.

13.0- Environmental Considerations


No special considerations are required.

14.0- Waste Management


Housekeeping shall be done on a daily basis. Solid waste and surplus
materials will be treated as per LEED requirements.

15.0- Hazardous Substances – Attach material data sheets


There are no hazardous substances.

16.0- Any Special Storage Requirements


No special storage is required.

17.0- Testing and Commissioning


After successful installation, Inspection Request will be raised.

18.0- Supporting Documents:


 Risk Assessment.
 ITP
 Checklist.