bamboo scaffolding method statement
bamboo scaffolding method statement
Table of Contents
1. Erection and Demolition of Bamboo Scaffolding
A. Scope
B. Human/Material Resources
C. Materials
D. Transporting Materials
E. Procedures for Erecting Scaffolding
F. Procedures for Dismantling Scaffolding
B. Human Resources
1. General Site Personnel
• site foremen
• signal man for hoisting
• safety supervisor
• trained scaffolder (for erection, dismantling, and modification)
• worker with a construction license and ten years of experience
(for inspecting scaffolding)
2. Common Equipment and Tools
• General hand tools
• A saw
• A utility knife
• A fall prevention device or independent rescue device
• Electric drill, hammer
C. Materials
• Bamboo
• Wooden boards
• Nylon strips
• Metal Tie
• Anchor Bolts
D. Transporting Materials
- Before transporting materials, the storage location should be agreed upon with the
site foremen
- Materials must not be stored at excessive heights.
- After lowering materials using a hoist, the security of the stored materials must be
checked to prevent falling.
- crane shall be used for vertical transportation.
2. Safety Preparations
2.1 The site foremen must distribute all safety equipment to the scaffolders, including
safety helmets, parachute safety belts, independent lifeline, fall protection clips,
and reflective vests, which must be worn by workers while on duty.
2.2 When erecting, dismantling scaffolding, or working at the edge of a building,
parachute safety belts and fall protection devices must be attached to the
independent rescue rope.
2.3 The independent lifeline must be secured to a stable position.
2.4 If necessary, the lifeline must be protected.
2.5 Hand tools (such as bamboo saws and scaffolding knives) must have a hand rope
attached.
2.6 The site foremen must strictly supervise workers to ensure that the procedures for
hoisting materials are correctly followed.
2.7 When scaffolding work is underway, the relevant area should be cordoned off to
prevent unauthorized personnel from entering.
2.8 Notify the site supervisor of the scaffolding location for the day and maintain
good communication.
2.9 All lifting machinery and equipment must have valid legal inspection certificates
and must be checked to ensure that they are in a safe and usable condition.
2.10 If the scaffolding is supported by the ground floor, the ground soil shall be well-
compacted and steel plate may be added between ground and scaffolding.
3. Procedures for Erecting Double Scaffolding
Erect double scaffolding
3.1 The distance from the concrete wall must not exceed 600 mm.
3.2 The distance between double scaffolding standard should not exceed 1.3 m.
3.3 The max. vertical spacing between ledger shall be 1.2m
3.4 The height of each boarded lift shall be between 1.9m and 2.1m.
3.5 The distance between small horizontal beams should not exceed 750 mm
3.6 The minimum width of the double scaffolding should be 750 mm (W).
3.7 For every 7m apart horizontally or less on the scaffold, there should be one such
raker provided. In exceptional case when the scaffold is less than 7m in width, two
such rakers should be provided near the two ends along the width of the scaffold.
To prevent any movement of the rakers, they should be inserted into the ground
for not less than 500mm or be securely fixed in position by suitable means.
Typical Details of Bamboo Scaffolding with Raker
(b) Method for Connecting Bamboo members
3.8 The overlapping length of two connected bamboo standards shall be 1.5 m - 2 m.
3.9 The overlapping length of two connected bamboo bracings and rakers shall be at
least 2 m.
3.10 The tail end of one bamboo standard should connect to the head end of another
bamboo standard.
3.11 All knots should be tightened with at least 5 rounds of nylon strips. The ends of
the nylon strips should be crossed and twisted to form a single twisted end which
passes through the knot twice to give one round turn for proper anchorage to
ensure properly knotting.
If the height of the scaffolding exceeds 15 m, steel bracket must be installed every 1.3
m to support the scaffolding.
8.1 The steel bracket must have at least three anchor bolts (HST3 M16).
8.2 All three anchor bolts must be installed with their design embedment depth.
8.3 For size, design, drawing and detailed calculation of the steel bracket, please refer
to other design submission.
3nos. of
HST3 M16
9.1 The scaffolding must be inspected by competent person. A Form 5 must be issued
before the scaffolding can be used.
1. Safety Precaution:
4. Safety Measures
4.1 During the dismantling process, there should be at least one qualified person
supervising on the ground.
4.2 The ground must be fence off and warning signs to remind workers from other
trades and the public to avoid approaching the dismantling area.
4.3 Before dismantling, a meeting must be held between the foreman and the
dismantling workers to explain the dismantling location and the falling bamboo
procedure.
4.4 Provide safe entry and exit points for the dismantling workers.
5. Starting Dismantle of Scaffolding
6.1 After the workers have stacked the bamboo supports, place warning signs around
the area and clear any site debris.
6.2 Large quantities of materials should not be stored on-site; arrangements should
be made as soon as possible with the main contractor to remove the bamboo from
the site.