0% found this document useful (0 votes)
16 views7 pages

Boq - Palisades

The document outlines the proposed renovation project for the 2nd floor terrace in Bacolod City, detailing a comprehensive bill of materials and associated costs. The total material cost is estimated at 55,640.00, with additional labor and contingency costs bringing the grand total to 95,306.00. The document includes specific quantities and unit prices for various construction materials required for the project.

Uploaded by

trojanlyquirit
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
16 views7 pages

Boq - Palisades

The document outlines the proposed renovation project for the 2nd floor terrace in Bacolod City, detailing a comprehensive bill of materials and associated costs. The total material cost is estimated at 55,640.00, with additional labor and contingency costs bringing the grand total to 95,306.00. The document includes specific quantities and unit prices for various construction materials required for the project.

Uploaded by

trojanlyquirit
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 7

PROJECT: PROPOSED RENOVATION OF 2ND FLOOR TERRACE

LOCATION: PALISADES SUBD. BRGY. FORTUNE TOWN BACOLOD CITY


DATE: APRIL 24, 2025

BILL OF MATERIALS

ITEM DESCRIPTION QTY. UNIT UNIT PRICE AMOUNT


1 PRELIMINARIES
Mobilization/Demobilization 1 lot 1,000.00 1,000.00
Removal of Debris & Clearing 1 lot 1,500.00 1,500.00
Sub-total: 2,500.00
2 COLUMN
Cement 2 bags 240.00 480.00
Mixing Sand 0.50 cu.m. 1,100.00 550.00
Sub-total: 1,030.00
3 MASONRY
6" CHB 60 pcs. 22.00 1,320.00
Cement 8 bags 240.00 1,920.00
Mixing Sand 2.00 cu.m. 1,100.00 2,200.00
10mm dia. RSB 5 lngth 135.00 675.00
#16 G.I. Tie Wire 5 kgs. 110.00 550.00
Sub-total: 6,665.00
4 ROOF FRAMING
Ga. 16 2"x4" C-Purlins 1.2MM 10 lngth 580.00 5,800.00
10mm dia. RSB 1 lngth 170.00 170.00
Welding Rod 5 kg. 120.00 600.00
Epoxy Primer 1 gal. 1,200.00 1,200.00
Lacquer Thinner 1 gal. 550.00 550.00
Sub-total: 8,320.00
5 WINDOWS
Sliding Door With Jalou Plus 1 lot 16,500.00 16,500.00
Sub-total: 16,500.00

6 CEILING WORKS
3.5mm Hadiflex 4 sheet 550.00 2,200.00
Double Furring 12 lngth 90.00 1,080.00
1" Concrete Nail 1 kg. 100.00 100.00
3/32" x 1" Blind Rivets 1 box 450.00 450.00
Carrying Chanel 8 pcs. 110.00 880.00
Wall angle 6 pcs. 35.00 210.00
W clip 5 rolls 4.00 20.00
#16 G.I. Tie Wire 1 kg. 65.00 65.00
Sub-total: 5,005.00
20 PAINTING WORKS
Bostik Powerseal - Water Profing 2 gals 900.00 1,800.00
Skimcoat 1 bags 500.00 500.00
Interior flat White - Primer 2 gals 850.00 1,700.00
Interior Final Coating 2 gals 960.00 1,920.00
Sub-total: 5,920.00
21 ROOFING SUPPLY & INSTALLATION
Roof Panel
Rib Type 0.40mm x 1.04 x LS 15 l.s. 350.00 5,250.00
Bended Accessories
False Gutter & others 1 lot 3,500.00 3,500.00
Hardware accessories
Tex Screw 100 pcs. 2.00 200.00
Blind Rivets 1 box 480.00 480.00
Elastoseal 6 packs 100.00 600.00
Touch up Paints 2 cans 350.00 700.00
Sub-total: 10,730.00
22 OTHERS
Acess Door 1 l.s. 3,500.00 3,500.00
Sub-total: 3,500.00

SUMMARY
1 PRELIMINARIES 2,500.00
8 MASONRY 6,665.00
9 ROOF FRAMING 8,320.00
12 WINDOWS 16,500.00
17 CEILING WORKS 5,005.00
20 PAINTING WORKS 5,920.00
21 ROOFING SUPPLY & INSTALLATION 10,730.00
22 OTHERS 3,500.00

Total Material Cost: 55,640.00

10% Contingencies: 5,564.00


Labor Cost: 30,602.00

Other Cost: 3,500.00


Grand Total: 95,306.00

Prepared By: Approved By:

Engr. Trojanly J. Quirit MS. MICHEALLE JANEO BELINE


Civil Engineer Owner
PRC #:
CONCRETE
FOOTING
L W T V NO. TOTAL
F-1 1.2 1.2 0.3 0.432 10 4.32

Cement 38.88
Sand 2.16
Gravel 4.32

WALL FOOTING
L W T V NO. TOTAL
WF-1 40 0.3 0.2 2.4 1 2.4

Cement 21.6
Sand 1.2
Gravel 2.4

S.O.G.
A T V NO. TOTAL
S-1 65 0.1 6.5 1 6.5

Cement 58.5
Sand 3.25
Gravel 6.5

COLUMN
L W H V NO. TOTAL
C-1 0.4 0.2 6 0.48 10 4.8

Cement 33.6
Sand 2.4
Gravel 4.8

BEAM
L W T V NO. TOTAL
B1 0 1 0

Cement 0
Sand 0
Gravel 0

SLAB 2ND FLOOR


A T V NO. TOTAL
S-1 0 1 0

Cement 0
Sand 0
Gravel 0

ROOF BEAM
L W T V NO. TOTAL
RB1 35.5 0.125 0.3 1.33125 1 1.33125

LITEL BEAM
L W T V NO. TOTAL
LB1 35.5 0.1 0.15 0.5325 1 0.5325

Total 1.86375

Cement 11.1825
Sand 0.931875
Gravel 1.86375

STAIRS

Cement 0
Sand 0
Gravel 0

TOTAL V: 19.88375

CEMENT 164
SAND 10
GRAVEL 20

MASONRY
L H A window level A
W1 40 3.6 144 40 1.4 56 38.89%
W2 8
W3 0

TOTAL 152

DOORS & WINDOWS


W H NO. A
D1 1 2.1 1 2.1
D2 0.8 2.1 4 6.72
W1 1.4 2.4 1 3.36
W2 1.2 1.2 4 5.76
W3 0.6 0.6 1 0.36
W4 0
TOTAL 18.3

TOTAL 133.7

CHB 3700
Cement 204
Sand 22
10mm 241

footing l w h no v
1.2 1.2 0.3 10 8
REBAR
FOOTING
NO. O REBAR NO. TOTAL
F-1 1.2 10 12 16mm

WALL FOOTING
NO. O REBAR NO. TOTAL
WF-1 0.5 165 82.5 10mm MAIN
0.3 165 49.5 10mm RING
132 10mm

S.O.G.
NO. O REBAR NO. TOTAL
S-1 48 1 48 10mm

COLUMN
NO. O REBAR NO. TOTAL
C-1 4 10 40 16mm MAIN
3 10 30 10mm RING

BEAM
NO. O REBAR NO. TOTAL
WF-1 0 0 16mm MAIN
0 0 10mm RING

SLAB 2ND FLOOR


NO. O REBAR NO. TOTAL
S-1 1 0 10mm

ROOF BEAM
NO. O REBAR NO. TOTAL
RB1 0.7 35.5 24.85 12mm MAIN
0.7 35.5 24.85 10mm RING

LITEL BEAM
NO. O REBAR NO. TOTAL
LB1 0.33 35.5 11.715 10mm MAIN
0.2 35.5 7.1 10mm RING
43.665 10mm

STAIRS 10mm

TOTAL
16mm 52
12mm 25
10mm 254

You might also like