5
5
4. Gap analysis
5. Example of application
REFERENCES (INDICATIVE)
The forecasting approach aims to prepare the company to leverage its strengths and to
facing the difficulties she will encounter in the future. It includes a definition of
objectives to be achieved and means to be implemented. It is divided into:
In other words, budget control is a procedure that compares ex post the achievements.
with the budget forecasts of a responsibility center.
The projected revenue is obtained from the sales budget. The variances on revenue
business matters are the responsibility of the business units. It is therefore from these units that must
emanate the adjustments of forecasts, the corrective actions. (see the application example)
Deviation of revenue = Actual revenue - Expected revenue
4.1.1. Definition:
The General Accounting Plan defines a predetermined cost as: "a cost assessed beforehand:"
So as to facilitate certain analytical processes,
· To enable management control through variance analysis.
- They can be calculated based on actual or average costs incurred during the periods.
previous accountants.
- They can be calculated based on the activity level of the considered company.
as "normal".
- We can calculate them based on an analysis conducted by a design office.
- costs calculated from an operating budget.
This last method involves establishing a direct link between budget calculation
of operation and the calculation of pre-established costs seems to us the best. Indeed, it allows
to determine the causes of the non-fulfillment of the budget and therefore the responsibilities.
4.1.3. Typology of predetermined costs: The pre-established costs are presented under
different forms:
A/ The standard cost: Costs are said to be 'standard' when they are calculated from
from a technical and economic analysis conducted by the methods office. They
present the characteristics of a standard.
Example:
The production of a series of 100 products requires 50 kg of raw material at €40 per kg.
What would be the pre-established cost of the raw material for an order of 500 products?
(5series) ?
Cost of a series = 40 DA x 50 kg = 2,000 DA.
Standard cost of 5 series = 2,000 DA x 5 = 10,000 DA.
Step 1 Preparation of a predetermined cost sheet for a unit produced. This sheet is
called standard unit cost sheet
Step 2 Determination of the predetermined cost of production recognized or actual (or real):
CPPC
The choice of the type of predetermined cost depends on the management style of the company and the type of
problem to solve.
5. Example of application:
The following example shows us how to analyze the different gaps, namely: (gap on
direct charges and variances on indirect charges) :
A manufacturing company uses the standard cost method, the actual situation of
The company resulting from the actual activity at the end of the period is as follows:
Remarks:
The variances: compare the actual results to the forecasts. By convention, a variance is calculated
in the real sense - forecast.
All variances can be analyzed in terms of a price variance and a quantity variance.
- Deviations on quantities are valued at a predetermined price (cost). Deviations on prices are
weighted by the actual quantity.
Corrigé :
Designation Actual cost (A.C) Standard cost (S.C) of the actual X° Gaps
Q P.U MTS Q P.U MTS FAV DEFAV
Direct MP 5500 kg 1 210 600 X09Kg=5 400kg 0.20 1,080 130
MOD 190H 1.68 319.20 600 X 0.35 = 210 H 1.60 336 16.8
Fees 1,140 600 X 0.35 = 210H 5 1050 90
indirects
Cost 2,669.2 2,466 203.2
The overall gap which is negative represents a loss of earnings for the company. This loss
is due to the non-compliance with the standards that were established by the company at the beginning of the period.
The analysis of discrepancies will allow us to detect their origins and to implement actions.
correctives.
The unfavorable variance on materials is mainly due to the variance in price and also to the variance in
quantity for which the cause needs to be investigated: decrease in quality of MP, adjustment issue with
machines, rebounds more important than expected.
b) Deviation on MOD:
Gap on MOD
The favorable gap in time (better productivity of the workforce)? is offset by the
increase in staff remuneration rates (including overtime)
VARIANCE on BUDGET (V/B) = ACTUAL COST - BUDGET of ACTUAL ACTIVITY (VC + FC)
ax + b
The budget equation is as follows: Y = a x + b where (a: standard variable cost, b: standard fixed cost, x:
activities)
Knowing that the normal activity is: 0.35 X 700 U = 245H
so: (1225 - 490) / 245H = 03DA
E/B = 1,140 - (3 x 190) + 490 = 1,140 - 1,060 = +80 (unfavorable)
Deviation on activity:
The actual activity may be lower than the normal activity. In this case, all expenses
fixes could not be attributed to production due to underactivity. In the opposite case,
The favorable gap translates to overactivity.
The variance on activity corresponds to the variance on the allocation of fixed costs (see method)
of the rational imputation of structural charges). If the gap is positive, it is therefore
unfavorable. If it is negative, then it is favorable
DEVIATION on ACTIVITY (E/A) = BUDGET of THE ACTUAL ACTIVITY - PREVIOUSLY ESTIMATED COST of
THE REAL ACTIVITY
(CUO Preetabli x NUO Reel)
CUO preétabis = 1225/245H = 05DA
E/A = 1 060 - 5 x 190H = 1 060 - 950 = +110DA (unfavorable)
We logically observe an unfavorable discrepancy since the workshop is underperforming (190H in
place of 245H)
-Variance on yield:
It comes from the fact that for a completed production, the consumption of work units is
different from the forecasts, hence a discrepancy in the quantity of units consumed.
This is an internal origin and the responsibility of the workshop or analysis center. If
The gap is positive, it is therefore unfavorable. If it is negative, it is therefore favorable.