The document is a daily breakdown report for Keystone Infra Pvt Ltd as of May 1-3, 2025, detailing the status of various fixed assets and their maintenance issues. It includes information on the location, registration numbers, reasons for breakdowns, actions taken, and present status of repairs for each asset. The report highlights ongoing repairs, parts required, and expected completion dates for the maintenance work.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
7 views

1254

The document is a daily breakdown report for Keystone Infra Pvt Ltd as of May 1-3, 2025, detailing the status of various fixed assets and their maintenance issues. It includes information on the location, registration numbers, reasons for breakdowns, actions taken, and present status of repairs for each asset. The report highlights ongoing repairs, parts required, and expected completion dates for the maintenance work.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 114

KEYSTONE INFRA PVT LTD.

DAILY BREAKDOWN REPORT AS ON MAY -01-05-2025


Focus Indent
Sl No Fixed Assets Location Reg No B/D Start Indent No Reason For BD Action & Rectification Present Status REMARKS
No

AIR COMPRESSOR , BCU , CLUSTER , NOX SEBSOR , U SOME MATERIAL ARE RECEIVED AS ON DATE -
1 AL BS-6 TIPPER NEW CAMP MN05C 4116 01/04/2025 1391 & 1392 MN/15 DISMANTLED DONE WAITING FOR REMAINIG
BOLT ARE DAMAGE 16-04-2025, FITMENT UNDER PROCESS

LOAD BODY DAMAGE , TYRE , BATTERY , DENTING


2 AL BS-3 TIPPER HILL SITE (NEW CAMP) NL02Q 8726 11/04/2025 004& 005 MN/276 DISMANTLED DONE NEW DALA BODY MAKING UNDER PROCESS
WORK , GEAR BOX SPARES & RUNNING REPAIR

LOAD BODY DAMAGE , TYRE , BATTERY , DENTING


3 AL BS-3 TIPPER HILL SITE (NEW CAMP) NL02Q 8642 25/04/2025 DISMANTLED DONE NEW DALA BODY MAKING UNDER PROCESS
WORK & RUNNING REPAIR

CYLINDER LINER , HEAD GASKET , PISTON & RING


4 AL BS-3 TIPPER HILL SITE (NEW CAMP) NL02Q 8721 29-04-2025 006 & 007 MN/276 SET , CR BEARING , VALVE OIL SEAL & ETC ARE DISMANTLED DONE
DAMAGE

PICKUP ISSUES & HEAD GASKET , CR BEARING ,


MAHINDRA BS-6 SHOWROOM - HILL PO DONE AT JAIN SALES AGENCY , PO NO - HO- ALL MATERIAL GIVE TO SHOWROOM AS ON DATE - 24-04-2025.
5 NL0D 7655 31/03/2025 1618 & 1619 MN/2394 LINER , PISTON , THRUST WASHER , VALVE OIL SEAL DISMANTLED DONE
CAMPER SITE 54 . PAYMENT IN PROCESS FITMENT UNDER PROCESS
& PULLY DEMPER ARE DAMAGE

KLEEMANN JAW QUOTATION SEND TO HO AS ON DATE - 27-04-


6 SEKMAI QUARRY K006.0115 26/04/2025 1693 MN/233 ENGINE FAN & ALTERNATOR BELT ARE DAMAGE DISMANTLED DONE
CRUSHER 2025

ENGINE HEATING ISSUE , PILOT LEVER FUCTION


7 PC-210-08MO NEW CAMP N710361 - 19 16/04/2025 1695 MN/283 DISMANTLED DONE
NOT WORKING PROPERLY

8 JCB BS-4 CHECKON SITE MN05C 3982 17/04/2025 1653 MN/135 ENGINE ECU NOT WORKING DISMANTLED DONE PO DONE ATMA & MA - PAYMENT IN PROCESS

SOME HYDRAULIC HOSE PIPE LEAKAGE , PICK UP


1658 TO SOME HYDRAULIC HOSE PIPE LEKAGE &
9 JCB BS-3 NEW CAMP MN01 9722 10/04/2025 MN/197 ISSUE , BREAK SYSTEM NOT WORKING PROPERLY & DISMANTLED DONE WAITING FOR THE REQUIRED MATERIAL
1663 MISSING . HOSE PIPE FITTING UNDER DONE
KING PIN ARE DAMAGE

SOME HYDRAULIC HOSE PIPE LEAKAGE , PICK UP


10 JCB BS-3 NEW CAMP MN01 9720 10/04/2025 DISMANTLING UNDER PROCESS
ISSUE , BREAK SYSTEM NOT WORKING PROPERLY

J15L4126 / VIB COUPLING M38 , BUSHING & SCREW ARE MATERIAL RECEIVED AS ON DATE - 16-04- DISPATCHED FROM KOLKATA BY SKY KING - 433217055 AS ON
11 TENDAM ROLLER NEW CAMP 01/04/2025 1620 MN/2382 DISMANTLED DONE
4H.3218/1520309 DAMAGE 2025. SOME MATERIAL PENDING DATE- 29-04-2025

NEED TIE ROD END & HOSE PIPE . NOT AVAILABLE AT LOCAL
NEW RECEVINIG MATERIAL FITMENT UNDER
12 PAVER 610605 08/04/2025 1633 MN/10 DRIVE SHAFT & TRACTION MOTOR ARE DAMAGE DISMANTLED DONE MARKET . SAMPLE SEND TO GUWAHATI AS ON DATE - 26-04-
CAMP(NAGALAND) PROCESS
2025

REQUIREMENT SEND TO VENDOR FOR NEW


13 MAHINDRA 10KVA DG NEW CAMP N2A20A24519 06/04/2025 ALTERNATOR BURND DISMANTLED DONE QUOTATION SEWND TO HO PU UNDER PROCESS
ALTERNATOR QUOTATION
Sl No Fixed Assets

1 AL BS-6 TIPPER

2 AL BS-3 TIPPER

3 AL BS-3 TIPPER

4 AL BS-3 TIPPER
MAHINDRA BS-6
5
CAMPER

KLEEMANN JAW
6
CRUSHER

7 PC-210-08MO

8 JCB BS-4

9 JCB BS-3
10 JCB BS-3

11 PAVER

12 MAHINDRA 10KVA DG
Location Reg No

NEW CAMP MN05C 4116

HILL SITE (NEW CAMP) NL02Q 8726

HILL SITE (NEW CAMP) NL02Q 8642

HILL SITE (NEW CAMP) NL02Q 8721


SHOWROOM - HILL
NL0D 7655
SITE

SEKMAI QUARRY K006.0115

NEW CAMP N710361 - 19

CHECKON SITE MN05C 3982

NEW CAMP MN01 9722


NEW CAMP MN01 9720

NEW
610605
CAMP(NAGALAND)

NEW CAMP N2A20A24519


DAILY BRE
Focus Indent
B/D Start Indent No
No

01/04/2025 1391 & 1392 MN/15

11/04/2025 004& 005 MN/276

25/04/2025

29-04-2025 006 & 007 MN/276


31/03/2025 1618 & 1619 MN/2394

26/04/2025 1693 MN/233

16/04/2025 1695 MN/283

17/04/2025 1653 MN/135

1658 TO
10/04/2025 MN/197
1663
10/04/2025

08/04/2025 1633 MN/10

06/04/2025
KEYSTONE INFRA PVT LTD.
DAILY BREAKDOWN REPORT AS ON MAY -02-
Reason For BD

AIR COMPRESSOR , BCU , CLUSTER , NOX SEBSOR , U


BOLT ARE DAMAGE

LOAD BODY DAMAGE , TYRE , BATTERY , DENTING


WORK , GEAR BOX SPARES & RUNNING REPAIR

LOAD BODY DAMAGE , TYRE , BATTERY , DENTING


WORK & RUNNING REPAIR

CYLINDER LINER , HEAD GASKET , PISTON & RING


SET , CR BEARING , VALVE OIL SEAL & ETC ARE
DAMAGE
PICKUP ISSUES & HEAD GASKET , CR BEARING ,
LINER , PISTON , THRUST WASHER , VALVE OIL SEAL
& PULLY DEMPER ARE DAMAGE

ENGINE FAN & ALTERNATOR BELT ARE DAMAGE

ENGINE HEATING ISSUE , PILOT LEVER FUCTION


NOT WORKING PROPERLY

ENGINE ECU NOT WORKING

SOME HYDRAULIC HOSE PIPE LEAKAGE , PICK UP


ISSUE , BREAK SYSTEM NOT WORKING PROPERLY &
KING PIN ARE DAMAGE
SOME HYDRAULIC HOSE PIPE LEAKAGE , PICK UP
ISSUE , BREAK SYSTEM NOT WORKING PROPERLY

DRIVE SHAFT & TRACTION MOTOR ARE DAMAGE

ALTERNATOR BURND
TD.
MAY -02-05-2025
Action & Rectification

DISMANTLED DONE

DISMANTLED DONE

DISMANTLED DONE

DISMANTLED DONE
DISMANTLED DONE

DISMANTLED DONE

DISMANTLED DONE

DISMANTLED DONE

DISMANTLED DONE
DISMANTLING UNDER PROCESS

DISMANTLED DONE

DISMANTLED DONE
Present Status

SOME MATERIAL ARE RECEIVED AS ON DATE -


16-04-2025, FITMENT UNDER PROCESS

NEW DALA BODY MAKING UNDER PROCESS

NEW DALA BODY MAKING UNDER PROCESS


PO DONE AT JAIN SALES AGENCY , PO NO - HO-
54 . PAYMENT IN PROCESS

QUOTATION SEND TO HO AS ON DATE - 27-04-


2025

PO DONE ATMA & MA - PAYMENT IN PROCESS

SOME HYDRAULIC HOSE PIPE LEKAGE &


MISSING . HOSE PIPE FITTING UNDER DONE
RECEVINIG MATERIAL FITMENT UNDER
PROCESS

REQUIREMENT SEND TO VENDOR FOR NEW


ALTERNATOR QUOTATION
REMARKS

WAITING FOR REMAINIG


ALL MATERIAL GIVE TO SHOWROOM AS ON DATE - 24-04
FITMENT UNDER PROCESS

WAITING FOR THE REQUIRED MATERIAL


NEED TIE ROD END & HOSE PIPE . NOT AVAILABLE AT LO
MARKET . SAMPLE SEND TO GUWAHATI AS ON DATE - 26
2025

QUOTATION SEWND TO HO PU UNDER PROCESS


KEYSTONE INFRA PVT LTD.
DAILY BREAKDOWN REPORT AS ON MAY -03-05-2025
Focus Indent
P Fixed Assets Location Reg No B/D Start Indent No Reason For BD Action & Rectification Present Status Expact Date To Be Ready REMARKS
No

1391 & AIR COMPRESSOR , BCU , CLUSTER , NOX PENDING MATERIAL DISPATCHED AS ON DATE - 01-
1 AL BS-6 TIPPER NEW CAMP MN05C 4116 01/04/2025 MN/15 DISMANTLED DONE ENGINE FITMENT UNDER PROCESS 15/05/2025
1392 SEBSOR , U BOLT ARE DAMAGE 05-2025. BY NETWORK - NICCN71930

LOAD BODY DAMAGE , TYRE , BATTERY , C CHANNEL , MS PLAIN SHEET , MS


HILL SITE (NEW
2 AL BS-3 TIPPER NL02Q 8726 11/04/2025 004& 005 MN/276 DENTING WORK , GEAR BOX SPARES & DISMANTLED DONE SQUARE PIPE - MATERIAL 20/05/2025
CAMP)
RUNNING REPAIR REQUIREMENTS INDENT RISED

HILL SITE (NEW LOAD BODY DAMAGE , TYRE , BATTERY , NEW DALA BODY MAKING UNDER
3 AL BS-3 TIPPER NL02Q 8642 25/04/2025 DISMANTLED DONE 17/05/2025
CAMP) DENTING WORK & RUNNING REPAIR PROCESS

CYLINDER LINER , HEAD GASKET ,


HILL SITE (NEW REQUIREMENTS SEND TO VENDOR
4 AL BS-3 TIPPER NL02Q 8721 29-04-2025 006 & 007 MN/276 PISTON & RING SET , CR BEARING , DISMANTLED DONE 25/05/2025
CAMP) FOR QUOTATION
VALVE OIL SEAL & ETC ARE DAMAGE

PICKUP ISSUES & HEAD GASKET , CR


MAHINDRA BS-6 SHOWROOM - 1618 & BEARING , LINER , PISTON , THRUST PO DONE AT JAIN SALES AGENCY , PO ALL MATERIAL GIVE TO SHOWROOM AS ON DATE -
5 NL0D 7655 31/03/2025 MN/2394 DISMANTLED DONE 10/05/2025
CAMPER HILL SITE 1619 WASHER , VALVE OIL SEAL & PULLY NO - HO-54 . PAYMENT IN PROCESS 24-04-2025. FITMENT UNDER PROCESS
DEMPER ARE DAMAGE

KLEEMANN JAW ENGINE FAN & ALTERNATOR BELT ARE QUOTATION SEND TO HO AS ON
6 SEKMAI QUARRY K006.0115 26/04/2025 1693 MN/233 DISMANTLED DONE 07/05/2025 MATERIAL IN GUWAHATI - TO BE DISPATCH
CRUSHER DAMAGE DATE - 27-04-2025

ENGINE HEATING ISSUE , PILOT LEVER REQUIREMENTS SEND TO VENDOR


7 PC-210-08MO NEW CAMP N710361 - 19 16/04/2025 1695 MN/283 DISMANTLED DONE 22/05/2025
FUCTION NOT WORKING PROPERLY FOR QUOTATION

PO DONE AT MA & MA - PAYMENT IN


8 JCB BS-4 CHECKON SITE MN05C 3982 17/04/2025 1653 MN/135 ENGINE ECU NOT WORKING DISMANTLED DONE 10/05/2025 VENDOR MATERIAL ORDER , MATERIAL IN TRSNIST
PROCESS

SOME HYDRAULIC HOSE PIPE LEAKAGE ,


SOME HYDRAULIC HOSE PIPE
1658 TO PICK UP ISSUE , BREAK SYSTEM NOT
9 JCB BS-3 NEW CAMP MN01 9722 10/04/2025 MN/197 DISMANTLED DONE LEKAGE & MISSING . HOSE PIPE 25/05/2025 WAITING FOR THE REQUIRED MATERIAL
1663 WORKING PROPERLY & KING PIN ARE
FITTING DONE
DAMAGE

WE FITTED THE REWINDING


MAHINDRA 10KVA N2A20A24519 & ALTERNATOR TO ANTOTHER DG ,
10 NEW CAMP 06/04/2025 13 MN/310 ALTERNATOR BURND DISMANTLED DONE 29/05/2025 QUOTATION SEND TO HO PU UNDER PROCESS
DG N2A20A24519 BUT ISSUE ON ALTERNATOR NOT IN
DG
P Fixed Assets

1 AL BS-6 TIPPER

2 AL BS-3 TIPPER

3 AL BS-3 TIPPER
4 AL BS-3 TIPPER

MAHINDRA BS-6
5
CAMPER

KLEEMANN JAW
6
CRUSHER

7 PC-210-08MO
8 JCB BS-4

9 JCB BS-3

MAHINDRA 10KVA
10
DG
Location Reg No

NEW CAMP MN05C 4116

HILL SITE (NEW


NL02Q 8726
CAMP)

HILL SITE (NEW


NL02Q 8642
CAMP)
HILL SITE (NEW
NL02Q 8721
CAMP)

SHOWROOM -
NL0D 7655
HILL SITE

SEKMAI QUARRY K006.0115

NEW CAMP N710361 - 19


CHECKON SITE MN05C 3982

NEW CAMP MN01 9722

N2A20A24519 &
NEW CAMP
N2A20A24519
Focus Indent
B/D Start Indent No
No

1391 &
### MN/15
1392

### 004& 005 MN/276

###
29-04-2025 006 & 007 MN/276

1618 &
### MN/2394
1619

### 1693 MN/233

### 1695 MN/283


### 1653 MN/135

1658 TO
### MN/197
1663

### 13 MN/310
P
KEYSTONE INFRA P
DAILY BREAKDOWN REPORT AS

Reason For BD

AIR COMPRESSOR , BCU , CLUSTER , NOX


SEBSOR , U BOLT ARE DAMAGE

LOAD BODY DAMAGE , TYRE , BATTERY ,


DENTING WORK , GEAR BOX SPARES &
RUNNING REPAIR

LOAD BODY DAMAGE , TYRE , BATTERY ,


DENTING WORK & RUNNING REPAIR
CYLINDER LINER , HEAD GASKET ,
PISTON & RING SET , CR BEARING ,
VALVE OIL SEAL & ETC ARE DAMAGE

PICKUP ISSUES & HEAD GASKET , CR


BEARING , LINER , PISTON , THRUST
WASHER , VALVE OIL SEAL & PULLY
DEMPER ARE DAMAGE

ENGINE FAN & ALTERNATOR BELT ARE


DAMAGE

ENGINE HEATING ISSUE , PILOT LEVER


FUCTION NOT WORKING PROPERLY
ENGINE ECU NOT WORKING

SOME HYDRAULIC HOSE PIPE LEAKAGE ,


PICK UP ISSUE , BREAK SYSTEM NOT
WORKING PROPERLY & KING PIN ARE
DAMAGE

ALTERNATOR BURND
INFRA PVT LTD.
PORT AS ON MAY -04-05-2025

Action & Rectification

DISMANTLED DONE

DISMANTLED DONE

DISMANTLED DONE
DISMANTLED DONE

DISMANTLED DONE

DISMANTLED DONE

DISMANTLED DONE
DISMANTLED DONE

DISMANTLED DONE

DISMANTLED DONE
025

Present Status

ENGINE FITMENT UNDER PROCESS

C CHANNEL , MS PLAIN SHEET , MS


SQUARE PIPE - MATERIAL
REQUIREMENTS INDENT RISED

NEW DALA BODY MAKING UNDER


PROCESS
REQUIREMENTS SEND TO VENDOR
FOR QUOTATION

PO DONE AT JAIN SALES AGENCY , PO


NO - HO-54 . PAYMENT IN PROCESS

QUOTATION SEND TO HO AS ON
DATE - 27-04-2025

REQUIREMENTS SEND TO VENDOR


FOR QUOTATION
PO DONE AT MA & MA - PAYMENT IN
PROCESS

SOME HYDRAULIC HOSE PIPE


LEKAGE & MISSING . HOSE PIPE
FITTING DONE

WE FITTED THE REWINDING


ALTERNATOR TO ANTOTHER DG ,
BUT ISSUE ON ALTERNATOR NOT IN
DG
Expact Date To Be Ready

15/05/2025

20/05/2025

17/05/2025
25/05/2025

10/05/2025

07/05/2025

22/05/2025
10/05/2025

25/05/2025

29/05/2025
REMARKS

PENDING MATERIAL DISPATCHED AS ON DAT


05-2025. BY NETWORK - NICCN71930
ALL MATERIAL GIVE TO SHOWROOM AS ON D
24-04-2025. FITMENT UNDER PROCESS

MATERIAL IN GUWAHATI - TO BE DISPAT


VENDOR MATERIAL ORDER , MATERIAL IN TR

WAITING FOR THE REQUIRED MATERIA

QUOTATION SEND TO HO PU UNDER PROC


KEYSTONE INFRA PVT LTD.

DAILY BREAKDOWN REPORT AS ON MAY -05-05-2025


Focus Indent
P Fixed Assets Location Reg No B/D Start Indent No Po No Reason For BD Action & Rectification Present Status Expact Date To Be Ready REMARKS
No

1391 & AIR COMPRESSOR , BCU , CLUSTER , NOX MATERILS RECEIVED AT IMPHAL NETWORK - NICCN71930 AND WAITING
1 AL BS-6 TIPPER NEW CAMP MN05C 4116 01/04/2025 MN/15 HO - 77 DISMANTLED DONE ENGINE FITMENT UNDER PROCESS 09/05/2025
1392 SEBSOR , U BOLT ARE DAMAGE FOR ARRIVAL AT NEW CAMP

LOAD BODY DAMAGE , TYRE , BATTERY , C CHANNEL , MS PLAIN SHEET , MS


HILL SITE (NEW
2 AL BS-3 TIPPER NL02Q 8726 11/04/2025 004& 005 MN/276 HO-380 DENTING WORK , GEAR BOX SPARES & DISMANTLED DONE SQUARE PIPE - MATERIAL PARTS WILL BE DISPATCHED ON 05-05-2025 FROM KOLKATA
CAMP)
RUNNING REPAIR REQUIREMENTS INDENT RISED

HILL SITE (NEW LOAD BODY DAMAGE , TYRE , BATTERY , NEW DALA BODY MAKING UNDER WORK PROGRESS SLOW DUE TO WELDER ARE INGAGED TO THE ANOTHER
3 AL BS-3 TIPPER NL02Q 8642 25/04/2025 DISMANTLED DONE 10/05/2025
CAMP) DENTING WORK & RUNNING REPAIR PROCESS WORK

CYLINDER LINER , HEAD GASKET ,


HILL SITE (NEW REQUIREMENTS SEND TO VENDOR
4 AL BS-3 TIPPER NL02Q 8721 29-04-2025 006 & 007 MN/276 HO-380 PISTON & RING SET , CR BEARING , DISMANTLED DONE PARTS WILL BE DISPATCHED ON 05-05-2025 FROM KOLKATA
CAMP) FOR QUOTATION
VALVE OIL SEAL & ETC ARE DAMAGE

PICKUP ISSUES & HEAD GASKET , CR


MAHINDRA BS-6 SHOWROOM - 1618 & BEARING , LINER , PISTON , THRUST PO DONE AT JAIN SALES AGENCY , PO ENGIUNE OVERHAUL IN PROCESS BY SHIVZ AUTO TECH, WILL BE
5 NL0D 7655 31/03/2025 MN/2394 HO-2909 DISMANTLED DONE 10/05/2025
CAMPER HILL SITE 1619 WASHER , VALVE OIL SEAL & PULLY NO - HO-54 . PAYMENT IN PROCESS CONFIRMED VERY SOON
DEMPER ARE DAMAGE

KLEEMANN JAW ENGINE FAN & ALTERNATOR BELT ARE QUOTATION SEND TO HO AS ON MATERILS RECEIVED AT IMPHAL NETWORK BY NETWORK - NICCN07135,
6 SEKMAI QUARRY K006.0115 26/04/2025 1693 MN/233 HO-324 DISMANTLED DONE 06/05/2025
CRUSHER DAMAGE DATE - 27-04-2025 AND WAITING FOR ARRIVAL AT NEW CAMP

ENGINE HEATING ISSUE , PILOT LEVER REQUIREMENTS SEND TO VENDOR


7 PC-210-08MO NEW CAMP N710361 - 19 16/04/2025 1695 MN/283 DISMANTLED DONE WAITING FOR QUOTATION AND FINAL WORD FROM HO
FUCTION NOT WORKING PROPERLY FOR QUOTATION

PO DONE AT MA & MA - PAYMENT IN MATERIAL DISPATCHED FROM KOLKATA BY SAFE EXPRESS ON 03-05-2025
8 JCB BS-4 CHECKON SITE MN05C 3982 17/04/2025 1653 MN/135 HO-288 ENGINE ECU NOT WORKING DISMANTLED DONE 10/05/2025
PROCESS (501546276832)

SOME HYDRAULIC HOSE PIPE LEAKAGE ,


SOME HYDRAULIC HOSE PIPE
1658 TO PICK UP ISSUE , BREAK SYSTEM NOT
9 JCB BS-3 NEW CAMP MN01 9722 10/04/2025 MN/197 DISMANTLED DONE LEKAGE & MISSING . HOSE PIPE WAITING FOR QUOTATION FROM MA & MA (IMPHAL - DEALER)
1663 WORKING PROPERLY & KING PIN ARE
FITTING DONE
DAMAGE

WE FITTED THE REWINDING


ALTERNATOR TO SAME DG BUT
MAHINDRA N2A20A24519 &
10 NEW CAMP 06/04/2025 13 MN/310 ALTERNATOR BURND DISMANTLED DONE STILL FAILED, SAME ALTERNATOR WAITING FOR PO FROM HO
10KVA DG N2A20A24519
FITTED IN RUNNING DG BUT STILL
FAILED
KEYSTONE INFRA PVT LTD.

DAILY BREAKDOWN REPORT AS ON MAY -06-05-2025

Focus Indent
P Fixed Assets Location Reg No B/D Start Indent No Po No Reason For BD Action & Rectification Present Status Expact Date To Be Ready REMARKS
No

1391 & AIR COMPRESSOR , BCU , CLUSTER , NOX


1 AL BS-6 TIPPER NEW CAMP MN05C 4116 01/04/2025 MN/15 HO - 77 DISMANTLED DONE ENGINE FITMENT UNDER PROCESS 09/05/2025 MATERILS RECEIVED AT NEW CAMP FITMENT UNDER PROCESS
1392 SEBSOR , U BOLT ARE DAMAGE

LOAD BODY DAMAGE , TYRE , BATTERY , C CHANNEL , MS PLAIN SHEET , MS


HILL SITE (NEW
2 AL BS-3 TIPPER NL02Q 8726 11/04/2025 004& 005 MN/276 HO-380 DENTING WORK , GEAR BOX SPARES & DISMANTLED DONE SQUARE PIPE - MATERIAL
CAMP)
RUNNING REPAIR REQUIREMENTS INDENT RISED

HILL SITE (NEW LOAD BODY DAMAGE , TYRE , BATTERY , NEW DALA BODY MAKING UNDER WORK PROGRESS SLOW DUE TO WELDER ARE INGAGED TO THE ANOTHER
3 AL BS-3 TIPPER NL02Q 8642 25/04/2025 DISMANTLED DONE 10/05/2025
CAMP) DENTING WORK & RUNNING REPAIR PROCESS WORK

CYLINDER LINER , HEAD GASKET ,


HILL SITE (NEW REQUIREMENTS SEND TO VENDOR
4 AL BS-3 TIPPER NL02Q 8721 29-04-2025 006 & 007 MN/276 HO-380 PISTON & RING SET , CR BEARING , DISMANTLED DONE
CAMP) FOR QUOTATION
VALVE OIL SEAL & ETC ARE DAMAGE

PICKUP ISSUES & HEAD GASKET , CR


MAHINDRA BS-6 SHOWROOM - 1618 & BEARING , LINER , PISTON , THRUST PO DONE AT JAIN SALES AGENCY , PO ENGIUNE OVERHAUL IN PROCESS BY SHIVZ AUTO TECH, WILL BE
5 NL0D 7655 31/03/2025 MN/2394 HO-2909 DISMANTLED DONE 10/05/2025
CAMPER HILL SITE 1619 WASHER , VALVE OIL SEAL & PULLY NO - HO-54 . PAYMENT IN PROCESS CONFIRMED VERY SOON
DEMPER ARE DAMAGE

KLEEMANN JAW ENGINE FAN & ALTERNATOR BELT ARE


6 SEKMAI QUARRY K006.0115 26/04/2025 1693 MN/233 HO-324 DISMANTLED DONE MATERIAL RECEIVED AT NEW CAMP 06/05/2025 WE WILL SEND TO SEKMAI QUARRY FOR FITMENT
CRUSHER DAMAGE

ENGINE HEATING ISSUE , PILOT LEVER REQUIREMENTS SEND TO VENDOR


7 PC-210-08MO NEW CAMP N710361 - 19 16/04/2025 1695 MN/283 DISMANTLED DONE WAITING FOR QUOTATION AND FINAL WORD FROM HO
FUCTION NOT WORKING PROPERLY FOR QUOTATION

PO DONE AT MA & MA - PAYMENT IN MATERIAL DISPATCHED FROM KOLKATA BY SAFE EXPRESS ON 03-05-2025
8 JCB BS-4 CHECKON SITE MN05C 3982 17/04/2025 1653 MN/135 HO-288 ENGINE ECU NOT WORKING DISMANTLED DONE 10/05/2025
PROCESS (501546276832)

SOME HYDRAULIC HOSE PIPE LEAKAGE ,


SOME HYDRAULIC HOSE PIPE
1658 TO PICK UP ISSUE , BREAK SYSTEM NOT
9 JCB BS-3 NEW CAMP MN01 9722 10/04/2025 MN/197 DISMANTLED DONE LEKAGE & MISSING . HOSE PIPE WAITING FOR QUOTATION FROM MA & MA (IMPHAL - DEALER)
1663 WORKING PROPERLY & KING PIN ARE
FITTING DONE
DAMAGE

WE FITTED THE REWINDING


ALTERNATOR TO SAME DG BUT
MAHINDRA N2A20A24519 &
10 NEW CAMP 06/04/2025 13 MN/310 ALTERNATOR BURND DISMANTLED DONE STILL FAILED, SAME ALTERNATOR WAITING FOR PO FROM HO
10KVA DG N2A20A24519
FITTED IN RUNNING DG BUT STILL
FAILED

BREAKER SEAL KIT , BUSH , CHISEL PO DONE AT KSAR ERATHMOVERS &


KOMATSU 1364 & HO- 234 &
11 NEW CAMP JH 350 01/05/2025 MN/2185 BUSHING , PLUG , RETAINER BAR , DISMANTLED DONE INDUSTRIAL SPARES & I EQUIP MATERIAL WILL BE DISPATCH SOON
BREAKER PC-300 1365 HO-239
STOPER PIN ETC ARE DAMAGE CORPORATION
KEYSTONE INFRA PVT LTD.

DAILY BREAKDOWN REPORT AS ON MAY -07-05-2025

Focus Indent Expact Date To Be


SL NO Fixed Assets Location Reg No B/D Start Indent No Po No Reason For BD Action & Rectification Present Status REMARKS
No Ready

1391 & AIR COMPRESSOR , BCU , CLUSTER , NOX


1 AL BS-6 TIPPER NEW CAMP MN05C 4116 01/04/2025 MN/15 HO - 77 DISMANTLED DONE ENGINE FITMENT UNDER PROCESS 09/05/2025 MATERILS RECEIVED AT NEW CAMP FITMENT UNDER PROCESS
1392 SEBSOR , U BOLT ARE DAMAGE

LOAD BODY DAMAGE , TYRE , BATTERY , C CHANNEL , MS PLAIN SHEET , MS


HILL SITE (NEW 004& 005 MN/276 AUTO SPARES PO DONE AT KSAR EARTHMOVERS , & FEBRICATION
2 AL BS-3 TIPPER NL02Q 8726 11/04/2025 HO-380 DENTING WORK , GEAR BOX SPARES & DISMANTLED DONE SQUARE PIPE - MATERIAL REQUIREMENTS
CAMP) 008 MN282 MATERIAL PO UNDER PROCESS
RUNNING REPAIR INDENT RISED

HILL SITE (NEW LOAD BODY DAMAGE , TYRE , BATTERY , NEW DALA BODY MAKING UNDER
3 AL BS-3 TIPPER NL02Q 8642 25/04/2025 DISMANTLED DONE 10/05/2025
CAMP) DENTING WORK & RUNNING REPAIR PROCESS

CYLINDER LINER , HEAD GASKET ,


HILL SITE (NEW NARAYANI TRADING COMPANY .
4 AL BS-3 TIPPER NL02Q 8721 29-04-2025 006 & 007 MN/277 HO-381 PISTON & RING SET , CR BEARING , DISMANTLED DONE
CAMP) MATERIAL WILL BE DISPATCH
VALVE OIL SEAL & ETC ARE DAMAGE

GEAR SHIFTING ISSUE , EXHAUST,


BIJANG QUARRY - FLEXIBLE PIPE , LOAD BODY BACK DOOR DISMANTLING UNDER AFTER DISMANTLING WE WILL RISE
5 AL BS-3 TIPPER NL02Q 8770 07/05/2025
NEW CAMP & GEAR BOX HOUSING BOLT ARE PROCESS MATERIAL INDET
DAMAGE

HILL SITE (NEW FRONT CBAIN GLASS BROKEN & STEEING PIPE FITTING DONE. DENTING TRANSPORT BILL PAYMENT DONE TOMORROW . MATERIAL PICKUP
6 AL BS-4 TIPPER NL02Q 8755 06/05/2025 DISMANTLED DONE 10/05/2025
CAMP) STEERING PIPE LEKAGE WORK PENDING DUE CRABIDE. TODAY

CHECKON - NEW ALL MATERIAL AVAILABLE AT STORE


7 AL BS-6 TM MN01AA 3348 06/05/2025 CLUTCH & GEAR SHIFTING ISSUE DISMANTLED DONE 08/07/2025
CAMP FITMENT UNDER PROCESS

PICKUP ISSUES & HEAD GASKET , CR


MAHINDRA BS-6 SHOWROOM - 1618 & BEARING , LINER , PISTON , THRUST PO DONE AT JAIN SALES AGENCY , PO NO - OVERHAUL ENGINE IN PROCESS AT SHIVZ AUTOTECH SHROOM WILL
8 NL0D 7655 31/03/2025 MN/2394 HO-2909 DISMANTLED DONE 10/05/2025
CAMPER HILL SITE 1619 WASHER , VALVE OIL SEAL & PULLY HO-54 . PAYMENT IN PROCESS BE CONFIRMED VERY SOON
DEMPER ARE DAMAGE

ENGINE HEATING ISSUE , PILOT LEVER REQUIREMENTS SEND TO VENDOR FOR


9 PC-210-08MO NEW CAMP N710361 - 19 16/04/2025 1695 MN/283 DISMANTLED DONE
FUCTION NOT WORKING PROPERLY QUOTATION

KING PIN
KING PIN DAMAGE & RADAITOR GIVE TO LATHE FOR SPINDLE BUSH
10 TATA XENON NEW CAMP NL02Q 8628 05/05/2025 DISMANMANTLE 11/05/2025 SPARES RECEIVED FROM LEATH , FITMENT UNDER PROCESS
NOTWORKING FITTING & RAIMINING
DONE

PO DONE AT MA & MA - PAYMENT IN MATERIAL DISPATCHED FROM KOLKATA BY SAFE EXPRESS ON 03-05-
11 JCB BS-4 CHECKON SITE MN05C 3982 17/04/2025 1653 MN/135 HO-288 ENGINE ECU NOT WORKING DISMANTLED DONE 10/05/2025
PROCESS 2025 (501546276832)

SOME HYDRAULIC HOSE PIPE LEAKAGE ,


1658 TO PICK UP ISSUE , BREAK SYSTEM NOT SOME HYDRAULIC HOSE PIPE LEKAGE &
12 JCB BS-3 NEW CAMP MN01 9722 10/04/2025 MN/197 DISMANTLED DONE WAITING FOR QUOTATION FROM MA & MA (IMPHAL - DEALER)
1663 WORKING PROPERLY & KING PIN ARE MISSING . HOSE PIPE FITTING DONE
DAMAGE

MAHINDRA N2A20A24519 & PO DONE AT MAX DG GUWAHATI -


13 NEW CAMP 06/04/2025 13 MN/310 ALTERNATOR BURND DISMANTLED DONE
10KVA DG N2A20A24519 MATERIAL DISPATCH SOON

MAHINDRA PO DONE AT MAX DG GUWAHATI -


14 NEW CAMP N2A20A24519 06/04/2025 13 MN/310 ALTERNATOR BURND DISMANTLED DONE
10KVA DG MATERIAL DISPATCH SOON

BREAKER SEAL KIT , BUSH , CHISEL PO DONE AT KSAR ERATHMOVERS &


KOMATSU 1364 & HO- 234 &
15 NEW CAMP JH 350 01/05/2025 MN/2185 BUSHING , PLUG , RETAINER BAR , DISMANTLED DONE INDUSTRIAL SPARES & I EQUIP MATERIAL WILL BE DISPATCH SOON
BREAKER PC-300 1365 HO-239
STOPER PIN ETC ARE DAMAGE CORPORATION
KEYSTONE INFRA PVT LTD.

DAILY BREAKDOWN REPORT AS ON MAY -08-05-2025

Focus Indent Expact Date To Be


SL NO Fixed Assets Location Reg No B/D Start Indent No Po No Reason For BD Action & Rectification Present Status REMARKS
No Ready

1391 & AIR COMPRESSOR , BCU , CLUSTER , NOX


1 AL BS-6 TIPPER NEW CAMP MN05C 4116 01/04/2025 MN/15 HO - 77 DISMANTLED DONE ENGINE FITMENT UNDER PROCESS 10/05/2025 MATERILS RECEIVED AT NEW CAMP FITMENT UNDER PROCESS
1392 SEBSOR , U BOLT ARE DAMAGE

LOAD BODY DAMAGE , TYRE , BATTERY , C CHANNEL , MS PLAIN SHEET , MS


HILL SITE (NEW 004& 005 MN/276 AUTO SPARES PO DONE AT KSAR EARTHMOVERS , & FEBRICATION
2 AL BS-3 TIPPER NL02Q 8726 11/04/2025 HO-380 DENTING WORK , GEAR BOX SPARES & DISMANTLED DONE SQUARE PIPE - MATERIAL REQUIREMENTS
CAMP) 008 MN282 MATERIAL PO UNDER PROCESS
RUNNING REPAIR INDENT RISED

HILL SITE (NEW LOAD BODY DAMAGE , TYRE , BATTERY , NEW DALA BODY MAKING UNDER
3 AL BS-3 TIPPER NL02Q 8642 25/04/2025 DISMANTLED DONE 10/05/2025
CAMP) DENTING WORK & RUNNING REPAIR PROCESS

CYLINDER LINER , HEAD GASKET ,


HILL SITE (NEW
4 AL BS-3 TIPPER NL02Q 8721 29-04-2025 006 & 007 MN/277 HO-381 PISTON & RING SET , CR BEARING , DISMANTLED DONE NARAYANI TRADING COMPANY .
CAMP)
VALVE OIL SEAL & ETC ARE DAMAGE

GEAR SHIFTING ISSUE , EXHAUST,


BIJANG QUARRY - FLEXIBLE PIPE , LOAD BODY BACK DOOR DISMANTLING UNDER AFTER DISMANTLING WE WILL RISE
5 AL BS-3 TIPPER NL02Q 8770 07/05/2025
NEW CAMP & GEAR BOX HOUSING BOLT ARE PROCESS MATERIAL INDET
DAMAGE

HILL SITE (NEW FRONT CBAIN GLASS BROKEN & STEEING PIPE FITTING DONE. DENTING
6 AL BS-4 TIPPER NL02Q 8755 06/05/2025 DISMANTLED DONE 10/05/2025 MATERIAL RECEIVED , DENTING WORK UNDER PROCESS
CAMP) STEERING PIPE LEKAGE WORK PENDING DUE CRABIDE.

PICKUP ISSUES & HEAD GASKET , CR


MAHINDRA BS-6 SHOWROOM - 1618 & BEARING , LINER , PISTON , THRUST PO DONE AT JAIN SALES AGENCY , PO NO - OVERHAUL ENGINE IN PROCESS AT SHIVZ AUTOTECH SHROOM WILL
7 NL0D 7655 31/03/2025 MN/2394 HO-2909 DISMANTLED DONE 10/05/2025
CAMPER HILL SITE 1619 WASHER , VALVE OIL SEAL & PULLY HO-54 . PAYMENT IN PROCESS BE CONFIRMED VERY SOON
DEMPER ARE DAMAGE

ENGINE HEATING ISSUE , PILOT LEVER REQUIREMENTS SEND TO VENDOR FOR


8 PC-210-08MO NEW CAMP N710361 - 19 16/04/2025 1695 MN/283 DISMANTLED DONE
FUCTION NOT WORKING PROPERLY QUOTATION

KING PIN
KING PIN DAMAGE & RADAITOR GIVE TO LATHE FOR SPINDLE BUSH
9 TATA XENON NEW CAMP NL02Q 8628 05/05/2025 DISMANMANTLE 11/05/2025 SPARES RECEIVED FROM LEATH , FITMENT UNDER PROCESS
NOTWORKING FITTING & RAIMINING
DONE

PO DONE AT MA & MA - PAYMENT IN MATERIAL DISPATCHED FROM KOLKATA BY SAFE EXPRESS ON 03-05-
10 JCB BS-4 CHECKON SITE MN05C 3982 17/04/2025 1653 MN/135 HO-288 ENGINE ECU NOT WORKING DISMANTLED DONE 10/05/2025
PROCESS 2025 (501546276832)

SOME HYDRAULIC HOSE PIPE LEAKAGE ,


1658 TO PICK UP ISSUE , BREAK SYSTEM NOT SOME HYDRAULIC HOSE PIPE LEKAGE &
11 JCB BS-3 NEW CAMP MN01 9722 10/04/2025 MN/197 DISMANTLED DONE WAITING FOR QUOTATION FROM MA & MA (IMPHAL - DEALER)
1663 WORKING PROPERLY & KING PIN ARE MISSING . HOSE PIPE FITTING DONE
DAMAGE

MAHINDRA N2A20A24519 & PO DONE AT MAX DG GUWAHATI -


12 NEW CAMP 06/04/2025 13 MN/310 ALTERNATOR BURND DISMANTLED DONE
10KVA DG N2A20A24519 MATERIAL DISPATCH SOON

MAHINDRA PO DONE AT MAX DG GUWAHATI -


13 NEW CAMP N2A20A24519 06/04/2025 13 MN/310 ALTERNATOR BURND DISMANTLED DONE
10KVA DG MATERIAL DISPATCH SOON

BREAKER SEAL KIT , BUSH , CHISEL PO DONE AT KSAR ERATHMOVERS &


KOMATSU 1364 & HO- 234 &
14 NEW CAMP JH 350 01/05/2025 MN/2185 BUSHING , PLUG , RETAINER BAR , DISMANTLED DONE INDUSTRIAL SPARES & I EQUIP MATERIAL WILL BE DISPATCH SOON
BREAKER PC-300 1365 HO-239
STOPER PIN ETC ARE DAMAGE CORPORATION
SL NO Fixed Assets Location

1 AL BS-6 TIPPER NEW CAMP

2 AL BS-3 TIPPER HILL SITE (NEW CAMP)

3 AL BS-3 TIPPER HILL SITE (NEW CAMP)

4 AL BS-3 TIPPER HILL SITE (NEW CAMP)

6 AL BS-4 TIPPER HILL SITE (NEW CAMP)

7 MAHINDRA BS-6 CAMPER SHOWROOM - HILL SITE

8 PC-210-08MO NEW CAMP

9 TATA XENON NEW CAMP

10 JCB BS-4 CHECKON SITE

11 JCB BS-3 NEW CAMP

12 MAHINDRA 10KVA DG NEW CAMP

13 MAHINDRA 10KVA DG NEW CAMP


KOMATSU BREAKER PC-
14 NEW CAMP
300
15 AL BS-3 TIPPER NEW CAMP
Focus Indent
Reg No B/D Start Indent No
No
MN05C 4116 01/04/2025 1391 & 1392 MN/15
004& 005 MN/276
NL02Q 8726 11/04/2025
008 MN282
NL02Q 8642 25/04/2025

NL02Q 8721 29-04-2025 006 & 007 MN/277

NL02Q 8755 06/05/2025

NL0D 7655 31/03/2025 1618 & 1619 MN/2394

N710361 - 19 16/04/2025 1695 MN/283

NL02Q 8628 05/05/2025

MN05C 3982 17/04/2025 1653 MN/135

MN01 9722 10/04/2025 1658 TO 1663 MN/197

N2A20A24519 06/04/2025 13 MN/310

N2P21A17696 06/04/2025 13 MN/310


JH 350 01/05/2025 1364 & 1365 MN/2185
MN01AA0330 08/05/2025
DAILY BR
Po No

HO - 77

HO-380

HO-381

HO-2909

HO-288
HO- 234 & HO-
239
KEYSTONE I
DAILY BREAKDOWN REP
Reason For BD
AIR COMPRESSOR , BCU , CLUSTER , NOX SEBSOR , U BOLT ARE
DAMAGE
LOAD BODY DAMAGE , TYRE , BATTERY , DENTING WORK , GEAR
BOX SPARES & RUNNING REPAIR
LOAD BODY DAMAGE , TYRE , BATTERY , DENTING WORK &
RUNNING REPAIR
CYLINDER LINER , HEAD GASKET , PISTON & RING SET , CR
BEARING , VALVE OIL SEAL & ETC ARE DAMAGE
FRONT CBAIN GLASS BROKEN & STEERING PIPE LEKAGE
PICKUP ISSUES & HEAD GASKET , CR BEARING , LINER , PISTON ,
THRUST WASHER , VALVE OIL SEAL & PULLY DEMPER ARE
DAMAGE
ENGINE HEATING ISSUE , PILOT LEVER FUCTION NOT WORKING
PROPERLY
KING PIN DAMAGE & RADAITOR NOTWORKING

ENGINE ECU NOT WORKING

SOME HYDRAULIC HOSE PIPE LEAKAGE , PICK UP ISSUE , BREAK


SYSTEM NOT WORKING PROPERLY & KING PIN ARE DAMAGE

ALTERNATOR BURND

ALTERNATOR BURND
BREAKER SEAL KIT , BUSH , CHISEL BUSHING , PLUG , RETAINER
BAR , STOPER PIN ETC ARE DAMAGE
REAR BRAKE PLATE AND LINER ASSY. REPLACEMENT
KEYSTONE INFRA PVT LTD.
AKDOWN REPORT AS ON MAY -09-05-2025
Action & Rectification

DISMANTLED DONE

DISMANTLED DONE

DISMANTLED DONE

DISMANTLED DONE

DISMANTLED DONE

DISMANTLED DONE

DISMANTLED DONE
KING PIN DISMANMANTLE
DONE
DISMANTLED DONE

DISMANTLED DONE

DISMANTLED DONE

DISMANTLED DONE
DISMANTLED DONE
DISMANTLED DONE
-09-05-2025
Present Status

ENGINE FITMENT UNDER PROCESS


C CHANNEL , MS PLAIN SHEET , MS SQUARE PIPE - MATERIAL
REQUIREMENTS INDENT RISED
NEW DALA BODY MAKING UNDER PROCESS

NARAYANI TRADING COMPANY .


STEEING PIPE FITTING DONE. DENTING WORK PENDING DUE
CRABIDE.
PO DONE AT JAIN SALES AGENCY , PO NO - HO-54 . PAYMENT IN
PROCESS

REQUIREMENTS SEND TO VENDOR FOR QUOTATION

GIVE TO LATHE FOR SPINDLE BUSH FITTING & RAIMINING

PO DONE AT MA & MA - PAYMENT IN PROCESS

SOME HYDRAULIC HOSE PIPE LEKAGE & MISSING . HOSE PIPE


FITTING DONE

PO DONE AT MAX DG GUWAHATI - MATERIAL DISPATCH SOON

PO DONE AT MAX DG GUWAHATI - MATERIAL DISPATCH SOON


PO DONE AT KSAR ERATHMOVERS & INDUSTRIAL SPARES & I
EQUIP CORPORATION
LOCAL PARTS PURCHASE DONE GUWAHATI
Expact Date To Be
Ready
14/05/2025

12/05/2025

10/05/2025

10/05/2025

11/05/2025

10/05/2025
11/05/2025
REMARKS

MATERILS RECEIVED AT NEW CAMP FITMENT UN

AUTO SPARES PO DONE AT KSAR EARTHMOVERS , & FEBRICATION

PARTS NOT DISPATCHED YET DUE TO PAYM

WORK IN PROGRESS

OVERHAUL ENGINE IN PROCESS AT SHIVZ AUTOTECH SHROOM W

WAITING FOR PO CONFIRMATION FROM

SPARES RECEIVED FROM LEATH , FITMENT UND


MATERIAL DISPATCHED FROM KOLKATA BY SAFE EXPRESS ON 03-05-
Arrived at GUWAHATI

QUOTATION SENT TO HO, WAITING FO

MANUAL PO DONE DUE TO FOCUS NOT WORKING, AT MAX DG GUWAH

MANUAL PO DONE DUE TO FOCUS NOT WORKING, AT MAX DG GUWAH


PARTS NOT DISPATCHED YET DUE TO PAYM
MATERIALS WILL BE DISPATCHED TODAY BY
KEYSTONE INFRA PVT LTD.
DAILY BREAKDOWN REPORT AS ON MAY -09-05-2025
Action
Focus
SL Fixed Locatio Inden Po & Expact Date
Reg No B/D Start Indent Reason For BD Present Status REMARKS
NO Assets n t No No Rectifi To Be Ready
No
cation

AIR COMPRESSOR ,
1391 DISMA
AL BS-6 NEW MN05C HO - BCU , CLUSTER , NOX ENGINE FITMENT
1 01/04/2025 & MN/15 NTLED 14/05/2025 WORK IN PROGRESS
TIPPER CAMP 4116 77 SEBSOR , U BOLT ARE UNDER PROCESS
1392 DONE
DAMAGE
LOAD BODY DAMAGE , C CHANNEL , MS PLAIN
HILL AUTO SPARES PO DONE AT
004& MN/276 TYRE , BATTERY , DISMA SHEET , MS SQUARE PIPE
AL BS-3 SITE NL02Q HO- KSAR EARTHMOVERS , &
2 11/04/2025 005 DENTING WORK , GEAR NTLED - MATERIAL
TIPPER (NEW 8726 380 FEBRICATION MATERIAL
008 MN282 BOX SPARES & DONE REQUIREMENTS INDENT
CAMP) PO UNDER PROCESS
RUNNING REPAIR RISED
HILL LOAD BODY DAMAGE ,
DISMA NEW DALA BODY
AL BS-3 SITE NL02Q TYRE , BATTERY ,
3 25/04/2025 NTLED MAKING UNDER 12/05/2025
TIPPER (NEW 8642 DENTING WORK &
DONE PROCESS
CAMP) RUNNING REPAIR

CYLINDER LINER , HEAD


HILL
GASKET , PISTON & DISMA PARTS NOT DISPATCHED
AL BS-3 SITE NL02Q 006 & HO- NARAYANI TRADING
4 29-04-2025 MN/277 RING SET , CR BEARING , NTLED YET DUE TO PAYMENT
TIPPER (NEW 8721 007 381 COMPANY .
VALVE OIL SEAL & ETC DONE ISSUE
CAMP)
ARE DAMAGE

HILL
FRONT CBAIN GLASS DISMA
AL BS-4 SITE NL02Q
6 06/05/2025 BROKEN & STEERING NTLED WORK UNDER PROGRESS 10/05/2025 WORK IN PROGRESS
TIPPER (NEW 8755
PIPE LEKAGE DONE
CAMP)

PICKUP ISSUES & HEAD


GASKET , CR BEARING , OVERHAUL ENGINE IN
SHOWR
MAHIND 1618 LINER , PISTON , DISMA PO DONE AT JAIN SALES PROCESS AT SHIVZ
OOM - NL0D MN/ HO-
7 RA BS-6 31/03/2025 & THRUST WASHER , NTLED AGENCY , PO NO - HO-54 . 10/05/2025 AUTOTECH SHROOM WILL
HILL 7655 2394 2909
CAMPER 1619 VALVE OIL SEAL & DONE PAYMENT IN PROCESS BE CONFIRMED VERY
SITE
PULLY DEMPER ARE SOON
DAMAGE
ENGINE HEATING ISSUE
DISMA REQUIREMENTS SEND
PC-210- NEW N71036 , PILOT LEVER FUCTION WAITING FOR PO
8 16/04/2025 1695 MN/283 NTLED TO VENDOR FOR
08MO CAMP 1 - 19 NOT WORKING CONFIRMATION FROM HO
DONE QUOTATION
PROPERLY
KING
PIN
KING PIN DAMAGE & GIVE TO LATHE FOR
TATA NEW NL02Q DISMA
9 05/05/2025 RADAITOR SPINDLE BUSH FITTING 11/05/2025 FITMENT UNDER PROCESS
XENON CAMP 8628 NMANT
NOTWORKING & RAIMINING
LE
DONE
MATERIAL DISPATCHED
FROM KOLKATA BY SAFE
DISMA
CHECKO MN05C HO- ENGINE ECU NOT PO DONE AT MA & MA - EXPRESS ON 03-05-2025
10 JCB BS-4 17/04/2025 1653 MN/135 NTLED 10/05/2025
N SITE 3982 288 WORKING PAYMENT IN PROCESS (501546276832),
DONE
Consignment Arrived at
GUWAHATI

SOME HYDRAULIC HOSE


PIPE LEAKAGE , PICK UP SOME HYDRAULIC HOSE
1658 DISMA
NEW MN01 ISSUE , BREAK SYSTEM PIPE LEKAGE & MISSING . QUOTATION SENT TO HO,
11 JCB BS-3 10/04/2025 TO MN/197 NTLED
CAMP 9722 NOT WORKING HOSE PIPE FITTING WAITING FOR PO
1663 DONE
PROPERLY & KING PIN DONE
ARE DAMAGE

MAHIND MANUAL PO DONE DUE TO


DISMA PO DONE AT MAX DG
RA NEW N2A20 FOCUS NOT WORKING, AT
12 06/04/2025 13 MN/310 ALTERNATOR BURND NTLED GUWAHATI - MATERIAL
10KVA CAMP A24519 MAX DG GUWAHATI -
DONE DISPATCH SOON
DG MATERIAL DISPATCH SOON

MAHIND MANUAL PO DONE DUE TO


DISMA PO DONE AT MAX DG
RA NEW N2P21A FOCUS NOT WORKING, AT
13 06/04/2025 13 MN/310 ALTERNATOR BURND NTLED GUWAHATI - MATERIAL
10KVA CAMP 17696 MAX DG GUWAHATI -
DONE DISPATCH SOON
DG MATERIAL DISPATCH SOON

HO- BREAKER SEAL KIT ,


KOMATS PO DONE AT KSAR
1364 234 BUSH , CHISEL BUSHING DISMA SOME PARTS REACHED
U NEW MN/ ERATHMOVERS &
14 JH 350 01/05/2025 & & , PLUG , RETAINER BAR , NTLED AND SOME DISPATCHED
BREAKE CAMP 2185 INDUSTRIAL SPARES & I
1365 HO- STOPER PIN ETC ARE DONE ON 09-05-2025
R PC-300 EQUIP CORPORATION
239 DAMAGE
REAR BRAKE PLATE DISMA MATERIALS DISPATCHED
AL BS-3 NEW MN01A LOCAL PARTS PURCHASE
15 08/05/2025 AND LINER ASSY. NTLED 11/05/2025 ON 09-05-2025 BY
TIPPER CAMP A0330 DONE GUWAHATI
REPLACEMENT DONE NETWORK (NICCN72192)
KEYSTONE INFRA PVT LTD.
DAILY BREAKDOWN REPORT AS ON MAY -11-05-2025
Action
Focus
SL Fixed Locatio Inden Po & Expact Date
Reg No B/D Start Indent Reason For BD Present Status REMARKS
NO Assets n t No No Rectifi To Be Ready
No
cation

AIR COMPRESSOR ,
1391 DISMA
AL BS-6 NEW MN05C HO - BCU , CLUSTER , NOX ENGINE FITMENT
1 01/04/2025 & MN/15 NTLED 14/05/2025 WORK IN PROGRESS
TIPPER CAMP 4116 77 SEBSOR , U BOLT ARE UNDER PROCESS
1392 DONE
DAMAGE

LOAD BODY DAMAGE , C CHANNEL , MS PLAIN AUTO SPARES PO DONE AT


HILL
004& MN/276 TYRE , BATTERY , DISMA SHEET , MS SQUARE PIPE KSAR EARTHMOVERS
AL BS-3 SITE NL02Q HO-
2 11/04/2025 005 DENTING WORK , GEAR NTLED - MATERIAL SOME PARTS DISPATCHED,
TIPPER (NEW 8726 380
008 MN282 BOX SPARES & DONE REQUIREMENTS INDENT & FEBRICATION MATERIAL
CAMP)
RUNNING REPAIR RISED PO UNDER PROCESS

HILL LOAD BODY DAMAGE ,


DISMA NEW DALA BODY
AL BS-3 SITE NL02Q TYRE , BATTERY ,
3 25/04/2025 NTLED MAKING UNDER 12/05/2025
TIPPER (NEW 8642 DENTING WORK &
DONE PROCESS
CAMP) RUNNING REPAIR

CYLINDER LINER , HEAD


HILL
GASKET , PISTON & DISMA PARTS NOT DISPATCHED
AL BS-3 SITE NL02Q 006 & HO- NARAYANI TRADING
4 29-04-2025 MN/277 RING SET , CR BEARING , NTLED YET DUE TO PAYMENT
TIPPER (NEW 8721 007 381 COMPANY .
VALVE OIL SEAL & ETC DONE ISSUE
CAMP)
ARE DAMAGE

PICKUP ISSUES & HEAD


GASKET , CR BEARING , OVERHAUL ENGINE IN
SHOWR
MAHIND 1618 LINER , PISTON , DISMA PO DONE AT JAIN SALES PROCESS AT SHIVZ
OOM - NL0D MN/ HO-
7 RA BS-6 31/03/2025 & THRUST WASHER , NTLED AGENCY , PO NO - HO-54 . 12/05/2025 AUTOTECH SHROOM WILL
HILL 7655 2394 2909
CAMPER 1619 VALVE OIL SEAL & DONE PAYMENT IN PROCESS BE CONFIRMED VERY
SITE
PULLY DEMPER ARE SOON
DAMAGE

ENGINE HEATING ISSUE


DISMA REQUIREMENTS SEND
PC-210- NEW N71036 , PILOT LEVER FUCTION WAITING FOR PO
8 16/04/2025 1695 MN/283 NTLED TO VENDOR FOR
08MO CAMP 1 - 19 NOT WORKING CONFIRMATION FROM HO
DONE QUOTATION
PROPERLY
KING
PIN
KING PIN DAMAGE & GIVE TO LATHE FOR
TATA NEW NL02Q DISMA
9 05/05/2025 RADAITOR SPINDLE BUSH FITTING 11/05/2025 FITMENT UNDER PROCESS
XENON CAMP 8628 NMANT
NOTWORKING & RAIMINING
LE
DONE
MATERIAL DISPATCHED
FROM KOLKATA BY SAFE
DISMA
CHECKO MN05C HO- ENGINE ECU NOT PO DONE AT MA & MA - EXPRESS ON 03-05-2025
10 JCB BS-4 17/04/2025 1653 MN/135 NTLED 10/05/2025
N SITE 3982 288 WORKING PAYMENT IN PROCESS (501546276832),
DONE
Consignment OUT FOR
IMPHAL

SOME HYDRAULIC HOSE


PIPE LEAKAGE , PICK UP SOME HYDRAULIC HOSE
1658 DISMA
NEW MN01 ISSUE , BREAK SYSTEM PIPE LEKAGE & MISSING . QUOTATION SENT TO HO,
11 JCB BS-3 10/04/2025 TO MN/197 NTLED
CAMP 9722 NOT WORKING HOSE PIPE FITTING WAITING FOR PO
1663 DONE
PROPERLY & KING PIN DONE
ARE DAMAGE

MANUAL PO DONE DUE TO


MAHIND
DISMA PO DONE AT MAX DG FOCUS NOT WORKING, AT
RA NEW N2A20
12 06/04/2025 13 MN/310 ALTERNATOR BURND NTLED GUWAHATI - MATERIAL MAX DG GUWAHATI -
10KVA CAMP A24519
DONE DISPATCH SOON PAYMENT NOT DONE
DG
MATERIAL DISPATCH SOON

MANUAL PO DONE DUE TO


MAHIND
DISMA PO DONE AT MAX DG FOCUS NOT WORKING, AT
RA NEW N2P21A
13 06/04/2025 13 MN/310 ALTERNATOR BURND NTLED GUWAHATI - MATERIAL MAX DG GUWAHATI -
10KVA CAMP 17696
DONE DISPATCH SOON PAYMENT NOT DONE
DG
MATERIAL DISPATCH SOON

HO- BREAKER SEAL KIT ,


KOMATS PO DONE AT KSAR SOME PARTS REACHED
1364 234 BUSH , CHISEL BUSHING DISMA
U NEW MN/ ERATHMOVERS & AND SOME DISPATCHED
14 JH 350 01/05/2025 & & , PLUG , RETAINER BAR , NTLED
BREAKE CAMP 2185 INDUSTRIAL SPARES & I ON 09-05-2025 (BY
1365 HO- STOPER PIN ETC ARE DONE
R PC-300 EQUIP CORPORATION BHAWANI ROADLINES
239 DAMAGE

REAR BRAKE PLATE DISMA


AL BS-3 NEW MN01A LOCAL PARTS PURCHASE PARTS REACHED IMPHAL
15 08/05/2025 AND LINER ASSY. NTLED 12/05/2025
TIPPER CAMP A0330 DONE GUWAHATI (NETWORK)
REPLACEMENT DONE
KEYSTONE INFRA PVT LTD.
DAILY BREAKDOWN REPORT AS ON MAY -12-05-2025
Action
Focus
SL Fixed Locatio Inden Po & Expact Date
Reg No B/D Start Indent Reason For BD Present Status REMARKS
NO Assets n t No No Rectifi To Be Ready
No
cation

AIR COMPRESSOR ,
1391 DISMA
AL BS-6 NEW MN05C HO - BCU , CLUSTER , NOX ENGINE FITMENT
1 01/04/2025 & MN/15 NTLED 14/05/2025 WORK IN PROGRESS
TIPPER CAMP 4116 77 SEBSOR , U BOLT ARE UNDER PROCESS
1392 DONE
DAMAGE

LOAD BODY DAMAGE , C CHANNEL , MS PLAIN AUTO SPARES PO DONE AT


HILL
004& MN/276 TYRE , BATTERY , DISMA SHEET , MS SQUARE PIPE KSAR EARTHMOVERS
AL BS-3 SITE NL02Q HO-
2 11/04/2025 005 DENTING WORK , GEAR NTLED - MATERIAL SOME PARTS DISPATCHED,
TIPPER (NEW 8726 380
008 MN282 BOX SPARES & DONE REQUIREMENTS INDENT & FEBRICATION MATERIAL
CAMP)
RUNNING REPAIR RISED PO UNDER PROCESS

HILL LOAD BODY DAMAGE ,


DISMA NEW DALA BODY
AL BS-3 SITE NL02Q TYRE , BATTERY ,
3 25/04/2025 NTLED MAKING UNDER 15/05/2025
TIPPER (NEW 8642 DENTING WORK &
DONE PROCESS
CAMP) RUNNING REPAIR

CYLINDER LINER , HEAD


HILL
GASKET , PISTON & DISMA PARTS NOT DISPATCHED
AL BS-3 SITE NL02Q 006 & HO- NARAYANI TRADING
4 29-04-2025 MN/277 RING SET , CR BEARING , NTLED YET DUE TO PAYMENT
TIPPER (NEW 8721 007 381 COMPANY .
VALVE OIL SEAL & ETC DONE ISSUE
CAMP)
ARE DAMAGE

PICKUP ISSUES & HEAD


GASKET , CR BEARING , AS DISCUSSED WITH THE
SHOWR
MAHIND 1618 LINER , PISTON , DISMA PO DONE AT JAIN SALES SHOWROOM FUEL
OOM - NL0D MN/ HO-
7 RA BS-6 31/03/2025 & THRUST WASHER , NTLED AGENCY , PO NO - HO-54 . 13/05/2025 CONTROL UNIT IS NEEDED ,
HILL 7655 2394 2909
CAMPER 1619 VALVE OIL SEAL & DONE PAYMENT IN PROCESS SAME WILL BE PROVIDED
SITE
PULLY DEMPER ARE TODAY
DAMAGE

MANUAL PO DONE DUE TO


ENGINE HEATING ISSUE
DISMA REQUIREMENTS SEND FOCUS NOT WORKING
PC-210- NEW N71036 , PILOT LEVER FUCTION
8 16/04/2025 1695 MN/283 NTLED TO VENDOR FOR PART DISPATCHED BY
08MO CAMP 1 - 19 NOT WORKING
DONE QUOTATION NATIONAL CARRIYING
PROPERLY
CORP. (RLY/00184)
KING
PIN
KING PIN DAMAGE & GIVE TO LATHE FOR
TATA NEW NL02Q DISMA
9 05/05/2025 RADAITOR SPINDLE BUSH FITTING 14/05/2025 FITMENT UNDER PROCESS
XENON CAMP 8628 NMANT
NOTWORKING & RAIMINING
LE
DONE
MATERIAL DISPATCHED
FROM KOLKATA BY SAFE
DISMA
CHECKO MN05C HO- ENGINE ECU NOT PO DONE AT MA & MA - EXPRESS ON 03-05-2025
10 JCB BS-4 17/04/2025 1653 MN/135 NTLED 15/05/2025
N SITE 3982 288 WORKING PAYMENT IN PROCESS (501546276832),
DONE
Consignment OUT FOR
IMPHAL

SOME HYDRAULIC HOSE


PIPE LEAKAGE , PICK UP SOME HYDRAULIC HOSE
1658 DISMA
NEW MN01 ISSUE , BREAK SYSTEM PIPE LEKAGE & MISSING . QUOTATION SENT TO HO,
11 JCB BS-3 10/04/2025 TO MN/197 NTLED
CAMP 9722 NOT WORKING HOSE PIPE FITTING WAITING FOR PO
1663 DONE
PROPERLY & KING PIN DONE
ARE DAMAGE

MANUAL PO DONE DUE TO


MAHIND
DISMA PO DONE AT MAX DG FOCUS NOT WORKING, AT
RA NEW N2A20
12 06/04/2025 13 MN/310 ALTERNATOR BURND NTLED GUWAHATI - MATERIAL MAX DG GUWAHATI -
10KVA CAMP A24519
DONE DISPATCH SOON PAYMENT NOT DONE
DG
MATERIAL DISPATCH SOON

MANUAL PO DONE DUE TO


MAHIND
DISMA PO DONE AT MAX DG FOCUS NOT WORKING, AT
RA NEW N2P21A
13 06/04/2025 13 MN/310 ALTERNATOR BURND NTLED GUWAHATI - MATERIAL MAX DG GUWAHATI -
10KVA CAMP 17696
DONE DISPATCH SOON PAYMENT NOT DONE
DG
MATERIAL DISPATCH SOON

HO- BREAKER SEAL KIT ,


KOMATS PO DONE AT KSAR SOME PARTS REACHED
1364 234 BUSH , CHISEL BUSHING DISMA
U NEW MN/ ERATHMOVERS & AND SOME DISPATCHED
14 JH 350 01/05/2025 & & , PLUG , RETAINER BAR , NTLED
BREAKE CAMP 2185 INDUSTRIAL SPARES & I ON 09-05-2025 (BY
1365 HO- STOPER PIN ETC ARE DONE
R PC-300 EQUIP CORPORATION BHAWANI ROADLINES
239 DAMAGE

114
DG Set NEW
15 000000 12/05/2025 ENGINE HEATING ISSUE UNDER OBSERVATION
62.5kva CAMP
00677
KEYSTONE INFRA PVT LTD.
DAILY BREAKDOWN REPORT AS ON MAY -13-05-2025
Action
Focus
SL Fixed Locatio Inden Po & Expact Date
Reg No B/D Start Indent Reason For BD Present Status REMARKS
NO Assets n t No No Rectifi To Be Ready
No
cation

AIR COMPRESSOR ,
1391 DISMA
AL BS-6 NEW MN05C HO - BCU , CLUSTER , NOX ENGINE FITMENT
1 01/04/2025 & MN/15 NTLED 14/05/2025 WORK IN PROGRESS
TIPPER CAMP 4116 77 SEBSOR , U BOLT ARE UNDER PROCESS
1392 DONE
DAMAGE

AUTO SPARES PO DONE AT


KSAR EARTHMOVERS
LOAD BODY DAMAGE , C CHANNEL , MS PLAIN
HILL SOME PARTS DISPATCHED
004& MN/276 TYRE , BATTERY , DISMA SHEET , MS SQUARE PIPE
AL BS-3 SITE NL02Q HO- FROM GHY TO IMPHAL ON
2 11/04/2025 005 DENTING WORK , GEAR NTLED - MATERIAL
TIPPER (NEW 8726 380 12-05-2025, NETWORK
008 MN282 BOX SPARES & DONE REQUIREMENTS INDENT
CAMP) (NICCN72252), &
RUNNING REPAIR RISED
FEBRICATION MATERIAL
PO UNDER PROCESS

HILL LOAD BODY DAMAGE ,


DISMA NEW DALA BODY
AL BS-3 SITE NL02Q TYRE , BATTERY ,
3 25/04/2025 NTLED MAKING UNDER 15/05/2025
TIPPER (NEW 8642 DENTING WORK &
DONE PROCESS
CAMP) RUNNING REPAIR

CYLINDER LINER , HEAD


HILL
GASKET , PISTON & DISMA PARTS NOT DISPATCHED
AL BS-3 SITE NL02Q 006 & HO- NARAYANI TRADING
4 29-04-2025 MN/277 RING SET , CR BEARING , NTLED YET DUE TO PAYMENT
TIPPER (NEW 8721 007 381 COMPANY .
VALVE OIL SEAL & ETC DONE ISSUE
CAMP)
ARE DAMAGE

PICKUP ISSUES & HEAD


GASKET , CR BEARING , AS DISCUSSED WITH THE
SHOWR
MAHIND 1618 LINER , PISTON , DISMA PO DONE AT JAIN SALES SHOWROOM FUEL
OOM - NL0D MN/ HO-
7 RA BS-6 31/03/2025 & THRUST WASHER , NTLED AGENCY , PO NO - HO-54 . 13/05/2025 CONTROL UNIT IS
HILL 7655 2394 2909
CAMPER 1619 VALVE OIL SEAL & DONE PAYMENT IN PROCESS NEEDED ,SAME IS
SITE
PULLY DEMPER ARE PROVIDED
DAMAGE
MANUAL PO DONE DUE TO
ENGINE HEATING ISSUE
DISMA REQUIREMENTS SEND FOCUS NOT WORKING
PC-210- NEW N71036 , PILOT LEVER FUCTION
8 16/04/2025 1695 MN/283 NTLED TO VENDOR FOR PART DISPATCHED BY
08MO CAMP 1 - 19 NOT WORKING
DONE QUOTATION NATIONAL CARRIYING
PROPERLY
CORP. (RLY/00184)
KING
PIN
KING PIN DAMAGE & GIVE TO LATHE FOR
TATA NEW NL02Q DISMA
9 05/05/2025 RADAITOR SPINDLE BUSH FITTING 14/05/2025 FITMENT UNDER PROCESS
XENON CAMP 8628 NMANT
NOTWORKING & RAIMINING
LE
DONE
MATERIAL DISPATCHED
FROM KOLKATA BY SAFE
DISMA
CHECKO MN05C HO- ENGINE ECU NOT PO DONE AT MA & MA - EXPRESS ON 03-05-2025
10 JCB BS-4 17/04/2025 1653 MN/135 NTLED 15/05/2025
N SITE 3982 288 WORKING PAYMENT IN PROCESS (501546276832),
DONE
Consignment OUT FOR
IMPHAL

SOME HYDRAULIC HOSE


PIPE LEAKAGE , PICK UP SOME HYDRAULIC HOSE
1658 DISMA
NEW MN01 ISSUE , BREAK SYSTEM PIPE LEKAGE & MISSING . QUOTATION SENT TO HO,
11 JCB BS-3 10/04/2025 TO MN/197 NTLED
CAMP 9722 NOT WORKING HOSE PIPE FITTING WAITING FOR PO
1663 DONE
PROPERLY & KING PIN DONE
ARE DAMAGE

MANUAL PO DONE DUE TO


MAHIND
DISMA PO DONE AT MAX DG FOCUS NOT WORKING, AT
RA NEW N2A20
12 06/04/2025 13 MN/310 ALTERNATOR BURND NTLED GUWAHATI - MATERIAL MAX DG GUWAHATI -
10KVA CAMP A24519
DONE DISPATCH SOON PAYMENT NOT DONE
DG
MATERIAL DISPATCH SOON

MANUAL PO DONE DUE TO


MAHIND
DISMA PO DONE AT MAX DG FOCUS NOT WORKING, AT
RA NEW N2P21A
13 06/04/2025 13 MN/310 ALTERNATOR BURND NTLED GUWAHATI - MATERIAL MAX DG GUWAHATI -
10KVA CAMP 17696
DONE DISPATCH SOON PAYMENT NOT DONE
DG
MATERIAL DISPATCH SOON
HO- BREAKER SEAL KIT ,
KOMATS PO DONE AT KSAR SOME PARTS REACHED
1364 234 BUSH , CHISEL BUSHING DISMA
U NEW MN/ ERATHMOVERS & AND SOME DISPATCHED
14 JH 350 01/05/2025 & & , PLUG , RETAINER BAR , NTLED
BREAKE CAMP 2185 INDUSTRIAL SPARES & I ON 09-05-2025 (BY
1365 HO- STOPER PIN ETC ARE DONE
R PC-300 EQUIP CORPORATION BHAWANI ROADLINES
239 DAMAGE

CYL HEAD GASKET, CORE LOCAL PURCHASE DONE


114
DG Set NEW PLUG, ROCKER COVER FROM KSAR, INVOICE YET
15 000000 12/05/2025 ENGINE HEATING ISSUE
62.5kva CAMP GASKET, INTAKE NOT RECEIVED, TO BE
00677
MANIFOLD GASKET DISPATCHED VIA AIR
KEYSTONE INFRA PVT LTD.
DAILY BREAKDOWN REPORT AS ON MAY -14-05-2025
SL Fixed Focus Action & Expact Date
Location Reg No B/D Start Indent No Po No Reason For BD Present Status REMARKS
NO Assets Indent No Rectification To Be Ready
AIR COMPRESSOR , BCU ,
AL BS-6 1391 & DISMANTLE ENGINE FITMENT
1 NEW CAMP MN05C 4116 01/04/2025 MN/15 HO - 77 CLUSTER , NOX SEBSOR , U 20/05/2025 WORK IS IN PROGRESS
TIPPER 1392 DONE UNDER PROCESS
BOLT ARE DAMAGE

AUTO SPARES PO
DONE AT KSAR
EARTHMOVERS SOME
C CHANNEL , MS
PARTS DISPATCHED
LOAD BODY DAMAGE , PLAIN SHEET , MS
FROM GHY TO IMPHAL
AL BS-3 HILL SITE 004& 005 MN/276 TYRE , BATTERY , DENTING DISMANTLE SQUARE PIPE -
2 NL02Q 8726 11/04/2025 HO-380 ON 12-05-2025,
TIPPER (NEW CAMP) 008 MN282 WORK , GEAR BOX SPARES DONE MATERIAL
NETWORK
& RUNNING REPAIR REQUIREMENTS
(NICCN72252), &
INDENT RISED
FEBRICATION
MATERIAL PO UNDER
PROCESS

LOAD BODY DAMAGE , NEW DALA BODY


AL BS-3 HILL SITE DISMANTLE
3 NL02Q 8642 25/04/2025 TYRE , BATTERY , DENTING MAKING UNDER 18/05/2025 WORK IS IN PROGRESS
TIPPER (NEW CAMP) DONE
WORK & RUNNING REPAIR PROCESS

CYLINDER LINER , HEAD


GASKET , PISTON & RING PO DONE TO
AL BS-3 HILL SITE DISMANTLE PARTS NOT
4 NL02Q 8721 29-04-2025 006 & 007 MN/277 HO-381 SET , CR BEARING , VALVE NARAYANI TRADING
TIPPER (NEW CAMP) DONE DISPATCHED YET
OIL SEAL & ETC ARE COMPANY
DAMAGE

PICKUP ISSUES & HEAD


GASKET , CR BEARING , PO DONE TO JAIN FITMENT DONE AND
MAHINDR
SHOWROOM 1618 & HO- LINER , PISTON , THRUST DISMANTLE SALES AGENCY , PO ENGINE UNDER
7 A BS-6 NL0D 7655 31/03/2025 MN/2394 15/05/2025
- HILL SITE 1619 2909 WASHER , VALVE OIL SEAL DONE NO - HO-54 . PAYMENT OBSERVATION (IDLE
CAMPER
& PULLY DEMPER ARE IN PROCESS RUNNING)
DAMAGE
PARTS DISPATCHED
ENGINE HEATING ISSUE , PO DONE TO SHANTHI
PC-210- N710361 - DISMANTLE THROUGH NATIONAL
8 NEW CAMP 16/04/2025 1695 MN/283 HO-392 PILOT LEVER FUCTION NOT TRADING - PAYMENT
08MO 19 DONE CARRIYING CORP.
WORKING PROPERLY IN PROCESS
(RLY/00184)

KING PIN GAVE AT LATHE SHOP


TATA KING PIN DAMAGE & FITMENT UNDER
9 NEW CAMP NL02Q 8628 05/05/2025 DISMANMANT FOR SPINDLE BUSH 16/05/2025
XENON RADAITOR NOTWORKING PROCESS
LE DONE FITTING & RAIMINING
MATERIAL
DISPATCHED FROM
PO DONE TO MA & MA KOLKATA BY SAFE
CHECKON DISMANTLE
10 JCB BS-4 MN05C 3982 17/04/2025 1653 MN/135 HO-288 ENGINE ECU NOT WORKING - PAYMENT IN 18/05/2025 EXPRESS ON 03-05-
SITE DONE
PROCESS 2025 (501546276832),
Consignment OUT FOR
IMPHAL

SOME HYDRAULIC HOSE


PIPE LEAKAGE , PICK UP PO DONE TO KSAR
1658 TO DISMANTLE MATERIALS TO BE
11 JCB BS-3 NEW CAMP MN01 9722 10/04/2025 MN/197 HO-406 ISSUE , BREAK SYSTEM NOT EARTH MOVERS -
1663 DONE DISPATCHED
WORKING PROPERLY & PAYMENT IN PROCESS
KING PIN ARE DAMAGE

PO DONE TO MAX DG
MAHINDR
N2A20A245 DISMANTLE GUWAHATI - MATERIALS TO BE
12 A 10KVA NEW CAMP 06/04/2025 13 MN/310 HO-389 ALTERNATOR BURND
19 DONE MATERIAL DISPATCH DISPATCHED
DG
SOON
PO DONE TO MAX DG
MAHINDR
N2P21A176 DISMANTLE GUWAHATI - MATERIALS TO BE
13 A 10KVA NEW CAMP 06/04/2025 13 MN/310 HO-389 ALTERNATOR BURND
96 DONE MATERIAL DISPATCH DISPATCHED
DG
SOON
PO DONE TO KSAR 3 ITEMS DISPATCHED
BREAKER SEAL KIT , BUSH ,
KOMATSU HO- ERATHMOVERS & (PO - HO 234)
1364 & CHISEL BUSHING , PLUG , DISMANTLE
14 BREAKER NEW CAMP JH 350 01/05/2025 MN/2185 234 & INDUSTRIAL SPARES &
1365 RETAINER BAR , STOPER DONE
PC-300 HO-239 & I EQUIP PO - HO 239 ITEMS
PIN ETC ARE DAMAGE
CORPORATION NOT DISPATCHED
CYL HEAD GASKET, LOCAL PURCHASE
114 CORE PLUG, ROCKER DONE FROM KSAR,
DG Set
15 NEW CAMP 0000000067 12/05/2025 ENGINE HEATING ISSUE COVER GASKET, INVOICE YET NOT
62.5kva
7 INTAKE MANIFOLD RECEIVED, TO BE
GASKET, TURBO DISPATCHED VIA AIR
KEYSTONE INFRA PVT LTD.
DAILY BREAKDOWN REPORT AS ON MAY -15-05-2025
Action &
SL Fixed Locatio Focus Expact Date
Reg No B/D Start Indent No Po No Reason For BD Rectificat Present Status REMARKS
NO Assets n Indent No To Be Ready
ion
AIR COMPRESSOR , BCU ,
AL BS-6 NEW MN05C 1391 & DISMANT ENGINE FITMENT
1 01/04/2025 MN/15 HO - 77 CLUSTER , NOX SEBSOR , U 20/05/2025 WORK IS IN PROGRESS
TIPPER CAMP 4116 1392 LE DONE UNDER PROCESS
BOLT ARE DAMAGE

AUTO SPARES PARTS DISPATCHED


FROM KSAR EARTHMOVERS ONE
C CHANNEL , MS PLAIN
HILL LOAD BODY DAMAGE , TYRE , PART PENDING (EXHAUST PIPE -
SHEET , MS SQUARE
AL BS-3 SITE NL02Q 004& 005 MN/276 BATTERY , DENTING WORK , DISMANT 6) FROM GHY
2 11/04/2025 HO-380 PIPE - MATERIAL
TIPPER (NEW 8726 008 MN282 GEAR BOX SPARES & LE DONE TO IMPHAL ON 12-05-2025,
REQUIREMENTS
CAMP) RUNNING REPAIR NETWORK (NICCN72252), &
INDENT RISED
FEBRICATION MATERIAL PO
UNDER PROCESS

HILL
LOAD BODY DAMAGE , TYRE , NEW DALA BODY
AL BS-3 SITE NL02Q DISMANT
3 25/04/2025 BATTERY , DENTING WORK & MAKING UNDER 19/05/2025 WORK IS IN PROGRESS
TIPPER (NEW 8642 LE DONE
RUNNING REPAIR PROCESS
CAMP)

HILL CYLINDER LINER , HEAD


AL BS-3 SITE NL02Q GASKET , PISTON & RING SET , DISMANT PO DONE TO NARAYANI
4 29-04-2025 006 & 007 MN/277 HO-381 PARTS NOT DISPATCHED YET
TIPPER (NEW 8721 CR BEARING , VALVE OIL SEAL LE DONE TRADING COMPANY
CAMP) & ETC ARE DAMAGE

PICKUP ISSUES & HEAD


SHOWR PO DONE TO JAIN SALES
MAHINDR GASKET , CR BEARING ,
OOM - NL0D 1618 & DISMANT AGENCY , PO NO - HO- NEED TO TAKE UPDATE FROM
7 A BS-6 31/03/2025 MN/2394 HO-2909 LINER , PISTON , THRUST 15/05/2025
HILL 7655 1619 LE DONE 54 . PAYMENT IN DEALER
CAMPER WASHER , VALVE OIL SEAL &
SITE PROCESS
PULLY DEMPER ARE DAMAGE

ENGINE HEATING ISSUE , PO DONE TO SHANTHI PARTS DISPATCHED THROUGH


PC-210- NEW N710361 DISMANT
8 16/04/2025 1695 MN/283 HO-392 PILOT LEVER FUCTION NOT TRADING - PAYMENT IN NATIONAL CARRIYING CORP.
08MO CAMP - 19 LE DONE
WORKING PROPERLY PROCESS (RLY/00184)

KING PIN
GAVE AT LATHE SHOP
TATA NEW NL02Q KING PIN DAMAGE & DISMANM
9 05/05/2025 FOR SPINDLE BUSH 16/05/2025 FITMENT UNDER PROCESS
XENON CAMP 8628 RADAITOR NOTWORKING ANTLE
FITTING & RAIMINING
DONE

PART REACHED IMPHAL, NEED TO


CHECKO MN05C DISMANT PO DONE TO MA & MA -
10 JCB BS-4 17/04/2025 1653 MN/135 HO-288 ENGINE ECU NOT WORKING TAKE UPDATE FROM DEALER
N SITE 3982 LE DONE PAYMENT IN PROCESS
(501546276832 - SAFE EXPRESS)
SOME HYDRAULIC HOSE PIPE
LEAKAGE , PICK UP ISSUE , PO DONE TO KSAR
NEW MN01 1658 TO DISMANT
11 JCB BS-3 10/04/2025 MN/197 HO-406 BREAK SYSTEM NOT EARTH MOVERS - MATERIALS TO BE DISPATCHED
CAMP 9722 1663 LE DONE
WORKING PROPERLY & KING PAYMENT IN PROCESS
PIN ARE DAMAGE

MAHINDR PO DONE TO MAX DG


NEW N2A20A2 DISMANT
12 A 10KVA 06/04/2025 13 MN/310 HO-389 ALTERNATOR BURND GUWAHATI - MATERIAL MATERIALS TO BE DISPATCHED
CAMP 4519 LE DONE
DG DISPATCH SOON

MAHINDR PO DONE TO MAX DG


NEW N2P21A1 DISMANT
13 A 10KVA 06/04/2025 13 MN/310 HO-389 ALTERNATOR BURND GUWAHATI - MATERIAL MATERIALS TO BE DISPATCHED
CAMP 7696 LE DONE
DG DISPATCH SOON

BREAKER SEAL KIT , BUSH , PO DONE TO KSAR 3 ITEMS DISPATCHED (PO - HO


KOMATSU
NEW 1364 & HO- 234 CHISEL BUSHING , PLUG , DISMANT ERATHMOVERS & 234) &
14 BREAKER JH 350 01/05/2025 MN/2185
CAMP 1365 & HO-239 RETAINER BAR , STOPER PIN LE DONE INDUSTRIAL SPARES & I PO - HO 239 ITEMS NOT
PC-300
ETC ARE DAMAGE EQUIP CORPORATION DISPATCHED
CYL HEAD GASKET,
LOCAL PURCHASE DONE FROM
114 CORE PLUG, ROCKER
DG Set NEW KSAR, INVOICE YET NOT
15 00000000 12/05/2025 ENGINE HEATING ISSUE COVER GASKET, INTAKE
62.5kva CAMP RECEIVED, TO BE DISPATCHED VIA
677 MANIFOLD GASKET,
AIR
TURBO
KEYSTONE INFRA PVT LTD.
DAILY BREAKDOWN REPORT AS ON MAY -16-05-2025
Action &
SL Fixed Locatio Indent Focus Expact Date
Reg No B/D Start Po No Reason For BD Rectificat Present Status REMARKS
NO Assets n No Indent No To Be Ready
ion

AIR COMPRESSOR , BCU ,


AL BS-6 NEW 1391 & DISMANT ENGINE FITMENT
1 MN05C 4116 01/04/2025 MN/15 HO - 77 CLUSTER , NOX SEBSOR , 20/05/2025 WORK IS IN PROGRESS
TIPPER CAMP 1392 LE DONE UNDER PROCESS
U BOLT ARE DAMAGE

AUTO SPARES PARTS


DISPATCHED FROM KSAR
C CHANNEL , MS
LOAD BODY DAMAGE , EARTHMOVERS ONE PART
HILL PLAIN SHEET , MS
004& TYRE , BATTERY , PENDING (EXHAUST PIPE - 6)
AL BS-3 SITE MN/276 DISMANT SQUARE PIPE -
2 NL02Q 8726 11/04/2025 005 HO-380 DENTING WORK , GEAR FROM GHY
TIPPER (NEW MN282 LE DONE MATERIAL
008 BOX SPARES & RUNNING TO IMPHAL ON 12-05-2025,
CAMP) REQUIREMENTS
REPAIR NETWORK (NICCN72252), &
INDENT RISED
FEBRICATION MATERIAL PO
UNDER PROCESS

HILL LOAD BODY DAMAGE ,


NEW DALA BODY
AL BS-3 SITE TYRE , BATTERY , DISMANT
3 NL02Q 8642 25/04/2025 MAKING UNDER 20/05/2025 WORK IS IN PROGRESS
TIPPER (NEW DENTING WORK & LE DONE
PROCESS
CAMP) RUNNING REPAIR

CYLINDER LINER , HEAD


HILL
GASKET , PISTON & RING PO DONE TO
AL BS-3 SITE 006 & DISMANT
4 NL02Q 8721 29-04-2025 MN/277 HO-381 SET , CR BEARING , NARAYANI TRADING PARTS NOT DISPATCHED YET
TIPPER (NEW 007 LE DONE
VALVE OIL SEAL & ETC COMPANY
CAMP)
ARE DAMAGE

PICKUP ISSUES & HEAD


PO DONE TO JAIN REMARKS FROM DEALER
SHOWR GASKET , CR BEARING ,
MAHIND SALES AGENCY , PO MIGHT TO CHANGE
OOM - 1618 & LINER , PISTON , THRUST DISMANT
5 RA BS-6 NL0D 7655 31/03/2025 MN/2394 HO-2909 NO - HO-54 . CATALYTIC CONVERTOR,
HILL 1619 WASHER , VALVE OIL LE DONE
CAMPER PAYMENT IN FINAL WORD NOT RECEIVED
SITE SEAL & PULLY DEMPER
PROCESS YET
ARE DAMAGE

ENGINE HEATING ISSUE , PO DONE TO PARTS DISPATCHED


PC-210- NEW PILOT LEVER FUCTION DISMANT SHANTHI TRADING - THROUGH NATIONAL
6 N710361 - 19 16/04/2025 1695 MN/283 HO-392
08MO CAMP NOT WORKING LE DONE PAYMENT IN CARRIYING CORP.
PROPERLY PROCESS (RLY/00184)
KING PIN GAVE AT LATHE SHOP
KING PIN DAMAGE &
TATA NEW DISMANM FOR SPINDLE BUSH
7 NL02Q 8628 05/05/2025 RADAITOR 18/05/2025 FITMENT UNDER PROCESS
XENON CAMP ANTLE FITTING &
NOTWORKING
DONE RAIMINING

PART REACHED IMPHAL,


PO DONE TO MA &
CHECKO ENGINE ECU NOT DISMANT NEED TO TAKE UPDATE FROM
8 JCB BS-4 MN05C 3982 17/04/2025 1653 MN/135 HO-288 MA - PAYMENT IN
N SITE WORKING LE DONE DEALER (501546276832 -
PROCESS
SAFE EXPRESS)

SOME HYDRAULIC HOSE


PIPE LEAKAGE , PICK UP PO DONE TO KSAR
1658
NEW ISSUE , BREAK SYSTEM DISMANT EARTH MOVERS - MATERIALS TO BE
9 JCB BS-3 MN01 9722 10/04/2025 TO MN/197 HO-406
CAMP NOT WORKING LE DONE PAYMENT IN DISPATCHED
1663
PROPERLY & KING PIN PROCESS
ARE DAMAGE
MAHIND PO DONE TO MAX DG
RA NEW DISMANT GUWAHATI - MATERIALS TO BE
10 N2A20A24519 06/04/2025 13 MN/310 HO-389 ALTERNATOR BURND
10KVA CAMP LE DONE MATERIAL DISPATCH DISPATCHED
DG SOON
MAHIND PO DONE TO MAX DG
RA NEW DISMANT GUWAHATI - MATERIALS TO BE
11 N2P21A17696 06/04/2025 13 MN/310 HO-389 ALTERNATOR BURND
10KVA CAMP LE DONE MATERIAL DISPATCH DISPATCHED
DG SOON

3 ITEMS DISPATCHED 09-05-


BREAKER SEAL KIT , PO DONE TO KSAR
KOMATS 2025 & 2 ITEMS DISPATCHED
BUSH , CHISEL BUSHING , ERATHMOVERS &
U NEW 1364 & HO- 234 DISMANT 13-05-2025(PO - HO 234)
12 JH 350 01/05/2025 MN/2185 PLUG , RETAINER BAR , INDUSTRIAL SPARES
BREAKE CAMP 1365 & HO-239 LE DONE &
STOPER PIN ETC ARE & I EQUIP
R PC-300 PO - HO 239
DAMAGE CORPORATION
ITEMS NOT DISPATCHED

CYL HEAD GASKET,


CORE PLUG, ROCKER PARTS DISPATCHED VIA SKY
DG Set NEW 114
13 12/05/2025 ENGINE HEATING ISSUE COVER GASKET, KING ON 14-05-2025 & TURBO
62.5kva CAMP 00000000677
INTAKE MANIFOLD PENDING
GASKET, TURBO
KEYSTONE INFRA PVT LTD.
DAILY BREAKDOWN REPORT AS ON MAY -17-05-2025
Action &
SL Fixed Locatio Indent Focus Expact Date
Reg No B/D Start Po No Reason For BD Rectificat Present Status REMARKS
NO Assets n No Indent No To Be Ready
ion

AIR COMPRESSOR , BCU ,


AL BS-6 NEW 1391 & DISMANT ENGINE FITMENT
1 MN05C 4116 01/04/2025 MN/15 HO - 77 CLUSTER , NOX SEBSOR , 20/05/2025 WORK IS IN PROGRESS
TIPPER CAMP 1392 LE DONE UNDER PROCESS
U BOLT ARE DAMAGE

AUTO SPARES PARTS


DISPATCHED FROM KSAR
C CHANNEL , MS
LOAD BODY DAMAGE , EARTHMOVERS ONE PART
HILL PLAIN SHEET , MS
004& TYRE , BATTERY , PENDING (EXHAUST PIPE),
AL BS-3 SITE MN/276 DISMANT SQUARE PIPE -
2 NL02Q 8726 11/04/2025 005 HO-380 DENTING WORK , GEAR FROM GHY TO
TIPPER (NEW MN282 LE DONE MATERIAL
008 BOX SPARES & RUNNING IMPHAL ON 12-05-2025,
CAMP) REQUIREMENTS
REPAIR NETWORK (NICCN72252), &
INDENT RISED
FEBRICATION MATERIAL PO
UNDER PROCESS

HILL LOAD BODY DAMAGE ,


NEW DALA BODY
AL BS-3 SITE TYRE , BATTERY , DISMANT
3 NL02Q 8642 25/04/2025 MAKING UNDER 20/05/2025 WORK IS IN PROGRESS
TIPPER (NEW DENTING WORK & LE DONE
PROCESS
CAMP) RUNNING REPAIR

CYLINDER LINER , HEAD


HILL
GASKET , PISTON & RING PO DONE TO SOME PARTS DISPATCHED VIA
AL BS-3 SITE 006 & DISMANT
4 NL02Q 8721 29-04-2025 MN/277 HO-381 SET , CR BEARING , NARAYANI TRADING NETWORK (NICCN72392) ON
TIPPER (NEW 007 LE DONE
VALVE OIL SEAL & ETC COMPANY 15-05-2025
CAMP)
ARE DAMAGE

PICKUP ISSUES & HEAD


PO DONE TO JAIN REMARKS FROM DEALER
SHOWR GASKET , CR BEARING ,
MAHIND SALES AGENCY , PO MIGHT TO CHANGE
OOM - 1618 & LINER , PISTON , THRUST DISMANT
5 RA BS-6 NL0D 7655 31/03/2025 MN/2394 HO-2909 NO - HO-54 . CATALYTIC CONVERTOR,
HILL 1619 WASHER , VALVE OIL LE DONE
CAMPER PAYMENT IN FINAL WORD NOT RECEIVED
SITE SEAL & PULLY DEMPER
PROCESS YET
ARE DAMAGE

ENGINE HEATING ISSUE , PO DONE TO PARTS DISPATCHED


PC-210- NEW PILOT LEVER FUCTION DISMANT SHANTHI TRADING - THROUGH NATIONAL
6 N710361 - 19 16/04/2025 1695 MN/283 HO-392
08MO CAMP NOT WORKING LE DONE PAYMENT IN CARRIYING CORP.
PROPERLY PROCESS (RLY/00184)
KING PIN GAVE AT LATHE SHOP
KING PIN DAMAGE &
TATA NEW DISMANM FOR SPINDLE BUSH
7 NL02Q 8628 05/05/2025 RADAITOR 18/05/2025 FITMENT UNDER PROCESS
XENON CAMP ANTLE FITTING &
NOTWORKING
DONE RAIMINING

PART REACHED IMPHAL,


PO DONE TO MA &
CHECKO ENGINE ECU NOT DISMANT NEED TO TAKE UPDATE FROM
8 JCB BS-4 MN05C 3982 17/04/2025 1653 MN/135 HO-288 MA - PAYMENT IN
N SITE WORKING LE DONE DEALER (501546276832 -
PROCESS
SAFE EXPRESS)

SOME HYDRAULIC HOSE


PIPE LEAKAGE , PICK UP PO DONE TO KSAR
1658
NEW ISSUE , BREAK SYSTEM DISMANT EARTH MOVERS - MATERIALS TO BE
9 JCB BS-3 MN01 9722 10/04/2025 TO MN/197 HO-406
CAMP NOT WORKING LE DONE PAYMENT IN DISPATCHED
1663
PROPERLY & KING PIN PROCESS
ARE DAMAGE
MAHIND PO DONE TO MAX DG
RA NEW DISMANT GUWAHATI - MATERIALS TO BE
10 N2A20A24519 06/04/2025 13 MN/310 HO-389 ALTERNATOR BURND
10KVA CAMP LE DONE MATERIAL DISPATCH DISPATCHED
DG SOON
MAHIND PO DONE TO MAX DG
RA NEW DISMANT GUWAHATI - MATERIALS TO BE
11 N2P21A17696 06/04/2025 13 MN/310 HO-389 ALTERNATOR BURND
10KVA CAMP LE DONE MATERIAL DISPATCH DISPATCHED
DG SOON

3 ITEMS DISPATCHED 09-05-


BREAKER SEAL KIT , PO DONE TO KSAR
KOMATS 2025 & 2 ITEMS DISPATCHED
BUSH , CHISEL BUSHING , ERATHMOVERS &
U NEW 1364 & HO- 234 DISMANT 13-05-2025(PO - HO 234)
12 JH 350 01/05/2025 MN/2185 PLUG , RETAINER BAR , INDUSTRIAL SPARES
BREAKE CAMP 1365 & HO-239 LE DONE &
STOPER PIN ETC ARE & I EQUIP
R PC-300 PO - HO 239
DAMAGE CORPORATION
ITEMS NOT DISPATCHED

CYL HEAD GASKET,


CORE PLUG, ROCKER
DG Set NEW 114 ALL PARTS RECEIVED &
13 12/05/2025 ENGINE HEATING ISSUE COVER GASKET,
62.5kva CAMP 00000000677 TURBO PENDING
INTAKE MANIFOLD
GASKET, TURBO

NEW SEAL KIT, KING PIN,


MOTOR ARTICULATE CYL. LEAK,
14 GRADER CHECKO MN 01 9723 16/05/2025 33 KING PIN BEARING PO NOT PREPARED YET
KING PIN DAMAGE
N REQUIRED
KEYSTONE INFRA PVT LTD.
DAILY BREAKDOWN REPORT AS ON MAY -18-05-2025
Action &
SL Fixed Locatio Indent Focus Expact Date
Reg No B/D Start Po No Reason For BD Rectificat Present Status
NO Assets n No Indent No To Be Ready
ion

AIR COMPRESSOR , BCU ,


AL BS-6 NEW 1391 & DISMANT ENGINE FITMENT
1 MN05C 4116 01/04/2025 MN/15 HO - 77 CLUSTER , NOX SEBSOR , 20/05/2025
TIPPER CAMP 1392 LE DONE UNDER PROCESS
U BOLT ARE DAMAGE

C CHANNEL , MS
LOAD BODY DAMAGE ,
HILL PLAIN SHEET , MS
004& TYRE , BATTERY ,
AL BS-3 SITE MN/276 HO-380 & DISMANT SQUARE PIPE -
2 NL02Q 8726 11/04/2025 005 DENTING WORK , GEAR
TIPPER (NEW MN282 HO-365 LE DONE MATERIAL
008 BOX SPARES & RUNNING
CAMP) REQUIREMENTS
REPAIR
INDENT RISED

HILL LOAD BODY DAMAGE ,


NEW DALA BODY
AL BS-3 SITE TYRE , BATTERY , DISMANT
3 NL02Q 8642 25/04/2025 MAKING UNDER 20/05/2025
TIPPER (NEW DENTING WORK & LE DONE
PROCESS
CAMP) RUNNING REPAIR

CYLINDER LINER , HEAD


HILL
GASKET , PISTON & RING PO DONE TO
AL BS-3 SITE 006 & DISMANT
4 NL02Q 8721 29-04-2025 MN/277 HO-381 SET , CR BEARING , NARAYANI TRADING
TIPPER (NEW 007 LE DONE
VALVE OIL SEAL & ETC COMPANY
CAMP)
ARE DAMAGE

PICKUP ISSUES & HEAD


PO DONE TO JAIN
SHOWR GASKET , CR BEARING ,
MAHINDRA SALES AGENCY , PO
OOM - 1618 & LINER , PISTON , THRUST DISMANT
5 BS-6 NL0D 7655 31/03/2025 MN/2394 HO-2909 NO - HO-54 .
HILL 1619 WASHER , VALVE OIL LE DONE
CAMPER PAYMENT IN
SITE SEAL & PULLY DEMPER
PROCESS
ARE DAMAGE

ENGINE HEATING ISSUE , PO DONE TO


PC-210- NEW PILOT LEVER FUCTION DISMANT SHANTHI TRADING -
6 N710361 - 19 16/04/2025 1695 MN/283 HO-392
08MO CAMP NOT WORKING LE DONE PAYMENT IN
PROPERLY PROCESS
KING PIN GAVE AT LATHE SHOP
KING PIN DAMAGE &
TATA NEW DISMANM FOR SPINDLE BUSH
7 NL02Q 8628 05/05/2025 RADAITOR 18/05/2025
XENON CAMP ANTLE FITTING &
NOTWORKING
DONE RAIMINING

PO DONE TO MA &
CHECKO ENGINE ECU NOT DISMANT
8 JCB BS-4 MN05C 3982 17/04/2025 1653 MN/135 HO-288 MA - PAYMENT IN
N SITE WORKING LE DONE
PROCESS
SOME HYDRAULIC HOSE
PIPE LEAKAGE , PICK UP PO DONE TO KSAR
1658
NEW ISSUE , BREAK SYSTEM DISMANT EARTH MOVERS -
9 JCB BS-3 MN01 9722 10/04/2025 TO MN/197 HO-406
CAMP NOT WORKING LE DONE PAYMENT IN
1663
PROPERLY & KING PIN PROCESS
ARE DAMAGE
PO DONE TO MAX DG
MAHINDRA NEW DISMANT GUWAHATI -
10 N2A20A24519 06/04/2025 13 MN/310 HO-389 ALTERNATOR BURND
10KVA DG CAMP LE DONE MATERIAL DISPATCH
SOON
PO DONE TO MAX DG
MAHINDRA NEW DISMANT GUWAHATI -
11 N2P21A17696 06/04/2025 13 MN/310 HO-389 ALTERNATOR BURND
10KVA DG CAMP LE DONE MATERIAL DISPATCH
SOON

BREAKER SEAL KIT , PO DONE TO KSAR


KOMATSU BUSH , CHISEL BUSHING , ERATHMOVERS &
NEW 1364 & HO- 234 DISMANT
12 BREAKER JH 350 01/05/2025 MN/2185 PLUG , RETAINER BAR , INDUSTRIAL SPARES
CAMP 1365 & HO-239 LE DONE
PC-300 STOPER PIN ETC ARE & I EQUIP
DAMAGE CORPORATION

CYL HEAD GASKET,


CORE PLUG, ROCKER
DG Set NEW 114
13 12/05/2025 ENGINE HEATING ISSUE COVER GASKET,
62.5kva CAMP 00000000677
INTAKE MANIFOLD
GASKET, TURBO

Mitsubishi NEW SEAL KIT, KING PIN,


ARTICULATE CYL. LEAK,
14 MOTOR CHECKO MN 01 9723 16/05/2025 33 KING PIN BEARING
KING PIN DAMAGE
GRADER N REQUIRED
Apollo
TOP INPUT SHAFT AND SPUR DISMANTL WAITING FOR NEW
15 Sensor 610605 17/05/2025 46 MN/440
DUSARA GEAR DAMAGE E DONE PARTS
Paver
REMARKS

WORK IS IN PROGRESS

AUTO SPARES PARTS


DISPATCHED FROM KSAR
EARTHMOVERS ONE PART
PENDING (EXHAUST PIPE),
FROM GHY TO
IMPHAL ON 12-05-2025,
NETWORK (NICCN72252), &
FEBRICATION MATERIAL PO
UNDER PROCESS

WORK IS IN PROGRESS

SOME PARTS RECEIVED ON


18-05-2025 (INVOICE NO. -
278)

REMARKS FROM DEALER


MIGHT TO CHANGE
CATALYTIC CONVERTOR,
FINAL WORD NOT RECEIVED
YET

PARTS DISPATCHED
THROUGH NATIONAL
CARRIYING CORP.
(RLY/00184)
FITMENT UNDER PROCESS

READY TO PICKUP MATERIALS


AT DEALER

MATERIALS TO BE
DISPATCHED

MATERIALS TO BE
DISPATCHED

MATERIALS TO BE
DISPATCHED

3 ITEMS DISPATCHED 09-05-


2025 & 2 ITEMS DISPATCHED
13-05-2025(PO - HO 234)
&
PO - HO 239
ITEMS NOT DISPATCHED

ALL PARTS RECEIVED &


TURBO PENDING

PO NOT PREPARED YET

PO NOT PREPARED YET


KEYSTONE INFRA PVT LTD.
DAILY BREAKDOWN REPORT AS ON MAY -19-05-2025
SL Focus Action & Expact Date To Be
Fixed Assets Location Reg No B/D Start Indent No Po No Reason For BD Present Status REMARKS
NO Indent No Rectification Ready
ENGINE HEATING
PO DONE TO PARTS DISPATCHED
ISSUE , PILOT
PC-210- N710361 - DISMANTLE SHANTHI TRADING THROUGH NATIONAL
1 NEW CAMP 16/04/2025 1695 MN/283 HO-392 LEVER FUCTION
08MO 19 DONE - PAYMENT IN CARRIYING CORP.
NOT WORKING
PROCESS (RLY/00184)
PROPERLY
3 ITEMS DISPATCHED 09-
BREAKER SEAL
PO DONE TO KSAR 05-2025 & 2 ITEMS
KIT , BUSH , CHISEL
KOMATSU HO- 234 ERATHMOVERS & DISPATCHED 13-05-
1364 & BUSHING , PLUG , DISMANTLE
2 BREAKER PC- NEW CAMP JH 350 01/05/2025 MN/2185 & HO- INDUSTRIAL 2025(PO - HO 234)
1365 RETAINER BAR , DONE
300 239 SPARES & I EQUIP & PO - HO
STOPER PIN ETC
CORPORATION 239 ITEMS NOT
ARE DAMAGE
DISPATCHED
Mitsubishi ARTICULATE CYL. SEAL KIT, KING PIN,
MOTOR NEW MN 01 9723 16/05/2025 33 MN/444 LEAK, KING PIN KING PIN BEARING PO NOT PREPARED YET
3
GRADER CHECKON DAMAGE REQUIRED

Apollo Sensor INPUT SHAFT AND DISMANTLE WAITING FOR NEW


4 TOP DUSARA 610605 17/05/2025 46 MN/440 PO NOT PREPARED YET
Paver SPUR GEAR DAMAGE DONE PARTS

PO DONE TO MA & READY TO PICKUP


CHECKON MN05C ENGINE ECU NOT DISMANTLE
5 JCB BS-4 17/04/2025 1653 MN/135 HO-288 MA - PAYMENT IN MATERIALS, PAYMENT
SITE 3982 WORKING DONE
PROCESS ALSO DONE AT DEALER

SOME HYDRAULIC
HOSE PIPE
LEAKAGE , PICK UP PO DONE TO KSAR
1658 TO ISSUE , BREAK DISMANTLE EARTH MOVERS - MATERIALS TO BE
6 JCB BS-3 NEW CAMP MN01 9722 10/04/2025 MN/197 HO-406
1663 SYSTEM NOT DONE PAYMENT IN DISPATCHED
WORKING PROCESS
PROPERLY & KING
PIN ARE DAMAGE

AIR COMPRESSOR ,
AL BS-6 MN05C 1391 & BCU , CLUSTER , DISMANTLE ENGINE FITMENT ALMOST COMPLETE,
7 NEW CAMP 01/04/2025 MN/15 HO - 77 20/05/2025
TIPPER 4116 1392 NOX SEBSOR , U DONE UNDER PROCESS UNDER TRIAL
BOLT ARE DAMAGE

SYNCRO RING AND


AL BS-6 DISMANTLE
8 NEW CAMP MN05C 4109 18/05/2025 42 MN/443 GEAR BOX NOISY
DONE
OTHER PARTS PO NOT PREPARED YET
TIPPER ORDERED

AL BS-6 DISMANTLE RADIATOR AND SENT TO DAMEN SINGH


9 NEW CAMP MN05C 3749 17/05/2025 ACCIDENT
DONE COOLER DAMAGED RADIATORS FOR REPAIRING
TIPPER
HO 380 PARTS RECEIVED
LOAD BODY C CHANNEL , MS
(FLEXIBLE EXHAUST PIPE
DAMAGE , TYRE , PLAIN SHEET , MS
HO-380 REMAINING),HO 365
AL BS-3 HILL SITE NL02Q 004& 005 MN/276 BATTERY , DISMANTLE SQUARE PIPE -
10 11/04/2025 & HO- PARTS RECEIVED (SHIM
TIPPER (NEW CAMP) 8726 008 MN282 DENTING WORK , DONE MATERIAL
365 REMAINING) &
GEAR BOX SPARES REQUIREMENTS
FEBRICATION MATERIAL
& RUNNING REPAIR INDENT RISED
PO UNDER PROCESS

LOAD BODY
DAMAGE , TYRE , NEW DALA BODY
AL BS-3 HILL SITE NL02Q DISMANTLE
11 25/04/2025 BATTERY , MAKING UNDER 20/05/2025 WORK IS IN PROGRESS
TIPPER (NEW CAMP) 8642 DONE
DENTING WORK & PROCESS
RUNNING REPAIR

CYLINDER LINER ,
HEAD GASKET ,
PO DONE TO SOME PARTS RECEIVED
AL BS-3 HILL SITE NL02Q PISTON & RING SET DISMANTLE
12 29-04-2025 006 & 007 MN/277 HO-381 NARAYANI ON 18-05-2025 (INVOICE
TIPPER (NEW CAMP) 8721 , CR BEARING , DONE
TRADING COMPANY NO. - 278)
VALVE OIL SEAL &
ETC ARE DAMAGE

CYL HEAD GASKET,


CORE PLUG,
114
DG Set ENGINE HEATING ROCKER COVER ALL PARTS RECEIVED &
13 NEW CAMP 000000006 12/05/2025
62.5kva ISSUE GASKET, INTAKE TURBO PENDING
77
MANIFOLD GASKET,
TURBO

PO DONE TO MAX
MAHINDRA N2A20A245 ALTERNATOR DISMANTLE DG GUWAHATI - MATERIALS TO BE
14 NEW CAMP 06/04/2025 13 MN/310 HO-389
10KVA DG 19 BURND DONE MATERIAL DISPATCHED
DISPATCH SOON
PO DONE TO MAX
MAHINDRA N2P21A176 ALTERNATOR DISMANTLE DG GUWAHATI - MATERIALS TO BE
15 NEW CAMP 06/04/2025 13 MN/310 HO-389
10KVA DG 96 BURND DONE MATERIAL DISPATCHED
DISPATCH SOON

PICKUP ISSUES &


HEAD GASKET , CR
PO DONE TO JAIN REMARKS FROM DEALER
BEARING , LINER ,
SALES AGENCY , PO MIGHT TO CHANGE
MAHINDRA SHOWROOM 1618 & PISTON , THRUST DISMANTLE
16 NL0D 7655 31/03/2025 MN/2394 HO-2909 NO - HO-54 . CATALYTIC CONVERTOR,
BS-6 CAMPER - HILL SITE 1619 WASHER , VALVE DONE
PAYMENT IN FINAL WORD NOT
OIL SEAL & PULLY
PROCESS RECEIVED YET
DEMPER ARE
DAMAGE

KING PIN DAMAGE KING PIN TIE ROD & GEAR


NL02Q
17 TATA XENON NEW CAMP 05/05/2025 & RADAITOR DISMANMANT LEVER BUSH 19/05/2025 WORK IS IN PROGRESS
8628
NOTWORKING LE DONE FITMENT PENDING
KEYSTONE INFRA PVT LTD.
DAILY BREAKDOWN REPORT AS ON MAY -20-05-2025

SL Focus Action & Expact Date


Fixed Assets Location Reg No B/D Start Indent No Po No Reason For BD Present Status REMARKS
NO Indent No Rectification To Be Ready

ENGINE HEATING
PO DONE TO PARTS DISPATCHED
ISSUE , PILOT
PC-210- N710361 - DISMANTLE SHANTHI TRADING THROUGH NATIONAL
1 NEW CAMP 16/04/2025 1695 MN/283 HO-392 LEVER FUCTION
08MO 19 DONE - PAYMENT IN CARRIYING CORP.
NOT WORKING
PROCESS (RLY/00184)
PROPERLY
3 ITEMS DISPATCHED 09-
BREAKER SEAL
PO DONE TO KSAR 05-2025 & 2 ITEMS
KIT , BUSH , CHISEL
KOMATSU HO- 234 ERATHMOVERS & DISPATCHED 13-05-
1364 & BUSHING , PLUG , DISMANTLE
2 BREAKER PC- NEW CAMP JH 350 01/05/2025 MN/2185 & HO- INDUSTRIAL 2025(PO - HO 234)
1365 RETAINER BAR , DONE
300 239 SPARES & I EQUIP & PO - HO
STOPER PIN ETC
CORPORATION 239 ITEMS NOT
ARE DAMAGE
DISPATCHED
Mitsubishi ARTICULATE CYL. SEAL KIT, KING PIN,
MOTOR NEW MN 01 9723 16/05/2025 33 MN/444 LEAK, KING PIN KING PIN BEARING PO NOT PREPARED YET
3
GRADER CHECKON DAMAGE REQUIRED

Apollo Sensor INPUT SHAFT AND DISMANTLE WAITING FOR NEW


4 TOP DUSARA 610605 17/05/2025 46 MN/440 PO NOT PREPARED YET
Paver SPUR GEAR DAMAGE DONE PARTS

PO DONE TO MA &
CHECKON MN05C ENGINE ECU NOT DISMANTLE PARTS PICKUP WILL BE
5 JCB BS-4 17/04/2025 1653 MN/135 HO-288 MA - PAYMENT IN
SITE 3982 WORKING DONE DONE TODAY
PROCESS

SOME HYDRAULIC
HOSE PIPE
LEAKAGE , PICK UP PO DONE TO KSAR
1658 TO ISSUE , BREAK DISMANTLE EARTH MOVERS - MATERIALS TO BE
6 JCB BS-3 NEW CAMP MN01 9722 10/04/2025 MN/197 HO-406
1663 SYSTEM NOT DONE PAYMENT IN DISPATCHED
WORKING PROCESS
PROPERLY & KING
PIN ARE DAMAGE

AIR COMPRESSOR ,
AL BS-6 MN05C 1391 & BCU , CLUSTER , DISMANTLE ENGINE FITMENT ENGINE OIL PIPE AND
7 NEW CAMP 01/04/2025 MN/15 HO - 77 22/05/2025
TIPPER 4116 1392 NOX SEBSOR , U DONE UNDER PROCESS GAUGE PENDING
BOLT ARE DAMAGE

SYNCRO RING AND


AL BS-6 MN05C DISMANTLE
8 NEW CAMP 18/05/2025 42 MN/443 GEAR BOX NOISY OTHER PARTS PO NOT PREPARED YET
TIPPER 4109 DONE
ORDERED

RADIATOR AND COOLER


AL BS-6 MN05C DISMANTLE RADIATOR AND LOCAL REPAIR DONE,
9 NEW CAMP 17/05/2025 ACCIDENT 22/05/2025
TIPPER 3749 DONE COOLER DAMAGED WAITING FOR PICKUP AND
FITMENT
HO 380 PARTS RECEIVED
LOAD BODY C CHANNEL , MS
(FLEXIBLE EXHAUST PIPE
DAMAGE , TYRE , PLAIN SHEET , MS
HO-380 REMAINING),HO 365
AL BS-3 HILL SITE NL02Q 004& 005 MN/276 BATTERY , DISMANTLE SQUARE PIPE -
10 11/04/2025 & HO- PARTS RECEIVED (SHIM
TIPPER (NEW CAMP) 8726 008 MN282 DENTING WORK , DONE MATERIAL
365 REMAINING) &
GEAR BOX SPARES REQUIREMENTS
FEBRICATION MATERIAL
& RUNNING REPAIR INDENT RISED
PO UNDER PROCESS

LOAD BODY
DAMAGE , TYRE , NEW DALA BODY
AL BS-3 HILL SITE NL02Q DISMANTLE
11 25/04/2025 BATTERY , MAKING UNDER 22/05/2025 WORK IS IN PROGRESS
TIPPER (NEW CAMP) 8642 DONE
DENTING WORK & PROCESS
RUNNING REPAIR

CYLINDER LINER ,
HEAD GASKET ,
PO DONE TO SOME PARTS RECEIVED
AL BS-3 HILL SITE NL02Q PISTON & RING SET DISMANTLE
12 29-04-2025 006 & 007 MN/277 HO-381 NARAYANI ON 18-05-2025 (INVOICE
TIPPER (NEW CAMP) 8721 , CR BEARING , DONE
TRADING COMPANY NO. - 278)
VALVE OIL SEAL &
ETC ARE DAMAGE

CYL HEAD GASKET,


CORE PLUG,
114 RADIATOR LOCAL REPAIR
DG Set ENGINE HEATING ROCKER COVER
13 NEW CAMP 000000006 12/05/2025 20/05/2025 DONE, WAITING FOR PICKUP
62.5kva ISSUE GASKET, INTAKE AND FITMENT
77
MANIFOLD GASKET,
TURBO

PO DONE TO MAX
MAHINDRA N2A20A24 ALTERNATOR DISMANTLE DG GUWAHATI - MATERIALS TO BE
14 NEW CAMP 06/04/2025 13 MN/310 HO-389
10KVA DG 519 BURND DONE MATERIAL DISPATCHED
DISPATCH SOON
PO DONE TO MAX
MAHINDRA N2P21A17 ALTERNATOR DISMANTLE DG GUWAHATI - MATERIALS TO BE
15 NEW CAMP 06/04/2025 13 MN/310 HO-389
10KVA DG 696 BURND DONE MATERIAL DISPATCHED
DISPATCH SOON

PICKUP ISSUES &


HEAD GASKET , CR
PO DONE TO JAIN
BEARING , LINER ,
SALES AGENCY , PO
MAHINDRA SHOWROOM 1618 & PISTON , THRUST DISMANTLE FINAL WORDS NOT
16 NL0D 7655 31/03/2025 MN/2394 HO-2909 NO - HO-54 .
BS-6 CAMPER - HILL SITE 1619 WASHER , VALVE DONE SHARED YET
PAYMENT IN
OIL SEAL & PULLY
PROCESS
DEMPER ARE
DAMAGE

KING PIN DAMAGE KING PIN TIE ROD & GEAR


NL02Q TIE ROD END &
17 TATA XENON NEW CAMP 05/05/2025 & RADAITOR DISMANMANT LEVER BUSH 20/05/2025
8628 ALLIGNMENT PENDING
NOTWORKING LE DONE FITMENT PENDING
KEYSTONE INFRA PVT LTD.
DAILY BREAKDOWN REPORT AS ON MAY -21-05-2025
Action &
Fixed Focus Reason For
SL NO Location Reg No B/D Start Indent No Po No Rectificatio
Assets Indent No BD
n

ENGINE
HEATING
ISSUE ,
PILOT
PC-210- N710361 - DISMANTLE
1 NEW CAMP 16/04/2025 1695 MN/283 HO-392 LEVER
08MO 19 DONE
FUCTION
NOT
WORKING
PROPERLY

BREAKER
SEAL KIT ,
BUSH ,
CHISEL
KOMATSU BUSHING ,
1364 & HO- 234 & DISMANTLE
2 BREAKER NEW CAMP JH 350 01/05/2025 MN/2185 PLUG ,
1365 HO-239 DONE
PC-300 RETAINER
BAR ,
STOPER PIN
ETC ARE
DAMAGE

ARTICULATE
Mitsubishi
NEW CYL. LEAK,
3 MOTOR MN 01 9723 16/05/2025 33 MN/444
CHECKON KING PIN
GRADER
DAMAGE

INPUT
Apollo
SHAFT AND DISMANTLE
4 Sensor TOP DUSARA 610605 17/05/2025 46 MN/440
SPUR GEAR DONE
Paver
DAMAGE

CONE
Kleeman
BREAKDOW
Mobile SEKMAI
5 K0720048 21/05/2025 N, PULLEY,
Crusher - CRUSHER
BELT AND
Cone
TENSIONER

ENGINE
CHECKON MN05C DISMANTLE
6 JCB BS-4 17/04/2025 1653 MN/135 ECU NOT
SITE 3982 DONE
WORKING
SOME
HYDRAULIC
HOSE PIPE
LEAKAGE ,
PICK UP
ISSUE ,
1658 TO BREAK DISMANTLE
7 JCB BS-3 NEW CAMP MN01 9722 10/04/2025 MN/197 HO-406
1663 SYSTEM DONE
NOT
WORKING
PROPERLY
& KING PIN
ARE
DAMAGE

AIR
COMPRESS
OR , BCU ,
AL BS-6 MN05C 1391 & CLUSTER , DISMANTLE
8 NEW CAMP 01/04/2025 MN/15 HO - 77
TIPPER 4116 1392 NOX DONE
SEBSOR , U
BOLT ARE
DAMAGE

AL BS-6 GEAR BOX DISMANTLE


9 NEW CAMP MN05C 4109 18/05/2025 42 MN/443
NOISY DONE
TIPPER

AL BS-6 DISMANTLE
10 NEW CAMP MN05C 3749 17/05/2025 ACCIDENT
DONE
TIPPER

LOAD BODY
DAMAGE ,
TYRE ,
BATTERY ,
HILL SITE
AL BS-3 NL02Q 004& 005 MN/276 HO-380 & DENTING DISMANTLE
11 (NEW 11/04/2025
TIPPER 8726 008 MN282 HO-365 WORK , DONE
CAMP)
GEAR BOX
SPARES &
RUNNING
REPAIR

LOAD BODY
DAMAGE ,
TYRE ,
HILL SITE
AL BS-3 NL02Q BATTERY , DISMANTLE
12 (NEW 25/04/2025
TIPPER 8642 DENTING DONE
CAMP)
WORK &
RUNNING
REPAIR
CYLINDER
LINER ,
HEAD
GASKET ,
PISTON &
HILL SITE
AL BS-3 NL02Q RING SET , DISMANTLE
13 (NEW 29-04-2025 006 & 007 MN/277 HO-381
TIPPER 8721 CR DONE
CAMP)
BEARING ,
VALVE OIL
SEAL & ETC
ARE
DAMAGE

114 ENGINE
DG Set
14 NEW CAMP 000000006 12/05/2025 HEATING
62.5kva
77 ISSUE

MAHINDRA N2A20A245 ALTERNAT DISMANTLE


15 NEW CAMP 06/04/2025 13 MN/310 HO-389
10KVA DG 19 OR BURND DONE

MAHINDRA N2P21A176 ALTERNAT DISMANTLE


16 NEW CAMP 06/04/2025 13 MN/310 HO-389
10KVA DG 96 OR BURND DONE

PICKUP
ISSUES &
HEAD
GASKET ,
CR
BEARING ,
LINER ,
MAHINDRA SHOWROO
1618 & PISTON , DISMANTLE
17 BS-6 M - HILL NL0D 7655 31/03/2025 MN/2394 HO-2909
1619 THRUST DONE
CAMPER SITE
WASHER ,
VALVE OIL
SEAL &
PULLY
DEMPER
ARE
DAMAGE

KING PIN
DAMAGE & KING PIN
TATA NL02Q
18 NEW CAMP 05/05/2025 RADAITOR DISMANMA
XENON 8628
NOTWORKI NTLE DONE
NG
5

Present Expact Date


REMARKS
Status To Be Ready

PARTS
DISPATCHE
PO DONE
D
TO
THROUGH
SHANTHI
NATIONAL
TRADING -
CARRIYING
PAYMENT
CORP.
IN PROCESS
(RLY/0018
4)

3 ITEMS
DISPATCHE
D 09-05-
PO DONE 2025 & 2
TO KSAR ITEMS
ERATHMOV DISPATCHE
ERS & D 13-05-
INDUSTRIA 2025(PO -
L SPARES & HO 234)
I EQUIP
CORPORATI &
ON PO - HO 239
ITEMS NOT
DISPATCHE
D

SEAL KIT,
KING PIN, PO NOT
KING PIN PREPARED
BEARING YET
REQUIRED

WAITING PO NOT
FOR NEW PREPARED
PARTS YET

PREPARING
THE INDENT

PART
PO DONE
RECEIVED,
TO MA &
FITMENT
MA - 22/05/2025
WILL BE
PAYMENT
DONE
IN PROCESS
TODAY
PO DONE
TO KSAR MATERIALS
EARTH TO BE
MOVERS - DISPATCHE
PAYMENT D
IN PROCESS

ENGINE ENGINE OIL


FITMENT PIPE AND
23/05/2025
UNDER GAUGE
PROCESS PENDING

SYNCRO
RING AND PO NOT
OTHER PREPARED
PARTS YET
ORDERED

RADIATOR
AND
COOLER
RADIATOR LOCAL
AND REPAIR
22/05/2025
COOLER DONE,
DAMAGED WAITING
FOR PICKUP
AND
FITMENT

C CHANNEL GEAR BOX


, MS PLAIN FITMENT
SHEET , MS UNDER
SQUARE PROGRESS
PIPE - &
MATERIAL FEBRICATI
REQUIREM ON
ENTS MATERIAL
INDENT PO UNDER
RISED PROCESS

NEW DALA
BODY
WORK IS IN
MAKING 22/05/2025
PROGRESS
UNDER
PROCESS
SOME
PO DONE
PARTS
TO
RECEIVED
NARAYANI
& FITMENT
TRADING
PROCESS
COMPANY
STARTED

CYL HEAD
GASKET, RADIATOR
CORE PLUG, LOCAL
ROCKER REPAIR
COVER DONE,
22/05/2025 WAITING
GASKET,
INTAKE FOR PICKUP
AND
MANIFOLD FITMENT
GASKET,
TURBO

PO DONE
TO MAX DG MATERIALS
GUWAHATI TO BE
- MATERIAL DISPATCHE
DISPATCH D
SOON

PO DONE
TO MAX DG MATERIALS
GUWAHATI TO BE
- MATERIAL DISPATCHE
DISPATCH D
SOON

PO DONE
TO JAIN
FINAL
SALES
WORDS
AGENCY ,
NOT
PO NO - HO-
SHARED
54 .
YET
PAYMENT
IN PROCESS

TIE ROD &


GEAR
LEVER WORK IN
22/05/2025
BUSH PROGRESS
FITMENT
PENDING
KEYSTONE INFRA PVT LTD.
DAILY BREAKDOWN REPORT AS ON MAY -22-05-2025

SL Focus Action & Expact Date


Fixed Assets Location Reg No B/D Start Indent No Po No Reason For BD Present Status REMARKS
NO Indent No Rectification To Be Ready

Kleeman CONE BREAKDOWN,


SEKMAI
1 Mobile K0720048 21/05/2025 60 - 62 PULLEY, BELT AND MANUAL INDENT PREPARED
CRUSHER
Crusher - Cone TENSIONER

ENGINE HEATING
PO DONE TO PARTS DISPATCHED
ISSUE , PILOT
PC-210- N710361 - DISMANTLE SHANTHI TRADING THROUGH NATIONAL
2 NEW CAMP 16/04/2025 1695 MN/283 HO-392 LEVER FUCTION
08MO 19 DONE - PAYMENT IN CARRIYING CORP.
NOT WORKING
PROCESS (RLY/00184)
PROPERLY
3 ITEMS DISPATCHED 09-
BREAKER SEAL
PO DONE TO KSAR 05-2025 & 2 ITEMS
KIT , BUSH , CHISEL
KOMATSU HO- 234 ERATHMOVERS & DISPATCHED 13-05-
1364 & BUSHING , PLUG , DISMANTLE
3 BREAKER PC- NEW CAMP JH 350 01/05/2025 MN/2185 & HO- INDUSTRIAL 2025(PO - HO 234)
1365 RETAINER BAR , DONE
300 239 SPARES & I EQUIP & PO - HO
STOPER PIN ETC
CORPORATION 239 ITEMS NOT
ARE DAMAGE
DISPATCHED
Mitsubishi ARTICULATE CYL. SEAL KIT, KING PIN,
MOTOR NEW MN 01 9723 16/05/2025 33 MN/444 LEAK, KING PIN KING PIN BEARING PO NOT PREPARED YET
4
GRADER CHECKON DAMAGE REQUIRED
SERVICE CHARGE
CHECKON MN05C ENGINE ECU NOT DISMANTLE FITMENT TO BE
7 JCB BS-4 17/04/2025 QUOTATION FOR WORK
SITE 3982 WORKING DONE DONE BY MA & MA
ORDER SUBMITTED

SOME HYDRAULIC
HOSE PIPE
LEAKAGE , PICK UP PO DONE TO KSAR
1658 TO ISSUE , BREAK DISMANTLE EARTH MOVERS - MATERIALS TO BE
8 JCB BS-3 NEW CAMP MN01 9722 10/04/2025 MN/197 HO-406
1663 SYSTEM NOT DONE PAYMENT IN DISPATCHED
WORKING PROCESS
PROPERLY & KING
PIN ARE DAMAGE

SYNCRO RING AND


AL BS-6 MN05C DISMANTLE
9 NEW CAMP 18/05/2025 42 MN/443 GEAR BOX NOISY OTHER PARTS PO NOT PREPARED YET
TIPPER 4109 DONE
ORDERED
RADIATOR AND COOLER
AL BS-6 MN05C DISMANTLE RADIATOR AND
10 NEW CAMP 17/05/2025 ACCIDENT 24/05/2025 RECEIVED, FITMENT UNDER
TIPPER 3749 DONE COOLER DAMAGED
PROCESS

LOAD BODY C CHANNEL , MS


DAMAGE , TYRE , PLAIN SHEET , MS
HO-380 GEAR BOX FITMENT DONE &
AL BS-3 HILL SITE NL02Q 004& 005 MN/276 BATTERY , DISMANTLE SQUARE PIPE - FEBRICATION MATERIAL PO
11 11/04/2025 & HO-
TIPPER (NEW CAMP) 8726 008 MN282 DENTING WORK , DONE MATERIAL UNDER PROCESS
365
GEAR BOX SPARES REQUIREMENTS
& RUNNING REPAIR INDENT RISED
LOAD BODY
DAMAGE , TYRE , NEW DALA BODY
AL BS-3 HILL SITE NL02Q DISMANTLE
12 25/04/2025 BATTERY , MAKING UNDER 25/05/2025 WORK IS IN PROGRESS
TIPPER (NEW CAMP) 8642 DONE
DENTING WORK & PROCESS
RUNNING REPAIR

CYLINDER LINER ,
HEAD GASKET ,
PO DONE TO SOME PARTS RECEIVED &
AL BS-3 HILL SITE NL02Q PISTON & RING SET DISMANTLE
13 29-04-2025 006 & 007 MN/277 HO-381 NARAYANI FITMENT PROCESS
TIPPER (NEW CAMP) 8721 , CR BEARING , DONE
TRADING COMPANY STARTED
VALVE OIL SEAL &
ETC ARE DAMAGE

CYL HEAD GASKET,


CORE PLUG,
114
DG Set ENGINE HEATING ROCKER COVER RADIATOR RECEIVED,
14 NEW CAMP 000000006 12/05/2025 23/05/2025 FITMENT IN PROGRESS
62.5kva ISSUE GASKET, INTAKE
77
MANIFOLD GASKET,
TURBO

PO DONE TO MAX
MAHINDRA N2A20A24 ALTERNATOR DISMANTLE DG GUWAHATI - PART DISPATCHED
15 NEW CAMP 06/04/2025 13 MN/310 HO-389
10KVA DG 519 BURND DONE MATERIAL (NETWORK - NICCN07655)
DISPATCH SOON
PO DONE TO MAX
MAHINDRA N2P21A17 ALTERNATOR DISMANTLE DG GUWAHATI - PART DISPATCHED
16 NEW CAMP 06/04/2025 13 MN/310 HO-389
10KVA DG 696 BURND DONE MATERIAL (NETWORK - NICCN07655)
DISPATCH SOON

PICKUP ISSUES &


HEAD GASKET , CR
BEARING , LINER , AS PER DEALER ONE CATALYTIC
MAHINDRA SHOWROOM 1618 & PISTON , THRUST DISMANTLE NEED TO CHANGE CONVERTOR IS IN OUR
17 NL0D 7655 31/03/2025 MN/2394 HO-2909
BS-6 CAMPER - HILL SITE 1619 WASHER , VALVE DONE CATALYTIC STOCK, ARRANGING TO
OIL SEAL & PULLY CONVERTOR FIT THE SAME
DEMPER ARE
DAMAGE
KEYSTONE INFRA PVT LTD.
DAILY BREAKDOWN REPORT AS ON MAY -23-05-2025

SL Fixed Indent Focus Action & Expact Date


Location Reg No B/D Start Po No Reason For BD Present Status REMARKS
NO Assets No Indent No Rectification To Be Ready

Kleeman
CONE BREAKDOWN,
Mobile SEKMAI
1 K0720048 21/05/2025 60 - 62 MN/659 PULLEY, BELT AND WAITING FOR PO
Crusher - CRUSHER
TENSIONER
Cone

ENGINE HEATING PO DONE TO PARTS DISPATCHED


PC-210- N710361 - ISSUE , PILOT LEVER DISMANTLE SHANTHI TRADING - THROUGH NATIONAL
2 NEW CAMP 16/04/2025 1695 MN/283 HO-392
08MO 19 FUCTION NOT DONE PAYMENT IN CARRIYING CORP.
WORKING PROPERLY PROCESS (RLY/00184)

BREAKER SEAL KIT , 3 ITEMS DISPATCHED 09-


PO DONE TO KSAR
BUSH , CHISEL 05-2025 & 2 ITEMS
KOMATSU HO- 234 ERATHMOVERS &
1364 & BUSHING , PLUG , DISMANTLE DISPATCHED 13-05-
3 BREAKER NEW CAMP JH 350 01/05/2025 MN/2185 & HO- INDUSTRIAL SPARES
1365 RETAINER BAR , DONE 2025(PO - HO 234)
PC-300 239 & I EQUIP
STOPER PIN ETC ARE & PO - HO 239
CORPORATION
DAMAGE ITEMS NOT DISPATCHED
Mitsubishi SEAL KIT, KING PIN,
NEW ARTICULATE CYL. LEAK,
4 MOTOR MN 01 9723 16/05/2025 33 MN/444 KING PIN BEARING PO NOT PREPARED YET
CHECKON KING PIN DAMAGE
GRADER REQUIRED
SERVICE CHARGE
CHECKON MN05C ENGINE ECU NOT DISMANTLE FITMENT TO BE
5 JCB BS-4 17/04/2025 QUOTATION FOR WORK
SITE 3982 WORKING DONE DONE BY MA & MA
ORDER SUBMITTED

SOME HYDRAULIC
HOSE PIPE LEAKAGE ,
PO DONE TO KSAR
1658 PICK UP ISSUE , PARTS DISPATCHED ON 20-
DISMANTLE EARTH MOVERS -
6 JCB BS-3 NEW CAMP MN01 9722 10/04/2025 TO MN/197 HO-406 BREAK SYSTEM NOT 05-2025 (BHAWANI
DONE PAYMENT IN
1663 WORKING PROPERLY ROADLINES)
PROCESS
& KING PIN ARE
DAMAGE

SYNCRO RING AND


AL BS-6 MN05C DISMANTLE
7 NEW CAMP 18/05/2025 42 MN/443 GEAR BOX NOISY OTHER PARTS WAITING FOR PO
TIPPER 4109 DONE
ORDERED

C CHANNEL , MS
LOAD BODY DAMAGE
PLAIN SHEET , MS
004& HO-380 , TYRE , BATTERY , GEAR BOX FITMENT DONE &
AL BS-3 HILL SITE NL02Q MN/276 DISMANTLE SQUARE PIPE - FEBRICATION MATERIAL PO
8 11/04/2025 005 & HO- DENTING WORK ,
TIPPER (NEW CAMP) 8726 MN282 DONE MATERIAL UNDER PROCESS
008 365 GEAR BOX SPARES &
REQUIREMENTS
RUNNING REPAIR
INDENT RISED

LOAD BODY DAMAGE


NEW DALA BODY
AL BS-3 HILL SITE NL02Q , TYRE , BATTERY , DISMANTLE
9 25/04/2025 MAKING UNDER 25/05/2025 WORK IS IN PROGRESS
TIPPER (NEW CAMP) 8642 DENTING WORK & DONE
PROCESS
RUNNING REPAIR
CYLINDER LINER ,
HEAD GASKET ,
PO DONE TO SOME PARTS RECEIVED &
AL BS-3 HILL SITE NL02Q 006 & PISTON & RING SET , DISMANTLE
10 29-04-2025 MN/277 HO-381 NARAYANI TRADING FITMENT PROCESS
TIPPER (NEW CAMP) 8721 007 CR BEARING , VALVE DONE
COMPANY STARTED
OIL SEAL & ETC ARE
DAMAGE

AL BS-6 MN05C GEAR BOX NOISY ON DISMANTLE GEARBOX PREPARING THE INDENT
11 NEW CAMP 23/05/2025 66-69
TIPPER 3745 APPLYING GEARS DONE DISMANTLED LIST

PO DONE TO MAX DG
MAHINDRA N2A20A24 ALTERNATOR DISMANTLE GUWAHATI - PART DISPATCHED
12 NEW CAMP 06/04/2025 13 MN/310 HO-389
10KVA DG 519 BURND DONE MATERIAL (NETWORK - NICCN07655)
DISPATCH SOON
PO DONE TO MAX DG
MAHINDRA N2P21A17 ALTERNATOR DISMANTLE GUWAHATI - PART DISPATCHED
13 NEW CAMP 06/04/2025 13 MN/310 HO-389
10KVA DG 696 BURND DONE MATERIAL (NETWORK - NICCN07655)
DISPATCH SOON

PICKUP ISSUES &


HEAD GASKET , CR
BEARING , LINER , AS PER DEALER ONE CATALYTIC
MAHINDRA
1618 & PISTON , THRUST DISMANTLE NEED TO CHANGE CONVERTOR IS IN OUR
14 BS-6 SHOWROOM NL0D 7655 31/03/2025 MN/2394 HO-2909
1619 WASHER , VALVE OIL DONE CATALYTIC STOCK, ARRANGING TO FIT
CAMPER
SEAL & PULLY CONVERTOR THE SAME
DEMPER ARE
DAMAGE
KEYSTONE INFRA PVT LTD.
DAILY BREAKDOWN REPORT AS ON MAY -24-05-2025

SL Fixed Indent Focus Action & Expact Date


Location Reg No B/D Start Po No Reason For BD Present Status REMARKS
NO Assets No Indent No Rectification To Be Ready

Kleeman
CONE BREAKDOWN,
Mobile SEKMAI
1 K0720048 21/05/2025 60 - 62 MN/659 PULLEY, BELT AND WAITING FOR PO
Crusher - CRUSHER
TENSIONER
Cone

ENGINE HEATING PO DONE TO PARTS DISPATCHED


PC-210- N710361 - ISSUE , PILOT LEVER DISMANTLE SHANTHI TRADING - THROUGH NATIONAL
2 NEW CAMP 16/04/2025 1695 MN/283 HO-392
08MO 19 FUCTION NOT DONE PAYMENT IN CARRIYING CORP.
WORKING PROPERLY PROCESS (RLY/00184)

BREAKER SEAL KIT , 3 ITEMS DISPATCHED 09-


PO DONE TO KSAR
BUSH , CHISEL 05-2025 (RECEIVED) & 2
KOMATSU HO- 234 ERATHMOVERS &
1364 & BUSHING , PLUG , DISMANTLE ITEMS DISPATCHED 13-05-
3 BREAKER NEW CAMP JH 350 01/05/2025 MN/2185 & HO- INDUSTRIAL SPARES
1365 RETAINER BAR , DONE 2025(PO - HO 234)
PC-300 239 & I EQUIP
STOPER PIN ETC ARE & PO - HO 239
CORPORATION
DAMAGE ITEMS NOT DISPATCHED
Mitsubishi SEAL KIT, KING PIN,
NEW ARTICULATE CYL. LEAK,
4 MOTOR MN 01 9723 16/05/2025 33 MN/444 KING PIN BEARING WAITING FOR PO
CHECKON KING PIN DAMAGE
GRADER REQUIRED
SERVICE CHARGE QUOTATION
CHECKON MN05C ENGINE ECU NOT DISMANTLE FITMENT TO BE FOR WORK ORDER
5 JCB BS-4 17/04/2025
SITE 3982 WORKING DONE DONE BY MA & MA SUBMITTED

SOME HYDRAULIC
HOSE PIPE LEAKAGE ,
PO DONE TO KSAR
1658 PICK UP ISSUE , PARTS DISPATCHED ON 20-
DISMANTLE EARTH MOVERS -
6 JCB BS-3 NEW CAMP MN01 9722 10/04/2025 TO MN/197 HO-406 BREAK SYSTEM NOT 05-2025 (BHAWANI
DONE PAYMENT IN
1663 WORKING PROPERLY ROADLINES)
PROCESS
& KING PIN ARE
DAMAGE

SYNCRO RING AND


AL BS-6 MN05C DISMANTLE
7 NEW CAMP 18/05/2025 42 MN/443 GEAR BOX NOISY OTHER PARTS WAITING FOR PO
TIPPER 4109 DONE
ORDERED

C CHANNEL , MS
LOAD BODY DAMAGE
PLAIN SHEET , MS
HILL SITE 004& HO-380 , TYRE , BATTERY , GEAR BOX FITMENT DONE &
AL BS-3 NL02Q MN/276 DISMANTLE SQUARE PIPE - FEBRICATION MATERIAL PO
8 (NEW 11/04/2025 005 & HO- DENTING WORK ,
TIPPER 8726 MN282 DONE MATERIAL UNDER PROCESS
CAMP) 008 365 GEAR BOX SPARES &
REQUIREMENTS
RUNNING REPAIR
INDENT RISED

LOAD BODY DAMAGE


HILL SITE NEW DALA BODY
AL BS-3 NL02Q , TYRE , BATTERY , DISMANTLE
9 (NEW 25/04/2025 MAKING UNDER 25/05/2025 WORK IS IN PROGRESS
TIPPER 8642 DENTING WORK & DONE
CAMP) PROCESS
RUNNING REPAIR
CYLINDER LINER ,
HEAD GASKET ,
HILL SITE PO DONE TO SOME PARTS RECEIVED &
AL BS-3 NL02Q 006 & PISTON & RING SET , DISMANTLE
10 (NEW 29-04-2025 MN/277 HO-381 NARAYANI TRADING FITMENT PROCESS
TIPPER 8721 007 CR BEARING , VALVE DONE
CAMP) COMPANY STARTED
OIL SEAL & ETC ARE
DAMAGE

AL BS-6 MN05C GEAR BOX NOISY ON DISMANTLE GEARBOX PREPARING THE INDENT
11 NEW CAMP 23/05/2025 66-69
TIPPER 3745 APPLYING GEARS DONE DISMANTLED LIST

PO DONE TO MAX DG
MAHINDRA N2A20A24 ALTERNATOR DISMANTLE GUWAHATI - PART DISPATCHED
12 NEW CAMP 06/04/2025 13 MN/310 HO-389
10KVA DG 519 BURND DONE MATERIAL (NETWORK - NICCN07655)
DISPATCH SOON
PO DONE TO MAX DG
MAHINDRA N2P21A17 ALTERNATOR DISMANTLE GUWAHATI - PART DISPATCHED
13 NEW CAMP 06/04/2025 13 MN/310 HO-389
10KVA DG 696 BURND DONE MATERIAL (NETWORK - NICCN07655)
DISPATCH SOON

PICKUP ISSUES &


HEAD GASKET , CR
BEARING , LINER , AS PER DEALER ONE CATALYTIC
MAHINDRA
SHOWROO 1618 & PISTON , THRUST DISMANTLE NEED TO CHANGE CONVERTOR IS IN OUR
14 BS-6 NL0D 7655 31/03/2025 MN/2394 HO-2909
M 1619 WASHER , VALVE OIL DONE CATALYTIC STOCK, ARRANGING TO FIT
CAMPER
SEAL & PULLY CONVERTOR THE SAME
DEMPER ARE
DAMAGE
KEYSTONE INFRA PVT LTD.
DAILY BREAKDOWN REPORT AS ON MAY -25-05-2025

SL Fixed Indent Focus Action & Expact Date


Location Reg No B/D Start Po No Reason For BD Present Status REMARKS
NO Assets No Indent No Rectification To Be Ready

Kleeman
CONE BREAKDOWN,
Mobile SEKMAI
1 K0720048 21/05/2025 60 - 62 MN/659 PULLEY, BELT AND WAITING FOR PO
Crusher - CRUSHER
TENSIONER
Cone

ENGINE HEATING PO DONE TO PARTS DISPATCHED


PC-210- N710361 - ISSUE , PILOT LEVER DISMANTLE SHANTHI TRADING - THROUGH NATIONAL
2 NEW CAMP 16/04/2025 1695 MN/283 HO-392
08MO 19 FUCTION NOT DONE PAYMENT IN CARRIYING CORP.
WORKING PROPERLY PROCESS (RLY/00184)

BREAKER SEAL KIT , 3 ITEMS DISPATCHED 09-


PO DONE TO KSAR
BUSH , CHISEL 05-2025 (RECEIVED) & 2
KOMATSU HO- 234 ERATHMOVERS &
1364 & BUSHING , PLUG , DISMANTLE ITEMS DISPATCHED 13-05-
3 BREAKER NEW CAMP JH 350 01/05/2025 MN/2185 & HO- INDUSTRIAL SPARES
1365 RETAINER BAR , DONE 2025(PO - HO 234)
PC-300 239 & I EQUIP
STOPER PIN ETC ARE & PO - HO 239
CORPORATION
DAMAGE ITEMS NOT DISPATCHED
Mitsubishi SEAL KIT, KING PIN,
NEW ARTICULATE CYL. LEAK,
4 MOTOR MN 01 9723 16/05/2025 33 MN/444 KING PIN BEARING WAITING FOR PO
CHECKON KING PIN DAMAGE
GRADER REQUIRED
SERVICE CHARGE QUOTATION
CHECKON MN05C ENGINE ECU NOT DISMANTLE FITMENT TO BE FOR WORK ORDER
5 JCB BS-4 17/04/2025
SITE 3982 WORKING DONE DONE BY MA & MA SUBMITTED

SOME HYDRAULIC
HOSE PIPE LEAKAGE ,
PO DONE TO KSAR
1658 PICK UP ISSUE , PARTS DISPATCHED ON 20-
DISMANTLE EARTH MOVERS -
6 JCB BS-3 NEW CAMP MN01 9722 10/04/2025 TO MN/197 HO-406 BREAK SYSTEM NOT 05-2025 (BHAWANI
DONE PAYMENT IN
1663 WORKING PROPERLY ROADLINES)
PROCESS
& KING PIN ARE
DAMAGE

SYNCRO RING AND


AL BS-6 MN05C DISMANTLE
7 NEW CAMP 18/05/2025 42 MN/443 GEAR BOX NOISY OTHER PARTS WAITING FOR PO
TIPPER 4109 DONE
ORDERED

C CHANNEL , MS
LOAD BODY DAMAGE
PLAIN SHEET , MS
HILL SITE 004& HO-380 , TYRE , BATTERY , GEAR BOX FITMENT DONE &
AL BS-3 NL02Q MN/276 DISMANTLE SQUARE PIPE - FEBRICATION MATERIAL PO
8 (NEW 11/04/2025 005 & HO- DENTING WORK ,
TIPPER 8726 MN282 DONE MATERIAL UNDER PROCESS
CAMP) 008 365 GEAR BOX SPARES &
REQUIREMENTS
RUNNING REPAIR
INDENT RISED

LOAD BODY DAMAGE


HILL SITE NEW DALA BODY
AL BS-3 NL02Q , TYRE , BATTERY , DISMANTLE
9 (NEW 25/04/2025 MAKING UNDER 27/05/2025 WORK IS IN PROGRESS
TIPPER 8642 DENTING WORK & DONE
CAMP) PROCESS
RUNNING REPAIR
CYLINDER LINER ,
HEAD GASKET ,
HILL SITE PO DONE TO SOME PARTS RECEIVED &
AL BS-3 NL02Q 006 & PISTON & RING SET , DISMANTLE
10 (NEW 29-04-2025 MN/277 HO-381 NARAYANI TRADING FITMENT PROCESS
TIPPER 8721 007 CR BEARING , VALVE DONE
CAMP) COMPANY STARTED
OIL SEAL & ETC ARE
DAMAGE

AL BS-6 MN05C GEAR BOX NOISY ON DISMANTLE GEARBOX PREPARING THE INDENT
11 NEW CAMP 23/05/2025 66-69
TIPPER 3745 APPLYING GEARS DONE DISMANTLED LIST

PO DONE TO MAX DG
MAHINDRA N2A20A24 ALTERNATOR DISMANTLE GUWAHATI - PART DISPATCHED
12 NEW CAMP 06/04/2025 13 MN/310 HO-389
10KVA DG 519 BURND DONE MATERIAL (NETWORK - NICCN07655)
DISPATCH SOON
PO DONE TO MAX DG
MAHINDRA N2P21A17 ALTERNATOR DISMANTLE GUWAHATI - PART DISPATCHED
13 NEW CAMP 06/04/2025 13 MN/310 HO-389
10KVA DG 696 BURND DONE MATERIAL (NETWORK - NICCN07655)
DISPATCH SOON
114
DG Set NOZZLE ABNORMAL
14 NEW CAMP 000000006 12/05/2025 STARTING ISSUE SENT TO LOCAR REPAIR
62.5kva SPRAY
77

PICKUP ISSUES &


HEAD GASKET , CR
BEARING , LINER , AS PER DEALER ONE CATALYTIC
MAHINDRA
SHOWROO 1618 & PISTON , THRUST DISMANTLE NEED TO CHANGE CONVERTOR IS IN OUR
15 BS-6 NL0D 7655 31/03/2025 MN/2394 HO-2909
M 1619 WASHER , VALVE OIL DONE CATALYTIC STOCK, ARRANGING TO FIT
CAMPER
SEAL & PULLY CONVERTOR THE SAME
DEMPER ARE
DAMAGE
KEYSTONE INFRA PVT LTD.
DAILY BREAKDOWN REPORT AS ON MAY -26-05-2025

SL Fixed Indent Focus Action & Expact Date


Location Reg No B/D Start Po No Reason For BD Present Status REMARKS
NO Assets No Indent No Rectification To Be Ready

Kleeman
CONE BREAKDOWN,
Mobile SEKMAI
1 K0720048 21/05/2025 60 - 62 MN/659 PULLEY, BELT AND WAITING FOR PO
Crusher - CRUSHER
TENSIONER
Cone

ENGINE HEATING ISSUE


PO DONE TO SHANTHI PARTS DISPATCHED THROUGH
PC-210- N710361 - , PILOT LEVER FUCTION DISMANTLE
2 NEW CAMP 16/04/2025 1695 MN/283 HO-392 TRADING - PAYMENT IN NATIONAL CARRIYING CORP.
08MO 19 NOT WORKING DONE
PROCESS (RLY/00184)
PROPERLY
3 ITEMS DISPATCHED 09-05-
BREAKER SEAL KIT ,
PO DONE TO KSAR 2025 (RECEIVED) & 2 ITEMS
KOMATSU HO- 234 BUSH , CHISEL BUSHING
1364 & DISMANTLE ERATHMOVERS & DISPATCHED 13-05-2025(PO -
3 BREAKER NEW CAMP JH 350 01/05/2025 MN/2185 & HO- , PLUG , RETAINER BAR ,
1365 DONE INDUSTRIAL SPARES & I HO 234)
PC-300 239 STOPER PIN ETC ARE
EQUIP CORPORATION & PO - HO 239 ITEMS NOT
DAMAGE
DISPATCHED
Mitsubishi
NEW ARTICULATE CYL. LEAK, SEAL KIT, KING PIN, KING
4 MOTOR MN 01 9723 16/05/2025 33 MN/444 WAITING FOR PO
CHECKON KING PIN DAMAGE PIN BEARING REQUIRED
GRADER

CHECKON MN05C ENGINE ECU NOT DISMANTLE FITMENT TO BE DONE BY SERVICE CHARGE QUOTATION
5 JCB BS-4 17/04/2025 FOR WORK ORDER SUBMITTED
SITE 3982 WORKING DONE MA & MA

SOME HYDRAULIC
HOSE PIPE LEAKAGE ,
1658 PO DONE TO KSAR
PICK UP ISSUE , BREAK DISMANTLE PARTS DISPATCHED ON 20-05-
6 JCB BS-3 NEW CAMP MN01 9722 10/04/2025 TO MN/197 HO-406 EARTH MOVERS -
SYSTEM NOT WORKING DONE 2025 (BHAWANI ROADLINES)
1663 PAYMENT IN PROCESS
PROPERLY & KING PIN
ARE DAMAGE

AL BS-6 MN05C DISMANTLE SYNCRO RING AND OTHER


7 NEW CAMP 18/05/2025 42 MN/443 GEAR BOX NOISY WAITING FOR PO
TIPPER 4109 DONE PARTS ORDERED
LOAD BODY DAMAGE , C CHANNEL , MS PLAIN
HILL SITE 004& HO-380 TYRE , BATTERY , SHEET , MS SQUARE PIPE GEAR BOX FITMENT DONE &
AL BS-3 NL02Q MN/276 DISMANTLE FEBRICATION MATERIAL PO
8 (NEW 11/04/2025 005 & HO- DENTING WORK , GEAR - MATERIAL
TIPPER 8726 MN282 DONE UNDER PROCESS
CAMP) 008 365 BOX SPARES & REQUIREMENTS INDENT
RUNNING REPAIR RISED
LOAD BODY DAMAGE ,
HILL SITE
AL BS-3 NL02Q TYRE , BATTERY , DISMANTLE NEW DALA BODY
9 (NEW 25/04/2025 27/05/2025 WORK IS IN PROGRESS
TIPPER 8642 DENTING WORK & DONE MAKING UNDER PROCESS
CAMP)
RUNNING REPAIR
CYLINDER LINER ,
HEAD GASKET , PISTON
HILL SITE
AL BS-3 NL02Q 006 & & RING SET , CR DISMANTLE PO DONE TO NARAYANI SOME PARTS RECEIVED &
10 (NEW 29-04-2025 MN/277 HO-381
TIPPER 8721 007 BEARING , VALVE OIL DONE TRADING COMPANY FITMENT PROCESS STARTED
CAMP)
SEAL & ETC ARE
DAMAGE
AL BS-6 MN05C GEAR BOX NOISY ON DISMANTLE
11 NEW CAMP 23/05/2025 66-69 GEARBOX DISMANTLED PREPARING THE INDENT LIST
TIPPER 3745 APPLYING GEARS DONE

PO DONE TO MAX DG
MAHINDRA N2A20A24 DISMANTLE PART DISPATCHED (NETWORK
12 NEW CAMP 06/04/2025 13 MN/310 HO-389 ALTERNATOR BURND GUWAHATI - MATERIAL
10KVA DG 519 DONE - NICCN07655)
DISPATCH SOON

PO DONE TO MAX DG
MAHINDRA N2P21A17 DISMANTLE PART DISPATCHED (NETWORK
13 NEW CAMP 06/04/2025 13 MN/310 HO-389 ALTERNATOR BURND GUWAHATI - MATERIAL
10KVA DG 696 DONE - NICCN07655)
DISPATCH SOON

114
DG Set NOZZLE ABNORMAL SPRAY SENT TO LOCAR REPAIR
14 NEW CAMP 000000006 12/05/2025 STARTING ISSUE
62.5kva
77

PICKUP ISSUES & HEAD


GASKET , CR BEARING ,
MAHINDRA LINER , PISTON , AS PER DEALER NEED TO ONE CATALYTIC CONVERTOR IS
SHOWROO 1618 & DISMANTLE
15 BS-6 NL0D 7655 31/03/2025 MN/2394 HO-2909 THRUST WASHER , CHANGE CATALYTIC IN OUR STOCK, ARRANGING TO
M 1619 DONE
CAMPER VALVE OIL SEAL & CONVERTOR FIT THE SAME
PULLY DEMPER ARE
DAMAGE
KEYSTONE INFRA PVT LTD.
DAILY BREAKDOWN REPORT AS ON MAY -27-05-2025
SL Fixed Indent Focus Action & Expact Date
Location Reg No B/D Start Po No Reason For BD Present Status REMARKS
NO Assets No Indent No Rectification To Be Ready
Kleeman
CONE BREAKDOWN,
Mobile SEKMAI
1 K0720048 21/05/2025 60 - 62 MN/659 PULLEY, BELT AND WAITING FOR PO
Crusher - CRUSHER
TENSIONER
Cone

ENGINE HEATING ISSUE , PO DONE TO SHANTHI PARTS DISPATCHED THROUGH


PC-210- N710361 - DISMANTLE
2 NEW CAMP 16/04/2025 1695 MN/283 HO-392 PILOT LEVER FUCTION TRADING - PAYMENT IN NATIONAL CARRIYING CORP.
08MO 19 DONE
NOT WORKING PROPERLY PROCESS (RLY/00184)

BREAKER SEAL KIT ,


PO DONE TO KSAR CHISEL, ISOLATOR STOPPER
KOMATSU HO- 234 BUSH , CHISEL BUSHING ,
1364 & DISMANTLE ERATHMOVERS & RECEIVED (PO - 234)
3 BREAKER NEW CAMP JH 350 01/05/2025 MN/2185 & HO- PLUG , RETAINER BAR ,
1365 DONE INDUSTRIAL SPARES & I & PO - HO 239 ITEMS
PC-300 239 STOPER PIN ETC ARE
EQUIP CORPORATION NOT DISPATCHED
DAMAGE

Mitsubishi
NEW ARTICULATE CYL. LEAK, SEAL KIT, KING PIN, KING
4 MOTOR MN 01 9723 16/05/2025 33 MN/444 WAITING FOR PO
CHECKON KING PIN DAMAGE PIN BEARING REQUIRED
GRADER

CHECKON MN05C ENGINE ECU NOT DISMANTLE FITMENT TO BE DONE BY SERVICE CHARGE QUOTATION
5 JCB BS-4 17/04/2025
SITE 3982 WORKING DONE MA & MA FOR WORK ORDER SUBMITTED

SOME HYDRAULIC HOSE


1658 PIPE LEAKAGE , PICK UP PO DONE TO KSAR EARTH
DISMANTLE PARTS DISPATCHED ON 20-05-
6 JCB BS-3 NEW CAMP MN01 9722 10/04/2025 TO MN/197 HO-406 ISSUE , BREAK SYSTEM MOVERS - PAYMENT IN
DONE 2025 (BHAWANI ROADLINES)
1663 NOT WORKING PROPERLY PROCESS
& KING PIN ARE DAMAGE

AL BS-6 MN05C DISMANTLE SYNCRO RING AND OTHER


7 NEW CAMP 18/05/2025 42 MN/443 GEAR BOX NOISY WAITING FOR PO
TIPPER 4109 DONE PARTS ORDERED

LOAD BODY DAMAGE ,


C CHANNEL , MS PLAIN
004& HO-380 TYRE , BATTERY , GEAR BOX FITMENT DONE &
AL BS-3 HILL SITE MN/276 DISMANTLE SHEET , MS SQUARE PIPE -
8 NL02Q 8726 11/04/2025 005 & HO- DENTING WORK , GEAR FEBRICATION MATERIAL PO
TIPPER (NEW CAMP) MN282 DONE MATERIAL REQUIREMENTS
008 365 BOX SPARES & RUNNING UNDER PROCESS
INDENT RISED
REPAIR

LOAD BODY DAMAGE ,


AL BS-3 HILL SITE TYRE , BATTERY , DISMANTLE NEW DALA BODY MAKING WELDING WORK COMPLETE,
9 NL02Q 8642 25/04/2025 29/05/2025
TIPPER (NEW CAMP) DENTING WORK & DONE UNDER PROCESS PAINTING JOB REMAINING
RUNNING REPAIR
CYLINDER LINER , HEAD
GASKET , PISTON & RING SOME PARTS RECEIVED &
AL BS-3 HILL SITE 006 & DISMANTLE PO DONE TO NARAYANI
10 NL02Q 8721 29-04-2025 MN/277 HO-381 SET , CR BEARING , VALVE FITMENT PROCESS STARTED, CON.
TIPPER (NEW CAMP) 007 DONE TRADING COMPANY
OIL SEAL & ETC ARE BUSH AND BEARING DISPATCHED
DAMAGE

AL BS-6 MN05C GEAR BOX NOISY ON DISMANTLE


11 NEW CAMP 23/05/2025 66-69 MN/709 GEARBOX DISMANTLED WAITING FOR PO
TIPPER 3745 APPLYING GEARS DONE
PO DONE TO MAX DG
MAHINDRA N2A20A245 DISMANTLE ALTERNATOR RECEIVED, WAITING
12 NEW CAMP 06/04/2025 13 MN/310 HO-389 ALTERNATOR BURND GUWAHATI - MATERIAL
10KVA DG 19 DONE FOR ENGG. FOR FITMENT
DISPATCH SOON
PO DONE TO MAX DG
MAHINDRA N2P21A176 DISMANTLE ALTERNATOR RECEIVED, WAITING
13 NEW CAMP 06/04/2025 13 MN/310 HO-389 ALTERNATOR BURND GUWAHATI - MATERIAL
10KVA DG 96 DONE FOR ENGG. FOR FITMENT
DISPATCH SOON
114
DG Set
14 NEW CAMP 000000006 12/05/2025 STARTING ISSUE NOZZLE ABNORMAL SPRAY SENT TO LOCAR REPAIR
62.5kva
77

PICKUP ISSUES & HEAD


GASKET , CR BEARING ,
MAHINDRA AS PER DEALER NEED TO CONFIRMATION FROM DALER
SHOWROO 1618 & LINER , PISTON , THRUST DISMANTLE
15 BS-6 NL0D 7655 31/03/2025 MN/2394 HO-2909 CHANGE CATALYTIC REQUIRED FOR THE FITMENT OF
M 1619 WASHER , VALVE OIL DONE
CAMPER CONVERTOR CATALYTIC CONVERTOR
SEAL & PULLY DEMPER
ARE DAMAGE
KEYSTONE INFRA PVT LTD.
DAILY BREAKDOWN REPORT AS ON MAY -28-05-2025

SL Focus Indent Action & Expact Date To


Fixed Assets Location Reg No B/D Start Indent No Po No Reason For BD Present Status REMARKS
NO No Rectification Be Ready

Kleeman Mobile CONE BREAKDOWN, PULLEY, BELT


1 SEKMAI CRUSHER K0720048 21/05/2025 60 - 62 MN/659 WIRTGEN QUOTATION RECEIVED PO UNDER PROGRESS
Crusher - Cone AND TENSIONER
PARTS DISPATCHED THROUGH
ENGINE HEATING ISSUE , PILOT LEVER DISMANTLE PO DONE TO SHANTHI TRADING -
2 PC-210-08MO NEW CAMP N710361 16/04/2025 1695 MN/283 HO-392 NATIONAL CARRIYING CORP.
FUCTION NOT WORKING PROPERLY DONE PAYMENT IN PROCESS
(RLY/00184)

BREAKER SEAL KIT , BUSH , CHISEL PO DONE TO KSAR CHISEL, ISOLATOR STOPPER
KOMATSU 1364 & HO- 234 & DISMANTLE RECEIVED (PO - 234)
3 NEW CAMP JTHB 350 01/05/2025 MN/2185 BUSHING , PLUG , RETAINER BAR , ERATHMOVERS & INDUSTRIAL
BREAKER PC-300 1365 HO-239 DONE & PO - HO 239 ITEMS
STOPER PIN ETC ARE DAMAGE SPARES & I EQUIP CORPORATION
NOT DISPATCHED
PO DONE TO KSAR
MITSUBISHI ARTICULATE CYL. LEAK, KING PIN
4 NEW CHECKON MN 01 9723 16/05/2025 33 MN/444 HO-589 ERATHMOVERS & INDUSTRIAL MATERIALS TO BE DISPATCHED
MOTOR GRADER DAMAGE
SPARES

DISMANTLE FITMENT TO BE DONE BY MA & SERVICE ASSISTANCE WITH SCAN


5 JCB BS-4 CHECKON SITE MN05C 3982 17/04/2025 ENGINE ECU NOT WORKING
DONE MA TOOL REQUIRED

SOME HYDRAULIC HOSE PIPE


1658 TO LEAKAGE , PICK UP ISSUE , BREAK DISMANTLE PO DONE TO KSAR EARTH PARTS DISPATCHED ON 20-05-
6 JCB BS-3 NEW CAMP MN01 9722 10/04/2025 1663 MN/197 HO-406 DONE MOVERS - PAYMENT IN PROCESS 2025 (BHAWANI ROADLINES)
SYSTEM NOT WORKING PROPERLY &
KING PIN ARE DAMAGE
DISMANTLE SYNCRO RING AND OTHER PARTS QUOTATION RECEIVED,
7 AL BS-6 TIPPER NEW CAMP MN05C 4109 18/05/2025 42 MN/443 GEAR BOX NOISY DONE ORDERED COMPARISON UNDER PROGRESS

LOAD BODY DAMAGE , TYRE , C CHANNEL , MS PLAIN SHEET , MS GEAR BOX FITMENT DONE &
HILL SITE (NEW 004& 005 MN/276 DISMANTLE
8 AL BS-3 TIPPER NL02Q 8726 11/04/2025 HO-507 BATTERY , DENTING WORK , GEAR SQUARE PIPE -PO DONE TO STEEL FEBRICATION MATERIAL PO
CAMP) 008 MN282 DONE HOUSE
BOX SPARES & RUNNING REPAIR UNDER PROCESS

LOAD BODY DAMAGE , TYRE ,


HILL SITE (NEW DISMANTLE NEW DALA BODY MAKING UNDER WELDING WORK COMPLETE,
9 AL BS-3 TIPPER NL02Q 8642 25/04/2025 BATTERY , DENTING WORK & 29/05/2025
CAMP) DONE PROCESS PAINTING JOB UNDER PROGRESS
RUNNING REPAIR

CYLINDER LINER , HEAD GASKET , SOME PARTS RECEIVED &


HILL SITE (NEW DISMANTLE PO DONE TO NARAYANI TRADING
10 AL BS-3 TIPPER NL02Q 8721 29-04-2025 006 & 007 MN/277 HO-381 PISTON & RING SET , CR BEARING , FITMENT PROCESS STARTED, CON.
CAMP) DONE COMPANY
VALVE OIL SEAL & ETC ARE DAMAGE BUSH AND BEARING DISPATCHED

GEAR BOX NOISY ON APPLYING DISMANTLE


11 AL BS-6 TIPPER NEW CAMP MN05C 3745 23/05/2025 66-69 MN/709 GEARS DONE GEARBOX DISMANTLED AWAITING FOR QUOTATIONS

DISMANTLE
12 AL BS-6 TIPPER SEKMAI CRUSHER MN05C 4110 27/05/2025 FRONT CROWN PINION NOISY UNDER PROCESS CHECKING UNDER PROGRESS INDENT TO BE RAISED

MAHINDRA 10KVA DISMANTLE SERVICE PERSON WILL REACH SITE


13 NEW CAMP N2A20A24519 06/04/2025 13 MN/310 HO-389 ALTERNATOR BURND ALTERNATOR RECEIVED
DG DONE ON TOMORROW FOR FITMENT

MAHINDRA 10KVA DISMANTLE SERVICE PERSON WILL REACH SITE


14 NEW CAMP N2P21A17696 06/04/2025 13 MN/310 HO-389 ALTERNATOR BURND ALTERNATOR RECEIVED
DG DONE ON TOMORROW FOR FITMENT

114 SENT TO LOCAR REPAIR,


15 DG Set 62.5kva NEW CAMP 00000000677 12/05/2025 STARTING ISSUE NOZZLE ABNORMAL SPRAY AWAITING FOR TEST REPORTS
PICKUP ISSUES & HEAD GASKET , CR
CONFIRMATION FROM DALER
MAHINDRA BS-6 1618 & BEARING , LINER , PISTON , THRUST DISMANTLE AS PER DEALER NEED TO CHANGE
16 SHOWROOM NL0D 7655 31/03/2025 MN/2394 HO-2909 REQUIRED FOR THE FITMENT OF
CAMPER 1619 WASHER , VALVE OIL SEAL & PULLY DONE CATALYTIC CONVERTOR
CATALYTIC CONVERTOR
DEMPER ARE DAMAGE