0% found this document useful (0 votes)
7 views

Compound Wall Estimate Excel (1) (1) (1)

The document outlines the estimation for constructing a compound wall, detailing various construction activities including excavation, concrete work, brickwork, plastering, and fencing. It provides a breakdown of quantities, rates, and total costs associated with each item, culminating in an estimated total cost of 399,928.97 for a 30-meter length wall. The document serves as a comprehensive measurement sheet for the project, specifying materials and labor requirements.

Uploaded by

harshibabu07
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
7 views

Compound Wall Estimate Excel (1) (1) (1)

The document outlines the estimation for constructing a compound wall, detailing various construction activities including excavation, concrete work, brickwork, plastering, and fencing. It provides a breakdown of quantities, rates, and total costs associated with each item, culminating in an estimated total cost of 399,928.97 for a 30-meter length wall. The document serves as a comprehensive measurement sheet for the project, specifying materials and labor requirements.

Uploaded by

harshibabu07
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 15

COMPOUND WALL ESTIMATION

ABSTRACT

Sr.no

9
10

11

12

13

14
COMPOUND WALL ESTIMATION

ABSTRACT

Description

Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan) including dressing of sides and ramming of bottoms, lift upto 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. All kinds of soil.

Filling in plinth with sand under floors including watering,rammming,consolidating and dressing complete up to 10 ton

Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level : 1

Providing and laying in position specified grade of reinforced cement concrete excluding the cost of centering, shuttering, finishing and r

Reinforced cement concrete work in wall (any thickess), including attached pilasters, buttresses, plinthand string courses, fillets, coloumns

Reinforced cement concrete work in beams, suspended floor, roofs, having slope up to 15 landing, balconies, shelves, chajjas,lintels, bands,

Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth
level : Thermo-Mechanically Treated bars of grade Fe-500D or more.

Brick work using common burnt clay building brick having crushing strength not less than 35 kg/sq.cm. in foundation and plinth in
cement mortar 1:6 (1 cement :6 fine sand)(B) Conventional extra Brick work in super structure above plinth level up to two level
(B)Conventional 6.13+6.19 (2936.64+160.96)=3097.6

15mm cement plaster on the rough side of single or half brick wall of mix 1:6 ( 1 cement : 6 fine sand).
Finishig wall with water proffing cement paint of required shade :13.44.1 New work (Two or more coats applied @ 3.84 kg/10sq.m)

Provding and fixing concertina coil fencing with punched tap concertina coil 600 mm dia 10 metre openable length (total length 90 m )
having 50 nos rounds per 6 metre length , upto 3 m height of wall with existing angle iron 'Y' shape placed 2.4 m or 3.0 m apart and with
9 horizontal R.B.T. reinforced barbed wire, stud tied with G.I. staples and G.I clips to retain horizontal including necessary bolts or G.I
barbed wire tied to angle iron all complete as per direction of Engineer-in-charge with reinfoced barbed tape (R.B.T)/spring core (2.5
mm thick) wire of high tensile strength of 165 kg/sq.mm with tape (0.52 mm thick) and weight 43.478 gm/metre (cost of M.S angle, C.C.
structural steel work riveted bolted or welded in built up sections, trusses, fixing and position and applying a priming coat of approved
steel primer all complete

Painting with synthetic enamel paint of approved brand and manufacture to give an even shade : 13.61.1 Two or more coats on new
work

Centering and shuttering including strutting, propping etc. and removal of form for all heights :

Foundations, footings, bases of columns, etc. for mass concrete

Column,Piller, Piers, Abutment, post and struts

Lintel,beams,plinth beams, girders,bressumers and cantilievers.


Qty Rate Unit Amount

17.64 181.85 M3 3207.83

1.47 398.00 M3 585.06

1.47 5789.60 M3 8510.71

3.62 7718.25 M3 27964.18

4.04 9306.00 CUM 37619.51

3.02 9763.80 CUM 29457.63

1200.00 83.50 kg 100200.00

17.58 2709.67 CUM 47647.04

187.26 292.85 M2 54839.09


187.26 91.25 M2 17087.48

30.00 290.80 RMT 8724.00

72.00 101.75 KG 7326.00

3.20 121.55 M2 388.96

24.19 284.85 M2 6890.52

44.10 773.70 M2 34120.17

27.83 552.05 M2 15360.79

TOTAL 399928.97

Estimated cost of 30 m. 399928.97


Measurment sheet
considerering 30.00 M length
No of column @ 3.00 m C/C =30 /3.00+1 =11 nos of column
Item
Items No Length Breadth Depth
no
Earthwork in foundation excavation
1
up to 1.5m depth.
for Column footing 9 1.20 1.20 1.20
for extra column pad 1 1.45 1.20 1.20

2 Filling in plinth with sand under floor

in footing 9 1.20 1.20 0.10


for extra column pad 1 1.45 1.20 0.10

Providing and laying in position


cement concrete of specified : 1:4:8 (1
3
cement : 4 fine sand : 8 graded stone
aggregate 40 mm nominal size)
for footing 9 1.20 1.20 0.10
for extra column pad 1 1.45 1.20 0.10

Providing and laying in position


4 specified grade of reinforced cement
concrete 1:1.5:3 (below plinth)

footing 9 1.00 1.00 0.25


column 9 0.35 0.35 0.75
H= 1.2-0.25-0.1-0.1= 0.75 m
for extra column pad footing 1 1.45 1.00 0.25
for extra column pad 1 0.70 0.35 0.75
reinforced cement concrete 1:1.5:3 in
5 column (above plinth)
above plinth level column 9 0.35 0.35 3.00
for double footing 2 0.35 0.35 3.00
reinforced cement concrete 1:1.5:3 in
6 beam
for plinth beam 10 2.65 0.23 0.38
11 column 10 span
for coping 10 2.65 0.23 0.12

Steel reinforcement for R.C.C. work, up


7 to plinth +column+beams @
100kg/cu.m

5.48+4.04+3.02=10.68 cu.m 1 10.68 100


8 Brick work in super structure in cement mortar 1:6
10 2.65 0.23 2.89
Total
15mm cement plaster on the rough
9 side of single or half brick wall of mix
1:6 ( 1 cement : 6 fine sand).
for wall 1x2 30.00 3.00
wall top 1x1 30.00 0.23
offect of wall 11x2 0.12 3
Total
ffing cement paint
10 of required shade :13.44.1 New work (Two or more coats applied @ 3.84 kg/10sq.m)
same as item no-10

tud tied with G.I.


11 staples and G.I clips to retain horizontal including necessary bolts or G.I barbed wire tied to angle iron a

1 1 30

ded in built up
12sections, trusses, fixing and position and applying a priming coat of approved steel primer all complete

10 1.6
wt @ 4.50 kg/m

paint of approved
13 brand and manufacture to give an even shade : 13.61.1 Two or more coats on new work

10 1.6 0.20
Centering and shuttering including
14 strutting, propping etc. and removal of
form for all heights :
Foundations, footings, bases of
A
columns, etc. for mass concrete
Foundation 9x4 1.00 0.25
Column 9x4 0.35 0.95
for extra column pad 1x2 1.45 0.25
1x2 1.00 0.25
column 1x2 0.70 0.95
1x2 0.35 0.95

Column,Piller, Piers, Abutment, post


B
and struts
column 9x4 0.35 3.00
for extra column pad 1x2 0.70 3
1x2 0.35 3.00

C
Lintel,beams,plinth beams, girders,bressumers and cantilievers.
Beam 10x2 2.65 0.38
coping 10x2 2.65 0.15
Quantity unit

15.55
2.09
17.64 M3

1.30
0.17
1.47 M3

1.30
0.17
1.47 M3

2.25
0.83

0.36
0.18
3.62 M3

3.31
0.74
4.04 M3

2.29

0.73 12.54
3.02 M3

1068.00 kg 10.68

17.58
17.58 cum

180.00
6.90
0.36
187.26 M2

187.26 M2

wire tied to angle iron all complete as per direction of Engineer-in-charge with reinfoced barbed tape (R.B.T)/spring cor

30.00 Rmt

el primer all complete

16.00 Rmt
4.50 370
72.00 kg

new work

3.20 M2
9.00
11.97
0.73
0.50
1.33
0.67
24.19 M2

37.80
4.20
2.10
44.10 M2

19.88
7.95
27.83 M2
ed barbed tape (R.B.T)/spring core (2.5 mm thick) wire of high tensile strength of 165 kg/sq.mm with tape (0.52 mm thic
of 165 kg/sq.mm with tape (0.52 mm thick) and weight 43.478 gm/metre (cost of M.S angle, C.C. blocks shall be paid sepa
M.S angle, C.C. blocks shall be paid separately)

You might also like