Erection of Assembly Erection of ESP Casing WMS (002)
Erection of Assembly Erection of ESP Casing WMS (002)
Date completed:
Ratan Singh
Start of work (date & time) 16 th oct 2023 @ 10:00 Expected duration of work: 15 th NOV 2023 @ 12:00
Scope of Works & S &H information received from site? √ Yes No
Risk assessment completed and reviewed? √ Yes No
Name of Contractor Performing Authority: Thermax ltd
This method statement describes the work procedure to be followed for Assembly & Erection of ESP (Electrostatic Precipitator)
Casing box up Phase-2 (Package-2). Nestle, Sanand.
2. SCOPE:
3. DETAILS OF MATERIAL:
At ground Assembly time- Length with nozzle<14.5mtr> width<8.692 mtr>Height<3.692 mtr> weight-14 ton
Dimensions after assembly along with Inlet and outlet nozzle
Length with nozzle<14.5 mtr> width<3.692 mtr>Height<8.910 mtr> weight-14 ton for vertically position.
Safety helmets, safety shoes, cotton hand gloves, safety goggles, leather hand Gloves.
Crane Positioning:
ESP
General work permit, height work, Hot work & Critical lifting work permit to be taken before starting the job by
performing authority.
All Tools & tackles to be used before starting the job once confirmed TPI done & Green tag has been either done or not
TPI certification hard copy also to be checked before commencing the job.
Before the work is started, a brief safety talk Shall be given on the scope of work and hazards associated with the work
to all the concerned for safety awareness.
Barricading of the work area shall be done by caution tape to avoid unauthorized persons entering the work area.
Ensure Safety compliance. (PPE’s, barricading, toolbox talk, medical fitness of operator, Test certificates (T.P.I.) of lifting
tools and tackles)
Description of work
9. ESP Casing Assembly & Erection.
Complete the water level of Bed with additional support for fixing if required.
Do the ground assembly of ESP casing column structure with Top girders, bottom girders, side panels, Nozzle, Collecting
PAGE \* MERGEFORMAT 9 | Page
Classification: Public
and Di-Emitting plate.
After welding work complete inspection work to be done for any leakage.
After inspection work complete fixing lifting hook for Erection work.
Sling fixing work at the assembled ESP Casing for the erection & guide rope will be fixed at ground on structure.
Properly fixing of tag line rope to control the assembled casing box up while lifting & erection.
Lifting of assembled casing for erection with Crane and 2 no’s Farhana will use for toeing & positioning vertical.
Lifting & positioning of assembled structure at top of base columns at 6-meter elevation.
Manpower will access by scaffold/man lift at 6-meter elevation for fastening bolts & welding to arrest ESP casing
structure at position.
After Securing the casing column properly, person will access through man lift for de slinging of structure and releasing
load from crane.
Supervisor shall ensure, during whole activity workers hand or any body part should be out of material that it could not
create any Injury to workers.
Avoid line of fire & flagman shall be deployed & area to be barricaded.
After completing the erection activity at nearby ESP area, ensure the Web sling & rope shall be removed from the
material.
Farhana/crane
What services will need to be ISOLATED…? (Electricity, Compressed Air, Hydraulics, Gravity, Springs, Other stored energy)
SERVICES TO BE ISOLATED: Not Applicable
if Face
Safety Reflective Eye Ear Protective Respiratory Respiratory Personal fall Protective
required Helmet
footwear vest protection
protection
protection gloves protection protection arrest system clothing
)
√ √ √ √
If using gloves or respiratory protection cotton mask or if any other, indicate type: Cut level 1 hand gloves