Excel Sched-VBA
Excel Sched-VBA
Content Outline
PAGE-1 : GENERAL INFORMATION
PAGE-2 : BILL OF QUANTITY
PAGE-3 : RESOURCE ALLOCATION
PAGE-4 : GANT CHART SCHEDULE
PAGE-5 : QUANTITY SCHEDULE
PAGE-6 : PHYSICAL % SCHEDULE
PAGE-7 : REVENUE SCHEDULE
PAGE-8 : MANPOWER SCHEDULE
PAGE-9 : MATERIAL SCHEDULE
PAGE-10 : EQUIPMENT SCHEDULE
PAGE-11 : MANPOWER COST SCHEDULE
PAGE-12 : MATERIAL COST SCHEDULE
PAGE-13 : EQUIPMENT COST SCHEDULE
PAGE-14 : SUB-CONTRACTOR COST SCHEDULE
PAGE-15 : GROSS BUDGET SCHEDULE
PAGE-16 : CASH-FLOW SCHEDULE
PAGE-17 : PAYMENT SCHEDULE
PAGE ONE : PROJECT INFORMATION
Project Name : Gidabo Lot II RMC Irrigation Devt. Project Schedule Start Date : Jan 01 2025 Holiday's
Client/Owner : Minister of Irrigation and Low land Schedule Duration :
Consultant : Ethiopian Engineering Corporation Schedule Finish Date : May 16 2025
Contractor : Ethiopian Construction Works Corporation Gant Time Scale 5-Days
Contract Amount Bef.VAT : Plan Time Scale 5-Days
Contract Amount W. VAT : Week Starts On : Thursday
Contract Duration : 360 Calendar Days Fiscal Year Start On : March
Contract Signing Date : Feb 13 2024
Contractual Commencement Date : Jan 01 2025
Contractual Completion Date : Feb 07 2025
Site Handover Date : Apr 01 2024
80.0% 80.0%
872,114.3 3.3%
40,000.0 0.2%
435,945.4 9.4%
364,553.1 1.4%
2,274,172.4 17.5%
3,756,997.4 19.8%
5,470,306.3 28.5%
Activity Auto
Finish Date
User Actual
Constraint Constraint Constraint Constraint Activity Auto Activity Auto
Type Application Date Date Start Date Finish Date
1/1/2025 1/6/2025
1/1/2025 1/7/2025
AUTO 1/20/2025 1/8/2025 1/16/2025
1/8/2025 1/15/2025
1/8/2025 1/12/2025
1/13/2025 1/19/2025
1/20/2025 1/22/2025
Work Shifts
Parameter Nr. Of
Parameter Reference Sheet Shift/Day
Value Shifts
Excavator 1 120 m3/hr 25 lit/hr 5,300 ETB/hr Common Excavation & Disposal up to 5km
Jack Hamer 1 18 m3/hr 26 lit/hr Common Excavation & Disposal up to 10km
Dozer 1 230 m3/hr 28 lit/hr Common Excavation & Disposal up to 15km
Grader 1 1680 m3/hr 18 lit/hr
Loader 1 14 lit/hr
Smooth Compactor 1 10 lit/hr
Sheep Foot Compactor 1 10 lit/hr
Work Crew Information
Direct
Primary Primary Resource Distance / Crew Norm Direct Material Direct Equipment
Unit Manpower Budget Cost Budget Rate
Resource Norm Unit/hr Grade Unit/hr. Cost Cost Cost
Site Engineer Forman Mason Carpenter Painter Barbender Daily Labor Driver
Direct Direct Direct Direct Direct Direct
Material Material Direct Material Direct Material Direct Material Equipment Equipment Equipment Equipment
Cement Sand Aggregate 01 Aggregate 02 Aggregate 03 Excavator Jack Hamer Dozer Grader
2
Direct Direct Direct Direct
Equipment Equipment Equipment Equipment
lblConstType lstConstType
lblConstDate txtUConstDate
lblKConstDate optFUConstDate
lblAConstDate txtAConstDate Enabled=Fals
e
lstConstType
txtUConstDat
e
optKConstDat
Enabled=False
e
txtConstDate Enabled=False
btnAdd Enabled=False
btnRemove Enabled=False
btnCancel Enabled=False
1 2 3 4 5 6 7 8 9 10
Activit Bill
Activity Activity Activity
CType UCDate KCDate y ID. Outline * Item WBS / Activity Description Dependency Start
Level Relationships Date
No. No.
1/22/2025 1 1 1 1 1 1 0
1/1/2025 0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
6.0 Days 1/6/2025 ### 1 1 0 0 0 0 0
0 0 0 0 0 0
7.0 Days 1/7/2025 1 1 1 0 0 0 0
0
2025/2026 2025/2026 2025/2026 2025/2026 2025/2026
Qtr-4 Qtr-4 Qtr-4 Qtr-4 Qtr-4
Planned Sub- Planned Own- Jan Jan Jan Jan Jan
Contract Force
Quantity Quantity Wk-1 Wk-2 Wk-3 Wk-3 Wk-4
6 days 6 days 6 days 6 days 2 days
### Mon 06 Sat 11 Thu 16 Tue 21 Wed 22
###
###
###
###
###
###
11,901.1 0
###
800.0 ###
980.0 ### 840.0 140.0
###
574.6 ###
3,221.2 ### 2,415.9 805.3
4,831.8 ### 4,831.8
6,442.4 ### 5,522.1 920.3
0 FALSE
Bill
Activity Project To-Date
Remaining
ID. Item WBS / Activity Description Contract Excuted
No. Amount Amount Contract Amount
No.
No.
2025/202
0
6
0 Qtr-4
Activity Gross ### Jan
Equipment Machinery
ID. Unit Capacity Work-
No. Description Days 0 Wk-1
### 6 days
### Mon 06
1 Crawler Dozer 0.00%
2 Motor-Grader 0.00%
3 Chain Excavator 0.00%
4 Wheel Excavator 0.00%
5 Wheel Loader 0.00%
6 Sheep Foot Compactor 0.00%
7 Smooth Compactor 0.00%
8 Dump Truck 0.00%
9 Shower Truck 0.00%
10 Fuel Truck 0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0 0 0 1 1 1 1 1 TRUE
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 43155.092 0
0 0 0 0 0 0 0 0 25893.055 0
0 0 0 0 0 0 0 0 39456.323 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 10067.723 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 4495.3221 0
0 0 0 0 0 0 0 0 2472.4272 0
0 0 0 0 0 0 0 0 7875.8043 0
0 0 0 0 0 0 0 0 6742.9832 0
0 0 0 0 0 0 0 0 11813.706 0
0 0 0 0 0 0 0 0 5619.1526 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 449.53221 0
0 0 0 0 0 0 0 0 158041.12 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 158041.12 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 34524.074 0
0 0 0 0 0 0 0 0 6473.2638 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 5178.6111 0
0 0 0 0 0 0 0 0 6904.8148 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 8631.0184 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 5178.6111 0
0 0 0 0 0 0 0 0 5075.0388 0
0 0 0 0 0 0 0 0 71965.432 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 71965.432 0
0 0 0 0 0 0 0 0 230006.55 0
0 0 0 0 0 0 0 0 -230006.6 0
0 0 0 0 19487212 17656662 14957852 28808857 80910584
0 0 0 0 0 0 0 0 0
0 0 0 0 19487212 17656662 14957852 28808857 80910584
0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 245700
0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0
0 0 0 0 571200 388800 0 0 0
0 0 0 0 7321.0909 3003.5909 237.8182 0 960000
0 0 0 0 196560 49140 0 0 0
0 0 0 0 0 0 0 0 4921.875
0 0 0 0 775081.09 440943.59 237.8182 0 1210622
0 0 0 0 0 0 0 0 0
0 0 0 0 662258.24 581776.88 502366.55 2026651 3773053
0 0 0 0 827.9908 443.71932 73.917776 4713.788 6059.4159
0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 34398
0 0 0 0 0 0 0 0 34398
0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0
0 0 0 0 4768.2593 4188.7935 3617.0391 14591.887 27165.979
0 0 0 0 99.358896 53.246319 8.8701331 565.65456 727.12991
0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0
0 0 0 0.4553589 451934.24 352203.17 268837.55 1913834 1703507
0 0 0 1.4553589 14064883 13287195 12420265 26293749 60684941
0 0 0 -1.455359 5422329 4369467 2537587 2515108 20225643
"Start Milestone (SMS)"
"Start Milestone (SMS)"
"Finish Milestone (FMS)"
"Finish Milestone (FMS)"
'------ '------
"Must Start On (MSO)"
"Must Start On (MSO)"
"Start No Later Than (SNLT)"
"Start No Later Than (SNLT)"
"Start No Earlier Than "Start No Earlier Than
(SNET)" (SNET)"
"Start As Late As Possible "Start As Late As Possible
(SALAP)" (SALAP)"
'------ '------
"Must Finish On (MFO)"
"Must Finish On (MFO)"
"Finish No Later Than (FNLT)"
"Finish No Later Than (FNLT)"
'------ '------
ConstraintMap = 1
"Start Milestone (SMS)","Finish Milestone (FMS)","Start No ConstraintMap = 3
Later Than (SNLT)"
"Start Milestone (SMS)","Finish Milestone (FMS)","Start No ConstraintMap = 5
Later Than (SNLT)","Start No Earlier Than (SNET)"
"Start Milestone (SMS)","Finish Milestone (FMS)","Start No
Later Than (SNLT)","Start No Earlier Than (SNET)","Start As ConstraintMap = 7
Late As Possible (SALAP)"
"Start Milestone (SMS)","Finish Milestone (FMS)","Start No
Later Than (SNLT)","Start No Earlier Than (SNET)","Start As ConstraintMap = 2
Late As Possible (SALAP)","Must Finish On (MFO)"
Later Than (SNLT)","Start No Earlier Than (SNET)","Start As ConstraintMap = 4
Late As Possible (SALAP)","Must Finish On (MFO)","Finish No
"Start Milestone (SMS)","Finish Milestone (FMS)","Start No
Later Than (SNLT)","Start No Earlier Than (SNET)","Start As ConstraintMap = 6
Late As Possible (SALAP)","Must Finish On (MFO)","Finish No
"Start Milestone
Later Than (SMS)","Finish
(FNLT)","Finish Milestone
No Earlier Than(FMS)","Start
(FNET)" No
Later Than (SNLT)","Start No Earlier Than (SNET)","Start As
Late As Possible (SALAP)","Must Finish On (MFO)","Finish No ConstraintMap = 8
Later Than (FNLT)","Finish No Earlier Than (FNET)","Finish As
Late As Possible (FALAP)"
"Start Milestone (SMS)","Finish Milestone (FMS)","Start No
Later Than (SNLT)","Start No Earlier Than (SNET)","Start As
Late As Possible (SALAP)","Must Finish On (MFO)","Finish No ConstraintMap = 0
Later Than (FNLT)","Finish No Earlier Than (FNET)","Finish As
Late As Possible (FALAP)","As Early As Possible (AEAP)"
"Start Milestone (SMS)","Finish Milestone (FMS)","Start No Later Than (SNLT)","Start No Earlier Than (SNET)","Start As Late As
an (SNET)","Start As Late As Possible (SALAP)","Must Finish On (MFO)","Finish No Later Than (FNLT)","Finish No Earlier Than (FNET)","Finis
Earlier Than (FNET)","Finish As Late As Possible (FALAP)","As Early As Possible (AEAP)"