Part 2 - Process Progress Check
Part 2 - Process Progress Check
C. Ask the team to estimate the effort and build the business case
accordingly.
D. Meet with product owner, team, and SMEs to define the
minimum viable product (MVP).
2.1.3 9. A company is losing market share to competitors with new business
models. The agile team is asked to restrict the number of features of
a product and release a version more quickly to the market.
The project manager needs to ensure that the review of the plan is
completed on time.
B. Follow the initial project plan, recognizing that the sponsor is the
key stakeholder and the new committee members work in a
lesser capacity.
C. Schedule a low-key introductory meeting with the new steering
committee and the team, while continuing to follow the initial
project plan.
D. Ensure that the new steering committee members receive the
project’s current status report.
2,2 14. In response to slippage on some scheduled tasks, the project
manager reprioritized a number of subsequent tasks to try to fix the
problem.
This did NOT work, so the project manager needs to escalate the
issue.
Which two (2) items will the project manager need to consult?
(Choose TWO.)
A. Change management plan
B. Stakeholder engagement plan
C. Communications management plan
D. Risk management plan
E. Configuration management plan
2,2 15. A governmental agency becomes a key stakeholder on a complex
project due to regulatory changes. In light of the change, the project
manager needs to develop an understanding of this new
stakeholder and identify any new high-level risks that may result
from the change.
Which two options should the project manager use? (Choose TWO.)
A. Schedule meetings with the new stakeholders.
B. Update the assumption log.
C. Revise the stakeholder engagement plan.
D. Check the risk management plan.
E. Update the project charter.
2,2 16. A project team has set up an unofficial online communications
platform to enhance communication.
The project manager was NOT aware that this platform existed until
Page 7 of 53
recently, after learning that its use has facilitated some activity that a
stakeholder finds concerning.
The project manager was NOT previously aware of the blog but has
discovered that team members are using it inappropriately. It has
caused some offense.
2,3 23. A project is at the planning stage. The project manager realizes that
producing a complex, multi-functional application is NOT feasible
with the current number of resources and decides to hire more
resources for the production of the application. The project
manager identifies and contracts temporary resources.
The project manager decides the best way to manage this risk is to
deliver all heavy equipment themselves, despite the significant
added expense.
Risk
Probability
Impact
A 1 5
B 4 4
C 2 5
D 2 2
Based on the table, in what order should the project manager rank
these risks for risk management purposes?
A. B, A, D, C
B. B, C, A, D
C. B, A, C, D
D. C, D, A, B
2,3 28. Prior to preparing a monthly project status report, a project team
brings three risks to the project manager’s attention.
SECTION 2
2,3 1. A company wants to reduce future operating costs by installing solar
panels on the facility being built by using a local government subsidy
for energy-efficient projects. They have NOT yet applied for the
subsidy.
Where should the project manager document this in the project charter?
A. As part of high-level requirements
B. In the key stakeholder list
C. In the overall project risks
D. As part of the resource management plan
2,3 3. A project manager implemented an approved change to manage a risk.
Three (3) months after the implemented change, the project manager
learns that the change did NOT produce the desired result, instead
producing negative consequences.
How can the project manager avoid this problem on future projects?
A. Update the probability and impact matrix after assessing any new
risks.
B. Revisit or change existing assumptions after reviewing the
assumption log.
C. Update the lessons learned register with the risk information.
Page 14 of 53
There is a 22% buffer in the project budget for cost overruns, but only
three (3) weeks left in the schedule.
Risk
Probability
Page 16 of 53
Impact
A
3
5
B
4
2
C
3
3
D
2
2
Based on the table, in what order should the project manager rank these
risks for risk management purposes?
A. A, C, B, D
B. B, A, D, C
C. C, D, A, B
D. D, A, C, B
2,3 10. While a project manager is preparing the monthly project status report,
four (4) new risks are identified. These four (4) risks could affect key
milestones.
What should the project manager do before presenting this new risk
information?
A. Review the risk report and lessons learned repository.
B. Review the organizational process assets and risk register.
C. Refer to the risk management plan and the risk report.
D. Add risks to the risk register, analyze them for impact to the project
and identify response plans.
2,3 11. Project C is a partnership between a major city and a government
contractor. Each of these entities have a different risk threshold, so it is
Page 17 of 53
the project manager’s role to ensure a risk approach that will satisfy
both parties. Project C has a realistic schedule and an adequate budget;
however, the project manager worries that unplanned events could
threaten the project’s success and cause the city sponsor to be
concerned.
Where should the project manager document this request in the project
charter?
A. Key stakeholder list
B. Overall project risks
Page 18 of 53
C. High-level requirements
D. Work exclusions
2,3 14. After missing two (2) consecutive major deadlines because of delayed
glass deliveries, a manufacturing company changes its glass supplier to
meet production deadlines. Three (3) months later, production reports
quality problems with the new glass. The project manager determines
that the supplier change caused quality problems.
How should the project manager avoid this issue in the future?
A. Update the risk information to the lessons learned register.
B. Review the assumption log to revisit or change current assumptions.
C. Confirm that an implemented risk response is effective.
D. Evaluate new risks and update the probability and impact matrix.
2,4 15. A project manager realizes that stakeholder interests will conflict on a
project and decides to utilize a stakeholder engagement assessment
matrix.
How should the project manager obtain approval of the project charter?
A. Conduct a stakeholder analysis.
B. B. Use facilitation and conflict management techniques to help the
three (3) stakeholders find consensus.
C. Request that the project sponsor resolve the conflict.
D. Use the project kick-off meeting to settle the project goals.
2,4 19. A small group of users complains during a project’s user acceptance
stage, stating that their expectations are NOT met.
learns that one stakeholder is ill and needs to decrease their level of
involvement.
Which two approaches should the project manager take? (Choose TWO.)
A. Assess and categorize these stakeholders using the Salience model.
B. Invite these stakeholders to team meetings to assure them that the
project team takes their work seriously.
C. Send a questionnaire out to this stakeholder group, asking about
their needs.
D. Share the stakeholder engagement matrix with the team.
Page 21 of 53
2,4 23. A company is struggling to define the scope of a new project that has
multiple phases with a high level of dependency between the phases.
Which two of the product owner’s meetings could the project manager
deprioritize so that they attend less frequently? (Choose TWO.)
A. Sprint retrospectives
B. Product SME consultations
C. Daily stand-up meetings
D. Team performance reviews
E. End-user feedback sessions
2,5 25. A deliverable on the project's critical path is behind schedule.
The cost performance index (CPI) is 1.3. The project manager is able to
put the project back on schedule.
Which three results are the most likely for this project? (Choose THREE.)
A. Activities will be performed in parallel.
B. Project scope will be revised.
C. Associated risks will increase.
D. Costs will increase.
E. The team should expect rework.
2,5 26. A project that should have been 90% complete by now is only 65%
complete. The total project budget is US$120,000 and the actual cost
spent to date (AC) is US$80,000.
Page 22 of 53
SECTION 3
2.5.2 1. Over the past six months, the cost per story in agile project A has risen
by more than 250% due to a faulty platform which is no longer
supported. The project will exceed the budget increment threshold at
the next iteration.
The project manager has verified that the component work packages
have been defined, and constraints for each component have been
identified.
2,6 4. A project manager is uncertain about the duration of a new project and
consults several groups of subject matter experts (SMEs). The first group
advises that development can be finished in 29 days. The second group
identifies some risks that could make the duration up to 46 days. The
third group proposes a new development method that can shorten the
time to 18 days.
What is the estimated development duration for the new product using
the Beta estimation technique?
A. 12 days
B. 16 days
C. 14 days
D. 20 days
2.6.1 6. A trend of stories is INCOMPLETE, and this becomes apparent at the end
of iterations. Several team members worked on these stories and NO
blockers were identified.
D. Work with the product owner to further break down the stories in the
backlog and update the Definition of Ready.
2.6.3 7. A project manager is visiting a software supplier's office. Some of the
sights are surprising: two people per workstation, estimations based on a
deck of cards, developers forcing their tests to fail, and routines with
names such as "traffic cop" and "ringleader".
In which three ways can the work be distributed for efficient execution?
(Choose THREE.)
A. Track readiness status to help the team initiate tasks at the right time.
B. Set deadlines to ensure that the team completes the work in
acceptable limits.
C. Use a task board to group tasks into rows and track progress across
columns.
D. Maintain a to-do task pool to limit the number of tasks in progress.
E. Pre-identify blockers to determine the order of execution.
2.6.3 9. Two start-up companies have merged, and now more than 100
developers on eight agile teams are working on a common portfolio.
How can the project manager forecast the completion date with more
accuracy and certainty?
A. Ensure upcoming backlog items are elaborated in more detail with
the team.
B. Educate the executive committee on the flexible nature of agile
planning.
C. Plan for variable-size iterations according to story complexity and
load.
D. Reduce frequency of the progress reports sent to senior stakeholders.
2.6.4 11. An ongoing agile project is measured as follows:
2-
Stories Stories Planned Earned
week
Planned Completed Value Value
Sprint
1 15 10 450K 300K
2 20 18 600K 540K
3 20 25 800K 1000K
4 22 25 1100K 1250K
Totals 77 78 2950K 3090K
According to the table, which two of the following are the project's
metrics? (Choose TWO.)
A. SPI = 0.98
B. CPI = 1.05
C. CPI = 1.30
D. SPI = 1.01
E. CPI=0.95
2.6.6 12. A start-up has grown quickly, and there are now four (4) agile teams
working on interrelated products. All teams have begun to experience
impediments and gaps related to work in other teams.
Which two measures would most effectively enable the teams to better
synchronize their deliveries? (Choose TWO.)
A. Alter the story size to ensure more complete integration to the IT
build requirements.
B. Use the IT predictive schedule to limit the features the software team
starts to develop.
C. Create a common Kanban board to queue and track progress of both
teams' deliverables.
D. Break down IT work packages into more granular tasks to align to the
software releases.
E. Define common milestones and an overall dependency network to be
used by both teams.
2.6.5 14. The IT integration team has a major setback in a hybrid project. Testing
has confirmed that the hardware does NOT support the target operating
system. The agile team's software releases must now run on a later
operating system version.
Which approach would be most effective to clear out these minor tasks
faster?
Page 29 of 53
A. Combine multiple minor tasks to make story sizes consistent with key
objectives.
B. Reprioritize the backlog to favor the smallest stories and re-assign
them daily.
C. Reprioritize the backlog on a daily basis so that recent triggers boost
story priority.
D. Integrate the small tasks to either the Definition of Done or
acceptance criteria.
2.6.3 16. A hybrid virtual reality project is running an agile software track and a
predictive electronics track. Halfway into the project, delays are
accumulating due to misaligned deliverable releases between the two
tracks.
Which tool or technique can the project manager use for this task?
A. Scatter diagram
B. Affinity diagram
C. Control chart
D. Histogram
2,7 18. A project has the following characteristics:
Given these findings, which agile practice would most effectively prevent
the problem?
A. Acceptance Test-Driven Development
B. Smoke Testing
C. Behavior-Driven Development
Page 32 of 53
In which two ways can the project manager help the agile teams improve
their work? (Choose TWO.)
A. Perform root-cause analysis in the next retrospectives.
B. Influence the product owners to right-size their portfolios.
C. Organize dedicated teams to reduce context-switching.
D. Appoint dedicated test teams to offload the agile teams.
E. Train the agile teams to improve time and focus management.
2.7.3 26. The agile team surpassed the planned number of stories in the last three
agile iterations.
How can the project manager be sure all the work performed is truly
complete?
A. Ask the product owner if results are satisfactory.
B. Check results against the Definition of Done.
C. Ask the team to cross-check other members' work.
D. Check the results of all the tests performed.
2.8.1 27. An empowered agile team showed impressive progress in the first four
iterations, but now the product owner has noticed low output in the
latest five iterations without any apparent reason.
Which two tools or techniques should the project manager use? (Choose
TWO.)
A. Prototypes
B. Expert judgment
C. Product analysis
D. Create requirements traceability matrix
2,8 30. A client brings a project manager into a project during the project's
execution stage.
The project manager reviews the project scope for cost estimating
purposes and notices that some deliverables were missed in the work
breakdown structure (WBS).
SECTION 4
2,8 1. Review the following project characteristics:
How should the project manager re-plan the project to support both
launches?
A. Use the contingency budget to cover sunken costs for the EU
launch and adjust plans for the non-EU launch.
B. Re-plan the project as a fully agile set of iterations and ensure that
fixed milestones are documented on the burn-down chart.
C. Plan analysis activities and tollgates for the EU launch and crash
the schedule for the non-EU launch.
D. Embed a set of iterations to analyze and develop the EU product,
while adjusting plans for the non-EU launch.
2.10. 17. A project manager recently joined a new project with the following
characteristics:
- Tight deadlines
- Global virtual team
- Fixed budget
During the planning stage, the project manager wants to avoid scope
creep and keep the team focused on delivering a product that meets
requirements.
2.10. 18. The project sponsor requests that an element of a product will be
swapped for the equivalent supplied by a local manufacturer in order
to have a more sustainable supply chain.
The project manager has updated the scope statement and schedule.
The vendor says that they will NOT correct the problem.
Before deciding on next steps, what should the project manager do?
A. Check the service level agreement (SLA) established with the
vendor.
B. Review the procurement management plan and contract
agreements.
C. Check the internal quality assurance reports.
D. Review the resource management plan and document lessons
learned.
2.11. 23. Near the end of a manufacturing project, several team members are
transferred to another project. To complete the work, the project
manager needs to acquire additional resource support from a new
supplier but is concerned about the cost risk of using a new supplier
at this advanced stage of the project.
Now, the project manager needs to work with the procurement team
to establish specifications and type of contract to be used.
2.11. 24. A deliverable does NOT meet the agreed-upon quality specifications
and is rejected by the customer. After investigation, the project team
finds a fault with the vendor-provided parts. This fault caused the
issue. The vendor says that they CANNOT correct the situation.
How could the two teams synchronize interactively but somewhat less
frequently?
A. Set up fishbowl windows at each site.
B. Add and execute a Scrum of Scrums layer.
C. Align iterations for common retrospectives.
D. Share a common electronic Kanban.
2.12. 27. A project team collected sensitive client data during the early stages
of a project to help develop the project management plan. The team
is now working on deliverables for the project when the compliance
manager discovers a data breach and alerts the team to a compliance
Page 43 of 53
issue.
What could the project manager use to avoid this issue in the future?
A. Stakeholder feedback
B. Risk assessments
C. Conflict management techniques
D. A professional relationship with the users
2.12.2 30. The Project Management Office wants to offer constant reporting
across the dozens of agile projects running concurrently. They want to
use information radiators to share progress status and key lessons
learned.
SECTION 5
Blueprint
QUESTIONS
ID
2,13 1. A project manager begins to prepare the project management
plan after receiving the project charter.
What next step should the project manager take in this scenario?
A. Utilize analogous estimating.
B. Seek advice from experts in the field.
C. Organize an initial kick-off call.
D. Request input from the project sponsor.
2.13.1 2. A new wildlife reserve project will have a staff of approximately 80
experts, builders, and logistics workers with exposure to various
safety risks. The project manager wants a scalable approach
combining flexibility and team dynamics with traditional safeguards.
2,13 4. Company P’s IT transformation project has three (3) deliverables, and
they have the following characteristics, according to the project team:
Which project lifecycle should the project manager use for this
project?
A. Select a fully agile project model, with a common user story and
three-week sprints.
B. Select a waterfall project model for deliverables, with firm
milestones and change control procedures.
C. Select a hybrid project model; position deliverable 2 as a single
agile sprint embedded in an overall waterfall project.
D. Select a hybrid project model; position deliverable 2 as a single
waterfall phase embedded in an overall agile project.
2,13 5. After six (6) iterations, significant variations have occurred to project
scope and schedule. These are due to the customer's technology
regulations and security policies, which are regularly reviewed. The
project manager suggests taking a new approach to the next
iteration to avoid possible delays.
problems for both teams. However, the agile team resolved their
problems a month before the malfunction.
What could the agile team have done to prevent the current
malfunction?
A. Deprioritized the stories impacted by information in the data
sheets
B. Asked the project sponsor to halt the project pending translation
corrections
C. Summarized their retrospective conclusions on information
radiators
D. Formally request a change of equipment supplier for the project
2.13.4 7. A consultant has advised an IT director to use a DevOps approach to
a migration project. The IT director wants to understand how the
necessary speed can be achieved in a safe way.
What should the prime contractor do to quickly close the deal, given
the new client requirements?
A. Subtract the parcel work from the quoted price and plan the
parcel as agile iterations paid based on time and materials.
B. Add a risk premium to the agreed price of the full works and add
a clause to renegotiate the new scope when it is fully defined.
C. Raise a change request to examine impact on scope and price and
close the deal when all information is available.
D. Exclude all work on the parcel from the project plan and pricing
and propose a separate contract when the scope becomes clear.
2.13.5 10. An innovative product fails to satisfy targeted consumers despite
significant investments in quality control and marketing campaigns.
Which agile practice would best prevent future failures of this nature?
A. Run continuous consumer usability testing on product releases.
B. Align objectives between the product owner and marketing.
C. Broaden the persona type definition of the target consumer.
D. Add more features and tests to the minimum viable product
(MVP).
2.13.4 11. An emergency vaccine roll-out project should be deployed to
vaccination centers as soon as confirmed locations are booked.
Factors such as delayed batch shipments, safety protocols, and target
age groups may block the deployment at the last minute. However,
the deployment process does NOT vary after passing the tollgate to
begin setup at a new location.
Which project approach would best support the goal to maximize the
number of centers deployed?
A. A fully predictive life cycle where each center deployment is a
phase subject to dependencies.
B. A set of agile deployment iterations embedded in a predictive set
of processes.
Page 49 of 53
How can the project manager accelerate the approvals and build
customer trust at the same time?
Page 50 of 53
What is Step 3?
A. The project manager should update the bid documents.
B. The project manager should obtain stakeholder acceptance.
C. The project manager should reassign the project team.
D. The project manager should reallocate the unused funds.
2,17 18. Review the following project characteristics:
Which three (3) documents should the project manager use for this
decision?
A. Final report, organizational process assets updates, and
procurement agreements
B. Procurement agreements, project document updates, and
organizational process assets updates
C. Procurement agreements, stakeholder engagement plan, and
organizational process assets updates
D. Final report, project document updates, and organizational
process assets updates
2,17 21. A project is completed, but the project manager and project team
members are being asked to do the following:
product a success.