ESTIMATE
ESTIMATE
DETAILED ESTIMATES
Item DESCRIPTION Qty. Unit Unit Cost Total Cost
1.0 GENERAL TECHNICAL REQUIREMENTS (Temporary Structure, Utilities and Services)
1.1 CONSTRUCTION SAFETY AND HEALTH PROGRAM 1.00 lot
A. Materials
Hard hat 30.00 pcs 395.00 11,850.00
Glove 90.00 set 200.00 18,000.00
garments 30.00 pcs 350.00 10,500.00
Signages 2.00 pcs 1,500.00 3,000.00
Facilities (water, sanitary, netc) 1.00 lot 16,000.00 16,000.00
59,350.00
EDC 86,057.50
2.0. SITEWORKS
2.1. CLEARING, GRUBBING AND WASTE DISPOSAL 840.00 sqm
A. Materials 0 0 0 0
B. Labor Cost
Foreman 3.00 man-days 800.00 2,400.00
Laborer 20.00 man-days 400.00 8,000.00
10,400.00
C. Equipment Cost
Crgo truck 16.00 hrs 1,000.00 16,000.00
Chainsaw 24.00 hrs. 800.00 19,200.00
Minor tools 10% 1,040.00
35,200.00
EDC 45,600.00 45,600.00
Area
Backfill for Total Floor Area (Main) 1.00 0.20 182.24 36.45
36.45
V= 96.97 cu.m.
Materials
Earth Fill 98.00 cu.m. 350.00 34,300.00
Spreading Utilize:
Foreman 1.00 man - days 800.00 800.00
Laborer 12.00 man - days 400.00 4,800.00
5,600.00
Output = 12.00 cu.m. per day
Duration = 2.99 say
Labor & Eqpt. Cost = 16,800.00
Compaction Utilize: V= 96.97 cu.m.
Materials
Coco Lumber 120.00 bd.ft. 25.00 3,000.00
Nylon String 4.00 roll 370.00 1,480.00
C.W. Nails 10.00 kgs 120.00 1,200.00
Material Cost 5,680.00
40% Labor Cost 2,272.00
Septic Tank
A. Top cover 0.00 kg
B. Floor 0.00 kg
C. Walls 0.00 kg
Summary - 183.00 - 347.00 3,982.50 kg
#1 G.I. Tie wire 119.00 kg
Summary of Materials
16mm Ø x 6m deformed bars 183.00 Lgs 560.00 102,480.00
10mm Ø x 6m deformed bars 347.00 Lgs 160.00 55,520.00
# 16 G.I. Wire 30.00 kgs 80.00 2,400.00
Material Cost 160,400.00
40% Labor Cost 64,160.00
V. Concrete Works
Mark Quantity Depth Width Length Volume
Column footings
CF1 12.00 0.30 1.20 1.20 5.18
Columns
C1 12.00 6.00 0.30 0.30 6.48
Wall Footing 1.00 0.15 0.40 85.50 5.13
Beams/ Concrete Gutter (0.25m x 0.35m)(average size) 1.00 0.35 0.25 76.00 6.65
Lintel Beam 1.00 0.20 0.15 22.50 0.68
Canopy 1.00 0.10 0.80 22.50 1.80
Corbel 2.00 0.50 0.30 0.60 0.18
Gutter 1.00 20.00 0.10 1.30 2.60
Flooring
Ground Floor 1.00 0.10 160.00 16.00
44.70
Materials
Cement, portland 402 bags 280.00 112,641.48
Sand, washed 22 cu.m. 380.00 8,492.81
Gravel, washed 45 cu.m. 650.00 29,054.35
Total material Cost 150,188.64
40% Labor Cost 60,075.46
Total Cost for CONCRETE WORKS 210,264.10
Summary of Materials
4" CHB 4,840 pcs 15.00 72,594.38
Cement, Portland 202 bags 250.00 50,525.69
Sand, washed 17 cu.m. 380.00 6,399.92
10mm Ø x 6m deformed bars 277.47 L 175.00 48,557.57
Tie wire (reflected in the 10.00 kgs 85.00 850.00
Material Cost 178,927.55
40% Labor Cost 71,571.02
Truss 1, n= 2
Particulars Description length pieces required total length
Exterior Frame Ð 2" x 2" x 5mm 6.00 2 12
vertical/diagonal web memberÐ 1.5" x 1.5" x 5.00 1 5
Truss 2, n= 2
Particulars Description length pieces required total length
Exterior Frame Ð 2" x 2" x 5mm 6.00 2 12
vertical/diagonal web memberÐ 1.5" x 1.5" x 6.00 1 6
Summary of materials
1,498.47 kg
Ð 2" x 2" x 5mm 12 pcs 620.00 7,440.00
Ð 1.5" x 1.5" x 5mm 11 pcs 460.00 5,060.00
10mm Ø x 6m plain round bar cross brace 11 pcs 220.00 2,420.00
10mm Ø x 6m plain round bar sagrod 5 pcs 220.00 1,100.00
1.5mm x 2" x 4" x 6m C - Purlins 38 pcs 795.00 30,210.00
5mm x 2" x 2" x 6m angle bar purlins cleats 2 pcs 620.00 1,240.00
12mm turn buckle 6 pcs 150.00 900.00
16mm Ø x 18" anchor bolt 32 pcs 125.00 4,000.00
6mm Ø x 25mm machine bolts 88 pcs 12.00 1,056.00
1/4"x1/4" Welded Screen Backing 3.13 sqm 100.00 313.00
Welding Rod 50.00 kgs 150.00 7,500.00
Red Lead Primer 5.00 gals 480.00 2,400.00
QDE Paint 5.00 gals 650.00 3,250.00
Paint Thinner 5.00 gals 275.00 1,375.00
Material Cost 68,264.00
40% Labor Cost 27,305.60
Prepainted
Rib Type Long Flashing
Span Galvanized Iron Roofing GA 24 in Grey Prepaint Finish, effective 36.00 ln. m 560.00 20,160.00
width 0.90m 180.00 ln. m 580.00 104,400.00
Blind rivets (100pcs) 50.00 boxes 75.00 3,750.00
Self drilling metal screw 1050.00 pcs 2.00 2,100.00
# 16 G.I. Wire 15.00 kgs 75.00 1,125.00
5mm THK Insulation 180.00 ln. m 65.00 11,700.00
Total material cost 143,235.00
35% Labor Cost 50,132.25
ARCHITECTURAL WORKS
15.0 CEILING WORKS 156.15 SQM
3.5mm thk Fiber Cement board = 156.15 sq.m. 156.15
Materials:
3.5mm thk Fiber Cement board 59.00 shts 400.00 23,600.00
12mm x 30mm x 5m Carrying Channel 28.00 pcs 150.00 4,200.00
W Clips 150 pcs 10.00 1,500.00
19mm x 50mm x 5m Metal Furring 197 lgth 150.00 29,550.00
Blind Rivets (1000pcs/box) 4 box 200.00 800.00 4,216.05
Flat Head Text Screw pcs 0.75 -
Material Cost: 59,650.00
Labor Cost: 26,842.50
Minor Tools: 1,342.13
EDC: 87,834.63
17.0 DOORS AND WINDOWS (including hardwares, acc. & fi 25.08 sqm
17.1 DOORS 11.76 sqm
Materials:
D-1 - Swing Door (2.1 sq.m.) 2.00 set 8,085.00 16,170.00 8085
D-1 - Swing Door (1.89 sq.m.) 4.00 set 7,276.50 29,106.00 7276.5
Material Cost: 45,276.00
Labor Cost: 20,374.20
Minor Tools: 1,018.71
EDC: 66,668.91
17.2 WINDOWS 13.32 sqm
Materials:
W-1 - Casement Window (0.96 sq.m.) 6.00 set 3,254.40 19,526.40 3254.4
W-2 - Awning Window (0.90 sq.m.) 2.00 set 3,015.90 6,031.80 3015.9
W-3 - Fixed Window (2.88 sq.m.) 2.00 set 6,825.60 13,651.20 6825.6
Material Cost: 39,209.40
Labor Cost: 17,644.23
Minor Tools: 882.21
EDC: 57,735.84
EDC: 124,404.75
ELECTRICAL WORKS
PLUMBING WORKS
Item NO. DESCRIPTION QTY UNIT UNIT PRICEMATERIAL COST
PLUMBING FIXTURES
3 Slop Sink 2 pcs 5,000.00 20,000.00
5 Urinal 2 pcs 4,000.00 8,000.00
11 Stainless Faucet 2 pcs 500.00 1,000.00
9 Floor Drain 6 pcs 500.00 3,000.00
TOTAL 32,000.00
LABOR 12,800.00
SUBTOTAL 44,800.00
WATERLINE PIPES AND FITTINGS
12 3/4" Ø PPR Gate Valve 1 pc 435.00 435.00
14 3/4 in Ø PPR Tee 9 pcs 45.00 495.00 973
15 3/4 in Ø PPR 90° elbow 18 pcs 40.00 900.00 643
16 3/4 in Ø PPR Coupling 10 pcs 35.00 500.00
17 1/2 in Ø PPR pipe 3 lgth (6m) 350.00 1,050.00 50
17 3/4 in Ø PPR pipe 2 lgth (6m) 435.00 870.00 50
TOTAL 4,250.00
LABOR 1,700.00
SUBTOTAL 5,950.00
SANITARY and WASTE WATER PIPES AND FITTINGS
18 4" (100mm) Ø cleanout 2 pcs 75.00 150.00
19 6" (150mm) Ø cleanout 2 pcs 75.00 150.00
20 3" (150mm) Ø cleanout 2 pcs 75.00 150.00
21 Stainless Floor Cleanout 4 pcs 300.00 1,200.00
22 150mm-100mm Ø PVC reducing wye 2 pcs 130.00 260.00
23 100mm PVC wye 7 pcs 130.00 910.00
24 150mm Ø PVC wye 2 pcs 130.00 260.00
26 100mm Ø PVC 90° Bend 7 pcs 130.00 910.00
27 150mm Ø PVC 45° Bend 3 pcs 130.00 390.00
28 100mm Ø PVC 45° Bend 7 pcs 130.00 910.00
29 150-100mm Ø PVC 45° Bend 2 pcs 130.00 260.00
30 4" PVC Ptraps for Floor Drains 4 pcs 200.00 800.00
33 3" 90 deg elbow 4 pcs 130.00 520.00
34 2" Brass P trap with cleanout for Lavatories 2 pcs 250.00 500.00
35 100mm-50mm PVC Sanitary wye 2 pcs 130.00 260.00
36 50mm Ø uPVC coupling 10 pcs 59.00 590.00
37 50mm Ø uPVC pipe x 6m L 2 L 1,000.00 2,000.00
38 100mm Ø uPVC pipe x 6m L 2 L 385.00 770.00
39 150mm Ø uPVC pipe x 6m L 2 L 385.00 770.00
40 75mm Ø uPVC pipe x 6m L 2 L 385.00 770.00
41 2" GI PIPE (6m) 2 L 1,200.00 2,400.00
TOTAL 14,930.00
LABOR 5,972.00
SUBTOTAL 20,902.00
CATCH BASINS 5mm thick x 4' x 8' Ordinary Ply
42 6" thk. CHB (500 PSI) 120 pcs 10.00 1,200.00
43 10mm Ø rebar 120 KG 176.00 21,120.00 3
44 Portland Cement (40kg) 52 bags 268.00 13,936.00 4
45 Sand 1.72 cu.m 280.00 481.60
46 Gravel 0.16 cu.m 730.00 116.80 22.75
47 Tie Wires # 16 260 kg 65.00 16,900.00 9.75
48 5mm thick x 4' x 8' Ordinary Plywood 4 sheet 360.00 1,440.00 0.325
TOTAL 55,194.40
LABOR 22,077.76
SUBTOTAL 77,272.16
DOWNSPOUT
49 100mm Ø x 6m PVC Pipe Series 1000 8 L 385.00 3,080.00 l=96x2
50 100mm Ø PVC Elbow, 45º 8 pcs 130.00 1,040.00
51 100 mm Ø PVC Clean Out/Plug 8 pcs 75.00 600.00
57 Tie Wires # 16 3 kg 65.00 195.00
TOTAL 4,915.00
LABOR 1,966.00
SUBTOTAL 6,881.00
MECHAINCAL WORKS
FIRE HYDRANT
76 2" Gate Valve, brass type 1 pc 2450 2450
77 2" G.I. Pipe, schedule 40 (Standard) 2 lgth (6m) 1950 3900 10.3
78 2" 90 deg G.I. Elbow, schedule 40 (Standard) 3 pcs 215 645
79 2" x1 1/2" 90 deg G.I. Elbow Reducer, schedule 40 (St 1 pc 245 245
79 1 1/2" Dia. Fire Hose Valve 1 pc 6500 6500
79 3/4" Teflon Tape 2 pcs 45 90
79 Red Oxide Metal Primer 1 gal 750 750
79 Paint Thinner 1 gal 400 400
79 #4 Paint Brush 2 pcs 85 170
Fire Hose Cabinet Complete Set (With the following
Items Included: 1 1/2"Dia. Pressure Regulating
Angle Valve, 1 1/2"Dia. x 100 Feet (30m) long,
1 set 26800 26800
Double Jacket Fire Hose wth Adjustable Nozzle,
Cabinet with Lock and Keys, Lock Nipple, and Hose
Rack)
TOTAL 41,950.00
LABOR 16,780.00
SUBTOTAL 58,730.00
Note: *Unit Prices are subject to change without prior notice
178.663
(Estimated) TOTAL AMOUNT: PHP 58,730.00 94.2287
110.2412
65.4685
123695.4815
Prepared by:
Architectural Estimates
Structural Estimates
Plumbing Estimates
Electrical Estimates
Recommending Approval:
Approved:
cu.m.
cu.m. per day
6.00 days 100%
cu.m.
cu.m.
43.20667
bd.ft.
bd.ft.
bd.ft.
Form Area
86.40
3.60
56.00
40.50
15.75
72.20
274.45 sq.m.
137.23 sq.m.
sqm
24%
29%
cu.m.
29%
29%
29%
#REF!
26%
38 PVC Solven 10 can 158.00 1,580.00
75.288775
126.77738
75.288775
410,092.39
II. EARTH WORKS
A. Excavation
Mark Quantity Depth Width Length Volume
C1F1 19.00 1.60 1.40 1.40 59.58
FTB 1.00 0.15 0.25 40.40 1.52
61.10
Labor & Equipment Cost
Utilize:
Foreman 1.00 man - days 800.00 800.00
Laborer 20.00 man - days 400.00 8,000.00
8,800.00
Output = 10.00 cu.m. per day
Duration = 6.11 say
Labor & Eqpt. Cost = 52,800.00
Total Cost for EXCAVATION 52,800.00
Area
Backfill for Total Floor A 1.00 0.20 182.24 36.45
36.45
V= 96.97 cu.m.
Materials
Earth Fill 98.00 cu.m. 350.00 34,300.00
Spreading Utilize:
Foreman 1.00 man - days 800.00 800.00
Laborer 12.00 man - days 400.00 4,800.00
5,600.00
Output = 12.00 cu.m. per day
Duration = 2.99 say
Labor & Eqpt. Cost = 16,800.00
Compaction Utilize: V= 96.97 cu.m.
cu.m.
cu.m.
DETAILED ESTIMATES
Item DESCRIPTION Qty. Unit Unit Cost Total Cost
1.0 GENERAL TECHNICAL REQUIREMENTS (Temporary Structure, Utilities and Services)
1.1 CONSTRUCTION SAFETY AND HEALTH PROGRAM 1.00 lot
A. Materials
Hard hat 30.00 pcs 395.00 11,850.00
Glove 90.00 set 200.00 18,000.00
garments 30.00 pcs 350.00 10,500.00
Signages 2.00 pcs 1,500.00 3,000.00
Facilities (water, sanitary, netc) 1.00 lot 16,000.00 16,000.00
59,350.00
EDC 86,057.50
2.0. SITEWORKS
2.1. CLEARING, GRUBBING AND WASTE DISPOSAL 840.00 sqm
A. Materials 0 0 0 0
B. Labor Cost
Foreman 3.00 man-days 800.00 2,400.00
Laborer 20.00 man-days 400.00 8,000.00
10,400.00
C. Equipment Cost
Crgo truck 16.00 hrs 1,000.00 16,000.00
Chainsaw 24.00 hrs. 800.00 19,200.00
Minor tools 10% 1,040.00
35,200.00
EDC 45,600.00 45,600.00
II. EARTH WORKS
A. Excavation
Mark Quantity Depth Width Length Volume
C1F1 19.00 1.60 1.40 1.40 59.58
FTB 1.00 0.15 0.25 40.40 1.52
61.10 cu.m.
Labor & Equipment Cost
Utilize:
Foreman 1.00 man - days 800.00 800.00
Laborer 20.00 man - days 400.00 8,000.00
8,800.00
Output = 10.00 cu.m. per day
Duration = 6.11 say 6.00 days
Labor & Eqpt. Cost = 52,800.00
Total Cost for EXCAVATION 52,800.00
Area
Backfill for Total Floor A 1.00 0.20 182.24 36.45
36.45 cu.m.
V= 96.97 cu.m.
Materials
Earth Fill 98.00 cu.m. 350.00 34,300.00
Spreading Utilize:
Foreman 1.00 man - days 800.00 800.00
Laborer 12.00 man - days 400.00 4,800.00
5,600.00
Output = 12.00 cu.m. per day
Duration = 2.99 say 3.00 days
Labor & Eqpt. Cost = 16,800.00
Compaction Utilize: V= 96.97 cu.m.
Plate Compactor 1.00 rent - days 450.00 450.00
Operator 1.00 mandays 400.00 400.00
Fuel 20.00 Liters 60.00 1,200.00
2,050.00
Output = 20.00 cu.m. per day
Duration = 4.85 say 5.00 days
Labor & Eqpt. Cost = 10,250.00
Total Cost for BACKFILL, SPREADING & COMPACTION 94,950.00
Name of Project: 2-STOREY RESIDENTIAL BUILDING
Location: SAN ISIDRO, GENERAL SANTOS CITY
Owner: ENGR. JUNLEX TUBILID
DETAILED ESTIMATES
Item DESCRIPTION Qty. Unit Unit Cost Total Cost
1.0 GENERAL TECHNICAL REQUIREMENTS (Temporary Structure, Utilities and Services)
1.1 CONSTRUCTION SAFETY AND HEALTH PROGRAM 1.00 lot
A. Materials
Hard hat 30.00 pcs 395.00 11,850.00
Glove 90.00 set 200.00 18,000.00
garments 30.00 pcs 350.00 10,500.00
Signages 2.00 pcs 1,500.00 3,000.00
Facilities (water, sanitary, netc) 1.00 lot 16,000.00 16,000.00
59,350.00
EDC 86,057.50
2.0. SITEWORKS
2.1. CLEARING, GRUBBING AND WASTE DISPOSAL 840.00 sqm
A. Materials 0 0 0 0
B. Labor Cost
Foreman 3.00 man-days 800.00 2,400.00
Laborer 20.00 man-days 400.00 8,000.00
10,400.00
C. Equipment Cost
Crgo truck 16.00 hrs 1,000.00 16,000.00
Chainsaw 24.00 hrs. 800.00 19,200.00
Minor tools 10% 1,040.00
35,200.00
EDC 45,600.00
157,682.40
45,600.00