4. Piling Checklist

The document is a piling checklist for a construction project, detailing the necessary steps and requirements for pile installation. It includes sections for recording the project's name, client information, and specific criteria for acceptable practices during the piling process. Each step is accompanied by options for marking compliance and space for remarks, signatures, and verification by relevant personnel.

Uploaded by

apurv.jadhav
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
6 views1 page

4. Piling Checklist

The document is a piling checklist for a construction project, detailing the necessary steps and requirements for pile installation. It includes sections for recording the project's name, client information, and specific criteria for acceptable practices during the piling process. Each step is accompanied by options for marking compliance and space for remarks, signatures, and verification by relevant personnel.

Uploaded by

apurv.jadhav
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 1

PILING CHECKLIST

Project Name WIR Ref. for CLT


Client / Employer Revision No:
PMC Cluster Reference
Contractor Location - Tower /Area Ref
Date Ins. Requested Floor Ref
Date Ins. Conducted Member/ Grid / Flat Ref

Contractor - Lodha -
S.N Description Acceptable Acceptable Remarks
Yes No NA Yes No NA
Pile position setting up: Three reference point
to be set up with respect to proposed pile
1 point. Centre line and location, Pile co-
ordinates of pile group and sequence (No
adjacent pile unless it has set concrete)
2 Liner provided (if required.)
Initial strata shown, approved & sample
preserved in the plastic bag with identification.
3 ( date, time, depth recorded) Founding depth
achieved and final strata sample preserved in
plastic bag with identification.
Required socketing depth achieved. Pile
penetration ratio recorded at depth specified
4
and checked with requirement given by geo-
tech consultant.
5 Cleaning of bore hole before concreting.
Reinforcement cut to the length & shape as per
drawing, the depth of pile bore with provision
6
of cover blocks in spiral pattern at the bottom
& sides.
7 Welding done to the cage as per requirement
Proper tremie lengths are available and placed
8 properly to accommodate the tremie at least
300mm from the bottom of the pile
Pile depth is checked and Concrete is casted
1m above the cut-off level, concrete shall
9
overflow above cut-off level to ensure all dust /
slurry particles comes out while pouring.
Final concrete top level of the pile casted is
10
recorded

Prepared & Checked by Contractor


S.N Name Designation Signature Date Remarks
Contractor -CM
Contractor -QA
Verified by Lodha / PMC
S.N Name Designation Signature Date Remarks
Lodha -CM

Checklist Ref: CO-LOD-GENE-QU-CN-CLT-004, Rev- 01, Date: 05-07-2024 Page 1 of 1