4. Piling Checklist
4. Piling Checklist
Contractor - Lodha -
S.N Description Acceptable Acceptable Remarks
Yes No NA Yes No NA
Pile position setting up: Three reference point
to be set up with respect to proposed pile
1 point. Centre line and location, Pile co-
ordinates of pile group and sequence (No
adjacent pile unless it has set concrete)
2 Liner provided (if required.)
Initial strata shown, approved & sample
preserved in the plastic bag with identification.
3 ( date, time, depth recorded) Founding depth
achieved and final strata sample preserved in
plastic bag with identification.
Required socketing depth achieved. Pile
penetration ratio recorded at depth specified
4
and checked with requirement given by geo-
tech consultant.
5 Cleaning of bore hole before concreting.
Reinforcement cut to the length & shape as per
drawing, the depth of pile bore with provision
6
of cover blocks in spiral pattern at the bottom
& sides.
7 Welding done to the cage as per requirement
Proper tremie lengths are available and placed
8 properly to accommodate the tremie at least
300mm from the bottom of the pile
Pile depth is checked and Concrete is casted
1m above the cut-off level, concrete shall
9
overflow above cut-off level to ensure all dust /
slurry particles comes out while pouring.
Final concrete top level of the pile casted is
10
recorded