48_King
48_King
Abstract
Telfer gold mine consists of both open pit and underground operations, including a mature sublevel cave.
Changes to mine design, the addition of subsequent sublevels, level footprint and increasing depth have all
resulted in a changing seismic hazard, which is managed using a combination of seismic exclusions zones and
dynamic ground support. The seismic hazard associated with high-stress slot development and production is
well understood, but the progression of seismic activity into areas of low expected seismic hazard required a
systematic upgrade to support.
A common theme is that changes to mine design have resulted in additional and changing seismic hazards,
with areas of existing infrastructure no longer adequately designed or supported for the future expected
demand. Understanding how changes to mine planning, addition of sublevels, footprint size and depth all
effect the evolving seismic hazard, have been key to managing the hazard.
Keywords: hazard management, seismicity, sublevel cave
1 Introduction
The Telfer gold mine (Telfer), owned by Newcrest Mining Limited, is located in the Great Sandy Desert 400 km
east-southeast of Port Hedland, and approximately 1,300 km northeast of Perth. The Telfer deposit was
discovered in 1971, when anomalous gold and copper values were returned from outcrops in what is now
known as Main Dome. In late 2000, the operation was put into care and maintenance after producing
approximately 6 Moz of gold. A feasibility study was undertaken in 2002 that established the strategy for
mining and processing ore from the surface and underground deposits. This led to the re-establishment of
open pit mining operations in 2004, and underground operations in 2006.
Telfer is currently producing from the Main Dome and West Dome pits, and the underground operations,
which consist of a sublevel cave (SLC), narrow vein, long-hole open-stoping (M Reefs) and long-hole retreat
stoping (Western Flanks). The SLC was initiated in late 2006, at the 4650 Level, 850 m below surface. The
cave broke through into the Main Dome open pit in late 2009. The footprint of the cave is approximately
1,000 m by 250 m, with the current SLC extraction levels some 1,085 m below surface.
The open pit is currently mining at rates in the order of 50 Mtpa of ore and waste, while the underground is
hoisting in the order of 6 Mtpa. The ore sources combine to feed a mill that treats approximately 24 Mtpa.
2 Mine geology
Telfer’s geology is divided into two main geological domes, namely West Dome and Main Dome, with
underground mining operations occurring in the Main Dome. The Main Dome formation is a large,
oval-shaped, double-plunging open fold, consisting of a sedimentary stratigraphic sequence (Figure 1).
The current underground operation is constrained within the Malu Formation, which is a massive sandstone
and quartzite unit with thinly interbedded pelitic strata. The Malu Formation is divided into three major
members; the Upper (UMM), Middle (MMM), and Lower (LMM) members, that have undergone moderate
to intense sericite and silica metasomatism.
A large regional fault zone, the Graben Fault, exists on the eastern flank of the main orebody, which is
intersected by mine development. A number of large fault structures are related to the Graben Fault.
3 Mine design
Figure 2 Telfer Mine transverse layout and mining front, 4475 Level and 4440 Level mining front
Caving was initiated at the 4650 Level and planned to progress seven levels to the 4500 Level, with the
haulage drive and orepass infrastructure located on the east of the 4475 Level, passing under the SLC.
The 4650 Level had a footprint of 315 × 185 m, with levels progressively increasing in size and stepping out
to the north and south, as far as the 4525 Level (1010 × 165 m). Below the 4525 Level, the footprint began
to reduce in north–south extent (Figure 3).
Below the 4600 Level, the SLC stepped in to the east to target higher grade reserves. However, the southern
part of the 4475 Level stepped back to the west of the above levels, resulting in the cave being pushed into
the high-stress abutment, with an increase in seismic activity around the slots drives post-2016 (Figure 4).
Figure 4 4475 Level step out to the west and seismic events over +1 ML coloured by time
The 4440 Level was added to the mine plan in 2015, with the footprint reducing significantly to 455 × 85 m,
located in the north and central section of the SLC footprint.
4 Seismic system
The Telfer seismic system was initially installed and commissioned in late 2005, and has since been upgraded
and expanded to include 43 operational triaxial geophones of different natural frequency; 22 4.5 Hz and
21 14 Hz geophones. This allows for the estimate of seismic source parameters and local magnitude, with the
seismic system providing real-time data transfer via the underground fibre optic network.
The sensor array took advantage of mine infrastructure to locate sensors at different depths and locations
around the SLC (Figure 5). The system layout and sensitivity was designed for location accuracies of less than
30 m, and recording of all events greater than local magnitude (ML) -1.5. Due to the development layout and
expected seismic hazard, a large proportion of sensors are located on the western side of the SLC, resulting
in higher system sensitivity and location accuracy on the western abutment of the SLC.
5 Seismic history
The seismic and mining history for the SLC is outlined in Table 2 and Figure 6. The seismic activity rate was
highest during cave propagation and breakthrough to the Main Dome pit.
Figure 6 Historic of seismicity >ML-1.5 at Telfer, 2005 to 2018, including 30 day moving average
Figure 7 Three months of seismic activity demonstrating stress concentration around the cave column
Since 2016, activity on the northeastern side of the SLC, up to approximately 4700 Level, has increased, which
appears to be a result of stress redistribution on the northeastern flank, with subsequent cave break-back.
This area also coincides with a confluence of major structures and rock units.
Figure 8 Plan of the 4475 Level showing energy index (pers. comm., Institute of Mine Seismology
November 2017)
The majority of damaging seismic events has been located on the western side of the SLC, with most of the
damage associated with the slot drives.
A recent report by Beck Engineering (2015), indicates that a reducing footprint means subsequent levels are
less ‘shadowed’ by levels above, and at times, slotting induces large movements and energy release. At some
other mines, such as Perseverance in Western Australia, shrinking level sizes have evolved a similar pattern
of seismicity encroaching on work areas with large seismic events and rockbursts occurring more frequently.
Figure 9 Magnitude/time chart, with cumulative number of events line, displaying response to firing.
The green stars along the bottom indicate SLC slot firing blasts
(a)
(b)
Figure 10 Plot of b-value (a) 2012–2016 at the 4430RL; and, (b) 2017 onwards, showing higher b-values to
the west and lower b-values in the east
Figure 11 Seismic events greater than +1.5 ML clustered around the 4475 and 4440 slot drive
6 Managing seismicity
Seismicity is managed through a hierarchy of controls, with the objective that hazards should be removed,
with protection measures or just-in-time forecasting techniques adopted only as a last resort.
Control measures can be categorised as either tactical or strategic:
Tactical applications are typically operational in nature, such as ground support, seismic exclusion
practices and seismic response trigger action response plans (TARP) for large events or rockbursts.
The TARPs detail the actions, communication and response required in the event of a large seismic
event experienced in a number of locations, or a local rockburst, respectively. This includes immediate
actions to be taken and reporting, as well as investigations and any remedial action required.
Strategic applications typically relate to mine planning and sequencing activities, such as shadowing
areas and pillar sizes. These are outlined in the Telfer Seismic Risk Management Plan.
Figure 12 Dynamic ground support scheme used in the slot drive and high seismic hazard areas
Within the SLC, outside of the above domains classified as requiring medium to high dynamic ground support,
the ground support standard was 50 mm FRS and fully bonded Posimix bolts.
Figure 13 Plan of development and production sequence to shadow crosscut development and pillars
Slot drives on subsequent levels maintain a minimum 40 m lead-lag, to reduce interaction between levels,
and crosscut lead-lag rules to maintain the production front between 0 and 45°.
Figure 14 Plan of 4440 Level showing crosscut firings in red, demonstrating the slot drive firings in green
passing the crosscuts before they are developed past their hold point
Figure 15 Section of the 4475 Level with identified structures and damage mapping recorded in mXrap
Figure 16 Decision flow chart to identify support upgrade requirements using Kaiser’s support damage
scale rating 1–5 (Kaiser et al. 1992)
Ground support upgrades utilised a combination of strengthened overlap mesh, Sandvik MD bolts and MDX
bolts, and cable bolts. Strengthened overlap mesh is described by Louchnikov et al. (2014), where the product
comprises a standard 5.6 mm weld mesh with the addition of two wires of the same diameter along the edge
of the sheet. This results in stronger and stiffer overlaps and reduces the risk of mesh failure at these
locations. The MDX bolt is a modification of the MD bolt, with a greater energy absorption and deformation
capacity, developed in conjunction with Telfer, as described by Darlington et al. (2018). The MDX bolt allows
for a more efficient installation, while providing greater than 25 kJ capacity (Darlington et al. 2018).
8 Conclusion
The evolving seismic hazard at Telfer has been well managed through an extensive seismic monitoring
network, TARPs and the implementation of the seismic risk management plan. The hazard has increased with
the addition of extra sublevels and mine design changes, as well as increasing cave size, but has not
experienced a step change in activity. However, the predictability of seismicity and its association with
blasting and slot firings is decreasing with time, as more seismicity is associated with stress redistribution
around and under the cave.
A common theme is that changes to mine design have resulted in additional and changing seismic hazards,
with areas of existing infrastructure no longer adequately designed or supported for the future expected
demand. Understanding how changes to mine planning, addition of sublevels, footprint size and depth all
effect the evolving seismic hazard is key to managing the hazard.
Acknowledgement
The authors thank Newcrest Mining Limited and Telfer Mine management for permission to publish this
paper. They also acknowledge previous members of the Telfer geotechnical department.
References
Beck Engineering, 2015, Updated Simulation of Global Mining Induced Deformation at Telfer, Beck Engineering, Sydney.
Darlington, B, Rataj, M, Balog, G & Barnett, D 2018, ‘Development of the MDX Bolt and in-situ dynamic testing at Telfer Gold Mine’,
in CC Li, X Li & Z-X Zhang (eds), Proceedings of Third International Conference on Rock Dynamics and Application, CRC Press.
Harris, PC & Wesseloo, J 2015, mXrap, version 5, computer software, Australian Centre for Geomechanics, The University of Western
Australia, Perth, https://www.mxrap.com
Kaiser, PK, Tannant, DD, McCreath, DR & Jesenak, P 1992, ‘Rockburst damage assessment procedure’, in PK Kaiser & DR McCreath
(eds), Rock Support in Underground Mining and Construction, A.A. Balkema, Rotterdam, pp. 639–647.
Louchnikov, V, Sandy, M, Watson, O, Orunesu, M & Eremenko, V 2014, ‘An overview of surface rock support for deformable ground
conditions’, Proceedings of the Twelfth AUSIMM Underground Operators Conference, The Australasian Institute of Mining
and Metallurgy, Melbourne, pp. 57–66.