The document provides a detailed estimation report for a G+1 residential row house with specific project details including dimensions, materials, and quantities for various construction elements. It covers excavation, concrete work, brickwork, reinforcement steel requirements, and plastering. The total estimated reinforcement steel quantity required for the project is 2,630 kg.
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0 ratings0% found this document useful (0 votes)
2 views
Complete Row House Estimation Report
The document provides a detailed estimation report for a G+1 residential row house with specific project details including dimensions, materials, and quantities for various construction elements. It covers excavation, concrete work, brickwork, reinforcement steel requirements, and plastering. The total estimated reinforcement steel quantity required for the project is 2,630 kg.
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 3
Complete Detailed Estimation Report –
G+1 Row House
1. Project Details
Project: Residential Row House (G+1)
Plot Size: 20 ft × 40 ft = 800 sq.ft (74.3 m²) Wall Thickness: 9 inches (0.23 m) No. of Floors: Ground + First (G+1) Floor Height: 10 ft each floor Number of Columns: 10 Column Size: 9 in × 12 in (0.23 m × 0.30 m) Beam Size: 9 in × 12 in (0.23 m × 0.30 m) Slab Thickness: 5 in (0.125 m) Footing Size: 1.2 m × 1.2 m × 0.45 m
2. Earthwork – Excavation & Filling
Excavation for footing (10 footings):
Volume = 1.5 m × 1.5 m × 1.5 m = 3.375 m³ × 10 = 33.75 m³
Backfilling = 50% of excavation = 16.875 m³
3. PCC (1:4:8)
Below footing: 1.5 m × 1.5 m × 0.1 m = 0.225 m³ × 10 = 2.25 m³
4. RCC for Footings
Footing Size: 1.2 m × 1.2 m × 0.45 m = 0.648 m³ × 10 = 6.48 m³
Reinforcement: 12 mm bars @ 150 mm c/c both ways, approx 184 kg total steel. 5. Plinth Beam & Wall
Plinth RCC Beam Volume (approx): 0.23 m × 0.3 m × 40 m = 2.76 m³
Brickwork above plinth: 40 m × 0.75 m × 0.3 m = 9 m³
6. Brickwork (Ground + First Floor)
Each Floor Wall Area = (2 × 12 + 2 × 6) × 3 m = 72 m² per floor
Total Wall Area = 144 m², Wall Volume = 144 × 0.23 = 33.12 m³
7. RCC Columns
Column Volume: 0.23 m × 0.3 m × 3 m × 10 columns × 2 floors = 4.14 m³
Reinforcement: Approx. 712 kg steel (including stirrups)
8. RCC Beams
Beam Volume: 0.23 m × 0.3 m × 30 m (total run) = 2.07 m³ × 2 = 4.14 m³
Steel: Approx. 278 kg
9. RCC Slab
Slab Area: 74.3 m² × 2 = 148.6 m²
Volume = Area × Thickness = 148.6 × 0.125 = 18.575 m³ Reinforcement (1% of volume): ≈ 1456 kg
10. Plastering
Total Wall Area: 144 m² × 2 sides = 288 m²
11. Flooring
Each Floor = 74.3 m² × 2 = 148.6 m²
Tiles or IPS flooring assumed.
12. Total Reinforcement Steel Summary
Structural Member Steel Quantity (kg) Footings 184 kg Columns 712 kg Beams 278 kg Slabs 1456 kg Total 2,630 kg