Build Comm
Build Comm
Building Commissioning
Doug Litwiller, PE, CEM Mike Robbins, LEED AP O+M
Building Maintenance Commissioning Specialist
Optimization Consultants Emory University
Tucker, GA & Ames, IA Atlanta, GA
1
Certificates of Completion for both AIA members and non-AIA members are
available upon request.
This course is registered with AIA CES for continuing professional education. As
such, it does not include content that may be deemed or construed to be an
approval or endorsement by the AIA of any material of construction or any
method or manner of handling, using, distributing, or dealing in any material or
product.
1
11/24/2020
Learning Objective 1:
Get an overview of building commissioning process.
Learning Objective 2:
Learn about the various phases of the commissioning process.
Learning Objective 3:
Learn about why the building commissioning process is important.
Learning Objective 4:
Understand the differences and similarities between new building
commissioning and retrocommissioning.
We are BMOC.
We optimize the value of the
workforce,
management, assets, and
CMMS in delivering building
maintenance services.
Emory University
Facilities Management
Division of Campus Services
BMOC, Inc. 201 Dowman Drive
2321 4th Street, Suite 300 Atlanta, GA 30322
Tucker, GA 30084
www.buildingmoc.com
2
11/24/2020
1. Opening Commentary
2. Putting it into Perspective
3. Building Commissioning “101”
What?
Why?
Who?
How?
$’s?
Keys to Success
A Word about “FDD”
4. “Re”/“Retro”/”Ongoing” Commissioning
5. Planning for Building Turnover
6. Q/A
7
10 Pounds
5 Pounds
Commissioning Resources
Ref # RESOURCE SOURCE URL
3
11/24/2020
Commissioning Resources
Ref # RESOURCE SOURCE URL
APPA/Building Commissioning
16 The Building Commissioning Handbook https://www1.appa.org/bookstore/store_browse.cfm?categoryid=4 $
Association
What Owners & Providers Should Know About APPA's Facilities Manager
21 https://www1.appa.org/FacilitiesManager/index.cfm?ItemNumber=2703 Free
Building Commissioning & Each Other Magazine (Jan/Feb 2015)
https://www.techstreet.com/ashrae/standards/guideline-0-2019-the-
23 Guideline 0-2019--The Commissioning Process ASHRAE $
commissioning-process?product_id=2076120
https://www.techstreet.com/ashrae/standards/ashrae-202-
24 ASHRAE 202-2018 ASHRAE $
2018?product_id=2025517
https://www.techstreet.com/ashrae/standards/guideline-1-1-2007-hvac-
Guideline 1.1-2007 HVAC&R Technical
25 ASHRAE r-technical-requirements-for-the-commissioning- $
Requirements for the Commissioning Process
process?product_id=1573306
26 Commissioning Process (online slides) Applied Energy Solutions https://www.slideshare.net/d_mackay/the-commissioning-process Free
Building Commissioning http://www.facomgrp.com/wp-content/uploads/2014/09/Twenty-
27 Building Commissioning 101 Free
Association Minute-Owner-Presentation-Rev-7-Short-Version.ppt
10
11
11
12
12
4
11/24/2020
13
13
1 2 3 4
+/- 4 Years
14
14
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54
15
15
5
11/24/2020
16
16
17
Two definitions…
18
18
6
11/24/2020
Reference #16: The Building Commissioning Handbook (APPA/Building Commissioning Association) 1-19
19
20
Project goals,
Measurable performance criteria,
Cost considerations,
Benchmarks,
Success criteria,
Supporting information.
21
21
7
11/24/2020
2-22
22
23
24
24
8
11/24/2020
25
26
26
27
27
9
11/24/2020
28
4-29
29
30
30
10
11/24/2020
31
31
32
33
33
11
11/24/2020
Reference #21: What Owners & Providers Should Know About Building Commissioning & Each (APPA’s Facilities Manager Magazine – Jan/Feb 2015) 5-34
34
35
35
36
12
11/24/2020
37
38
39
13
11/24/2020
Benefits of In-House:
Better institutional knowledge of standards;
Standardization of BAS graphics, programming,
etc.
Retaining of project knowledge in-house
Improved support to FM group as questions or
issues arise post-turnover
6-40
40
41
42
42
14
11/24/2020
Post-
Planning Design Construction Pre-Occupancy
Occupancy
43
43
OPR
Form Cx
Team
Basis of
Design
Initial Cx
Plan
Post-
Planning Design Construction Pre-Occupancy
Occupancy
44
44
Update OPR
OPR
& BOD
Design
Form Cx Doc
Team Reviews
Basis of Refine
Design Cx Plan
and
Initial Cx Spec
Plan
Post-
Planning Design Construction Pre-Occupancy
Occupancy
45
45
15
11/24/2020
Submittal
Approval &
Start
Update OPR CMMS
OPR
& BOD Update
Design
Form Cx Doc
Team Reviews
Basis of Refine
Design Cx Plan
and
Initial Cx Spec
Plan
Post-
Planning Design Construction Pre-Occupancy
Occupancy
46
46
CAUTION!
Do not overlook the importance of having
the asset management program in place
BEFORE the day the building is turned
over.
47
47
Submittal
Approval &
Start
Update OPR CMMS
OPR
& BOD Update
Design Prepare
Form Cx Doc Test
Team Reviews Procedures
Post-
Planning Design Construction Pre-Occupancy
Occupancy
48
48
16
11/24/2020
Submittal
Approval &
Start
Update OPR CMMS
OPR
& BOD Update
Design Prepare
Form Cx Doc Test
Team Reviews Procedures
Post-
Planning Design Construction Pre-Occupancy
Occupancy
49
49
Resolved faster;
Cheaper to resolve;
50
50
Submittal
Approval &
Start
Update OPR CMMS Startup
OPR
& BOD Update
Design Prepare
Form Cx Doc Test
Team Reviews Procedures
Post-
Planning Design Construction Pre-Occupancy
Occupancy
51
51
17
11/24/2020
Submittal
Approval &
Start
Update OPR CMMS Startup
OPR
& BOD Update
Design Prepare Functional
Form Cx Doc Test Testing
Controls,
Team Reviews Procedures Balancing, etc.
Post-
Planning Design Construction Pre-Occupancy
Occupancy
52
52
53
53
Submittal
Approval &
Start
Update OPR CMMS Startup
OPR
& BOD Update
Design Prepare Functional
Form Cx Doc Test Testing
Controls,
Team Reviews Procedures Balancing, etc.
Post-
Planning Design Construction Pre-Occupancy
Occupancy
54
54
18
11/24/2020
55
55
Submittal
Approval &
Start
Update OPR CMMS Startup O&M
OPR
& BOD Update Review
Design Prepare Functional Owner
Form Cx Doc Test Testing Training
Controls,
Team Reviews Procedures Balancing, etc.
Post-
Planning Design Construction Pre-Occupancy
Occupancy
56
56
Submittal
Approval &
Start
Update OPR CMMS Startup O&M
OPR
& BOD Update Review
Design Prepare Functional Owner
Form Cx Doc Test Testing Training
Controls,
Team Reviews Procedures Balancing, etc.
CMMS
Refine Prepare & Updated
Basis of Issues
Cx Plan Use and
Design Log
and Checklists Complete
Update &
Initial Cx Spec Pre-
Resolve
Plan Functional
Testing
Post-
Planning Design Construction Pre-Occupancy
Occupancy
57
57
19
11/24/2020
GOAL!
Have the asset management program
100% complete at building turnover so
preventive maintenance work orders
start coming out immediately and ALL
work requests associated with this new
building will be logged on DAY 1!
58
58
Submittal
Approval &
Start
Update OPR CMMS Startup O&M
OPR PM’s Start
& BOD Update Review
Design Prepare Functional Owner Cx Report
Form Cx Doc Test Testing Training w/Systems
Controls, Manual
Team Reviews Procedures Balancing, etc.
CMMS
Refine Prepare & Updated Seasonal
Basis of Issues
Cx Plan Use and Testing
Design Log
and Checklists Complete
Update & Warranty
Initial Cx Spec Pre-
Resolve Review
Plan Functional
Testing
Post-
Planning Design Construction Pre-Occupancy
Occupancy
7-59
59
60
60
20
11/24/2020
61
61
62
5. Why BECx?
Mitigate Contractual Risk Prevent Indoor Air Quality Optimize Energy
Problems Performance
Enhance Security & Improve Operations & Meet Regulatory and
Resiliency Maintenance Program Requirements
63
63
21
11/24/2020
64
64
65
% of Total Source
Construction Cost
~ 1% Reference #20: The Building Commissioning Handbook
(APPA/Building Commissioning Association)
~0.25% Reference #27: 2018 Commissioning Cost/Benefit Study
Findings (Lawrence Berkeley National Lab)
0.5% - 1.5% Reference #1: United State General Services
Administration
0.3% - 1.1% Reference #4: California Commissioning Collaborative
66
66
22
11/24/2020
67
68
69
23
11/24/2020
70
71
71
72
72
24
11/24/2020
73
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54
74
74
75
75
25
11/24/2020
76
76
77
9-78
78
26
11/24/2020
“Re”/“Retro”/”Ongoing” Commissioning
Retrocommissioning
1. “Retrocommissioning” is the application of the
commissioning process to existing buildings.
2. RCx is a process that seeks to improve how
building equipment and systems function
together.
3. RCx often resolve problems that occurred during
design or construction, or address problems that
have developed throughout the building's life.
4. RCx improves a building's operations and
maintenance (O&M) procedures to enhance
overall building performance.
79
79
“Re”/“Retro”/”Ongoing” Commissioning
Recommissioning
1. “Recommissioning” is another type of
commissioning that occurs when a building that
has already been commissioned undergoes
another commissioning process.
2. The decision to recommission may be triggered
by a change in building use or ownership, the
onset of operational problems, or some other
need.
80
80
“Re”/“Retro”/”Ongoing” Commissioning
Ongoing Commissioning
1. Incorporates the key aspects and Re and Retro
but the process is “ongoing” in a never-ending
cycle.
81
81
27
11/24/2020
10-82
82
83
84
84
28
11/24/2020
85
86
86
Submittal
Approval &
Start
Update OPR CMMS Startup O&M
OPR PM’s Start
& BOD Update Review
Design Prepare Functional Owner Cx Report
Form Cx Doc Test Testing Training w/Systems
Controls, Manual
Team Reviews Procedures Balancing, etc.
CMMS
Refine Prepare & Updated Seasonal
Basis of Issues
Cx Plan Use and Testing
Design Log
and Checklists Complete
Update & Warranty
Initial Cx Spec Pre-
Resolve Review
Plan Functional
Testing
Post-
Planning Design Construction Pre-Occupancy
Occupancy
87
87
29
11/24/2020
88
88
GOAL!
89
89
Quote #1
90
90
30
11/24/2020
1. Opening Statement:
Becomes less important as individuals know their role. We
want conversation and communication!
2. TOW Membership:
Confirm we have the right stakeholders with the right
information participating at the right time so we can make
better decisions!
3. FM Personnel:
Who (by name) is going be involved in the building?
What is their role and responsibilities and when do
they need to get involved?
When will the new hires be on-board?
91
91
92
11-93
93
31
11/24/2020
94
Best Practices
1. Start meeting with the team early – no later than 12
to 18 months prior to Substantial Completion.
2. Get the “customers” involved early.
3. Emphasize the team (avoid “we/they”).
4. Continue to meet post-Substantial Completion.
5. Send out agendas
6. Distribute meeting notes within 48 hours.
7. Do not turn it into a “project meeting”.
8. Focus on:
• What
• By When
• By Who 95
95
96
96
32
11/24/2020
Commissioning Resources
Ref # RESOURCE SOURCE URL
97
Commissioning Resources
Ref # RESOURCE SOURCE URL
APPA/Building Commissioning
16 The Building Commissioning Handbook https://www1.appa.org/bookstore/store_browse.cfm?categoryid=4 $
Association
What Owners & Providers Should Know About APPA's Facilities Manager
21 https://www1.appa.org/FacilitiesManager/index.cfm?ItemNumber=2703 Free
Building Commissioning & Each Other Magazine (Jan/Feb 2015)
https://www.techstreet.com/ashrae/standards/guideline-0-2019-the-
23 Guideline 0-2019--The Commissioning Process ASHRAE $
commissioning-process?product_id=2076120
https://www.techstreet.com/ashrae/standards/ashrae-202-
24 ASHRAE 202-2018 ASHRAE $
2018?product_id=2025517
https://www.techstreet.com/ashrae/standards/guideline-1-1-2007-hvac-
Guideline 1.1-2007 HVAC&R Technical
25 ASHRAE r-technical-requirements-for-the-commissioning- $
Requirements for the Commissioning Process
process?product_id=1573306
26 Commissioning Process (online slides) Applied Energy Solutions https://www.slideshare.net/d_mackay/the-commissioning-process Free
Building Commissioning http://www.facomgrp.com/wp-content/uploads/2014/09/Twenty-
27 Building Commissioning 101 Free
Association Minute-Owner-Presentation-Rev-7-Short-Version.ppt
98
99
99
33
11/24/2020
100
100
34