06_Realistic_Power_System-Simulations_IEC-61850_FMTP
06_Realistic_Power_System-Simulations_IEC-61850_FMTP
in IEC 61850
applications, different interfaces to relays and
new tools to prove performances
Andrea Bonetti – FMTP POWER AB [email protected]
The protection relay takes the decision during the power system TRANSIENT!
11
WHAT ABOUT IEC 61850?
12
SHOULD I JUST BE SCARED ABOUT ALL OF THIS ?
13
WE HAVE SOME IMPORTANT COMMITTEES AND STANDARDS
14
TC 95 - MT4
TC 38
”NEW” Formats for Merging Unit data, from TC 38
”LE” - PROT
”LE” - PQ
”LE” - PQ
Relay performances (example for IEC 60255-121) from TC 95 – MT4
Relay performances and IEC 61850 GOOSE
Standardized and realistic tests
SIR Diagrams are the result of standardized realistic network simulation tests
Power system simulations are expected to be used for performing these tests.
Simplified software tools are appearing on the market based on the test definitions of the
Standard.
Standardized and realistic tests
HIL:
Hardware In order to perform these tests
in the Loop
a real time power system simulator is
required, which can simulate the behavior
of the remote relay(s) and circuit
breaker(s), and also to simulate the power
system on the direct behavior of the relay
under tests
(operation for only one phase, operation for all
the phases for instance).
Hardware in the Loop (IEC 61850 Technology)
Simulated Merging Unit
Power Merging
Conventional Unit 1
Relay under test System
Model
Relay Operation
affects the Power
System simulation!
Hardware in the Loop (IEC 61850 Technology)
Simulated Merging Unit
Merging
IEC 61850 Relay Power System Unit 1
under test Model
Analog signa
Amplifier
Relay response (GOOSE)
(Trip, Start, Trip L1, L2 or L3…)
Relay Operation
affects the Power
System simulation!
Hardware in the Loop (IEC 61850 Technology)
Simulated Merging Unit
Merging
IEC 61850 Relay Power System Unit 1
under test Model
SAMU
(under test?)
Sampled Values
(SV) Data Stream VT/CT secondary I
and U
AMP
Analog signa
Amplifier
Relay response (GOOSE)
(Trip, Start, Trip L1, L2 or L3…)
Relay Operation
affects the Power
System simulation!
Hardware in the Loop (IEC 61850 Technology)
Are we testing “the same thing”?
All the A/D conversion chain of the relay is included in The “A/D conversion chain” is in the MU that
the test. must be simulated in the Simulator!
Models to be created.
CT/VT behavior is simulated in the Simulator. We have
reasonable models for them.
Are we testing “the same thing”?
All the A/D conversion chain of the relay is included in The A/D conversion chain” is in the SAMU.
the test. Each SAMU is a different SAMU (transient
performances TC 38)?
CT/VT behavior is simulated in the Simulator. We have
reasonable models for them.
How do we handle Process Bus at IEC 60255-1xx level?
We need new tools
Should similar tests with missing samples or “´wrong order samples” be a mandatory part of the relay type tests?
CONCLUSIONS
31
- ACCEPT IT
- CONTRIBUTE TO IMPROVE IT
- CONTRIBUTE TO HAVE IT MORE USER FRIENDLY
32