CE3003-Prefabricated-Structures-Lecture-Notes-1
CE3003-Prefabricated-Structures-Lecture-Notes-1
com
ROHINI COLLEGE OF ENGINEERING & TECHNOLOGY
construction method such as hilly region and also when normal construction
materials are not easilyavailable.
2. PFS facilities can also be created at near a site as is done to make concrete
3. Structures which are used repeatedly and can be standardized such as mass
housing storage sheds, godowns, shelter, bus stand security cabins, site offices,
Fool over bridges road bridges. Tubular structures, concrete building blocks etc.,
are prefabricatedstructures
prefabricated systems
The first three types are mainly classified according to their degree of precast
elements used in the construction. For example brick is small unit of pre casted material and
used in buildings. This is called as small prefabrication and the degree of precast element is
very low.
Medium prefabrication:
Suppose the roofing systems and horizontal members are provided with pre casted
elements. These constructions are known as medium prefabricated construction. Here the
degree of precast elements is moderate.
Large prefabrication:
In large prefabrication most of the members like wall panels, roofing / flooring
systems, beams and columns are prefabricated. Here the degree of precast elements is high.
One of the mainfactors which affect the factory prefabrication is transport. The width of the
road, mode of transport vehicles are the factors which determines the prefabrication which
is to be done on-site or in factory. Suppose the factory is situated far away from the
construction site and the vehicle needs to cross congested traffic areas with heavy weighing
elements the cast in- site prefabrication is preferred. Even though the same condition as the
cast in site prefabrication is preferred only when umbers of houses are more for small
CE3003 PREFABRICATED STRUCTURES
elements the conveyance is easier with normal type of lorry and tractors. We can adopt
factory or off-site prefabrication for this type of construction.
In the total prefabrication systems, the space frames are casted as a single unit and
erected at the site. The wall fitting and other fixing are done on site. This type of
construction is known as open system of prefabrication.
In this system the whole things are casted with fixing and erected on their position.
Partial prefabrication:
In this method of construction, the building elements required are precast and then
erected. Since the casting of horizontal elements (roof / floor) often take more time due to
erection of frame work, the completion of the building is delayed and hence this method is
restored. In most of the building sites, this method is popular, so in industrial buildings
where the elements have longer spans. Use of double tees, channel units, cored stabs, slabs,
hyperboloid shells, etc, are some of the horizontal elements used.
This method is efficient when the elements are readily available and the building has
reached the roof level. The delay caused due to erection of framework, delay due to removal
of framework is eliminated completely in this method of construction suitable for any type
of building provided lifting and erection equipment’s are available.
Total prefabrication:
Very high speeds can be achieved by using this method of construction. The method
can be employed for frame type of construction or for panel type; the total prefabrication is
done on-site or off-site. The choice of the two methods depend on the situations when the
factory produced elements are transported and erected on site, we call it off-site
prefabrication. If this method is to be adopted we should have a very good transportation
facility for the products to be transported to the site of construction. If the elements are cast
near the building site and erected, the transportation of elements can be eliminated, but we
have to consider the space availability for establishing such facilities though it is temporary.
Select fittings, fasteners, adhesive and sealants that allow for quicker assembly
and facilitate the removal of reusable materials.
Design to accommodate deconstruction
Logistics. Reduce building complexity.
Design for reusable materials.
Design for flexibility and adaptability.
ADVANTAGES
Self supporting readymade components are used, so the need for formwork,
shuttering and scaffolding is greatly reduced.
On-site construction and condition is minimized.
DISADVANTAGES
Careful handling of prefabricated components such as concrete panels (or) steel and
glass panels is reduced.
Attention has to be paid to the strength and corrosion resistance of the joining of
prefabricated sections to avoid failure of the joint.
Transportation costs may be higher for voluminous prefabricated sections than for the
materials of which they are made, which can often be packed more efficiently.
Large group of buildings from the same type of prefabricated elements tend to look
drab and monotonous Local jobs are lost.
The center lines of load bearing walls shall coincide with the grid lines.
b. In case of external walls the grid lines shall coincide with the center
line of the wall or a line on the wall 5 cm from the internal face of the
wall.
d. Preferred increments for the still heights, doors, windows and other
fenestration shall be 1m. e. In case of internal columns the grid lines shall
coincide with the center lines of columns.
e. In case of external columns, the grid lines shall coincide with the center lines
CE3003 PREFABRICATED STRUCTURES
of the columns in the storey or a line in the column from the internal face of the
column in the topmost storey.
The storey height is fixed between finished floor levels as 2.8m and if the
thickness of slab is<15cm storey height is fixed as 2.7m. The Centre
distance between the load bearing walls can be chose from a set of
modules. The use of other dimensions is not allowed.
In the design of a building, modular grid can be used consisting of parallel
line spaced at a value of module M or Mp and a grid line chosen as a base
for setting out a part of a building becomes a modular axis.
In the fig (a), a typical grid is chosen for load bearing walls without duct.
The interior walls are placed so that their centerlines coincide with the
modular axis. In the fig (b), a grid is shown for load bearing walls with
hollow ducts in between. The centre line of the grid is found by deducting
the size of duct.
1.4 PRODUCTION
The location of pre casting yards consist of storage facilities suitable for
transporting and erection equipment’s and availability of raw materials are the critical
factors which should be carefully planned and provided for effective and economic use
of pre-cast concrete components in construction.
The manufacture of the components can be done in a centrally located factor of in a site
where pre casting yards set-up at or near the site of work.
SYSTEMS PRODUCTION
These techniques however may be grouped into three basic method of production. These
are
Stand system
In the stand system the prefabricates mature at the point where they were molded While
the production team moves to successive stands the bed on which prefabricates.
Conveyor belt
The conveyor belt system of production splits the whole production process in to a series
of operation carried out at a separate successive and permanent point to the heat may be
by means of conveyor belt trolleys & crane etc.
Aggregate system
The word aggregates describes a large, complex permanently installed set of machines
and mechanical application which can carry out most of the separate operation involved
in casting concrete components.
It is a capital intensive production where work is done throughout the year preferably
under a covered shed to avoid the effects of seasonal variations high level of
mechanization can always be introduced in this system where the work can be organized
in a factory like manner with the help of constant team of workmen.
In this scheme, the components are manufactured at site near the site of work as possible.
This system is normally adopted for a specific job order for a short period. The work is
normally carried out in open space with locally a valuable labour force. The equipment
machinery and moulds are of mobile nature.
Therefore there is a definite economy with respect to cost of transportation. This system
suffers from basic drawback of its non-suitability to any high degree of mechanization.
It has no elaborate arrangements for quality control.
The various processes involved in the manufacture of precast elements are classified as
follows:
1) Main process
3) Subsidiary process
MAIN PROCESS
1) Providing and assembling the moulds, placing reinforcement cage in position for
reinforced concrete work, and
This process is necessary for the successful completion of the process covered by the
main process.
precast products.
CONCRETE--------- MOULD------------STEEL
MIXING-------- PREPARATION-------CUTTING
COMPONENT
COMPACTION
CURING
DEMOULDING
STORAGE
While transporting the prefab elements in various systems, such as wages, trucks,
bullock cards etc. care should be taken to avoid excessive cantilever actions and desired
supports are maintained. Special care should be taken in negotiating sharp beds uneven
of slushy roads to avoid undesirable stresses in elements and in transport vehicles.
Before loading the elements in the transporting media, care should be taken to ensure
the base packing for supporting the elements are located at specified portion only.
1.5.2 ERECTION
It is the process of assembling the Prefabrication element in the find portion as per the
drawing. In the erection of prefab elements the following items of work are to be carried
out.
1). Slinging of the prefabricated elements.
2). Tying up of erection slopes connecting to the erection hooks.
4). Cleaning the steel inserts before incorporation in the joints lifting and setting the
elements to correct position.
5). Adjustments to get the stipulated level line and plumb.
The erection work in various construction jobs by using prefab elements differs with risk
condition, hence skilled foremen, and workers to be employed on the job.
Equipment’s required for the prefab elements in industry can be classified as.
3) Concrete mixers
4) Vibrators
6) Transport machines
Planning co-ordination
It is important to have the pre caster erector/installer and builder working together to
achieve best performance.
• Check for site accessibility and precast panels delivery to site especially low bed
trailers
CE3003 PREFABRICATED STRUCTURES
• Check whether adequate space for temporary storage before installation and
ground conditions. (firm ground & leveled)
• Lifting heights.
• Working radius
• Lifting gears
Skilled personnel’s
• Rigger
• Signaled etc
• Crane model
• Crane safe working load (SWL) (i.e) Based on 15% capacity build in
F.O.S. 1.33 o Lifting capacity must be 1.5 times the total weight i.e) F.O.S 1.5
• Crane boom length is relation to the vertical and horizontal clearance from the
building.
Installation Process
• Check the panels delivered for correct marking lifting hook and position etc.
• Pc Dimension compliance
• Reinforcement Provision/position
1. Setting out
• Check the panels delivered for marking, lifting hook and condition.
• Check starter bars for vertical components before hoisting for installation
4. Grouting works
• Collect test cube sample for testing for critical element or load bearing
elements
5. Connecting joints
• Do Concreting
1. Setting out
• Check protruding/ starter bars are within the Specified tolerance to prevent
any observation during the erection process
• Balcony planter box and shall be supported more than 2 location based on
design considerations
3. Connections/Jointing
5. Erection Purpose
• In Japan
• In Singapore
• DBS China square used the system to erect is efficient and faster
Slab
The roofing slab/flooring slab system consists of planks, which is supported over
R.C.C Joist. The planks can be made in any one of the following form with or without
prestressing.
According to the span & loads.
1. Hollow core sections
2. Double tee section\Channel sections
3. Light weight concrete roofing slab
4. Solid rectangular planks
The usual widths of these types of slabs are 0.5 m & spanning to the requirement
up to a maximum limit of 5 m without prestressing. The thicknesses of planks are
casted in two steps with different mould in access invisible action with adjacent slab by
putting
necessary reinforcement & concreting site.
Joist
The joists are designed as a small beams loaded from planks. These joists
transmit the
loads to the main beams through the channels provided in the main beams in this joist,
triangular shaped stirrups are provided to get the proper bonding or connection with the
planks. The joists are casted partially in the factory the apex portion of the triangular
stirrup will be projecting from the casted top surface. In this projecting a connecting rod
will be inserted and additional base from planks also inserted. This will give monolithic
action as well as the plank will act as a continuous slab over the joists.
Beams (Main & Secondary)
All the main and secondary beams are the same size of 300 x 300 mm varies
reinforcements are provided at varies conditions according to the moments. The beams
are casted for the clear distance between the columns. A square of 10 cm x 10 cm hole
or a depth of 10 cm are provided on either side to achieve the connection with other
beam reinforcement or column reinforcements by proper welding. After welding the
concrete has to be done at the junction with proper care.
At the junction of columns and beams it is necessary or part site controlling for this
purpose the top ends of the beams are trap pored properly. So that it with give access to
site concrete and for needle vibrators to get proper compaction.
Wall Panels
The wall panels are casted with all fixing like door, ventilation, window frames.
These wall panels are non load bearing wall. Therefore neglect solid rectangular cross
section wall panel with R.C.C. from the view of thermal effects and safety the
minimum of 150 mm is provided as wall thickness. This wall is a sandwich type. That
is cellular concrete blocks of 75 mm thick is sandwiched by R.C.C. M25 grade concrete
to a thickness of 37,5 mm on either face with minimum reinforcement since, the walls
are in steel moulds there will be no used to plastering on either face of wall.
This is one of advantage of precast wall panels. The main design factor is the
handling stresses in wall panels.
The infillings may be any light weight, low cost material like brick bats, bricks
light weight concrete acquainted concrete etc. Since the preparation and availability of
raw materials are easy in the case of cellular concrete we are adopting cellular concrete
as infill’s in walls.
Columns
Many type of columns available in prefabricated system. Grooves are provided
on the required faces to keep the walls in position. These grooves will act as a part of
columns and since the area of column has been increased due to nibs will give addition
moment carrying as well as load carrying capacity of columns. At the same time this
grooves give a mild ornamental look to our building.
• The planks are casted to a standard size and they are connected with RCC joists
• The loads from planks are transmitted to RCC joists and then to main beams.
• The main beams are provided with channel sections 10cm projections on the
• The loads from slabs to the main beam will come as point loads.
• The roofing / flooring slabs system consists of planks which are supported over
RCC joist.
• The planks can be made in any one of the following form with or without
• The usual width of these of slabs is 0.5m and spanning to the requirement up to a
• The thicknesses of planks are casted in two steps with different mould to access
Precast RC planks:
• This system consists of precast RC planks supporting over partially precast joist.
RC planks are made with thickness party varying between 3 cm and 6 cm.
• There are haunches in the planks which are tapered.
• When the plank is put in between the joists, the space above 3 cm thickness is
filled with in-situ concrete to get tee-beam effect of the joists.
• The planks are made in module width of 30 cm with maximum length of 150 cm
and the maximum weight of the dry panel is 50 kg.
• Precast joists are rectangular in shape, 15 cm wide and the precast portion is
15cm deep.
• The main reinforcement of the overhang provided at the top in the in-situ
concrete attains sufficient strength.
• The savings achieved in practical implementations compared with conventional
RCC slab about 25%.
• The prefabricated brick panel roofing system consist of is made of first class
brick reinforced with two MS bars of 6mm dia and joists filled with either 1:3
cement mortar or M15 concrete.
• Precast panel channels are trough shaped with the outer side corrugated and
grooved at the ends to provide shear key action and to transfer moments between
adjacent units.
• The lengths of the units are adjusted to suit the span.
• The flange thickness is 30mm to 35mm.
• A savings of 14% has been achieved in actual implementation in various projects.
• Precast hollow slabs are panels in which voids are created by earthen kulars,
without decreasing the stiffness or strength.
• These hollow slabs are lighter than solid slabs and thus save the cost of concrete,
steel and the cost of walling and foundation too due to less weight.
• The width of the panel is 300mm and depth may vary from 100mm to 150mm as
per the span.
• The outer sides are corrugated to provide transfer of shear between adjacent
units.
L - Panel roofing:
• Unreinforced pyramidal brick roof construction system is suitable for low cost
houses in cyclone affected and other coastal areas.
• Corrosion of reinforcement was found to be the major cause of failure of RCC
structure in coastal area and a pyramidal roof with brick and cement concrete
without reinforcement was therefore developed.
• The roofing is provided with peripheral RCC ring beam.
• When shear walls are designed and constructed properly, and they will have the
strength and stiffness to resist the horizontal forces.
• In building construction, a rigid vertical diaphragm capable of transferring
lateral forces from exterior walls, floors, and roofs to the ground foundation
in a direction parallel to their planes.
• Lateral forces caused by wind, earthquake and uneven settlement loads in addition to
the weight of structure and occupants; create powerful twisting forces.
• These forces can literally tear a building apart reinforcing a frame by attaching or
placing a rigid wall inside it maintains the shape of the frame and prevents rotation at
the joints.
• Shear walls are especially important in high rise building subjected to lateral wind and
seismic forces.
• Shear wall buildings are usually regular in plan and in elevation, in some building,
lower floor are used for commercial purposes and the building are characterized with
larger plan
• RC shear wall
• Plywood shear wall
• RC hollow concrete brick masonry wall
• Steel plate shear wall
RC shear wall:
• In general these walls are continuous throughout the building height however, some
walls are discontinuous as the street front or basement level to allow for commercial or
parking spaces.
2. The creation of prefabricated shear panels have made it possible to inject strong shear
assemblies into small walls the fall at either side of a opening in a shear wall
• This walls are constructed by reinforced the hollow concrete block masonry, by
taking advantage of hollow spaces and shape of the hollow blocks.
• It requires continuous steel rods both in the vertical and horizontal directions at
structurally critical locations of the wall panels.
• RHCBM element are designing both as load bearing walls for gravity loads and
also shear walls for lateral seismic loads to safety withstand earthquakes.
• Steel plate shear wall s stem consists of a steel plate wall, boundary columns and
horizontal floor beams.
• Together the steel plate girder, the column act as a vertical plate girder and steel
plate wall act as its web.
• The horizontal floor beams act more or less as transverse stiffeners in a plate
girder.
• The steel plate shear wall systems have been used in recent year in highly seismic
areas to resists lateral loads.
Beams:
• All the main and secondary beams are the same size of 300 mm x 300
mm varies reinforcement are provided at various conditions
according to the moments.
• The beams are casted for the clear distance between the columns.
• A square of 10 cm x 10 cm hole for a depth of 10 cm are provided on
either sides to achieve the connection with other beam reinforcement or
column reinforcement by proper welding.
CE3003 PREFABRICATED STRUCTURES
Wall panels:
• The wall panels are casted with all fixing like door, ventilator, and window frames.
• These wall panel are non load bearing wall. Therefore neglect solid
rectangular cross section wall panel with RCC from the view of
thermal effects and safety the minimum of 150 mm is provided as wall
thickness.
• This wall is a sandwich type that is cellular concrete blocks of 75 mm
thick is sandwiched by RCC.
• M25 grade concrete to a thickness of 37.5 mm on either face with
minimum reinforcement.
• Since, the walls are in steel moulds there will be no need for plastering
on either face of wall. This is one of the advantages of precast wall
panels.
• The main design factor is handling stresses in wall panels.
Columns:
All the main part of a building, including exterior wall and interior wall, floor slab,
roofs, and staircase, may be made up from large panel structure are used in two
main design schemes, frame-panel and panel building. In frame-panel building, all
the base loads are borne by the building’s frame, and as enclosure element.
Frameless buildings are assembled from panels that perform the load bearing and
enclosing functions simultaneously.
1. Large panel structure for Exterior wall
In the first case, they are made from gypsum slag concrete or from other materials
that act as enclosures. In the case of load bearing structure, the wall panels, which
combine enclosing and load bearing function, are made from heavy or lightweight,
silicate or cellular concrete, or vibration set brick or ceramic work.
The dimensions of the panels are determined by the dimensions of the rooms (in
apartment houses), their height is equal to the height of a story, the width is equal to
the depth or width of a room, and the thickness of the walls between rooms is
usually 10-14 cm(between apartment 14-18 cm)
3. Large panel structure for floor slab:
• The large panel structure of floor slabs are usually made from reinforced concrete,
the area of the floor slabs in apartment buildings usually equals the area of one room
and be as great as 30 sq.m.
• Flagging panels have an area of 5-8 sq m. The large panel floor slabs of housing
public, and administrative building are of both the solid and sandwich types in the
latter, provision is made for a sound insulation layer to reduce air and impact notice.
• Composite floor panels, consisting of a load bearing reinforced concrete panel
combined with a floor or ceiling panel and soundproofing, insulating, and other lay
r, a e often used in housing construction.
4. Large panel structure for Roof Element:
• The large panel roof elements are used in housing and public buildings mainly in
the form of combined articles roofs, and in industrial buildings the roof panels have
a span of up to 12 m.
• The weight of large panel structure depends on the method of dividing the building
into prefabricated element; it is usually 1.5-7.5 tons.
• Large panel structure of a high rise apartment building consist of (1) foundation
slab,(2) exterior wall panel,(3) interior wall panel, (4) floor slab,(5) deck ,(6)
exterior panel in the process of installation
• At the joints, the panels have to which steel connecting pieces are welded, thus
linking together all the panels and providing general stability of the building.
• Large panel structures are used in the construction of high rise building.
This also correct because the greater part of the stresses are caused by dead load is by
the uses of stresses.
One can find no real reason for this aversion partly because the cracking of tension
chord has no significance and partly because the possibility of cracking can be
reduced by stressing the tensioned bars before there concreting.
Fibster welder used to stress the tensioned bar after the load had been applied
vierendeel columns are excellent for the stanchions of frames and the columns of
other reinforced concrete structures while trusses are fairly suitable for use in any kind
of that structure .
An additional advantage of these type of columns is that tube pipes and other lines
can be easily be attached to and led through the shaft.
This means that forms the standard point of operation, lost and unutilized area
decrease to a minimum inside the building itself.
In comparison with a structure with moment t-bearing joints the above solution is
connected with greater force effect.
If vierendeel columns and trusses are used the bearing of latter requires only a slight
surplus in material.
In precast concrete construction the joint between the element are of very
important.
• Dry joint
• Wet joint
The wet joints are by using mortar or in-situ concrete where as the dry joint is done by
welding or bolting. The following consideration shall be taken into account.
Structural requirements: The connection must with all requirements regarding the
transmission of forces, moment and permissible deformation or rotation.
Tolerances: The measure to which deviates must be taken up in the joint. It is called joint
flexibility.
Aesthetical requirements : The joints remains completely or in part exposed.
Mode of Erection: With regard to available erection equipment fastest possible erection,
and avoidance or minimizing ob bracing, support, etc
Necessity of checking and adjusting : The joint must be checked whether it is proper
dimensioned or not . Therefore the adjustment may be possible.
Design of joint:
The entire structure as well as each unit own must be designed to resist all loads, forces
and moments acting there on when the structure is in the use.
Stability of structures
The overall stability of the structure must be need during each phase of construction.
Loading condition during construction
Loading condition during construction my causes higher stresses than those through
normal usage. Temperature loads are erected due to erection , material and temperature
supports.
Unequal settlement
In case of fixed end joint the possibility of settlement at the supports should be
investigated.
Reinforcement anchorages:
In general the connection will require additional reinforcement bars and anchorage which
must be so designed that a sound fill and proper compaction of the concrete can be
realized.
Chamfers:
Square edges of all precast elements are liable to sapling or chipping and also causes
accident.
Bond:
The bond surface which should transmit vertical shear must either be roughed or ribbed
Bolted Connection:
When using bolted connection , tolerance can be increased by either providing one of
the plates of each pair with a slot or by drilling the bolt hole.
Advantages
• It is very simple.
• Scaffoldings are not necessary .
• Easy of hoisting process .
• Easy of assembling .
Disadvantages :
• Formation of joints is very difficult .
• Joints are at corners , where the moments usually reach their maximum values
.
The trend to lesson the number of joints and to precast larger members in one
piece leads to the prefabrication of entire frames . Such frames are as shown in figure ,
but these solutions are appropriate only for site prefabrication . The production of frames
does not cause particular trouble , but their hoisting is more difficult and requires careful
preparation . The stress distribution of straight members during their hoisting is, in
general, statically determined . Example that of a beam lifted at two points or at more
than two points when using a balance, or a cable – rocker or that of column lifted at one
point and supported at its lower end.
The stress distribution arising in frames during their hoisting. On the other hand,
is frequently statically redundant. The tilting of a frame from the horizontal into the
vertical position, lifted at two points by two separately acting hoisting machines,
illustrates the above statement. If these two points are not hoisted exactly at the same
time and with prefect uniformity , the frame itself will be affected by torsion. Connecting
the two suspension points by a balance or a cable rocker enables the frame to be hoisted
at one single point.
Now the stress distribution is statically determined but if the rocker is not
suspended at the exact point, torsion can also arise in this case. This shows that the
hoisting of a frame is far more complicated than hoisting a straight member. The hoisting
of asymmetric frame is particularly difficult. In this case the force affecting the rocker
CE3003 PREFABRICATED STRUCTURES
does not act at the same place during the tilting up process as it does later, when the frame
is already suspended. Therefore, the elimination of torsion during hoisting and placing
requires either the transfer of the suspension point on the rocker after the tilting up is
finished or the application of a counter weight. Entire frames are precast as a rule, in a
horizontal position on the ground close to their final location. They can also be produced
in a vertical position standing side by side.
While transporting the prefab elements in various systems, such as wages, trucks,
bullock cards etc. care should be taken to avoid excessive cantilever actions and desired
supports are maintained. Special care should be taken in negotiating sharp beds uneven
of slushy roads to avoid undesirable stresses in elements and in transport vehicles.
Before loading the elements in the transporting media, care should be taken to ensure
the base packing for supporting the elements are located at specified portion only.
3.5.2 ERECTION
It is the process of assembling the Prefabrication element in the find portion as per the
drawing. In the erection of prefab elements the following items of work are to be carried
out.
1). Slinging of the prefabricated elements.
2). Tying up of erection slopes connecting to the erection hooks.
4). Cleaning the steel inserts before incorporation in the joints lifting and setting the
elements to correct position.
5). Adjustments to get the stipulated level line and plumb.
The erection work in various construction jobs by using prefab elements differs with risk
condition, hence skilled foremen, and workers to be employed on the job.
Equipment’s required for the prefab elements in industry can be classified as.
3) Concrete mixers
4) Vibrators
6) Transport machines
Planning co-ordination
It is important to have the pre caster erector/installer and builder working together to
achieve best performance.
• Check for site accessibility and precast panels delivery to site especially low bed
trailers
CE3003 PREFABRICATED STRUCTURES
• Check whether adequate space for temporary storage before installation and
ground conditions. (firm ground & leveled)
• Lifting heights.
• Working radius
• Lifting gears
Skilled personnel’s
• Rigger
• Signaled etc
• Crane model
• Crane safe working load (SWL) (i.e) Based on 15% capacity build in
F.O.S. 1.33 o Lifting capacity must be 1.5 times the total weight i.e) F.O.S 1.5
• Crane boom length is relation to the vertical and horizontal clearance from the
building.
Installation Process
• Check the panels delivered for correct marking lifting hook and position etc.
• Pc Dimension compliance
• Reinforcement Provision/position
1. Setting out
• Check the panels delivered for marking, lifting hook and condition.
• Check starter bars for vertical components before hoisting for installation
4. Grouting works
• Collect test cube sample for testing for critical element or load bearing
elements
5. Connecting joints
• Do Concreting
1. Setting out
• Check protruding/ starter bars are within the Specified tolerance to prevent
any observation during the erection process
• Balcony planter box and shall be supported more than 2 location based on
design considerations
3. Connections/Jointing
5. Erection Purpose
• In Japan
• In Singapore
• DBS China square used the system to erect is efficient and faster
Advantages
Disadvantages
A shear transfer by bond between precast and in-situ elements is possible, when
the shear stress is low. It is not necessary to deliberately roughen the surface texture of
precast units beyond the as-cast finish, which may be of a slip-forming, extrusion or
tamped finish. Shear transfer by shear friction requires the presence of a permanent
normal compressive force. The force may arise from permanent gravity loads, by
prestressing or be artificially induced by reinforcement bars placed across the joints.
Shear keys for the transfer of shear forces between elements are obtained by cast in-situ
concrete or grout in joints between the elements which surface castellations. Under the
action of a shear load, the shear keys act as mechanical locks that prevent significant
slips at the interface.
2. Expansion Joints
3. Contraction Joints
4. Isolation Joints
0.I D
'
{ 0. 2 D
52
Unregulated cracks can grow and result in an unacceptably rough surface as well
as water infiltration into the base, sub base and sub grade, which can enable other types
of pavement distress.
Contraction joints are the most common type of joint in concrete pavements, thus
the generic term joint‖ generally refers to a contraction joint. Contraction joints are
chiefly defined by their spacing and their method of load transfer. They are generally
between 1/4 – 1/3 the depth of the slab and typically spaced every 3.1 – 15 m
Isolation joints have one very simple purpose they completely isolate the slab
from something else. That something else can be a wall or a column or a drain pipe.
Here are a few things to consider with isolation joints:
• Walls and columns, which are on their own footings that are d p than the slab
sub grade, are not going to move the same way a slab does as it shrinks or
expands from drying or temperature changes or as the sub grade compresses a
little.
• Isolation joints are formed by placing preformed joint material next to the
column or wall or standpipe prior to pouring the slab. Isolation joint material is
typically asphalt- impregnated fiberboard, although plastic, cork, rubber, and
neoprene are also available.
• Isolation joint material should go all the way through the slab, starting at the sub
base, but should not extend above the top.
• For a cleaner looking isolation joint, the top part of the preformed filler can be
cut off and the space filled with elastomeric sealant. Some proprietary joints
come with removable caps to form this sealant reservoir.
• Joint materials range from inexpensive asphalt-impregnated fiberboard to cork
to closed cell neoprene. Cork can expand and contract with the joint, does not
extrude, and seals out water. Scott White with APS Cork says that the required
performance is what determines the choice of joint materials. How much motion
is expect, exposure to salts or chemicals, and the value of the structure would all
come into play—and of course the cost.
• At columns, contraction joints should approach from all four directions ending
at the isolation joint, which should have a circular or a diamond shaped
configuration around the column. For an I-beam type steel column, a pinwheel
configuration can work. Always place the slab concrete first and do not install
the isolation joint material and fill around the column until the column is
carrying its full dead load.
Requirements of joints
a. The joints should be leveled
Joint Techniques:
The joint technique is a vital role for prefabricated structures. The joint
mechanism is implemented to prefabricated elements. In case of dry joint the joint is
under the category of bolting and welding .The bolted or welded connection should be
designed properly with economical consideration. In case of wet joint the joint is in situ
concrete. The in situ concrete should be in rich mortar.
Design of expansion joint
1. The expansion joint are provided to accommodate movements of thermal
expansion
2. To avoid the cracks expansion joints should be provided
3. The thermal are formed due to summer seasons and the precast member
will expand behind the original dimension. This cause the cracks will be
developed in the prefabricated structures
4. Hence to avoid the formation of cracks expansion joint should be provided
5. AS per NBC the structures which are more than 20m the expansion joint
must be provided the material are used for expansion joints bitumen with
mineral , filler and cork strip. The expansion joint is protected by a sealing
compound at the top against intrusion. The building is commonly separated
the structure. The welded joints between the panels which permits the
rotation.
CE3003 PREFABRICATED STRUCTURES
The exposed roof elements are higher expansion produced the materials are also
expanded. The common building material, linear co-efficient of thermal expansion are
given below
a) Shrinkage effects
b) Thermal effects:
Bridges are subjected to all modes of heat transfer, radiation, convection and
conduction. Each mode affects the thermal gradients generated in a bridge
superstructure differentially. Climate influences vary geographically resulting
in different seasonal and average properties.
Example:
A massive concrete box girder bridge will be much slower to respond to an
imposed thermal situation, particularly diurnal variation than steel plate Girder
Bridge composed of many relatively thin steel elements.
Variation in superstructure average temperature produces elongation and
shortening .Therefore thermal movement ranges calculated using a maximum and
minimum anticipated bridge. Super structure average temperature anticipated
during the structures life time. The consideration in the proceeding have led to the
following temperature guide lines
∆temp = α. Lt. . ∂ T
Where
Lt =Tributary length of the structure subjected to thermal variation
α= Co-efficient of thermal expansion 0.000006 in /0 F for concrete and
0.0000065 in /0 F
∂ T= Bridge superstructure average temperature ranges as a function on
bridge type and location Generally these settings are specified for
temperature of 400 F , 640 F and 800 F
• Lengthening of columns.
• Jointing of beams.
• Forming of joints of arched structure.
• Joining of joints of post tensioned structures.
• Joining of precast to monolithic reinforced concrete structures.
The depth of the calyx is dimensioned according to the long or side length of the
column. The depth of the calyx should be equal to 12.5% of the length of the
column.
The opening of the calyx is 6-10 cm greater in all direction than the class
of the column. This is enabling the vibrator to be operated while concreting at
the bottom of the calyx of checked by leveling before concreting.
A similar steel plate is also put on the lower end of the column when
positioning the column. These two steel plates must be on each other. The
dimensions of these steel plates are frame 100x100x10 to 150x150x10 mm a
chord into the concrete after the column is put in placed properly plumbed two
advantages of the calyx joint should be mentioned.
1. The placing plumbing and fixing of the column as well as the
subsequent filling of the calyx with concrete is for simpler and
requires less time than in the case of a welded joint.
One method of forming a hinge like joint consists either or placing to beam on to
a small cantilever protracting frame the column or of putting it on the bottom of an
adequately shaped opening left out of the column shaft.
The beam rests temporarily on a tongue like extension on a steel plate placed in
this opening on the supporting surface the tongue is also furnished with a steel plate
anchored into the concrete The other parts of the tongue are supported after the placing
has been finished with concrete cast through an opening left for this purpose.
2. Subsequent concreting.
3. Steel plate.
The lengthening of columns can be executed similarly to the joining with footing,
accordingly the upper columns rests on the lower ones by a tongue like extension. The
steel bars of the main reinforcement are joined by overlapping looped steel bars a
welding. There after the stirrups have to be placed of finally the joint must be
concreted.
The functions of beams can be affected either by overlapping the protracting steel bars
or by welding them together.
Fig. shows the hinge like joint of purlins. In this method the whole shear must be born
by both cantilevers (i.e.) by two separate structures therefore it is expedient to form this
joint at least for large girders.
The method illustrated in the fig presents a dry joint of beams which is called a bolted
front. The advantages of this joint are immediate bearing capacity.
Precast arches are usually produced and assembled in the form of three hinged
structures. When the constant load has already been applied the centre joint is
frequently eliminated. The omission of the centre joint increases the rigidity of the
structures. Naturally arched structures can also be precast in a piece i.e. in the form of
two hinged ones.
Hinges of arched structures can be made by using either steel shors are more expensive,
but the centre transmission of forces is enhanced by their use of forming of joints on an
arched structure.
The arrangement of the Centre junction and the end hinge of an arched structure. This
method was used in the construction of the hall for the middle rolling train in
D.O.Sgyor. The structure was precast of assembled in the form of a three-hinged arched
transformed latest into a two-hinged one.
Post tensioned structure can generally be joined for more simply then the usual
reinforced concrete structures, by using post tensioning it can be ensured that in the
entire structure. The joints included only compressive can develop consequently the
problem of joining can be solved in a very easy manner namely by placing plane
surfaces side by side and then filling the gaps with cement mortar by so doing longer
beams can also be produced from shorter precast member. Thus is post tensioned
structures the forming of joints does not cause difficulties.
Sketches on solution of principles relating to the joining of post tensioned structure are
to be illustrated in the fig. all these joints are of course rigid and moment bearing. It is
not permissible for the mortar which is to be poured into the ducts of the stressing
cables to avoid this cable ducts are joined by placing a shore piece of tube or rubber
ring into the duct itself.
In this case the function can be established in the same way as already been described in
the previous paragraph an joining namely by placing the end of the beam either on to a
cantilever protruding from the column or into an opening formed i to the columns shaft.
When making the joint, first of all a 2.5 cm deep cavity is chiseled out of the sole of the
precast column. The bottom of this cavity should be roughen d so as to
attain a belter band between the concrete of the monolithic beam and the precast
column.
• This connection for SSB beams may be considered if the vertical shear force is very
CE3003 PREFABRICATED STRUCTURES
small
• The plate should have sufficient thickness to prevent it from bending. In
determining the thickness, the maximum cantilever moment may be assumed to
occur at the column reinforcing bars.
• To avoid point bearing ,special care should be taken to install the beam
perpendicular to column face.
• For lateral location of the beams ,saddle plates may be used.
• The bearing plate must be provided with permanent protection against corrosion and
against fire.
BEAM TO COLUMN CONNECTION WITH ANGLE CORBEL
• This connection for SSB when carried out according to variant ―A‖ is only able
to transmit small vertical shear force and could be generally considered only for
temporary structures
• VARIANT “A”
• In variant A the angles are connected with the horizontal flange up and by mild
steel bolts
• Point bearing on the column face can be avoided by applying an epoxy layer at
the interface with the vertical angles just prior to placing the angles
• The entire corbel construction should be prefabricated and must be cast in which
CE3003 PREFABRICATED STRUCTURES
• The corbel consists of two vertically placed channels to which, outside the
column horizontal bearing plates are welded
• An additional tie must be provided immediately under the corbel, in an end
column also above the corbel to counteract the splitting forces
BEAM TO COLUMN CONNECTION WITH STEEL JOIST CORBEL,
ENCASED IN THE BEAM
• This connection for SSB can depend the size of the bearing surface, transmit a
fairly large vertical shear force.
• In this case the beams are supported on a steel joist corbel which extends into a
recess in the end of the beam.
VARIANT A
• The corbel is formed by a cast-in broad flange rolled steel I section.
• Additional tie is provided to counteract the splitting forces.
VARIANT B
• Could be considered if the beams must also be located vertically.
• The corbel consists of two rolled steel I sections with splice plates welded in
between the webs, so that the bolts can pass through a hole in the beam.
• Additional tie under the corbel to counteract the splitting forces.
• Corbel must be provided with a permanent protection against corrosion and fire
VARIANT B
• The beams have notched ends and are supported on corbels.
• The notched ends must be reinforced against the vertical shear force and also
against torsion if it is eccentrically loaded.
VARIANT C
• Columns are provided with concrete corbels which are bolted to the column
faces.
• It is advisable to use high tensile bolts and provide an Epoxy layer at the column
a d corbel interface. The bolts and nuts must have permanent protection against
corrosion and fire.
CE3003 PREFABRICATED STRUCTURES
• To prevent the beams from toppling, beam and column interface could be shaped
to form a tongue and groove joint.
• The hanger construction consists of two vertical channels with flanges facing
each other which are welded to anchor bars projecting from top of beam
• During erection, these channels are placed on an equalizing pad on top of the
corbel.
• The beam is secured vertically and laterally by tightening a nut with washer on a
bolt which projects from the corbel through the slot in between the channel flanges.
It has also been suggested that the degree of progressivity in a collapse be defined
as the ratio of total collapsed area or volume to the area or volume damaged or
destroyed directly by the triggering event.
• The isolated failure of this key member or section then initiates a sequence of
events, coursing failure of the entire structure
d. Verification procedures
First the requirements, particularly the question if collapse resistance is necessary.
should he clarified. The necessity depends on the structure's significance with respect
to the consequences of a collapse, including the immediate material and immaterial
losses but also indirect effects, e.g., the possible impairment of the infrastructure and
of civil and national defense_ Another criterion for the determination of requirements
is the structure's degree of Exposure to hazards of war, malicious action, and natural
disasters. The exposure can be considered particularly high for public buildings,
major bridges, and other lifeline structures, If collapse resistance is deemed
necessary, the following design objectives must be specified:
1. Assumable extent of accidental circumstances
2. Assumable extent of initial local failure
3. Acceptable extent of collapse progression
4. Acceptable extent of damage to the remaining structure
5. Applicable load combinations and safety factors
The following design strategies to prevent progressive collapse are mentioned in the
literature and have at least partially made their way into-the design codes:
These methods are further discussed in Section 4 below. The prediction of the
structural behavior following a local failure requires suitable verification procedures
Accurate analysis will require a high degree of expertise and modeling effort. Thus,
development and validation of simplified but admissible verification methods would be a
worthwhile undertaking. The design criteria I. to IV. Listed above are to date only partially
addressed in codes and guidelines. As far as applicable design criteria are not available in
codified form, they should be agreed upon by the contracting and other affected parties or
established by the building authorities. It is anticipated that the design criteria can only
partly be developed from first principles and reliability theory.
There will remain necessity for judgment and a decision-making process, most
notably when stipulating the acceptable extent of collapse progression. On the other hand,
the choices to he made here are relatively transparent—at least when compared to the
choice of a safety index 13 so that an informed societal consensus is in principle possible
(even when that consensus leads to the conclusion that certain kinds of structures should
better not be build).
ASCE 7-02
The American society of civil engineers minimum design load for buildings and
other structure (ASCE,2002) has a section on general structure integrity that reads thus
building and other structures Shall be design d to sustain local Damage with the
structural system as a whole remaining stable and not being damaged to an extent
disproportionate to the original local damage.
This shall be achieved through an arrangement of the structural element That
provides stability to the entire structural system by transferring loads from Any locally
damaged region to adjacent regions capable of resisting those Loads without collapse.
ACI 318-02
The code provisions include a general statement that "In the detailing of
reinforcement and connections members of a structure shall be effectively tied together
to improve integrity of overall structure'' and many specific prescriptive requirements
for continuity of reinforcing steel and interconnection of components.
There are additional requirements for the typing together of precast structural
components. None of the ACI provisions are threat specific in anyway.
The 2003 edition of the GSA'"s facilities standards for the public buildings
service (GSA, 2003 a) retained the "Progressive Collapse'' heading from the 2000
edition.
Exemptions based on the type and size of the structure (for instance, any building
of over 10 stories is non- exempt) and is unrelated to the level of threat.
The GSA Progressive collapse analysis and design guidelines for new federal
office buildings and major modernization projects(GSA,2003b) begins with a process
for determining whether a building is exempt from Progressive Collapse considerations.
Exemption is based on the type and size of the structure (for instance any building of
over 10 stories is non-exempt) and is unrelated to the level of threat.
Considerable detail is provided regarding the features of the analysis and the
acceptance criteria.
In recent years, a lot of achievements have been made to incorporate these influential
factors into building codes accurately as well as practically. The basis for IBC 2000
seismic provisions is the 1997 NEHRP "Recommended Provisions for the Development
of Seismic Regulations for New Buildings and Other Structures" (FEMA 302).
Criteria Selection
In IBC 2000, the following basic information is required to determine the seismic loads:
I. Seismic Use Group According to the nature of Building Occupancy, each structure is
assigned a Seismic Use Group (I, II, or III) and a corresponding Occupancy Importance (1)
factor (1 E 1.0, 1.25, or 1.5).Seismic Use Group I structures are those not assigned to either
Seismic Use Group H or III. Seismic Use Group 11 are structures whose- failure would
result- in a substantial public hazard due to occupancy or use. Seismic Use Group III is
assigned to structures for which failure would result in loss of essential facilities required
liar post earthquake recovery and those containing substantial quantities of hazardous
substances.
2. Site Class eased on the soil properties, the site of building is classified as A, B, C, D, E
CE3003 PREFABRICATED STRUCTURES
and F to reflect the soil-structure interaction. Refer to 113C 2000. for Site Class
definition.
maps reflect seismic hazards on the basis of contours. They provide the maximum
considered
earthquake spectral response acceleration at short period SS and at 1-second period Sl. They
are for Site Class B, with 5% of critical damping. Refer to the maps in IBC 2000.
used to account for these characteristics. Systems with higher ductility have higher R
values.
With the above basic parameters available, the following design and analysis criteria can be
determined. Seismic Design Category. The Seismic Design Category is based on the
seismic group and the design spectral response acceleration coefficients, SDS and SDI,
which will be explained later.
The Seismic Design Category for a structure can be determined in accordance} Seismic
Design Categories are used to determine the permissible structural systems, the limitations
on height and irregularity of the structural components that must be designed for seismic
resistance and the types of lateral force analysis that must be performed.
Seismic Use Groups I and II structures located on sites with mapped maximum considered
earthquake spectral response acceleration at 3.-second period SI, equal to or greater than
0.75g, shall be assigned to Seismic Design Category E. Seismic Use Group IIl structures
located on such sites shall be assigned to Seismic Design Category F. A structure assigned
to Seismic Design Category E or F shall not be sited where there is the potential for an
active Fault to cause rupture of the ground surface at the structure. Building Irregularity.
Building with irregular shapes, changes in mass from floor to floor, variable stiffness with
Thus, for each type of these irregularities, additional design requirements shall be
followed to maintain seismic-resisting capacity. IIIC 2000 requires that all buildings be
Structures assigned to Seismic Design Category A need only comply with the
following:
The direction of application of seismic forces used in design shall be that which will
produce the most critical load effect in each component. The design seismic forces are
The effect of this lateral force shall be taken as E in the load combinations.
buildings. Because damaging earthquakes are care, economics dictate that damage to
• In this approach the structure is designed such that if any one component fails,
alternate paths are available for the load in that component and the general
collapse does not occur.
• This approaches the benefit of simplicity and directness in its most common
applications, design for redundancy requires that a building structure be able to
tolerate loss of any one column without collapse this is an objective easily
understood performance requirements the problem with the redundancy approach
as typically practiced is that it does not account for difference in vulnerability .
• Clearly one column redundancy when each column is a W8x35 does not provide
the same level of safety as when each column is a 2000 I/ft build up section.
• Indeed and explosion that cloud take out the 2000 I/ft column would likely
destroy several of the W8 columns making one column redundancy inadequate to
prevent collapse in that case.
• And ate codes and standards mandate redundancy do not distinguish between two
situation they threat every column as equally likely to be destroy d in fact since it
is generally much easier to design for redundancy of a small and lightly loaded
column redundancy requirements may have the unfortunate consequence of
encouraging design with small(and vulnerable) columns rather than fewer larger
column.
• For safety against deliberate attacks (as opposed to random accidence) this may
Local Residence
Interconnection or continuity
This is strictly speaking not a third approach separate from redundancy and local
residence. But a means of improving either redundancy of or local residence (or
both).Studies of many recent building collapses have shown that the figure could have been
Avoided or at least reduced in scale, at fairly small additional cost if structural components
had been interconnecting more effectively. This is the basis of the structural integrity
requirement in the ACI 318 specification (ACI 2002)
An earthquake is the sudden shaking of the surface of the earth caused by the passage
of seismic waves through the earth’s crust. During the earthquake, vibrations occur in all
directions radiating from the epicenter. The sudden release of energy cause structure to
vibrate and inertia forces are acting on them. Most of the earthquakes are result from
tectonic events, primarily movements on the faults, and remaining related to the manmade.
The lack of earthquake knowledge and its incorporation in the building design and
execution leads to the failure of structures.
• Vertical and horizontal movement and the inertia of buildings cause frequent
changes in buildings’ weight.
• Use of poor-quality material.
• Massive structure (greater the mass of the structure, more the lateral force is
exerted on the building).
• More the height of building, lesser its stability.
There are 9 severe earthquakes has witnessed by India in the last 3 decades between
1990 to 2020 and reports claim the number of causalities approx. 30500. Although, certain
parts of the country are more prone to earthquakes (seismic zone V of IS 1893(Part 1)-
2016) than the others [4]. No region can be considered free from earthquakes. In the Indian
scenario, minor earthquakes are reported near the seduction zone (Himalayan belt) on a
daily basis, whereas in the interpolate region (Deccan plateau) few major earthquakes have
been observed over the years. The performance of the built environment during the past
earthquakes has shown its brittle nature and has created an itch among the engineers and
architects to move towards seismically efficient buildings.
OBJECTIVE
The main aim of a structural engineer is to prevent the structural damages that are caused
due to earthquakes.
• To increase the stability of structures against inertial forces using modern techniques
• To know about new and advanced methods for earthquake-resistant structures.
• To prevent deflection of structure which causes failure by using new and advanced
methods.
METHODOLOGY
Since it is clear that our main reason for this research is to make the public aware and
improve towards this ruinous phenomenon that is Earthquake matter. We have decided to
research new technologies for the construction of earthquake-resistant structures, starting
with local On the other hand, up to more percentage of housing reserves in rural areas, the
urban population grew rapidly during last decade. The growth of the urban population in
building projects, and then discovered and cited new approaches that the world is still
using right now.
• Creating idea
• Evaluation for its necessity
• Supervising projects
• Researching website
• Collecting information
• Conclusion
NECESSITY FOR EARTHQUAKE-RESISTANT CONSTRUCTION
As per census 2011 India, there are more than 330 million dwelling units in the
country, two-thirds out of which are rural households. According to India's geological
survey, the country has been classified into four seismic zones having different seismic
capabilities the Indian census by 32% has increased from 286 million in 2001 to 377
million in 2011.
About 30% constitute residential units of seismic zone IV and V.These rural building
units are mainly made by the use of locally available materials like mud and unburnt
bricks, stone walls, or walls made of burnt bricks, all these are very poor in construction and
maintenance. Besides a large percentage of housing facilities in rural areas, the urban
population has increased rapidly during the last decade. The growth of the urban population
in the Indian census by 32% has increased from 286 million in 2001 to 377 million in 2011.
The urban population is estimated to be around 590 million by the end of 2030.As per the
statistics, 50% of the demand for construction work in India comes from infrastructure.
Sector, the rest comes from industrial activities, residential and commercial development,
etc [1][6]. Due to this rapid urbanization, demand for infrastructure, essential infrastructure,
residential layout, and community development has increased.
The occurrence of earthquakes in (day time or night time) plays a major role as they
have a direct impact on the occupancy of buildings. for example. The Latur earthquake
(1993) took place in the early hours around 3:53 AM most people were sleeping in the
affected area. On the contrary, the Bhuj earthquake (2001) occurred around 8.46 AM, in
which most people woke up and there was minimal interference in the building. The two
earthquakes showed poor performance of non - engineered building units such as random
rubble masonry in mud mortar with heavy roofs as well as modern multi-story RC framed
buildings (Figure 2).
The Last seismic experience shows that modern residential buildings lack seismic designs.
Further, the importance of incorporating seismic principles in the structural design of the
building to function as a single unit during the earthquake has become clear. Empowering
rural communities to ensure seismic safety of building stock by generating awareness about
earthquakes and the significance of earthquake-resistant buildings. The environment built in
urban areas should be planned and has to be carefully prepared in the initial stages so that
the constructing layout is suited for seismic performance.
BUILDING TYPOLOGIES
The classification of the building is based on the material used in the building such as