WEEK 1
WEEK 1
Objectives
To participate in the daily site activities and gain practical experience
To collect technical information on the ongoing construction works
To observe and understand the step-by-step processes and procedures taken in
different activities at the site
Work completed
Levelling
This process was caried out at the base/ excavated level for the pipe line running from the
manhole MH-169 to MH-170.
Before the activity was carried out, the gradient at the proposed level was first calculated.
Difference∈IL
Gradient =
Difference∈elevation
After obtaining the gradient, then the reduced levels and formation levels were obtained.
These enabled us to obtain the cut for excavation.
On ground, the dumpy level was used in the exercise. It was first setup and levelled correctly.
Procedure
2. Levelling up;
a) Position the telescope parallel to any two foot screws, then turn the two foot screws
uniformly (at the same speed) and simultaneously either outwards or inwards (i.e. in
opposite directions) until the bubble is brought to the centre.
b) There after turn the telescope through 90 0 i.e. until it's over the third foot screw, this
will cause the bubble to be off the centre, then turn the third foot screw only until the
bubble is brought back to the centre.
c) Turn the telescope back to its initial position (a), and re-level if necessary and then
turn it through an angle of 1800.
3. Target observation: Once the instrument has been levelled and parallax removed, the
next stage is to sight to the target.
1m
To obtain the respective Northing, N and Easting, E, we added the coordinate at the
edge to the distance between the edge and centre which was 1m.
N = 1274.985 + 1.000 = 1274.985
E = 525.200 + 1.000 = 526.200
1. Points on the base were then located for each centre line using the total station
ensuring that the respective points contained the northing, N or easting, E along the
centre lines.
Figure 4 Placing staff at a point to read off coordinates with a total station
2. The points were then marked off using a marker.
Marked point.
1. The required position of the pedestal was located by measuring 40mm (minimum
concrete cover) from the edge of the rebars on both sides.
2. The position of the key was then marked out as shown in the figure and then cut using
a grinder with a concrete cutting disc.
4. Debris was then cleaned out, and the rough area was blown.
This process is also referred to as roughening and it was carried out to ensure that the
concrete to be cast will bond with the concrete of the footing.
Rebar installation and tying
This involved inserting and tying the stirrups and J-L hook rebars into the reinforcement bars
Reinforcement bar
Two-legged
stirrups
720mm
320mm
320 mm
320 mm
1. The centre was offset at a suitable distance of 720mm (The 20mm was to cater for the
thickness of the formboard) to obtain drilling points which were then marked off.
2. Holes were then drilled at the marked points at either side of the base/ footing.
720mm
3. Short steel bars were then inserted in the holes and a string was tied between them
ensuring that it was kept taught.
Figure 13 String tied between steel bars
4. The distance from the outer surface of the formboard was then measured and
compared with the expected distance – in this case the expected being 500mm.
This was calculated as follows;
Distance from board to string = distance from centre point – (thickness of column +
thickness of formboard)
Distance = 720 – (200+20) = 500mm
5. If the distance was less or more then the formwork was adjusted by hitting it with a
hammer until it was well aligned. This was done along its entire length.
6. The formwork was then fixed in the obtained position by inserting a timber piece
supported by a stee bar as shown in the figure
1. With the ground level and compressed, a geotextile membrane will be placed along the
whole length of the pipeline to cover the ground and walls.
2. Stone dust will then be poured to a height of 150mm.
3. The pipes will the be laid along the line more stone dust placed to a height of 300mm from
the top of the pipes to cover the pipes completely.
4. Geotextile membrane will be used to cover the top before soil is added and compressed.
Figure 17 Section of pipe and different layers in ground
Figure 23 Section of plan showing construction zones - 4190, 4010 and 4060
BARNGI TERRY
Signature:_____________________
Date:_________________________