FIDIC Form of Contract
FIDIC Form of Contract
Citation: Nwogu P.C., and Emedosi A. (2024) FIDIC Form of Contract: A Study Review, British Journal of Environmental Sciences,
12(2),43-48
ABSTRACT: FIDIC (Fédération Internationale des Ingénieurs - Conseils) is an International body whose
membership consists of National Associations of Consulting Engineers. It has in publication different suites
of contracts used for international engineering projects, viz; FIDIC REDBOOK (Construction), FIDIC
YELLOW BOOK (Plant& DB), SILVER BOOK (Turnkey/EPC) and FIDIC GREENBOOK (Short Form
Contract). Generally, the FIDIC contract contains 20 Clauses but seventeen (17) of which have common
clause names and the suitability of this FIDIC Suite is a measure of ‘Risk distribution’. Whereas there is an
obvious similarity with regards to the number of clauses contained in each of the FIDIC Suites, but this paper
limits attention only to General Provisions, Force Majeure, Claims, Disputes and Arbitration.
INTRODUCTION
Popular Standard FIDIC Contract will always encompass an in-depth defined topics covering jobs and
authority, work conditions, delays brought about by specialists, methodology for dispute settlement, liability
and risk related issues. FIDIC is an acronym for Fédération Internationale des Ingénieurs – Conseils which
translates to ‘the International Federation of Consulting Engineers’; headquartered in Geneva, Switzerland.
FIDIC membership consists of the National Associations of Consulting Engineers. The suite of contracts
FIDIC publishes for international engineering projects is its most well-known product.
There are twenty (20) provisions in total; seventeen (17) of which have common clause names, are included
in the major contracts of 1999. FIDIC contracts are widely relevant and used, as evidenced by the fact that
they have been translated into fifteen languages (Hillig et al., 2010). The major classifications of FIDIC
include the FIDIC REDBOOK (Construction), FIDIC YELLOW BOOK (Plant& DB), SILVER BOOK
(Turnkey/EPC) and FIDIC GREENBOOK (Short Form Contract)
The FIDIC REDBOOK (Construction) is an agreement structure where the design is carried out by the
employer and the contractor is paid on an estimation premise. Accordingly, the RedBook follows the
conventional procurement route of Design, Bid and Build. The Acknowledged contract Sum depends on
quantity of work; the contractor is paid for the extent of work achieved. The FIDIC YELLOW BOOK (Plant&
43
British Journal of Environmental Sciences 12(2),43-48, 2024
Print ISSN: 2055-0219(Print)
Online ISSN: 2055-0227(online)
Website: https://www.eajournals.org/
Publication of the European Centre for Research Training and Development–UK
DB) is an agreement structure where the design is completed by the contractor who will be paid on lump sum
basis. It is viewed as an even agreement structure holding a fair harmony between the interests of the two
players to the agreement. On the other hand, SILVER BOOK (Turnkey/EPC) is a contract in which the design
is performed by a contractor who receives a lump sum payment. This contract is intended for EPC / Turnkey
projects. Most of the shared risk is assigned to the contractor in SILVER BOOK. It is not intended to be used
when significant unidentified risks are planned or expected. The short form of FIDIC is FIDIC GREENBOOK.
This type of contract is used for relatively small projects or works that are repetitive or of limited duration.
Work must be carried out according to the plan developed by the employer. FIDIC guidelines state that the
acceptable limits for the capital value and duration are $500,000 and 6 months respectively (Jaeger & Hök,
2010).
This paper, therefore, focuses on these four major FIDIC Suites and as well as few Clauses in a bid to
reviewing the most commonly used standard-form of construction contract in international projects.
One common element seen in the 1999 Red Book is the engineer's role. Depending on the situation, he may
be required to act on behalf of the employer or to reach a just conclusion. The absence of any mention of an
impartial Engineer in the contract may cause Contractors some anxiety. A member of the Employer’s staff is
designated in the contract as the authorized individual to shoulder the responsibility of the Engineer (Hillig et
al., 2010). Albeit there is lack of express reference to an impartial Engineer in the contract, Clause 3.5
(Determination) provides that where agreement cannot be reached between the Employer and Contractor over
the settlement of any claims; that the Engineer shall make a fair determination while relevant circumstances
are taking into consideration. However, his role in fair determination and/or pre-arbitral decision-making has
witness obvious amendments. According to Wade, (2005) for instance, while incorporation the FIDIC RED
Book into its Standard Bidding Documents, the World Bank sanctioned notable modifications. The most
notable of these was the addition of a mandatory Dispute Review Board to replace the Engineer’s customary
pre-arbitral “Decision”, which was previously required for all large contracts. Due in part to this and in
response to dynamic global perspectives on dispute settlement, FIDIC released a Red Book supplement in
1996 that allowed the use of a Dispute Adjudication Board in lieu of an “Engineer’s Decision”
Regarding contractor claims, there are two notable deviations from the JCT SBC 2005 contract. First, the only
Red Book with tight time limits is the 1999 edition. Secondly, the sections that include the events that support
the claims are dispersed across the whole contract and are not included in thorough occurrence listings.
Clauses 13.2 on value engineering and 20 on the impartial dispute adjudication board are new additions.
According to Murdoch and Hughes (1999: p. 113, cited in the preamble to the 1999 Red Book), the most
interesting thing about the 1999 Red Book is that it is divided into general conditions and specific conditions
(Hillig et al., 2010). It is clear from the contract’s preamble that these two parts together constitute the terms
of the contract governing the parties’ rights and obligations. FIDIC contracts witnessed a humongous reduction
44
British Journal of Environmental Sciences 12(2),43-48, 2024
Print ISSN: 2055-0219(Print)
Online ISSN: 2055-0227(online)
Website: https://www.eajournals.org/
Publication of the European Centre for Research Training and Development–UK
in the number of clauses. The Red Book as well as Yellow and Silver Books contain 20 clauses; this is a far
reduction from the original 72 clauses.
The Engineer must consult with the parties concerned in order to attempt to come to an agreement when he is
called upon to decide a problem or settle a claim. If a compromise cannot be found, the engineer must fairly
decide while taking into account all pertinent information. Dispute Adjudication Board (DAB) will hear any
case and make a decision whenever the parties cannot agree on the Engineer's determination. A just and
equitable division of risks and obligations between the two contract parties is evidenced in Yellow Book. The
fundamental idea is that the contractor should only be expected to be bound by and price for conditions that
he knows about or can reasonably predict and price in his bids. The risk is thus assigned to the party best
prepared to handle and control that risk. Therefore, Yellow book has stipulations that provides compensation
and a time extension in the event of unanticipated delays, such as late receipt of designs or unexpected physical
obstacles or circumstances encountered during project execution (Wade, 2005)
In the Turnkey projects supported by this FIDIC Suite, the Contractor is required to encompass a broader
spectrum of risks pertaining to the ultimate cost and duration for such endeavors. These risks may encompass
unfavorable ground conditions, an assured outcome, and other similar factors. Demanding contractors to
assume such additional risks implies that the project's price will rise correspondingly in order to account for
the supplementary risk-taking (Wade, 2005).
To a certain degree, according to (Smith, 1989) FIDIC acknowledged in its initial remarks to the Silver Book
the challenge posed by this provision for projects encompassing significant underground tasks or cases where
the Contractor lacks sufficient time during the tender period to evaluate the conditions. It states that the Silver
Book is unsuitable for deployment in such circumstances:
45
British Journal of Environmental Sciences 12(2),43-48, 2024
Print ISSN: 2055-0219(Print)
Online ISSN: 2055-0227(online)
Website: https://www.eajournals.org/
Publication of the European Centre for Research Training and Development–UK
i. “If there is insufficient time or information for tenderers to scrutinize and check the Employer‘s
Requirements or for them to carry out their designs, risk assessment studies and estimating (taking
account of Sub-Sub-Clauses 4.12 and 5.1).”
ii. “If construction will involve substantial work underground or work in other areas which tenderers
cannot inspect.”
Unlike the Red and Yellow books, The Silver Book does not make reference to the Engineer, as the Employer
has less control over Engineering. The focus in Engineering now is on verifying the final performance and
ensuring easy operation, maintenance, etc.
GENERAL PROVISIONS
The understanding of the general provisions of the FIDIC Suites is key to its holistic implementation in any
contract. The fundamental elements encompassed in Clause 1 of FIDIC include but not limited to: Definitions,
interpretation, communications, Law and Language, Priority of Documents, Contract Agreement, Assignment,
Compliance with Laws. The listed provisions are always stated and defined in the Conditions of Contract as
they form structural components of every other clause; hence the “General Provisions” of FIDIC Suites is far
from just being an introductory section. Guidance on contract Interpretation is one of the key mandates of the
general provision; demonstrating in clear terms the roles and obligations of parties and ensuring an effective
communication all through the contract duration.
FORCE MAJEURE
A Force majeure Condition is an inexorably key element of contract that has secured an all-round global
application. Regularly, under such a Provision, where a party has been kept from playing out an agreement by
an occasion outside of its reach, it will be pardoned for its postponement in carrying out its agreed obligations,
or, in an outrageous case, it could be pardoned from being required to eventually carrying out the agreement
by any stretch of the imagination.(International construction law n.d.)
According to (Samerezeldin & Helw, 2017), “the concept of force majeure, basically, is a civil law concept
that is found, in a way or another, in the civil codes of most civil law jurisdictions, while common law does
46
British Journal of Environmental Sciences 12(2),43-48, 2024
Print ISSN: 2055-0219(Print)
Online ISSN: 2055-0227(online)
Website: https://www.eajournals.org/
Publication of the European Centre for Research Training and Development–UK
not recognize such concept with the same wide definition and application; thus, without drafting an adequate
and proper force majeure clause, the parties of the contract, especially that is govern by the common law, will
be at the mercy of the rigid provisions of the law”.
Based on the assertion of (Hillig et al., 2010) this Clause, “Force Majeure” means an extraordinary occurrence
or condition:
It is expected of the party who is or will be kept from discharging its enshrined obligation under the contract
arrangement by Force Majeure to initiate a prompt notice to the other party of the condition surrounding the
Force Majeure without failing to indicate the obligations which is or will be prevented. Having given the Force
majeure notice, such affected party shall be excused for performing the obligations to the extent the force
majeure precludes. However, most times the invocation of this clause is always detrimental to the other party
as this is evidenced in the determination of extension of time and the payment of its associated incurred cost.
Albeit, not all extension of time results in payment of any form of cost.
Every contractual formation or arrangement has a claim/dispute potential. Claim has some many tentacles
such that it can manifest owing to different reasoning emanating within the confines of the contractual and
legal frameworks. Construction Claim can be characterized as a solicitation by one or the other party to the
agreement, generally the Project worker, for remuneration for harms brought about by disappointment of the
other party to satisfy his piece of commitments as determined in the agreement (Shah et al., 2017).
FIDIC condition of contract provides that at any material time when the Contractor holds himself to be entitled
to extension of time for completion and/or any added payment that such contractor must put up a notice in
written to the Employer through the Engineer or Employer’s Representative (in the case of Silver Book);
stating such circumstances triggering the claims and with supporting particulars. However, this must be
achieved within the material time (28 days) within which the contractor becomes aware or expected to have
become aware of such claim triggers. Upon receipt of such notice, the Engineer will swing into its
determination (Clause 3.5) and will eventually reply with approval or disapproval with supporting comments.
Where there is no consensus ad idem then such will eventually give rise to dispute. In this case FIDIC provides
that any dispute be adjudicated by the Dispute Adjudication Board which the parties must unanimously agree
on DAB appointment by the date fixed in the Appendix to Tender.
The contract provisions suggest that DAB’s decision in the matter involving the parties to the contract remains
sacrosanct unless and until objected and rejected by either party. Following the dissatisfaction with DAB’s
resolution by either party, such aggrieved party shall notify the other party of his dissatisfaction stating his
reasoning(s) for his dissatisfaction.
According to Hillig et al. (2010) , “except as stated in Sub-Clause 20.7 [Failure to Comply with Dispute
Adjudication Board’s Decision] and Sub-Clause 20.8 [Expiry of Dispute Adjudication Board’s Appointment],
neither Party shall be entitled to commence arbitration of a dispute unless a notice of dissatisfaction has been
47
British Journal of Environmental Sciences 12(2),43-48, 2024
Print ISSN: 2055-0219(Print)
Online ISSN: 2055-0227(online)
Website: https://www.eajournals.org/
Publication of the European Centre for Research Training and Development–UK
given in accordance with this Sub-Clause”. However, Arbitration shall only be resorted to in the event that the
parties still could not settle amicably following the dissatisfaction of either party.
CONCLUSION
The FIDIC Suites as discussed above cover all aspects of contract ranging from RED Book through YELLOW
Book, SILVER Book and to GREEN Book. It is important to emphasize on the humongous need for Project
analysis and Evaluation in order to decipher the specific Suite that can be applied to any particular contract.
Some of the elements of FIDIC are distinct from those of the standard-form contracts that are frequently
utilized in the English legal system, although many of the concepts of the contract are comparable. This is
particularly true with regard to the DAB's frequent site visits starting at the outset of a project and the stringent
notification deadlines for the contractor's claims. The FIDIC Suites have a positive impact throughout the
project duration; ensuring a smooth understanding of parties’ responsibilities which eventually results in a
smooth project delivery.
REFERENCES
Hillig, J. B., Dan-Asabe, D., Donyavi, S., Dursun, O., &Thampuratty, A. (2010). Fidic’s red book 1999
edition: A study review. In Proceedings of Institution of Civil Engineers: Management, Procurement
and Law (Vol. 163, Issue 3, pp. 129–133). https://doi.org/10.1680/mpal.2010.163.3.129
Jaeger, A. V., &Hök, G. S. (2010). FIDIC - A guide for practitioners. In FIDIC - A Guide for Practitioners.
Springer Berlin Heidelberg. https://doi.org/10.1007/978-3-642-02100-8
Robinson, M. D. (Consulting engineer). (2011). A contractor’s guide to the FIDIC conditions of contract.
Wiley-Blackwell.
Samerezeldin, A., &Helw, A. A. (2017). Force Majeure Concept in Construction Contracts under Civil and
Common Laws.
Shah, A., Scholar, P., Bhatt, R., Bhavsar, J. J., & Co-Ordinater, P. (n.d.). Types and Causes of Construction
Claims. www.ijert.org
Smith, G. (1989). Chartered Arbitrator.
Wade, C. (n.d.). International Construction Contracts and Dispute Resolution ICC-FIDIC Conference
Cairo-International Construction Contracts and Dispute Resolution ICC-FIDIC Conference Cairo
2005 An Overview of FIDIC Contracts.
48