Cost of Construction Estimation
Cost of Construction Estimation
The costs of a constructed facility to the owner include both the initial capital cost
and the subsequent operation and maintenance costs. Each of these major cost
categories consists of a number of cost components.
The capital cost for a construction project includes the expenses related to the inital
establishment of the facility:
The operation and maintenance cost in subsequent years over the project life cycle
includes the following expenses:
The magnitude of each of these cost components depends on the nature, size and
location of the project as well as the management organization, among many
considerations. The owner is interested in achieving the lowest possible overall
project cost that is consistent with its investment objectives.
For example, one construction firm makes estimates of the expected cost in five
different areas:
Contingent amounts not spent for construction can be released near the end of
construction to the owner or to add additional project elements.
In this chapter, we shall focus on the estimation of construction cost, with only
occasional reference to other cost components. In Chapter 6, we shall deal with the
economic evaluation of a constructed facility on the basis of both the capital cost and
the operation and maintenance cost in the life cycle of the facility. It is at this stage
that tradeoffs between operating and capital costs can be analyzed.
Cost estimating is one of the most important steps in project management. A cost
estimate establishes the base line of the project cost at different stages of
development of the project. A cost estimate at a given stage of project development
represents a prediction provided by the cost engineer or estimator on the basis of
available data. According to the American Association of Cost Engineers, cost
engineering is defined as that area of engineering practice where engineering
judgment and experience are utilized in the application of scientific principles and
techniques to the problem of cost estimation, cost control and profitability.
Allocation of joint costs. Allocations of cost from existing accounts may be used to
develop a cost function of an operation. The basic idea in this method is that each
expenditure item can be assigned to particular characteristics of the operation.
Ideally, the allocation of joint costs should be causally related to the category of
basic costs in an allocation process. In many instances, however, a causal
relationship between the allocation factor and the cost item cannot be identified or
may not exist.
For example, in construction projects, the accounts for basic costs may be classified
according to (1) labor, (2) material, (3) construction equipment, (4) construction
supervision, and (5) general office overhead. These basic costs may then be
allocated proportionally to various tasks which are subdivisions of a project.
Construction cost constitutes only a fraction, though a substantial fraction, of the total
project cost. However, it is the part of the cost under the control of the construction
project manager. The required levels of accuracy of construction cost estimates vary
at different stages of project development, ranging from ball park figures in the early
stage to fairly reliable figures for budget control prior to construction. Since design
decisions made at the beginning stage of a project life cycle are more tentative than
those made at a later stage, the cost estimates made at the earlier stage are
expected to be less accurate. Generally, the accuracy of a cost estimate will reflect
the information available at the time of estimation.
1. Design Estimates. For the owner or its designated design professionals, the
types of cost estimates encountered run parallel with the planning and design
as follows:
o Screening estimates (or order of magnitude estimates)
o Preliminary estimates (or conceptual estimates)
o Detailed estimates (or definitive estimates)
o Engineer's estimates based on plans and specifications
Since the trade off between the capital cost and the operating cost is an essential
part of the economic evaluation of a facility, the operating cost is viewed not as a
separate entity, but as a part of the larger parcel of life cycle cost at the planning
and design stage. The techniques of estimating life cycle costs are similar to
those used for estimating capital costs, including empirical cost functions and the
unit cost method of estimating the labor, material and equipment costs. However,
it is the interaction of the operating and capital costs which deserve special
attention.
The value of the cost exponent may influence the decision whether extra capacity
should be built to accommodate future growth. Similarly, the economy of scale
may also influence the decision on rehabilitation at a given time. As the
rehabilitation work becomes extensive, it becomes a capital project with all the
implications of its own life cycle. Hence, the cost estimation of a rehabilitation
project may also involve capital and operating costs.
***************************