Sfety Justification Report
Sfety Justification Report
B44-04E08410.doc 2 of 115
EEIG ERTMS USERS GROUP
CONTENTS
1 Introduction .................................................................................................................................... 5
2 Scope ............................................................................................................................................ 6
2.1 General ........................................................................................................................................ 6
2.2 Safety Concept ............................................................................................................................ 7
3 Rationale ....................................................................................................................................... 9
3.1 Justification for Index 47. ............................................................................................................. 9
3.2 Process description ................................................................................................................... 10
3.3 Completeness of hazard identification ....................................................................................... 12
4 System Definition......................................................................................................................... 14
4.1 Introduction ................................................................................................................................ 14
4.2 Detailed System Definition - System Structure.......................................................................... 14
4.2.1 General 14
4.2.2 CCS TSI System Description 14
4.2.3 System Structure Illustration 22
22
4.2.4 Interfaces 22
4.2.5 System boundary 30
4.3 Detailed System Definition - Functional Analysis ...................................................................... 31
4.3.1 Functional consideration concerning safety in railway operations31
4.3.2 Process 32
4.3.3 Functional Analysis 33
4.3.4 Failure Modes 40
5 Hazard Identification .................................................................................................................... 41
5.1 Process ...................................................................................................................................... 41
5.2 Assumptions .............................................................................................................................. 43
5.2.1 Common Cause 43
5.2.2 Link of Causes to System Hazards 43
5.2.3 Untimely brake application or train trip 44
5.3 Log of hazards ........................................................................................................................... 44
5.4 Log of System hazards .............................................................................................................. 90
5.5 Consistency check of input/output interfaces to/from CCS TSI ................................................. 92
6 Control-Command and Signalling Safety Requirements ............................................................ 93
6.1 General ...................................................................................................................................... 93
6.2 DB example for quantitative safety requirements ...................................................................... 93
6.2.1 Introduction 93
6.2.2 Preconditions 93
6.2.3 Results of the Risk Analysis 93
6.2.4 Relation of TIRF to THRs 93
6.2.5 Values 95
6.2.6 Experience on working with the Risk Analyses (RA) 96
6.3 UK example for quantitative safety requirements ...................................................................... 98
7 References ................................................................................................................................ 104
8 Recommendation for next steps. ............................................................................................... 105
8.1.1 Comparison of national examples for safety requirements 105
8.1.2 Link between Causal Analysis and Index 47 105
8.1.3 Mandatory safety requirements 105
8.1.4 Consolidation of Index 47 by application in practice 105
8.1.5 Apportionment of safety requirements to On-board and Track-side 105
8.1.6 Apportionment of safety requirements to constituents 105
9 Open Points List. ....................................................................................................................... 106
B44-04E08410.doc 3 of 115
EEIG ERTMS USERS GROUP
B44-04E08410.doc 4 of 115
EEIG ERTMS USERS GROUP
Justification Report
1 Introduction
1.1.1.1 This document has been produced as an informative document to provide the
Rationale and Justification for the requirements in “Safety Requirements and
Requirements to Safety Analysis for Interoperability for the Control-Command and
Signalling Sub-System” {Ref.: 1} (the Index 47 document) necessary for the Control-
Command and Signalling Technical Specification for Interoperability for both High
Speed {Ref.: 4} and Conventional Rail CCS CR TSI {Ref.: 5}. In the following “CCS
TSI” is used and covers for both TSI’s. In the current version of the document the
THR’s have not been harmonised, therefore chapter 6 includes examples from
different countries. Throughout the document the text has been written as if
harmonised THR’s have been achieved
1.1.1.2 The approach taken has been to make full use of existing documents and these are
referenced from Index 47 Document {Ref.: 1} and this Justification Report. The
present version of the Justification Report includes examples of THR’s from different
Railways. It has not been possible in this version to harmonise the THR values.
1.1.1.3 Chapter 2 clarifies the scope of this document and Chapter 3 provides the
description of the process used to derive the safety requirements in the Index 47
Document {Ref.: 1} and the justification. Chapter 4 clarifies the detailed System
Definition of the Control-Command and Signalling system as defined in the TSI for
the purposes of deriving the safety requirements. Chapter 4 also describes the
relevant Functions of the Control-Command and Signalling system necessary to
carry out a safe train run and to be used for the Hazard Identification.
1.1.1.4 Chapter 5 provides the Hazard identification and the Agreed Control-Command and
Signalling Hazard List. This will lead to the safety requirements expressed as a
THR corresponding to a SIL for each hazard described in chapter 6.
1.1.1.5 Chapter 7 is the References used in the Justification Report. Chapter 8 is
'Recommendation for next steps' and Chapter 9 is an Open Points list.
B44-04E08410.doc 5 of 115
EEIG ERTMS USERS GROUP
2 Scope
2.1 General
2.1.1.1 The scope of this informative document 'Justification Report' is to provide the
Rationale and Justification for deriving the Safety Requirements specified in the
Index 47 normative document {Ref.: 1}. The Index 47 Document {Ref.: 1} specifies
the mandatory safety requirements for CCS TSI that have to be respected in any
CCS implementation, to ensure that solutions to achieve safety do not jeopardise
interoperability. According to EN 50129 {Ref.: 16} additional analysis work is
necessary based on the system design (Causes for Hazards, Apportionment of
safety targets). The apportionment of safety targets, concerning ETCS, is done in
Index 27 (Subset 91 {Ref.: 6}) for the 'ETCS core hazard' (Exceedance of the safe
speed / distance as advised to ETCS).
2.1.1.2 The scope of the Safety Requirements in Index 47 Document {Ref.: 1} is to cover
part of phase 3 (EN 50126) {Ref.: 15}. It is not the intention to cover the whole Life
Cycle of CCS TSI.
2.1.1.3 By using the Functional Approach for defining the Hazards the functionality of Class
B systems will be included in the analyses since the functional approach will cover
the functions provided by a Class A or Class B system as defined in the CCS TSI
document, however it is not intended to define safety requirements for Class B
equipment. The derived safety requirements will only be mandatory for the Class A
system.
2.1.1.4 The scope has been aligned to the CCS TSI scope that had been decided through
the political processes including Article 21 Committee. The CCS TSI scope can not
in itself guarantee the overall safety since the National part is outside the CCS TSI
scope.
2.1.1.5 It has also been decided through a political process that ERTMS Level 3 has been
excluded from the scope of the Index 47 document {Ref.: 1}.
2.1.1.6 The figure below illustrates CCS TSI safety as part of the CCS overall safety. The
Index 47 document {Ref.: 1} specifies the safety of "CCS TSI trackside" (item 1) and
"CCS TSI onboard" (item 2) only. It should be noted that the items 3, 4 and 5 are
not included. Nevertheless it is obvious that to certify the safety of the overall
system the national part has to be considered.
2.1.1.7
B44-04E08410.doc 6 of 115
EEIG ERTMS USERS GROUP
CC onboard CC trackside
(Annex A) (Annex A)
CC onboard CC trackside
(Annex B) (Annex B)
National part of CC CC onboard CC trackside National part of CC
onboard (Annex C) (Annex C) trackside
Onboard Trackside
2.1.1.8 The National Safety Assessments 3 and 5 from figure 1 must include the safety
assessment of the interface to the CCS TSI Trackside part.
2.1.1.9 The Safety Assessment 1and 5 if carried out separately will require a clear definition
of the interface between RBC and Interlocking.
2.1.1.10 The safety requirements will be developed according to EN 50129:2003 {Ref.: 16}
Appendix A and derived not further than to tolerable hazard rates (THR)
corresponding to a Safety Integrity Level (SIL). (See EN 50129:2003 {Ref.: 16}
“Figure A.2 – Global process overview”).
2.2.1.1 The applied safety concept - described in the drawing below - is compliant with EN
50126/50129 {Ref.: 15 and 16}. This concept consists of two parts, the Risk
Analysis and the Causal Analysis.
2.2.1.2
B44-04E08410.doc 7 of 115
EEIG ERTMS USERS GROUP
RISK ANALYSIS
1 System Definition
2 Hazard Identification (System Hazards)
3 Consequence Analysis (Fatality, Criticality)
4 Level of Safety / Tolerable Risk
5 Apportionment of Tol. Risk to Hazards
CAUSE ANALYSIS
1 Technical failures
2 Human reliability (Handling failures)
3 Assignment of SILs to
non-quantifiable systematic failures
2.2.1.3 Applying a top-down approach, a Risk Analysis serves to derive and introduce
safety requirements (THR’s / SIL’s). This is normally done by the operating company
(railways).
2.2.1.4 Via a bottom-up approach, hazard control is done by performing a Causal Analysis
in order to meet the safety requirements and to ensure that from the system design
no new system hazards arise. During a Causal Analysis causes of hazards are
evaluated or analysed by a structured hierarchical approach to hazard analysis and
hazard tracking (Methods are described in table E.6 of EN 50129 {Ref.: 16}). This is
the supplier's responsibility.
While carrying out a Causal Analysis, the 'Fragile Points' {Ref.: 13} have to be
considered in order to ensure that all safety relevant causes for hazards of the
technical solution have been included.
In order to increase the contingent of quantifiable failures, the Causal Analysis shall
consider handling failures (as described in Reason, J.T. Human Error {Ref.: 14})
e.g. train or RBC data entry and operational rules (as far as they describe
procedures necessary in terms of handling) quantitatively. Since handling failures
are systematic failures, the quantitative consideration is a deviation to EN standards.
2.2.1.5 The remit of Index 47 {Ref.: 11} comprehends step 1 and 2 of the Risk Analysis and
the safety requirements. In order to harmonise safety requirements (THR’s / SIL’s)
requirements it is not necessarily essential to carry out steps 3, 4 and 5. A
harmonisation of safety requirements may as well take place on THR-level only.
2.2.1.6 While carrying out a Causal Analysis, the 'Fragile Points' {Ref.: 13} have to be
considered in order to ensure that all safety relevant causes for hazards have been
included.
2.2.1.7 Systematic failures (e.g. in terms of maintenance, creation of static line profile,
software failures) are according to EN 50129 {Ref.: 16} not quantifiable. For this
reason systematic failures are not considered by the risk budget of a THR, even
though systematic failures are covered by the qualitative safety requirements of
Index 47 in the System Hazards.
B44-04E08410.doc 8 of 115
EEIG ERTMS USERS GROUP
3 Rationale
This chapter describes the justification for Index 47 and the detailed process used to
identify potential areas of weakness and to derive the safety requirements in the Index
47 document.
System
Trackside Onboard
Other technical Other technical
components components
e.g. GSM-R, e.g. GSM-R,
HABD HABD
3.1.1.4 The CCS TSI’s, CCS CR TSI {Ref.: 5} and CCS HS TSI {Ref.: 4} defines safety in
the chapter 3.2.1 and 4.2.1 but this is not sufficient to define the safety requirements
in detail to ensure the consideration of random and systematic failures including
operating failures (e.g. train data input). Therefore an open point was raised and the
B44-04E08410.doc 9 of 115
EEIG ERTMS USERS GROUP
remit for Index 47 {Ref.:11} was approved on 15-09-03 to close the open point.
3.1.1.5 According to EN 50 129 {Ref.: 16} safety is defined by a declaration about risk. EN
50129:2003, defines in 3.1.45 safety as: freedom from unacceptable levels of risk of
harm and in 3.1.43 risk is defined as: the combination of the frequency, or
probability, and the consequence of a specified hazardous event. A THR - as
introduced by CCS CR TSI - is not equivalent to risk. Thus it leads to the perception
that the given THR without derivations is not sufficient to make a statement about
safety. In addition to this the THR’s given in CCS CR TSI lack reference parameters
e.g. the system dimensions and reference time for the hazard. As result each nation
draws up its individual risk and hazard analysis. The national approaches differ
significantly in the majority of cases and in the end this may jeopardises
interoperability.
3.1.1.6 The basis for the risk and hazard analyses has to be comparable, especially the
system definition and the system boundaries. It is therefore the task of the Index 47
document to develop a common interoperable base which in this case is a system
definition and an agreed list of CCS TSI hazards with proposals for THR’s.
3.1.1.7 The basis for the development approach follows EN 50 129 {Ref.: 16} Appendix A.
3.1.1.8 In order to fulfil the process in EN 50 129 {Ref.: 16} a Functional approach is used
to:
o ensure completeness
o ensure independence from technical solutions
allow safety requirements for single constituents to be derived
3.1.1.9 The Functional approach gives the possibility to map accident statistics to the
hazards. Railway statistics for accidents normally reveal a systematic structure
(This is the case for Germany: EDS, old STABAG). Accidents could be classified
according to different causes which are on a functional level and independent from
technical solutions. Since Index 47 uses the functional approach, this gives the
possibility to relate Index 47 functions to the accident statistics. This mapping may
then be used to derive the TIRF and related THR’s based on fatality of accidents.
3.1.1.10 As a starting point all functions that are essential for the safe control of the railway
traffic and that are essential for operations, including those required under degraded
conditions are taken into account.
3.1.1.11 The functions used for the hazard identification are only the functions that are
relevant for CCS TSI. That are functions that:
o are totally or partly carried out by the CCS TSI (issuing the brake command)
o that affects the CCS TSI (e.g. functions that provides information/input which is
necessary for CCS TSI e.g. data input).
B44-04E08410.doc 10 of 115
EEIG ERTMS USERS GROUP
structure according to a model including elements, interfaces and boundaries.
Target: System Architecture drawing, List of input & output interfaces
3.2.1.3 Step 2: Detailed System Definition - Functional Analysis
Input: Function Lists from European railways based on operational knowledge of the CCS
system functions necessary to run a train safely.
Functional Analysis Of Trans – European Rail Operation {Ref.: 8}.
Task: Identify functions that are essential for the safe control of the railway traffic and that
are essential for operations, including those required under degraded conditions.
Identify functions relevant for CCS TSI, that is functions that:
o are totally or partly carried out by the CCS TSI (issuing the brake
command)
o that affects the CCS TSI (e.g. functions that provides information/input
which is necessary for CCS TSI e.g. data input).
Identify list of failure modes.
Target: List of functions to be used for the Hazard Identification and list of failure modes.
3.2.1.4 Step 3: Hazard Identification
Input: List of functions (from Step 2).
List of failure modes.
Definition of a Hazard from EN50129 {Ref.: 16}.
System Architecture Drawing.
Task: Apply appropriate failure modes to the functions to identify the hazards according
to the Hazard Definition.
Fill a table for each hazard including:
function
function description
naming hazard
limitations
simplified consequence analysis
examples for causes for the hazards
output interface
Target: Log of Hazards.
3.2.1.5 Step 4: Identification of System Hazards
Input: Log of hazards (from Step 3)
System architecture (from Step 1)
Task: Allocate each hazard to the system architecture.
Hazards which can be allocated at the output interfaces of CCS TSI are System
Hazards. Other hazards are causes for CCS TSI hazards or consequences of
them.
Target: Division of Log of hazards into:
o CCS TSI System Hazard Log
o Log of Hazards on the interface to CCS TSI and causes found within the CCS
TSI System.
3.2.1.6 Step 5: Systematic check of the in/output to the CCS TSI system for consistency
check.
Input: Interfaces in/output to the CCS TSI system (from Step 1)
B44-04E08410.doc 11 of 115
EEIG ERTMS USERS GROUP
Task: Consistency check for identifying System Hazards.
Target: Complete CCS TSI Hazard Log.
3.2.1.7 Step 6: Introduction of safety requirements to CCS TSI System
hazards
Input: CCS TSI System Hazard Log (from Step 4)
Task: Apply THR corresponding to a SIL to each System Hazard
Target: Safety Requirements for CCS TSI (THR corresponding to a SIL)
3.2.1.8 General 'model of system structure' used for the hazard identification process
B44-04E08410.doc 12 of 115
EEIG ERTMS USERS GROUP
B44-04E08410.doc 13 of 115
EEIG ERTMS USERS GROUP
4 System Definition
4.1 Introduction
4.1.1.1 This chapter describes the system definition from CCS CR TSI according to “step 1”
(from the process description in chapter 3.2) and elaborates a functional system
definition according to “step 2”.
4.2.1.3 The purpose of this analysis is to provide a definition of the system structure of the
Control Command and Signalling TSI subsystem in the context of safety analysis.
The task is to derive an architectural structure according to the model including
elements, interfaces and boundaries.
4.2.1.4 In this chapter the system will be described in terms of its “hardware structure” only
to define the elements and internal interfaces as well as the interfaces to the
external environment (other TSI as well as non TSI environment) which need not be
considered. Thus the borders of the system will become clear and the level of detail
will be set.
4.2.1.5 These elements are supported by mandated operational processes such as
Operational rules from the EEIG ERTMS User Group in the TSI
Operation.
4.2.2 CCS TSI System Description
4.2.2.1 This chapter is an extract of the relevant chapters of CCS CR TSI {Ref.: 5}. The
extract from the CCS TSI will be used to establish the Index 47 System definition
and interfaces.
Exact reference to that document is provided within the headlines of the following
subchapters.
4.2.2.2 The Control-Command subsystem is characterised by the following Basic
B44-04E08410.doc 14 of 115
EEIG ERTMS USERS GROUP
Parameters (Reference: CCS CR TSI {Ref.: 5}. chapter 4.1):
Control-Command safety characteristics relevant to interoperability
On-board ETCS functionality
Track-side ETCS functionality
EIRENE functions
ETCS and EIRENE air gap interfaces
On-Board Interfaces Internal to Control Command
Trackside Interfaces Internal to Control Command
Key Management
ETCS-ID Management
HABD (hot axle box detector)
Compatibility with track-side Train Detection Systems
Electromagnetic Compatibility
ETCS DMI (driver machine interface)
EIRENE DMI (driver machine interface)
Interface to data recording for regulatory purposes
Visibility of track-side Control-Command objects
4.2.2.3 Functional and technical specifications of the Subsystem
(Reference: CCS CR TSI {Ref.: 5} chapter 4.2):
Control-Command safety characteristics relevant to interoperability
On-board ETCS functionality
Track-side ETCS functionality
EIRENE functions
ETCS and EIRENE air gap interfaces
On-Board Interfaces Internal to Control-Command
Interface between ETCS and STM
GSM-R/ETCS
Odometry
Trackside Interfaces Internal to Control-Command
Functional interface between RBC’s
Technical interface between RBC’s
GSM-R/RBC
Eurobalise/LEU
Euroloop/LEU
Requirements on pre-fitting of ERTMS track side equipment
Key Management
ETCS-ID Management
Hot axle box detector
Compatibility with Track-side Train Detection Systems
Electromagnetic Compatibility
Internal Control-Command Electromagnetic compatibility
Electromagnetic Compatibility Between Rolling Stock and Control-Command track-side
Equipment
B44-04E08410.doc 15 of 115
EEIG ERTMS USERS GROUP
ETCS DMI (Driver Machine Interface)
EIRENE DMI (Driver Machine Interface)
Interface to Data Recording for Regulatory Purposes
Visibility of track-side Control-Command objects
4.2.2.4 Functional and technical specifications of the interfaces to other Subsystems:
(Reference: CCS CR TSI {Ref.: 5} chapter 4.3):
Interface to the Subsystem Traffic Operation and Management
Operating Rules
ETCS Driver Machine Interface
EIRENE Driver Machine Interface
Interface to data recording for regulatory purposes
Guaranteed train braking performance and characteristics
Isolation of ETCS on-board equipment
Key Management
Hot Axle Box Detectors
Driver Vigilance
Use of Sanding
Driver’s External Field of View
Interface to the Subsystem Rolling Stock
Compatibility with track-side Train Detection Systems
Electromagnetic Compatibility Between Rolling Stock and CCS Track-side Equipment
Guaranteed train braking performance and characteristics
Position of Control-Command On-board Antennae
Physical environmental conditions
Electromagnetic Compatibility
Isolation of On-Board ETCS functionality
Data Interfaces
Hot Axle Box Detectors
Vehicle Headlights
Driver Vigilance
Odometry
Interface to data recording for regulatory purposes
Onboard pre-fitting
Interfaces to Subsystem Infrastructure
Train Detection Systems.
Track-side Antennae
Physical environmental conditions
Electromagnetic Compatibility
Interfaces to Subsystem Energy
Electromagnetic Compatibility
4.2.2.5 Operating rules
(Reference: CCS CR TSI {Ref.: 5} chapter 4.4)
B44-04E08410.doc 16 of 115
EEIG ERTMS USERS GROUP
Responsibility of infrastructure manager or railway undertaking
Maintenance plan
4.2.2.7 Professional qualifications.
(Reference: CCS CR TSI {Ref.: 5} chapter 4.6)
Interfaces considered in addition to TSI CCS (missing or unclear description in TSI CCS),
necessary for a system definition in terms of safety analysis, are marked in italic text.
(Those are announced to AEIF).
ON-BOARD
B44-04E08410.doc 17 of 115
EEIG ERTMS USERS GROUP
Interfaces:
JRU downloading tool
ERTMS/ETCS on-board
Environmental conditions
EMC
● Odometry:
Safety
Onboard ETCS funtionality (only Odometry)
Interfaces:
ERTMS ETCS on-board
Environmental conditions
EMC
Track external to CCS (not mentioned in TSI)
● External STM:
Functions and safety (according to national specifications)
Interfaces:
ERTMS ETCS on-board
Class B system air gap (according to national specifications)
Environmental conditions (according to national specifications)
EMC (according to national specifications)
● ERTMS/GSM-R on-board:
EIRENE functions
Interfaces:
ERTMS ETCS on-board
GSM-R
EIRENE DMI
Environmental conditions
EMC
TRACK-SIDE
● RBC
Safety
Track-side ETCS funtionality
ETCS and EIRENE air gap interfaces
Interfaces:
Neighbouring RBC
ERTMS GSM-R track-side
Key management centre
ETCS-ID Management
Interlocking
Environmental conditions
EMC
● Radio in-fill unit
Safety
Track-side ETCS functionality
B44-04E08410.doc 18 of 115
EEIG ERTMS USERS GROUP
ETCS and EIRENE air gap interfaces
Interfaces:
ERTMS GSM-R track-side
Key management system
ETCS-ID Management
Interlocking and LEU
Environmental conditions
EMC
● Eurobalise
Safety
ETCS and EIRENE air gap interfaces
Interfaces:
LEU Eurobalise
ETCS-ID Management
Environmental conditions
EMC
● Euroloop
Safety
ETCS and EIRENE air gap interfaces
Interfaces:
LEU Euroloop
ETCS-ID Management
Environmental conditions
EMC
● LEU Eurobalise
Safety
Track-side ETCS functionality
Interfaces:
Track-side signalling
Eurobalise
ETCS-ID Management
Environmental conditions
EMC
● LEU Euroloop
Safety
Track-side ETCS functionality
Interfaces:
Track-side signalling
Euroloop
ETCS-ID Management
Environmental conditions
EMC
● Safety Platform track-side
Safety
Interfaces: None
CMI (RBC Operator) (not mentioned in TSI)
Static Trackside Data (not mentioned in TSI)
B44-04E08410.doc 19 of 115
EEIG ERTMS USERS GROUP
Train detection
Train detection interfaces: (external to CCS?)
4.2.2.11 Example of Groups of Interoperability constituent in the CCS Assembly
(Reference: CCS CR TSI {Ref.: 5} table 5.1b and 5.2b):
ON-BOARD
TRACK-SIDE
B44-04E08410.doc 20 of 115
EEIG ERTMS USERS GROUP
Track-side ETCS functionality
ETCS and EIRENE air gap interfaces
Interfaces
Track-side signalling
ETCS-ID Management
Environmental conditions
EMC
B44-04E08410.doc 21 of 115
EEIG ERTMS USERS GROUP
On-Board
ERTMS ETCS on-board
ETCS and EIRENE air gap interfaces
RBC (level 2 and 3)
Radio in-fill unit (optional level 1)
Eurobalise airgap
Euroloop airgap (optional level 1)
Interfaces:
STM (implementation of interface K optional)
ERTMS GSM-R on-board
Odometry
Key management centre
ETCS ID Management
ETCS DMI
Key Management
Physical environmental conditions
EMC
Data interface (includes vigilance and train integrity RST Interfaces
Safety information recorder Compatibility with track-side Train Detection Systems
Train (RS) external to CCS (not mentioned in TSI) EMC Between Rolling Stock and CCS Track-side Equipment
Driver external to CCS (not mentioned in TSI) Guaranteed train braking performance and characteristics
Static Train Data (not mentioned in TSI) Position of Control-Command On-board Antennae
Maintenance ERTMS (not mentioned in TSI) Physical environmental conditions
Electro-magnetic Compatibility
Isolation of ETCS on-board equipment
Safety Platform on-board Data Interfaces
Interfaces: Hot Axle Bearing Detectors
None Vehicle Headlights
Driver Vigilance
Safety Information Recorder: Odometry
Interfaces: Interface to data recording for regulatory purposes
JRU downloading tool Trainside pre-fitting
ERTMS/ETCS on-board
Environmental conditions
EMC
OPE Interfaces
Odometry: Operating Rules
Interfaces: ETCS DMI
ERTMS ETCS on-board EIRENE DMI
Environmental conditions Interface to data recording for regulatory purposes
EMC Guaranteed train braking performance and characteristics
Track external to CCS (not mentioned in TSI) Isolation of ETCS on-board equipment
Key Management
External STM: Hot Axle Box Detectors
Interfaces: Driver Vigilance
ERTMS ETCS on-board Use of Sanding
Class B system airgap Driver's External Field of View
Environmental conditions
EMC
ERTMS/GSM-R on-board:
Interfaces:
ERTMS ETCS on-board
GSM-R Track-side
EIRENE DMI
Environmental conditions
EMC
INS Interfaces
Track-side Train Detection Systems.
Track-side Antennae
RBC Physical environmental conditions
ETCS and EIRENE air gap interfaces Electromagnetic Compatibility
Interfaces:
Neighbouring RBC
ERTMS GSM-R track-side
Key management centre
ETCS-ID Management
Interlocking
Environmental conditions ENE Interfaces
EMC Electromagnetic Compatibility
Eurobalise
ETCS and EIRENE air gap interfaces
Interfaces:
LEU Eurobalise
Environmental conditions
EMC
LEU Eurobalise
Track-side ETCS functionality
Interfaces:
Track-side signalling
Eurobalise
Environmental conditions
EMC
Euroloop
ETCS and EIRENE air gap interfaces
Interfaces:
LEU Euroloop
Environmental conditions
EMC
LEU Euroloop
Track-side ETCS functionality
Interfaces:
Track-side signalling
Euroloop
Environmental conditions
EMC
4.2.4 Interfaces
4.2.4.1 The allocation of functions of the Driver and Signalman in the system structure is
based on the functionality fulfilled, which can be inside or outside the defined
system. This can be obtained from the following drawings.
B44-04E08410.doc 22 of 115
EEIG ERTMS USERS GROUP
4.2.4.2 Signalman
System Environment
4.2.4.3 The Driver has two functions: 1) ERTMS operator and 2) train driver. Even though
there is only one driver, he comprises two types of functionalities. The interface is
between the two functionalities: Concerning the "model of the system structure" in
chapter 4, all functions the driver does in his function as operator of the train are
allocated outside the defined system. Concerning functions the driver does in terms
of ERTMS DMI, he is acting as operator of ERTMS (communicating, interacting with
and monitoring ERTMS onboard device) and therefore these functions are allocated
within the defined system.
Train Preparation
Monitors Infrastructure for Hazards
Operates and Monitors Train Systems
Operates Voice Radio Communications
Operates Drivers Controls
Manages Train, Movements and Situations
System Environment
B44-04E08410.doc 23 of 115
EEIG ERTMS USERS GROUP
on-board interface K optional)
2 ERTMS ETCS ERTMS GSM-R on-board
on-board
3 ERTMS ETCS Odometry
on-board
4 ERTMS ETCS Key management centre
on-board
5 ERTMS ETCS ETCS ID Management
on-board
6 ERTMS ETCS ETCS DMI
on-board
7 ERTMS ETCS Key Management
on-board
8 ERTMS ETCS Data interface (includes
on-board vigilance and train integrity
9 ERTMS ETCS Safety information
on-board recorder
10 Safety JRU downloading tool
Information
Recorder
11 Safety ERTMS/ETCS on-board
Information
Recorder
12 Odometry ERTMS ETCS on-board
13 External STM ERTMS ETCS on-board
14 External STM Class B system airgap
15 ERTMS/GSM-R ERTMS ETCS on-board
on-board
16 ERTMS/GSM-R GSM-R (track-side)
on-board
17 ERTMS/GSM-R EIRENE DMI
on-board
18 RBC Neighbouring RBC
19 RBC ERTMS GSM-R track-side
20 RBC Key management centre
21 RBC ETCS-ID Management
22 RBC Interlocking
23 Radio in-fill unit ERTMS GSM-R track-side
24 Radio in-fill unit Key management centre
25 Radio in-fill unit ETCS-ID Management
26 Radio in-fill unit Interlocking and LEU
27 Eurobalise LEU Eurobalise
28 Euroloop LEU Euroloop
29 LEU Eurobalise Track-side signalling
30 LEU Eurobalise Eurobalise
31 LEU Euroloop Track-side signalling
32 LEU Euroloop Euroloop
33 ERTMS ETCS Physical environmental
on-board conditions
34 ERTMS ETCS EMC
on-board
35 Safety Platform None
on-board
36 Safety Environmental conditions
Information
B44-04E08410.doc 24 of 115
EEIG ERTMS USERS GROUP
Recorder
37 Safety EMC
Information
Recorder
38 Odometry Environmental conditions
39 Odometry EMC
50 External STM Environmental conditions
41 External STM EMC
42 ERTMS/GSM-R Environmental conditions
on-board
42a ERTMS/GSM-R EMC
on-board
43 RBC Environmental conditions
44 RBC EMC
45 Radio in-fill unit Environmental conditions
46 Radio in-fill unit EMC
47 Eurobalise Environmental conditions
48 Eurobalise EMC
49 Euroloop Environmental conditions
50 Euroloop EMC
51 LEU Eurobalise Environmental conditions
52 LEU Eurobalise EMC
53 LEU Euroloop Environmental conditions
54 LEU Euroloop EMC
55 Safety Platform None
track-side
56 LEU Eurobalise ETCS-ID Management
57 LEU Euroloop ETCS-ID Management
B44-04E08410.doc 25 of 115
EEIG ERTMS USERS GROUP
*1 Interface is in the CCS TSI and therefore in the list in 4.2.2.10 but the interface is via the LEU Euroloop.
There are no Euroloop without LEU Euroloop.
B44-04E08410.doc 26 of 115
EEIG ERTMS USERS GROUP
From To Description
B44-04E08410.doc 27 of 115
EEIG ERTMS USERS GROUP
activated
10 RST CCS TSI on- Odometry (tachometer)
board
11 National CCS: CCS TSI On- National CCS status: active,
On-Board Board passive
4.2.4.7 The following illustration is based on the 'System Structure Illustration' and elaborated
with focus on the output interfaces (Interfaces from CCS, as described in the CCS TSI,
to other subsystems).
Emergency brake
CCS TSI
Subsystem Traffic Operation
Management (OPE)
On-board Driver
rack-side
On-board
B44-04E08410.doc 28 of 115
EEIG ERTMS USERS GROUP
- distance to brake target
indication
- predicted speed at brake
target indication
- Auxiliary Driving
Information (e.g.
approaching a tunnel or
lowering the pantograph)
- text messages
- acknowledgement request
- emergency stop (via GSM-R
voice)
3 CCS TSI: → National CCS: - activation command for - SUBSET 091
On-board On-board national CCS (2.2.2),
chapter 2,
2.5.3: 'STM'
4 CCS TSI: → National CCS: - synchronisation request - SUBSET 032
Track- Trackside - emergency stop (2.0.0), page
side notification 7, figure 1:
- 'RBC
information'
B44-04E08410.doc 29 of 115
EEIG ERTMS USERS GROUP
Concluding chapter 4.2 this picture puts the result into context.
System Environment
8 2 9 1 6
timetable
•Enters Train data
•Manages Degraded Mode Operations
•Isolate ERTMS Trainborne System
List of temporary speed if required
•Acknowledgements desired by CCS
restrictions On-board National CCS:
On-board
3
Train preparer
DMI 11
Infrastructure:
5 Radar
System
10
Rolling Stock:
Provide static line data GSM-R / Tachometer
3 Fixed network
x
Output Interface No. x
Y
Input Interface No. Y
(Note: All connecting lines are intended to be of the same line width)
4.2.5.1 Note 1
The System as described in 4.2.5 is dependant on other systems: Other systems may
influence the defined system via the input interfaces. In the context of Index 47, other
systems influencing the defined system are considered as being ideal (functioning
without errors). Nevertheless, if the scope of safety assessment is expanded to the
overall safety of railways, the influence of the other systems have to be considered.
4.2.5.2 Note 2
The analysis and evaluation of the link between input and output interfaces within the
defined System (4.2.5) is the task of the Causal Analysis, according to the applied
safety concept in 2.2.
B44-04E08410.doc 30 of 115
EEIG ERTMS USERS GROUP
Requirements for
safety
in railway applications
4.3.1.3 Railway operations can be described as the totality of all measures that serve the
conveyance of persons or goods.
4.3.1.4 In this, maintenance is regarded – although other definitions are possible – as not
belonging to railway operations. The maintenance process is however included in
determining the relevant functions for safe railway operation.
4.3.1.5 In consideration of the tasks to be performed here, the following further sub-division
results:
Railway operations
4.3.1.6 "Planning" covers the following examples: route management – including the
preparation of operational documents for the performance of moves –, planning of the
conveyance of special consignments and vehicles, preparation of the necessary
instructions for action by persons involved in railway operations, and the training and
advanced training of those involved. This also however includes the principle that
facilities are designed in such a manner that hazards arising from operating errors are
prevented or, at least, made more difficult.
4.3.1.7 "Performance" includes railway operations in the narrower sense; this is to be defined
as the intentional movement of railway vehicles on a railway infrastructure and
comprises all measures directly connected with it. "Train operation" is a term
commonly used for this as well. In the following, the term "moves" is used for the
intentional movement of railway vehicles, since it is not necessary to distinguish
between train and shunting moves in this connection.
B44-04E08410.doc 31 of 115
EEIG ERTMS USERS GROUP
4.3.1.8 "Performance" also includes the execution of construction and maintenance work,
which can - insofar as it does not have any effect on the performance of moves - be
disregarded.
4.3.1.9 "Monitoring" comprises all measures which serve to ensure that the rules applying to
the safe performance of operations are complied with. This also includes the
supervision of operational safety, the activity of railway traffic managers and the
activity of those monitoring staff in actual railway operations. Scheduling tasks – even
if they contain a "monitoring" component – are to be allocated to "performance" since
they serve the performance of moves.
4.3.1.10 All of the areas mentioned above contribute to the safety of railway operations, but to
different degrees. The following deals only with "performance" in more detail.
4.3.1.11 The fundamental connections below can be identified for the safe movement of railway
vehicles:
Safe performance
of moves
with railway vehicles
4.3.1.12 For more far-reaching considerations, the definition as above does not seem sufficient
since the terms are in part too theoretical and make a further examination of
completeness more difficult. In addition, the classification is very much oriented
towards the actual performance of moves and thus inevitably does not consider further
aspects that are of significance for safety.
4.3.1.13 Instead, the functional approach will be used, where the relevant phases as in the
time-related sequence of a move should first of all be defined and further functions
allocated here.
4.3.2 Process
4.3.2.1 The functions used for the hazard identification are sufficient general to cover all
possible applications and there will therefore not be a need for using an application
approach in addition.
4.3.2.2 The functions used for the hazard identification are derived in a process according to
the following.
B44-04E08410.doc 32 of 115
EEIG ERTMS USERS GROUP
4.3.2.3 The relevant phases as in the time-related sequence of a move should first of all be
defined and further functions allocated here.
4.3.2.4 The following phases result of a train movement:
Plan move
Prepare move
Schedule move
Set up conditions for move
Authorise move
Perform move
Conclude move
4.3.2.5 As a starting point all functions relevant for the railway operation are taken into
account. Functions in terms of construction and maintenance works are considered if
they affect the train run.
4.3.2.6 From these functions only those which are relevant for CCS TSI are kept. Those are
functions that are totally or partly carried out by the CCS TSI effect the CCS TSI (e.g.
functions that provide information/input which is necessary for CCS TSI). To decide if
a function has relevance to CCS TSI and to verify it, adequate expertise is pre-
requisite.
4.3.2.7 The remaining functions are to be detailed until a specific realisation level has been
achieved. It becomes apparent that it is possible only as from a certain degree of detail
to make meaningful definitions for functions which enable further sub-division and
assessment.
4.3.2.8 According to the Rationale it is not desirable to deal with functions on a specific
realisation level. Therefore the more general functions from (4.3.2.4) will be used
assuring the detailed functions are covered. As far as the degraded modes are
representing specific realisations, they are also covered.
4.3.2.9 The resulting functions are used for hazard identification.
B44-04E08410.doc 33 of 115
EEIG ERTMS USERS GROUP
1 Plan move The functions to be exercised at the
planning level do not as yet govern
any individual case (no single,
concrete movement) but initially
specify the boundary conditions; to
this extent, an enumeration could be
done without. Nevertheless,
interfaces to the systems used during
this phase may arise (e.g. with
reference to data exchange).
1.1 Check whether movement(s) can actually checking whether and under what
be performed (plausibility check for conditions specified vehicles can run
pathing application) on specified infrastructure
1.1.1 running system prerequisites
1.2.2.1 Produce
1.2.2.2 Publicise
1.2.3 special operational arrangements This is required in the event of
special provisions in/deviations from
the rules, e.g. in respect of out-of-
gauge loads/ vehicles, test runs
1.2.3.1 Produce
1.2.3.2 publicise
2.1 Providing vehicles required (including vehicles must be suitable for the
means of traction) respective concrete scenario (i.e.
specific movement).
2.2 Providing staff Staff are to be provided in the
numbers required - i.e. in the
numbers required to carry out the
relevant movement in accordance
with the applicable regulations.
2.3 Forming the train
B44-04E08410.doc 34 of 115
EEIG ERTMS USERS GROUP
2.4.2 preparation of motive power stock
2.4.3 establish condition and fitness for function X functionality of
of vehicle's brakes brakes is
prerequisite for
correct calculation
of braking curves
2.4.4 »train initialisation« Train number, max. permissible X information
speed, effective braking power, necessary
length, load if applicable.
2.5 Providing information required for The adjacent information may be
movement known in advance (as a result of the
planning phase) (e.g. timetable
documents citing routing and
destination as well as information
about track-related
deviations/particularities) or be
announced at short notice (e.g. for
shunting moves) (e.g. diversionary
routes); also classified as special
features are details of non-standard
consignments that are not scheduled
to run permanently in the train.
2.5.1 purpose of movement
B44-04E08410.doc 35 of 115
EEIG ERTMS USERS GROUP
4.1.3 take account of restrictions on type of
traction
4.1.4 take account of restrictions on use of
certain vehicles
4.2 Setting track elements Take account of reliability: e.g. do not
switch occupied switches; this
function is to be assigned to the
»Protecting track elements« function
for the preceding or following
movement.
4.2.1 track switches
4.2.2 switches in safety overlap
4.2.3 flank protection devices
4.7.2 protection against opposing moves Opposing moves also include X function partly
movements in the opposite direction executed in the
to that allowed (e.g. inadmissible interlocking
setting back).
4.7.3 protection against collisions at switches
B44-04E08410.doc 36 of 115
EEIG ERTMS USERS GROUP
5 Authorising move
6 Perform move
B44-04E08410.doc 37 of 115
EEIG ERTMS USERS GROUP
movements
6.1.3.4 max. permissible speed when setting as above X
back in the event of danger
6.1.3.5 max. permissible speed when entering as above X
dead-end tracks
6.1.3.6 max. permissible speed when entering as above X
partially occupied tracks
6.1.3.7 max. permissible speed for reasons of not a function for protecting X
safety of track works movement
6.1.3.8 max. permissible speed in case of X
temporary speed restrictions
6.2 Observing (further) line-related restrictions
6.2.1 lower pantograph(s) at required point Turntables, traversers, crane X
trackage, other sections without
catenary or to be passed with
pantograph down.
6.2.2 switch off motive power unit current (main Insulated sections, changes of X
switch off) at required point system, depot gates with insulated
catenary adaptor.
6.2.3 limiting current consumption (high-voltage
limit values)
6.2.4 no sanding at specified points Points, turntables, traversers (in each
case except in hazardous
circumstances)
6.2.5 where possible, prevent motive power
units travelling light from stopping on
sections they have sanded
6.2.6 avoid stopping with pantographs raised
beneath section insulators and section
divisions
6.2.7 warning by issuing acoustic signals at Indication by means of trackside
requisite point signals or corresponding instructions
on what to do.
6.2.8 avoid stopping at points not suitable for Emergency brake override; function X
the adoption of auxiliary measures or only is only of relevance, however, in the
poorly so event of an incident (notably fire).
6.2.9 take account of restrictions in the use of e.g. eddy-current brake X
specified brake designs
6.2.10 Prove reliability of movementb - loading gauge X route suitability
- power supply
- axle load
6.2.11 Reversing in the event of danger ERTMS/ETCS FRS 11.3.2 and SRS X
4.4.18 and 5.13
6.3 Observing (further) vehicle-related
restrictions
6.3.1 no manual sanding during skidding
6.3.2 take note of conditions governing the Max. permissible speed as function
raising of lowered pantographs of pantograph design; do not raise
beneath overhead crossings and
section insulators.
6.3.3 take note of operating restrictions for E.g. do not exceed continuous
motive power unit tractive effort for any length of time;
function has purpose of maintaining
availability.
6.4 Ensure stops required for reasons of
safety
6.4.1 stopping at a signal at danger Cab display is synchronised with X
signals at danger. This includes the
provision that onward movement
following a stopping event may only
occur once the stop has been
revoked.
6.4.2 stopping before stationary vehicles to the extent that vehicles are not X
B44-04E08410.doc 38 of 115
EEIG ERTMS USERS GROUP
protected by signals at danger
(depending on the mode of
operation)
6.4.3 stopping at track closings Reference may not be necessary, X
since track closings are indicated by
means of signals at danger.
6.4.4 stopping before other obstacles (than to the extent that the movement has X
vehicles) on the track been specifically authorised to do so.
6.5 Ensuring stops required (= scheduled) for = customer stops
other reasons
6.5.1 stop for passenger entry/egress at
designated point
6.5.2 stop to load/unload
6.5.3 stop for change of staff
6.7 Check for safety-related deviations to Not a basic function of train running;
vehicles on the movement concerned and serves to ensure the »safe state of
adopt measures railway installations«.
6.7.1 running-gear irregularities
7.1.2 return track elements to normal position Normal position for level crossings is
(where applicable) generally »Barriers open«, whilst no
normal position is necessarily
required for switches.
7.2 Protecting parked vehicles
7.2.1 applying brakes X
B44-04E08410.doc 39 of 115
EEIG ERTMS USERS GROUP
8 Miscellaneous
B44-04E08410.doc 40 of 115
EEIG ERTMS USERS GROUP
5 Hazard Identification
5.1 Process
5.1.1.1 The hazard identification is based on the abstract functional system definition (chapter
4). For this reason the hazards identified are independent of specific realisations or
applications. Specific realisations or circumstances are to be taken into consideration
by the Causal Analysis, which evaluates/analyses the technical solution in order to
identify causes for hazards and verify if new hazards arise from system design.
5.1.1.2 Following a systematic approach all aspects taken into account while analysing
functions and their failure modes are written down to a Hazard Identification Table.
5.1.1.3 Hazard Identification Table
Panel headline Headline explanation
Examples for causes for Examples for direct causes for the hazard
the hazard
Annotation If anything else which does not fit in the boxes above is
of greater importance, it is to be mentioned here.
Also grouping of hazards to a single hazard is to be
mentioned here.
5.1.1.4 The functions considered as CCS TSI relevant, resulting from the functional analysis
(chapter 4.3.3) are taken into account as a basis for hazard identification. Such
functions that are only in part CCS TSI relevant, the part of the function which is CCS
TSI relevant is taken into account for hazard identification. (Only this part is described
in the panel 'Function description')
5.1.1.5 With expert knowledge failure modes (key words to identify typical failure modes, see
check list in chapter 4.3.4) has been applied to CCS TSI relevant functions. Failure
modes of CCS TSI relevant functions are CCS TSI relevant hazards. Experts from
different railways have been consulted in order to check the completeness of the
B44-04E08410.doc 41 of 115
EEIG ERTMS USERS GROUP
hazards identified.
5.1.1.6 CCS TSI relevant hazards are to be checked, if they are safety relevant or not, based
on a simplified consequence analysis. If there is a probability higher than 0 of an
accident as direct consequence of a CCS TSI relevant hazard, the hazard is safety
relevant.
5.1.1.7 EN 50129:2003 {Ref.: 16} defines in 3.1.1 accident as “an unintended event or series
of events that results in death, injury, loss of a system or service, or environmental
damage”. For deriving the CCS TSI relevant hazards the accidents taken into account
are:
Accident Explanation
Derailment a) Vehicle sliding off or lifting-off from
track, even if it rerails itself again
b) double-track movement of a vehicle
Collision with road traffic Collision between railway vehicle and road
traffic on a level crossing (excluding misuse of
level crossings).
5.1.1.8 The accidents mentioned above are only considered in case they are arising from a
CCS TSI failure. Only CCS TSI relevant hazards which are safety relevant are kept for
further consideration.
5.1.1.9 System Border Check
As final step the resulting hazards from step 3 are put to a 'system border check' to
decide about the allocation in the system model (chapter 3.2.1.8):
5.1.1.10 System Hazard: Hazard Type A
If an output interface (OUTI) transmits erroneous information to the System
Environment, we are dealing with a System Hazard.
5.1.1.11 Causes for System Hazards:
Type B
Type C
5.1.1.12 Hazard Type B
A failure has either been occurred within the OUTI (The appropriate element works
correctly, but the information is transmitted erroneously via the OUTI to the System
Environment) or the System provides the OUTI with erroneous information.
Causes for that could be:
B44-04E08410.doc 42 of 115
EEIG ERTMS USERS GROUP
- A hazard has occurred within an ELI as a result of information processing.
- A hazard has occurred within an ELI. (The appropriate transmitting
element(s) work correctly, but the information is transmitted erroneously to
the receiving element(s))
- A hazard has occurred within an INI (The incoming information from the
System Environment is correct, but it is transmitted erroneously to the
system)
5.1.1.13 Hazard Type C
The System Environment provides the INI with erroneous
information
5.1.1.14 In case of a hazard matching type (A) it is a System hazard. Taking into account the
considerations of chapter 3.2 it is to decide which output interfaces are involved
('Output Interfaces', chapter 4.2.4.7 and 4.2.4.8). For each output interface involved,
an individual hazard is to be included in the final System hazard log (chapter 5.3). For
each of those System Hazards THR/SIL will be introduced.
5.1.1.15 In case of a hazard matching type (B) it is a cause for another hazard. It will be
documented to show that this hazard is considered. The analysis or evaluation of this
hazard shall be done by a Cause Analysis (see 2.2.1.4).
5.1.1.16 In case of a hazard matching type (C) it is either completely outside of the defined
system or occurs at the input interface to the defined system. Hazards occurring at the
input interfaces to the system are not considered since those are hazards belonging to
other systems (see also 4.2.5.1). If correct information from other systems is falsified
within an input interface, then this is considered as hazard, but analysed/evaluated by
a Causal Analysis (see 2.2.1.4). If the hazard is completely outside of the defined
system, no further evaluation in terms of the defined system is done since those
hazards are not in the scope of TSI CCS..
5.1.1.17 In case some hazards are considered to have the same causes and consequences,
they are merged together and handled as a single hazard.
5.1.1.18 Examples for the causes are listed for each hazard.
5.1.1.19 Systematic consistency cross-check of the inputs/outputs to/from the defined system in
order to ensure completeness of the hazards found
5.1.1.20 The Hazard Identification Table with a more complete set of panels is supposed to be
used if a failure mode of a function turns out to be a System Hazard. If a function
during analysis turns out to have no relevance in finding a new System Hazard, the
amount of panels of the Hazard Identification Table may be reduced appropriately.
5.2 Assumptions
5.2.1 Common Cause
Two ore more hazards may occur together as a result of a common cause. The
consideration and evaluation of common causes is the task of a Causal Analysis, as
defined in EN 50129 {Ref.: 16} Figure A.2.
B44-04E08410.doc 44 of 115
EEIG ERTMS USERS GROUP
Limitations It is assumed in the case of this hazard that EBP has been correctly
established. Data input into ETCS is considered separately.
Simplified incorrect data input
consequence
analysis
System border check Hazard Type C
B44-04E08410.doc 45 of 115
EEIG ERTMS USERS GROUP
Hazard wrong train number in system
[2.4.4-1]
Annotation Train number is service related not ETCS.
B44-04E08410.doc 46 of 115
EEIG ERTMS USERS GROUP
Limitations In the case of this hazard, only the inputting of data is considered.
Annotation Failure modes of this function are causes for hazards [6.2.10-0] /
[6.2.10-1]
B44-04E08410.doc 47 of 115
EEIG ERTMS USERS GROUP
Function reporting of engineering works/worksites
[4.6.2]
Function description The reporting of engineering works/worksites is directed to the
interlocking operators. They may - if necessary - take measures
(limitation of speed or blocking routes).
Annotation The failure modes of this function are causes for further hazards dealt
with in hazard [6.1-0] / [6.1-1].
System border check Hazard Type C
B44-04E08410.doc 48 of 115
EEIG ERTMS USERS GROUP
Limitations
Simplified Collision
consequence
collision with road traffic
analysis
Examples for causes monitoring function inactive
for the hazard
intervention function inactive
error by staff (inadmissible auxiliary action to override the intervention
function)
Annotation
B44-04E08410.doc 49 of 115
EEIG ERTMS USERS GROUP
Limitations Proving that the preconditions for permission to proceed have been
met is considered separately.
Simplified Derailment
consequence
contact
analysis
collision with road traffic
collision
Examples for causes error by staff (assisted move permitted or inadmissible issue of
for the hazard command authorising motive power unit to proceed)
incorrect information from signalbox regarding meeting the
preconditions for permission to proceed
movement authority inadmissibly generated in the ETCS central unit
incorrect information transmitted from the ETCS central unit
incorrect evaluation of information in the ETCS on-board unit
wrong values prescribed by ETCS on-board unit
incorrect data displayed on DMI
Incorrect use of 'track ahead free' ackowledgement
Annotation The term »inadmissible permission to proceed« also applies if
an order to run on sight is (not) given or displayed
a movement authority continues to be given or displayed beyond
the area monitored (transfer to another automatic train control
system).
System border check Hazard Type A (Output Interface No. 2)
B44-04E08410.doc 50 of 115
EEIG ERTMS USERS GROUP
Simplified Derailment
consequence
contact
analysis
collision with road traffic
collision
Examples for causes incorrect information from signalbox
for the hazard
information incorrectly evaluated in the ETCS central unit
information incorrectly transmitted from the ETCS central unit
information incorrectly evaluated in the ETCS on-board unit
incorrect transmission of emergency stop via GSM-R (voice)
System border check Hazard Type A (Output Interface No. 2)
B44-04E08410.doc 51 of 115
EEIG ERTMS USERS GROUP
Examples for causes project-planning errors (speed restriction not provided for, incorrect
for the hazard value for permissible speed, start or end of restricted speed section
wrongly projected)
data input omitted (speed restriction not entered, incorrect value for
permissible speed) in respect of temporary speed restrictions
data incorrectly entered (start or end of a restricted-speed section) in
respect of temporary speed restrictions
position of movement incorrectly identified
incorrect information transmitted from the ETCS central unit (start or
end of a restricted-speed section wrongly transmitted)
incorrect evaluation of information in the ETCS on-board unit
wrong values prescribed by ETCS on-board unit
data incorrectly displayed on DMI
inadequate braking effect
monitoring function inactive
intervention function inactive
Annotation No distinction is made between permanent and temporary speed
restrictions, as this has no bearing on the relevant function/hazard.
System border check Hazards Type A
[6.1-0] Output Interface No. 2
[6.1-1] Output Interface No. 1
B44-04E08410.doc 52 of 115
EEIG ERTMS USERS GROUP
Annotation No distinction is made between permanent and temporary speed
restrictions, as this has no bearing on the relevant function/hazard.
For the following processing steps, this hazard is grouped together with
further hazards to form [6.1-0] / [6.1-1] and is no longer considered
separately.
B44-04E08410.doc 53 of 115
EEIG ERTMS USERS GROUP
Simplified damage to vehicle
consequence
damage to railway facilities
analysis
derailment
Annotation No distinction is made between permanent and temporary speed
restrictions, as this has no bearing on the relevant function/hazard.
For the following processing steps, this hazard is grouped together with
further hazards to form [6.1-0] / [6.1-1] and is no longer considered
separately.
B44-04E08410.doc 56 of 115
EEIG ERTMS USERS GROUP
Hazard speed not reduced in time given speed restrictions when running
on bridges
[6.1.1.4-2]
Limitations Observance of the respective (section-related) max. permissible speed
and increases in speed is considered separately.
Simplified damage to vehicle
consequence
damage to railway facilities
analysis
derailment
Annotation No distinction is made between permanent and temporary speed
restrictions, as this has no bearing on the relevant function/hazard.
For the following processing steps, this hazard is grouped together with
further hazards to form [6.1-0] / [6.1-1] and is no longer considered
separately.
B44-04E08410.doc 57 of 115
EEIG ERTMS USERS GROUP
Annotation No distinction is made between permanent and temporary speed
restrictions, as this has no bearing on the relevant function/hazard.
For the following processing steps, this hazard is grouped together with
further hazards to form [6.1-0] / [6.1-1] and is no longer considered
separately.
B44-04E08410.doc 58 of 115
EEIG ERTMS USERS GROUP
B44-04E08410.doc 59 of 115
EEIG ERTMS USERS GROUP
Function description ETCS monitors adherence to section-related speed restrictions
(inclusive of the relevant max. permissible speed) and prevents these
being disregarded by intervening accordingly. In the case of increases
in speed, it is additionally checked that these are not executed until the
entire length of the train has cleared the section in question.
Hazard speed increased too early given speed restrictions on account of
[6.1.1.6-3] the track superstructure
Limitations Observance of the respective (section-related) max. permissible speed
and reductions in speed is considered separately.
Annotation No distinction is made between permanent and temporary speed
restrictions, as this has no bearing on the relevant function/hazard.
For the following processing steps, this hazard is grouped together with
further hazards to form [6.1-0] / [6.1-1] and is no longer considered
separately.
B44-04E08410.doc 60 of 115
EEIG ERTMS USERS GROUP
Limitations Observance of the respective (section-related) max. permissible speed
and increases in speed is considered separately.
Annotation No distinction is made between permanent and temporary speed
restrictions, as this has no bearing on the relevant function/hazard.
For the following processing steps, this hazard is grouped together with
further hazards to form [6.1-0] / [6.1-1] and is no longer considered
separately.
B44-04E08410.doc 61 of 115
EEIG ERTMS USERS GROUP
Simplified damage to vehicle
consequence
damage to railway facilities
analysis
contact
Examples for causes project-planning errors (speed restriction not provided for, incorrect
for the hazard value for permissible speed, start or end of restricted speed section
wrongly projected)
data input omitted (speed restriction not entered, incorrect value for
permissible speed) in respect of temporary speed restrictions
data incorrectly entered (start or end of a restricted-speed section) in
respect of temporary speed restrictions
position of movement incorrectly identified
incorrect information transmitted from the ETCS central unit (start or
end of a restricted-speed section wrongly transmitted)
incorrect evaluation of information in the ETCS on-board unit
wrong values prescribed by ETCS on-board unit
data incorrectly displayed on DMI
inadequate braking effect
monitoring function inactive
intervention function inactive
Annotation No distinction is made between permanent and temporary speed
restrictions, as this has no bearing on the relevant function/hazard.
System border check Hazards Type A
[6.1.1.8-0] Output Interface No. 2
[6.1.1.8-1] Output Interface No. 1
B44-04E08410.doc 62 of 115
EEIG ERTMS USERS GROUP
Function max. permissible speed in the event of deviations in track elements
from nominal state (with reference to movement at a defined speed)
[6.1.1.10]
Function description The limitation of speed in the event of deviations in track elements from
nominal state (disruption, exceedance of limit values) is a measure to
guarantee the safe condition of railway infrastructure. It is the task of
the command and control system to display and monitor the
appropriate speed restrictions.
Annotation Speed restrictions in the event of deviations in track elements from
nominal state result in temporary speed limits and are considered in
hazard [6.1-0] / [6.1-1].
[6.1.2.1]
Function description ETCS monitors the max. permissible speed for the movement, entered
as VMAX, which is limited as a function of the ride engineering on the
vehicles in the rake, and prevents this being exceeded by intervening
accordingly.
Hazard permissible speed of train due to running properties of vehicles is
[6.1.2.1-0] / [6.1.2.1- incorrectly shown / not enforced
1]
Limitations Restrictions in speed on account of the brake system on vehicles are
considered separately. All other speed restrictions arising out of the
interaction between vehicle/vehicle components and track/track
components are assigned to hazards 6.1 ff. (»line-related speed
restrictions«).
Simplified damage to vehicle
consequence
damage to railway facilities
analysis
derailment
Examples for causes error by staff
for this hazard
incorrect data input
monitoring function inactive
intervention function inactive
B44-04E08410.doc 63 of 115
EEIG ERTMS USERS GROUP
System border check Hazards Type A
[6.1.2.1-0] Output Interface No. 2
[6.1.2.1-1] Output Interface No. 1
[6.1.2.2]
Function description ETCS monitors the max. permissible speed for the movement, entered
as VMAX, which is limited as a function of the brake system on the
vehicles, and prevents this being exceeded by intervening accordingly.
Hazard max. permissible speed as a function of the brake system on
[6.1.2.2] vehicles is not adhered to
Limitations Restrictions in speed on account of the ride engineering on vehicles
are considered separately.
Simplified inadequate braking effect
consequence
analysis
System border check Hazard Type B
B44-04E08410.doc 64 of 115
EEIG ERTMS USERS GROUP
Simplified damage of trains
consequence
analysis derailment
B44-04E08410.doc 65 of 115
EEIG ERTMS USERS GROUP
Examples for causes project-planning errors (start or end of applicable section wrongly
for this hazard projected)
position of movement incorrectly identified
incorrect evaluation of information in the ETCS on-board unit
wrong values prescribed by ETCS on-board unit
data incorrectly displayed on DMI
monitoring function inactive
intervention function inactive
Annotation Hazards arising from non-observance of speed restrictions for other
reasons are dealt with as separate hazards.
Exceedance of the max. permissible speed on account of sighting
conditions is not considered here, as approximate values only can be
given for this speed, which is variable in any case, and the attendant
function (ensure stop before obstacles) is by definition irrelevant to the
ETCS DB pilot, moreover.
System border check Hazards Type A
[6.1.3.1-0] Output Interface No. 2
[6.1.3.1-1] Output Interface No. 1
B44-04E08410.doc 66 of 115
EEIG ERTMS USERS GROUP
Examples for causes project-planning errors (start of applicable section wrongly projected)
for this hazard
position of movement incorrectly identified
incorrect evaluation of information in the ETCS on-board unit
wrong values prescribed by ETCS on-board unit
data incorrectly displayed on DMI
monitoring function inactive
intervention function inactive
Annotation For the following processing steps, this hazard is grouped together with
further hazards to form hazard
[6.1.3.1-0] / [6.1.3.1-1] and is no longer considered separately.
B44-04E08410.doc 67 of 115
EEIG ERTMS USERS GROUP
B44-04E08410.doc 68 of 115
EEIG ERTMS USERS GROUP
System border check Hazards Type A
[6.1.3.2-0] Output Interface No. 2
[6.1.3.2-1] Output Interface No. 1
Function max. permissible speed when setting back in the event of danger
[6.1.3.4]
Function description When reversing the permissible speed is to be displayed and
monitored by the command and control system.
Hazard permissible speed when reversing in the event of danger is
[6.1.3.4-0] / [6.1.3.4- incorrectly shown / not enforced
1]
Limitations The speed limit caused by track characteristics is dealt with separately.
Since in this case other functions are authoritative (6.4.1 and 6.4.3) the
exceedance of the permissible speed as a single cause does not lead
to an accident/incident.
Simplified In case of collision, collision with road traffic:
consequence Increase of extent of damage
analysis
System border check Hazards Type A
[6.1.3.4-0] Output Interface No. 2
[6.1.3.4-1] Output Interface No. 1
B44-04E08410.doc 69 of 115
EEIG ERTMS USERS GROUP
Function description The end of a dead-end track is a location at which a stop is always
required. In ETCS, this stop is monitored like a stop at an end of
movement authority and no special speed restriction is monitored. The
function is covered by hazard [6.4.1-1].
Hazard speed not reduced in time when entering dead-end tracks
[6.1.3.5-2]
Annotation The restriction of speed when entering dead-end tracks is a procedure-
related restriction serving to reduce the extent of any damage in the
event of contact. The respective function and the hazards derived there
from are enumerated merely for the sake of completeness and are not
considered in any greater detail hereafter. This function is covered by
hazard [6.4.1-1].
B44-04E08410.doc 70 of 115
EEIG ERTMS USERS GROUP
Annotation The restriction of speed when entering a partially occupied track is a
procedure-related restriction serving to reduce the extent of any
damage in the event of a collision. The respective function and the
hazards derived therefrom are enumerated merely for the sake of
completeness and are not considered in any greater detail hereafter.
This function is covered by hazard 6.4.1-1.
B44-04E08410.doc 71 of 115
EEIG ERTMS USERS GROUP
B44-04E08410.doc 72 of 115
EEIG ERTMS USERS GROUP
Limitations Observance of the respective (section-related) max. permissible speed
and increases in speed is considered separately.
Simplified industrial accident
consequence
analysis
Examples for causes data incorrectly entered (start of a restricted-speed section)
for the hazard
position of movement incorrectly identified
incorrect information transmitted from the ETCS central unit (start of a
restricted-speed section wrongly transmitted)
incorrect evaluation of information in the ETCS on-board unit
wrong values prescribed by ETCS on-board unit
data incorrectly displayed on DMI
inadequate braking effect
monitoring function inactive
intervention function inactive
Annotation The speed restriction involved is always temporary.
For the following processing steps, this hazard is grouped together with
further hazards to form hazard [6.1.3.7-0] / [6.1.3.7-1] and is no longer
considered separately.
B44-04E08410.doc 73 of 115
EEIG ERTMS USERS GROUP
Examples for causes data incorrectly entered (end of a restricted-speed section)
for the hazard
position of movement incorrectly identified
incorrect information transmitted from the ETCS central unit (end of a
restricted-speed section wrongly transmitted)
incorrect evaluation of information in the ETCS on-board unit
wrong values prescribed by ETCS on-board unit
data incorrectly displayed on DMI
monitoring function inactive
intervention function inactive
Annotation The speed restriction involved is always temporary.
For the following processing steps, this hazard is grouped together with
further hazards to form hazard [6.1.3.7-0] / [6.1.3.7-1] and is no longer
considered separately.
B44-04E08410.doc 74 of 115
EEIG ERTMS USERS GROUP
Examples for causes RBC displays to RBC operator, that temporary speed restriction has
for the hazard been applied successfully when in fact no temporary speed restriction
had been applied to on-board
data input omitted (speed restriction not entered, incorrect value for
permissible speed) in respect of temporary speed restrictions
data incorrectly entered (start or end of a restricted-speed section) in
respect of temporary speed restrictions
position of movement incorrectly identified
incorrect information transmitted from the ETCS central unit (start or
end of a restricted-speed section wrongly transmitted)
incorrect evaluation of information in the ETCS on-board unit
wrong values prescribed by ETCS on-board unit
data incorrectly displayed on DMI
inadequate braking effect
monitoring function inactive
intervention function inactive
Annotation No distinction is made between permanent and temporary speed
restrictions, as this has no bearing on the relevant function/hazard.
For the following processing steps, this hazard is grouped together with
further hazards to form hazards [6.1-0] / [6.1-1] and is not considered
separately.
[6.2.1]
Function description ETCS transmits the order to lower the pantograph before locations at
which this is required.
Hazard Lowering pantograph indication incorrectly shown (FRS ref.:
[6.2.1-0] 4.8.1.5a)
B44-04E08410.doc 75 of 115
EEIG ERTMS USERS GROUP
Examples for causes project-planning error (section in which pantograph is to be lowered not
for the hazard projected, start or end of section wrongly projected)
data input omitted (section in which pantograph is to be lowered is not
entered or else the start or end of the section is incorrectly entered) in
respect of a temporary requirement to lower the pantograph
position of movement incorrectly identified
information incorrectly transmitted from the ETCS central unit (start or
end of section in which pantograph is to be lowered incorrectly
transmitted)
incorrect evaluation of order in the ETCS on-board unit
wrong values prescribed by ETCS on-board unit
data incorrectly displayed on DMI
error by staff
System border check Hazard Type A (Output Interface No. 2)
[6.2.1]
Function description ETCS transmits the order to lower the pantograph before locations at
which this is required.
Hazard pantograph not lowered
[6.2.1-1]
Simplified damage to vehicle
consequence
damage to overhead line equipment
analysis
contact
Examples for causes project-planning error (section in which pantograph is to be lowered not
for the hazard projected)
data input omitted (section in which pantograph is to be lowered is not
entered) in respect of a temporary requirement to lower the pantograph
position of movement incorrectly identified
order to lower pantograph not transmitted by the ETCS central unit
incorrect evaluation of order in the ETCS on-board unit
wrong values prescribed by ETCS on-board unit
data incorrectly displayed on DMI
error by staff (order not carried out)
B44-04E08410.doc 76 of 115
EEIG ERTMS USERS GROUP
Annotation For the following processing steps, this hazard is grouped together with
further hazards to form hazard [6.2.1-0] and is no longer considered
separately.
[6.2.1]
Function description ETCS transmits the order to lower the pantograph before locations at
which this is required.
Hazard pantograph not lowered in time
[6.2.1-2]
Simplified damage to vehicle
consequence
damage to overhead line equipment
analysis
contact
Examples for causes project-planning error (section in which pantograph is to be lowered not
for the hazard projected)
data input omitted (section in which pantograph is to be lowered is not
entered) in respect of a temporary requirement to lower the pantograph
position of movement incorrectly identified
order to lower pantograph not transmitted by the ETCS central unit
incorrect evaluation of order in the ETCS on-board unit
wrong values prescribed by ETCS on-board unit
data incorrectly displayed on DMI
error by staff (order not carried out)
Annotation For the following processing steps, this hazard is grouped together with
further hazards to form hazard [6.2.1-0] and is no longer considered
separately.
[6.2.1]
Function description ETCS transmits the order to raise the pantograph at the end of
sections at the beginning of which the pantograph was to be lowered.
Hazard pantograph raised too early
[6.2.1-3]
Simplified damage to vehicle
consequence
damage to overhead line equipment
analysis
contact
B44-04E08410.doc 77 of 115
EEIG ERTMS USERS GROUP
Examples for causes project-planning error (end of section in which pantograph is to be
for the hazard lowered incorrectly projected)
incorrect data input (end of section in which pantograph is to be
lowered) in respect of a temporary requirement to lower the pantograph
position of movement incorrectly identified
information incorrectly transmitted from the ETCS central unit (end of
section in which pantograph is to be lowered incorrectly transmitted)
incorrect evaluation of information in the ETCS on-board unit
wrong values prescribed by ETCS on-board unit
data incorrectly displayed on DMI
error by staff (pantograph raised without authorisation)
Annotation For the following processing steps, this hazard is grouped together with
further hazards to form hazard [6.2.1-0] and is no longer considered
separately.
Function switch off motive power unit current (main switch off) at required point
[6.2.2]
Function description ETCS transmits the order to switch off the motive power unit before
locations at which this is required.
Hazard motive power unit not switched off at requisite location
[6.2.2-0]
Limitations This hazard is a collective representation of hazards, since their
consequences are identical. Proceeding in this way makes the material
more manageable and straightforward for further processing.
Simplified damage to vehicle
consequence
damage to overhead line equipment
analysis
B44-04E08410.doc 78 of 115
EEIG ERTMS USERS GROUP
Examples for causes project-planning error (section in which motive power unit is to be
for the hazard switched off not projected, start or end of section wrongly projected)
data input omitted (section in which motive power unit is to be switched
off not entered or else the start or end of the section is incorrectly
entered) in respect of a temporary requirement to switch the motive
power unit off
position of movement incorrectly identified
information incorrectly transmitted from the ETCS central unit (start or
end of section in which motive power unit is to be switched off
incorrectly transmitted)
order to switch motive power unit on transmitted too early by the ETCS
central unit
incorrect evaluation of order in the ETCS on-board unit
wrong values prescribed by ETCS on-board unit
data incorrectly displayed on DMI
error by staff (order not carried out)
Annotation The wording »switch off motive power unit« generally means that the
master switch on the motive power unit is to be switched off.
Owing to the fact that Index 47 is focusing on personal injuries and that
the consequences of this hazard being considered here only concern
damage to property, it will no longer be considered hereafter.
Function switch off motive power unit current (main switch off) at required point
[6.2.2]
Function description ETCS transmits the order to switch off the motive power unit before
locations at which this is required.
Hazard motive power unit not switched off
[6.2.2-1]
Simplified damage to vehicle
consequence
damage to overhead line equipment
analysis
B44-04E08410.doc 79 of 115
EEIG ERTMS USERS GROUP
Examples for causes project-planning error (section in which motive power unit is to be
for the hazard switched off not projected)
data input omitted (section in which motive power unit is to be switched
off not entered) in respect of a temporary requirement to switch the
motive power unit off
position of movement incorrectly identified
order to switch motive power unit off not transmitted by the ETCS
central unit
incorrect evaluation of order in the ETCS on-board unit
wrong values prescribed by ETCS on-board unit
data incorrectly displayed on DMI
error by staff (order not carried out)
Annotation For the following processing steps, this hazard is grouped together with
further hazards to form hazard [6.2.2-0] and is no longer considered
separately.
Function switch off motive power unit current (main switch off) at required point
[6.2.2]
Function description ETCS transmits the order to switch off the motive power unit before
locations at which this is required.
Hazard motive power unit not switched off in time
[6.2.2-2]
Simplified damage to vehicle
consequence
damage to overhead line equipment
analysis
B44-04E08410.doc 80 of 115
EEIG ERTMS USERS GROUP
Examples for causes project-planning error (start of section in which motive power unit is to
for the hazard be switched off incorrectly projected)
incorrect data input (start of section in which motive power unit is to be
switched off) in respect of a temporary requirement to switch the
motive power unit off
position of movement incorrectly identified
information incorrectly transmitted from the ETCS central unit (start of
section in which motive power unit is to be switched off incorrectly
transmitted)
incorrect evaluation of information in the ETCS on-board unit
wrong values prescribed by ETCS on-board unit
data incorrectly displayed on DMI
error by staff (order carried out too late)
Annotation For the following processing steps, this hazard is grouped together with
further hazards to form hazard [6.2.2-0] and is no longer considered
separately.
Function switch off motive power unit current (main switch off) at required point
[6.2.2]
Function description ETCS transmits the order to switch off the motive power unit before
locations at which this is required.
Hazard motive power unit switched off too early
[6.2.2-3]
Simplified damage to vehicle
consequence
damage to overhead line equipment
analysis
B44-04E08410.doc 81 of 115
EEIG ERTMS USERS GROUP
Examples for causes project-planning error (end of section in which motive power unit is to
for the hazard be switched off incorrectly projected)
incorrect data input (end of section in which motive power unit is to be
switched off) in respect of a temporary requirement to switch the
motive power unit off
position of movement incorrectly identified
information incorrectly transmitted from the ETCS central unit (end of
section in which motive power unit is to be switched off incorrectly
transmitted)
incorrect evaluation of information in the ETCS on-board unit
wrong values prescribed by ETCS on-board unit
data incorrectly displayed on DMI
error by staff (motive power unit switched back on without
authorisation)
Annotation For the following processing steps, this hazard is grouped together with
further hazards to form hazard [6.2.2-0] and is no longer considered
separately.
Function avoid stopping at points not suitable for the adoption of auxiliary
6.2.8 measures or only poorly so
Function description This function serves to ease the rescue and to limit the extent of
damage in case of an incident (avoid stopping in tunnels in case of
fire).
The command and control system is to display the appropriate
sections.
Hazard stopping at points where stopping is not permitted
[6.2.8]
Simplified Only in case of an incident:
consequence Increase of extent of damage
analysis
Examples for causes project-planning errors (speed restriction not provided for, incorrect
for the hazard value for permissible speed, start or end of restricted speed section
wrongly projected)
position of movement incorrectly identified
incorrect information transmitted from the ETCS central unit
incorrect evaluation of information in the ETCS on-board unit
wrong values prescribed by ETCS on-board unit
data incorrectly displayed on DMI
System border check Hazard Type A (Output Interface No. 2)
B44-04E08410.doc 82 of 115
EEIG ERTMS USERS GROUP
Simplified Contact
consequence
Damage of railway vehicle
analysis
Damage of catenary
Examples for causes project-planning
for the hazard
data input omitted
position of movement incorrectly identified
information incorrectly transmitted from the ETCS central
incorrect evaluation of order in the ETCS on-board unit
wrong values prescribed by ETCS on-board unit
error by staff
System border check Hazards Type A
[6.2.10-0] Output Interface No. 2
[6.2.10-1] Output Interface No. 1
B44-04E08410.doc 83 of 115
EEIG ERTMS USERS GROUP
[6.2.11]
Function description FRS 11.3.2
SRS 4.4.18 and 5.13
Hazard Authorisation for reversing in the event of danger not given
[6.2.11]
Limitations The hazard arising from any unintentional movement by the vehicle
is considered separately in fuction 4.7.2.
The supervision in distance and speed when reversing in the event of
danger is considered separately in function 6.1.3.4.
Simplified Only in case of an incident:
consequence Increase of extent of damage
analysis
Examples for causes project-planning errors
for the hazard
position of movement incorrectly identified
incorrect information transmitted from the ETCS central unit
incorrect evaluation of information in the ETCS on-board unit
wrong values prescribed by ETCS on-board unit
System border check Hazard Type A (Output Interface No. 1)
B44-04E08410.doc 84 of 115
EEIG ERTMS USERS GROUP
Examples for causes faulty project planning (position of possible stopping place)
for the hazard
end of route release incorrectly transmitted by ETCS central unit
end of route release not taken account of in ETCS on-board unit
monitoring function inactive
intervention function inactive
error by staff (inadmissible auxiliary action to override the intervention
function)
Annotation Signal at danger is taken to mean all orders that, on grounds of safety
(e.g. end of route, occupation by vehicles of the section in advance,
non-negotiability of the section in advance), prescribe a stop for a
movement at a specified location.
System border check Hazard Type A (Output Interface No. 1)
B44-04E08410.doc 85 of 115
EEIG ERTMS USERS GROUP
Examples for causes end of route release incorrectly transmitted by ETCS central unit
for the hazard
end of route release incorrectly evaluated in ETCS on-board unit
braking curve incorrectly identified
position of movement incorrectly identified
monitoring function activated too late
intervention function activated too late
error by staff (brake operated too late)
inadequate braking effect
Annotation Signal at danger is taken to mean all orders that, on grounds of safety
(e.g. end of route, occupation by vehicles of the section in advance,
non-negotiability of the section in advance), prescribe a stop for a
movement at a specified location.
System border check Hazard Type A (Output Interface No. 1)
B44-04E08410.doc 86 of 115
EEIG ERTMS USERS GROUP
Annotation Signal at danger is taken to mean all orders that, on grounds of safety
(e.g. end of route, occupation by vehicles of the section in advance,
non-negotiability of the section in advance), prescribe a stop for a
movement at a specified location.
System border check Hazard Type A (Output Interface No. 1)
[6.4.3]
Function description The stop required before track closings is a special form of signal at
danger, as the location in question is already established prior to the
movement being authorised and it is always necessary to stop there.
The ETCS protection function corresponds to that activated to prevent
signals being passed at danger. Hence the comments made in respect
of hazard 6.4.1-1 apply by analogy.
Hazard not stopping before track closings
[6.4.3]
Simplified Contact
consequence
analysis
B44-04E08410.doc 87 of 115
EEIG ERTMS USERS GROUP
Function Check for safety-related deviations to railway installations on used
route
[6.6]
Function description It is to be ensured with the aid of suitable means of diagnosis/display
that irregularities in the ETCS central unit and trackside equipment are
detected where they have a bearing on safety.
Hazard Irregularities in the ETCS central unit or in trackside equipment
[6.6] not detected
Limitations Maintenance and the irregularities to be detected within this framework
are considered separately.
Simplified movement authority inadmissibly generated
consequence
incorrect information transmitted from the ETCS central unit
analysis
position of movement incorrectly identified
monitoring function inactive
System border check Hazard Type B
B44-04E08410.doc 88 of 115
EEIG ERTMS USERS GROUP
Simplified where the vehicle is properly secured:
consequence none
analysis otherwise:
collision
collision with road traffic
contact
derailment
Examples for causes error by staff (air brake not manually applied)
for the hazard
function not actuated by ETCS on-board unit
function not executed by brake system
System border check Hazard Type A (Output Interface No. 1)
B44-04E08410.doc 89 of 115
EEIG ERTMS USERS GROUP
B44-04E08410.doc 90 of 115
EEIG ERTMS USERS GROUP
5 [6.1-0] permissible speed as a function of route characteristics 2
incorrectly shown
B44-04E08410.doc 91 of 115
EEIG ERTMS USERS GROUP
26 [6.4.1-1] not stopping at the end of a movement authoritiy 1
(without stopping beyond the end of movement
authority)
B44-04E08410.doc 92 of 115
EEIG ERTMS USERS GROUP
6.1 General
This chapter contains so far examples of national safety requirements. Some work is still to be
done in order to enable harmonisation of THRs and SILs imposed on the System Hazards,
constituting the harmonised safety requirements for CCS for interoperability: First the
comparison of national examples for safety requirements has to be triggered. Therefore the
member states are asked to contribute to chapter 6 of the document by deriving - on basis of
Index 47 - national values for THRs (In order to achieve a high level of comparability,
assumptions about Level of tolerable Risk, Criticality, Fatality and the apportionment of the
tolerable Risk to the System Hazards should be included). Secondly the Causal Analysis has to
be carried out and linked to the 'Log of System Hazards' of chapter 5.4 to ensure as well, that
additional System Hazards arising from system design will be discovered.
After finishing these 'next steps' this chapter will contain the harmonised mandatory CCS safety
requirements.
B44-04E08410.doc 93 of 115
EEIG ERTMS USERS GROUP
victims
1,61 10 11
TIRFETCSpilotLine,randomFailures 0,1 0,7 TIRFETCS passenger hour
6.2.4.3 =
6.2.4.4 This is in a first approach equally distributed among the pilot line’s 13 ETCS System
Hazards:
TIRFETCSpilotLine,randomFailures, perHazard
THRSystemHazard
6.2.4.7
Fk C k
TIRFETCSpilotLine,randomFailures, perHazard
THRSystemHazard
6.2.4.8
Fk
As F, the fatality of the most fatal accident which may occur as consequence of a
hazard is taken into consideration.
B44-04E08410.doc 94 of 115
EEIG ERTMS USERS GROUP
6.2.5 Values
1 2 3 4 5 6
average fatality average fatality THR
No System hazard
at v=40km/h at v=200km/h
(hazards/hour)
[victims / [victims /
(passenger x (passenger x v=40km/h v=200km/h
accident)] accident)]
1 unauthorised setting back 4 10 4 1 10 2 3,1 10 9 1,24 10 10
2 passing the defined border of the
shunting area
(balise 'stop if in shunting')
3 move inadmissibly authorised 4 10 4 1 10 2 3,1 10 9 1,24 10 10
4 permission to proceed not withdrawn in 4 10 4 1 10 2 3,1 10 9 1,24 10 10
time in the event of danger
5 permissible speed as a function of route 4 10 4 1 10 2 3,1 10 9 1,24 10 10
characteristics incorrectly shown
6 permissible speed as a function of route
characteristics not enforced
7 permissible speed when passing level
crossings incorrectly shown
8 permissible speed when passing level
crossings not enforced
9 permissible speed on account of the 2,6 10 5 6,4 10 4 5 10 8 1,93 10 9
design of the overhead line incorrectly
shown
10 permissible speed on account of the
design of the overhead line not
enforced
11 permissible speed of train due to 4 10 4 1 10 2 3,1 10 9 1,24 10 10
running properties of vehicles
incorrectly shown
12 permissible speed of train due to
running properties of vehicles not
enforced
13 permissible speed when running on 8,3 10 4 --
1,5 10 9 -
sight incorrectly shown
14 permissible speed when running on
sight not enforced
15 permissible shunting speed incorrectly
shown
16 permissible shunting speed not
enforced
17 permissible speed when reversing
incorrectly shown
B44-04E08410.doc 95 of 115
EEIG ERTMS USERS GROUP
18 permissible speed when reversing in
the event of danger not enforced
19 permissible speed on grounds of track 0,77 0,77 1,61 10 12 1,61 10 12
works incorrectly shown
20 max. permissible speed on grounds of
track works not enforced
21 lowering pantograph indication 2,6 10 5 6,4 10 4 5 10 8 1,93 10 9
incorrectly shown
22 stopping at points where stopping is not
permitted
23 Information about route unsuitability not
advised to the driver
24 enter a section of the route which is not
permitted to (due to route suitability)
25 authorisation for reversing in the event
of danger not given
26 not stopping at the end of a movement 4 10 4 1 10 2 3,1 10 9 1,24 10 10
authoritiy (without stopping beyond the
end of movement authority)
27 not stopping at the end of a movement 4 10 4 1 10 2 3,1 10 9 1,24 10 10
authoritiy (but stopping beyond the
end of movement authority)
28 start moving without having a correct 4 10 4 1 10 2 3,1 10 9 1,24 10 10
movement authority
29 air brake not applied when vehicle 4 10 4 1 10 2 3,1 10 9 1,24 10 10
parked
B44-04E08410.doc 97 of 115
EEIG ERTMS USERS GROUP
B44-04E08410.doc 98 of 115
EEIG ERTMS USERS GROUP
5 [6.1-0] Permissible speed as a 10-4/hr UK philosophy is that safety is in the
function of route enforcement system rather than the
characteristics not driver/displayed information and hence the
shown to the driver display system is only marginally safety
related.
B44-04E08410.doc 99 of 115
EEIG ERTMS USERS GROUP
8 [6.1.1.3-1] max. permissible speed 10-7/hr speeds UK philosophy is that safety is in the
when passing level up to & enforcement system rather than the
crossings is not including 25% driver/displayed information and hence the
enforced over speed; enforcement system provides the safety.
It is considered that there is an element of
10-9/hr speeds
mitigation in the driver not speeding
in excess of
excessively due to his route knowledge.
25% over
speed;
Consequences for level crossing may be
different but not considered to be a
material affect based on preliminary
assessment.
9 [6.1.1.8-0] max. permissible speed NA Not required by UK, fully covered by items
on account of the 5 & 6.
design of the overhead
line is not shown to the
driver
10 [6.1.1.8-1] max. permissible speed NA Not required by UK, fully covered by items
on account of the 5 & 6.
design of the overhead
line is not enforced
11 [6.1.2.1-0] max. permissible speed 10-4/hr UK philosophy is that safety is in the
of train due to running enforcement system rather than the
properties of vehicles is driver/displayed information and hence the
not shown to the driver display system is only marginally safety
related.
7 References
Ref # Document
1 Safety Requirements and Requirements to Safety Analysis for Interoperability for
the Control-Command and Signalling Sub-System.
2 Directive 96/48/EC of 23 July 1996 on the interoperability of the trans-European
high-speed rail system
3 Directive 2001/16/EC of 19 March 2001 on the interoperability of the trans-
European conventional rail system
4 Commission Decision of 30 May 2002 concerning the technical specification for
interoperability relating to the control-command and signalling subsystem of the
trans-European high-speed rail system referred to in Article 6(1) of Council Directive
96/48/EC (notified under document number C(2002) 1947)
5 CCS TSI CR: 2001/16/EC - 01/16-ST01 part 2 Version EN 07 24.11.2004
6 Index 27/UNISIG Subset 91 Safety Requirements for the Technical Interoperability
of ETCS in Levels 1 & 2
7 All Class 1 specifications for ETCS as defined in Annex A of the Control-Command
and Signalling Technical Specification for Interoperability
8 Functional Analysis Of Trans – European Rail Operation Reference EEIG:01 E 129
version 2 dated 08.07.04.
9 ETCS and GSM-R Change Control Process
10 All Class 1 specifications for GSM-R as defined in Annex A of the Control-
Command and Signalling Technical Specification for Interoperability
11 Index 47 Remit V1EEIG : 03E415
12 EEIG Operational Rules Writing Group: Crosscheck of functions
13 ERTMS Operational Rules Writing Group: Fragile Points
14 Reason, J. T. (1990) Human Error. Cambridge: Cambridge University Press
15 EN 50126:1999 Railway applications - The specification and demonstration of
Reliability, Availability, Maintainability and Safety (RAMS)
16 EN 50129:2003 Railway applications - Communication, signalling and processing
systems - Safety related electronic systems for signalling
17 Commission Decision of 29 April 2004 modifying Annex A to Decision 2002/731/EC
of 30 May 2002 and establishing the main characteristics of Class A system
(ERTMS) of the control - command and signalling subsystem of the trans- European
conventional rail system referred to in Directive 2001/16/EC of the European
Parliament and of the Council (notified under document number C(2004) 1559)
(2004/447/EC)