Method_Statement replacement of PV Module

This document outlines the method statement for the replacement of a defective PV module at the Anton Oil project, scheduled for June 5, 2025. It details the necessary permits, certifications, isolation types, and the step-by-step process required to complete the task safely. Key steps include obtaining a work permit, conducting a toolbox talk, and specific equipment and tools needed for the job.

Uploaded by

Hussein Hisham
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
8 views1 page

Method_Statement replacement of PV Module

This document outlines the method statement for the replacement of a defective PV module at the Anton Oil project, scheduled for June 5, 2025. It details the necessary permits, certifications, isolation types, and the step-by-step process required to complete the task safely. Key steps include obtaining a work permit, conducting a toolbox talk, and specific equipment and tools needed for the job.

Uploaded by

Hussein Hisham
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 1

SPECIEFIC TASK METHOD STATEMENT

Contractor’s Company Project/ contract


Date of the work scheduled: 05/06/2025 name Anton Oil number BLK9/IRQ-OP-
CON-1190
Facility/Area/Location B9/SPP

SAP Work Order №:


General Work Title:
To perform job for Replacement of Defective PV Module

Equipment Info/№: PV Module

 If Applicable: ✔
Type of Permit: CWP. ✔ SPWP. HWP. BCWP
Type of Certificate: CSEC. EXC. RC. Scaffolding Cert. N/A

Type of Isolation: EIC. MIC. N/A. ✔

 PO & PA confirm that the task will be carried out as per the defined steps in this MS
Permit Originator Fazel
Name Signature
/ Performing Authority
 IA accepts and endorses steps of work defined in this MS
Issuing Authority Name
Signature
 KEBL Emergency Response Representative accepts and endorses steps of work defined in this MS
ER Representative Name
Signature
(If applicable)

 Breck down the job steps:


№ Main steps of the work process Equipment / Tools Required
1 Obtain a valid work permit

2 Understand the job and conduct toolbox talk regarding the task

3 Turn Off the Inverter.

4 Put the Tracker to T-Level Mode by using the tracker mobile app

5 Remove the defective PV module and install the new PV module. HAND TOOLS

6 Retorque the new PV module (14-20 NM) HAND TOOLS

7 Reconnect the MC-4 connector with the string. HAND TOOLS

8 Put the tracker into Automatic Mode through the mobile APP. HAND TOOLS

9 Turn ON the inverter and measure the current in the string.

1
House keeping all working area
0
1
Close the PTW