P6 Schedule
P6 Schedule
1 Project: LCHS - B1 Establishment of Infrastructure in LDA City, Housing Scheme (Phase-I) 907.50d 16-Jun-22 08:00 AM A 24-Jun-25 05:00 PM 24-Jun-25 05:00 PM, Project: LCHS - B1 Establishment of Infrastructure in LD
2 WBS: LCHS - B1.7 Completion Milestone 907.25d 16-Jun-22 08:00 AM 24-Jun-25 03:00 PM 24-Jun-25 03:00 PM, WBS: LCHS - B1.7 Completion Milestone
3 A1430 Construction of Foundation 907.25d 16-Jun-22 08:00 AM 24-Jun-25 03:00 PM
4 A1440 Cable Laying 907.25d 16-Jun-22 08:00 AM 24-Jun-25 03:00 PM
5 A1450 Equipment Installation 907.25d 16-Jun-22 08:00 AM 24-Jun-25 03:00 PM
6 A1460 Project Finish 907.25d 16-Jun-22 08:00 AM 24-Jun-25 03:00 PM
7 WBS: LCHS - B1.2 Preliminary Phase 16.25d 16-Jun-22 08:00 AM A 05-Jul-22 05:00 PM A
8 A1000 NOC from WAPDA 1.00d 16-Jun-22 08:00 AM A 16-Jun-22 05:00 PM A
9 A1010 IFC Drawings 1.00d 16-Jun-22 08:00 AM A 16-Jun-22 05:00 PM A
10 A1020 Mobilization 16.25d 16-Jun-22 08:00 AM A 05-Jul-22 05:00 PM A
11 WBS: LCHS - B1.6 Execution Phase 907.50d 16-Jun-22 08:00 AM A 24-Jun-25 03:00 PM 24-Jun-25 03:00 PM, WBS: LCHS - B1.6 Execution Phase
12 WBS: LCHS - B1.6.7 Procurement of Civil Construction Material 109.25d 04-Jul-22 08:00 AM A 12-Nov-22 03:00 PM A
13 A1130 Procurement of Civil Construction Material 109.25d 04-Jul-22 08:00 AM A 12-Nov-22 03:00 PM A
14 WBS: LCHS - B1.6.6 Construction of Foundation 135.00d 16-Jun-22 08:00 AM A 26-Nov-22 03:00 PM A
15 A1170 Excavation & Compaction 102.50d 19-Jul-22 08:00 AM A 19-Nov-22 03:00 PM A
16 A1180 Pouring of Lean Concrete 129.25d 23-Jun-22 08:00 AM A 26-Nov-22 03:00 PM A
17 A1190 Brick Masonry for Foundation 129.25d 16-Jun-22 08:00 AM A 19-Nov-22 03:00 PM A
18 A1200 Pouring of Pads Concrete 129.25d 16-Jun-22 08:00 AM A 19-Nov-22 03:00 PM A
19 WBS: LCHS - B1.6.5 Procurement of Electrical Equipmet/Materials 17-Jun-24
600.75d 08:0008:00
16-Jun-22 AM, WBS:
AM ALCHS - B1.6.508:00
17-Jun-24 Procurement
AM of Electrical Equipmet/Materials
20 A1470 Wapda Design Approval - Delay 513.75d 16-Jun-22 08:00 AM A 01-Mar-24 05:00 PM A
21 A1480 Issuance of PO 7.50d 01-Mar-24 08:00 AM A 09-Mar-24 03:00 PM A
22 A1490 PO Vetting/Approval Process 6.50d 09-Mar-24 08:00 AM A 16-Mar-24 03:00 PM A
23 A1500 Manufacturing of Equipment 38.50d 18-Mar-24 08:00 AM A 02-May-24 05:00 PM A
24 A1510 Wapda Inspection at Factory 13.50d 01-May-24 08:00 AM A 16-May-24 05:00 PM A
25 A1520 Equipment Delivery at Site 13.50d 16-May-24 08:00 AM A 31-May-24 05:00 PM A
26 A1530 Wapda Inspection at Site 12.25d 01-Jun-24 08:00 AM A 17-Jun-24 08:00 AM
27 WBS: LCHS - B1.6.4 Laying of Cables 151.50d 23-Dec-24 08:00 AM A 24-Jun-25 03:00 PM 24-Jun-25 03:00 PM, WBS: LCHS - B1.6.4 Laying of Cables
28 A1210 Excavation 151.50d 23-Dec-24 08:00 AM A 14-Jun-25 03:00 PM Excavation
29 A1220 Thrust Bore and Installation of 8'' UPVC Pipe Class-D 144.50d 28-Dec-24 08:00 AM A 21-Jun-25 03:00 PM Thrust Bore and Installation of 8'' UPVC Pipe Class-D
30 A1230 Thrust Bore and Installation of 4'' UPVC Pipe Class-D 143.38d 28-Dec-24 08:00 AM A 20-Jun-25 01:00 PM Thrust Bore and Installation of 4'' UPVC Pipe Class-D
31 A1240 Sand Bedding 142.50d 28-Dec-24 08:00 AM A 19-Jun-25 03:00 PM Sand Bedding
32 A1250 Cable Laying 129.25d 15-Jan-25 08:00 AM A 20-Jun-25 03:00 PM Cable Laying
33 A1260 Bricks Laying with Warning Tape 146.50d 26-Dec-24 08:00 AM A 21-Jun-25 03:00 PM Bricks Laying with Warning Tape
34 A1270 Sand Top Cover 145.50d 27-Dec-24 08:00 AM A 21-Jun-25 03:00 PM Sand Top Cover
35 A1280 Laying of Bricks 142.75d 01-Jan-25 08:00 AM A 23-Jun-25 05:00 PM Laying of Bricks
36 A1290 Backfilling 142.50d 02-Jan-25 08:00 AM A 24-Jun-25 03:00 PM Backfilling
37 WBS: LCHS - B1.6.3 Installation of Equipment 55.75d 07-Apr-25 08:00 AM 12-Jun-25 05:00 PM 12-Jun-25 05:00 PM, WBS: LCHS - B1.6.3 Installation of Equipment
38 A1310 Installation of RMU 51.75d 07-Apr-25 08:00 AM 07-Jun-25 03:00 PM
39 A1320 Earthing of RMU 22.00d 14-May-25 08:00 AM 09-Jun-25 05:00 PM
40 A1330 Installation of Pad Mounted Transformer 52.75d 09-Apr-25 08:00 AM 11-Jun-25 05:00 PM
41 A1340 Earthing of Pad Mounted Transformer 21.00d 16-May-25 08:00 AM 10-Jun-25 05:00 PM
42 A1350 Installation of DBs 52.50d 09-Apr-25 08:00 AM 11-Jun-25 03:00 PM
43 A1360 Earthing of DBs 25.75d 12-May-25 08:00 AM 11-Jun-25 03:00 PM
44 A1370 Termination of Equipmen 21.25d 19-May-25 08:00 AM 12-Jun-25 05:00 PM
45 WBS: LCHS - B1.5 Finalization of Project 9.50d 13-Jun-25 08:00 AM 24-Jun-25 05:00 PM 24-Jun-25 05:00 PM, WBS: LCHS - B1.5 Finalization of Project
46 A1400 Testing and Commissioning 9.50d 13-Jun-25 08:00 AM 24-Jun-25 05:00 PM
47 A1410 Final Document & Project Handing Over 9.50d 13-Jun-25 08:00 AM 24-Jun-25 05:00 PM
48 A1420 Project Completion 9.50d 13-Jun-25 08:00 AM 24-Jun-25 05:00 PM