P6 Schedule

The document outlines the establishment of infrastructure in LDA City, Housing Scheme (Phase-I), detailing various activities, their timelines, and milestones from June 2022 to June 2025. Key components include construction phases, procurement of materials, and installation of equipment, with specific tasks assigned to different work breakdown structures (WBS). The project aims for completion by June 24, 2025, with a focus on critical tasks and remaining work efforts.

Uploaded by

Aleem Joiya
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
5 views

P6 Schedule

The document outlines the establishment of infrastructure in LDA City, Housing Scheme (Phase-I), detailing various activities, their timelines, and milestones from June 2022 to June 2025. Key components include construction phases, procurement of materials, and installation of equipment, with specific tasks assigned to different work breakdown structures (WBS). The project aims for completion by June 24, 2025, with a focus on critical tasks and remaining work efforts.

Uploaded by

Aleem Joiya
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Establishment of Infrastructure in LDA City,

Housing Scheme (Phase-I)


# Activity ID Activity Name Original Start Finish 2025 2026
Duration December January February March April May June July August S October N December
January

1 Project: LCHS - B1 Establishment of Infrastructure in LDA City, Housing Scheme (Phase-I) 907.50d 16-Jun-22 08:00 AM A 24-Jun-25 05:00 PM 24-Jun-25 05:00 PM, Project: LCHS - B1 Establishment of Infrastructure in LD
2 WBS: LCHS - B1.7 Completion Milestone 907.25d 16-Jun-22 08:00 AM 24-Jun-25 03:00 PM 24-Jun-25 03:00 PM, WBS: LCHS - B1.7 Completion Milestone
3 A1430 Construction of Foundation 907.25d 16-Jun-22 08:00 AM 24-Jun-25 03:00 PM
4 A1440 Cable Laying 907.25d 16-Jun-22 08:00 AM 24-Jun-25 03:00 PM
5 A1450 Equipment Installation 907.25d 16-Jun-22 08:00 AM 24-Jun-25 03:00 PM
6 A1460 Project Finish 907.25d 16-Jun-22 08:00 AM 24-Jun-25 03:00 PM
7 WBS: LCHS - B1.2 Preliminary Phase 16.25d 16-Jun-22 08:00 AM A 05-Jul-22 05:00 PM A
8 A1000 NOC from WAPDA 1.00d 16-Jun-22 08:00 AM A 16-Jun-22 05:00 PM A
9 A1010 IFC Drawings 1.00d 16-Jun-22 08:00 AM A 16-Jun-22 05:00 PM A
10 A1020 Mobilization 16.25d 16-Jun-22 08:00 AM A 05-Jul-22 05:00 PM A
11 WBS: LCHS - B1.6 Execution Phase 907.50d 16-Jun-22 08:00 AM A 24-Jun-25 03:00 PM 24-Jun-25 03:00 PM, WBS: LCHS - B1.6 Execution Phase
12 WBS: LCHS - B1.6.7 Procurement of Civil Construction Material 109.25d 04-Jul-22 08:00 AM A 12-Nov-22 03:00 PM A
13 A1130 Procurement of Civil Construction Material 109.25d 04-Jul-22 08:00 AM A 12-Nov-22 03:00 PM A
14 WBS: LCHS - B1.6.6 Construction of Foundation 135.00d 16-Jun-22 08:00 AM A 26-Nov-22 03:00 PM A
15 A1170 Excavation & Compaction 102.50d 19-Jul-22 08:00 AM A 19-Nov-22 03:00 PM A
16 A1180 Pouring of Lean Concrete 129.25d 23-Jun-22 08:00 AM A 26-Nov-22 03:00 PM A
17 A1190 Brick Masonry for Foundation 129.25d 16-Jun-22 08:00 AM A 19-Nov-22 03:00 PM A
18 A1200 Pouring of Pads Concrete 129.25d 16-Jun-22 08:00 AM A 19-Nov-22 03:00 PM A
19 WBS: LCHS - B1.6.5 Procurement of Electrical Equipmet/Materials 17-Jun-24
600.75d 08:0008:00
16-Jun-22 AM, WBS:
AM ALCHS - B1.6.508:00
17-Jun-24 Procurement
AM of Electrical Equipmet/Materials
20 A1470 Wapda Design Approval - Delay 513.75d 16-Jun-22 08:00 AM A 01-Mar-24 05:00 PM A
21 A1480 Issuance of PO 7.50d 01-Mar-24 08:00 AM A 09-Mar-24 03:00 PM A
22 A1490 PO Vetting/Approval Process 6.50d 09-Mar-24 08:00 AM A 16-Mar-24 03:00 PM A
23 A1500 Manufacturing of Equipment 38.50d 18-Mar-24 08:00 AM A 02-May-24 05:00 PM A
24 A1510 Wapda Inspection at Factory 13.50d 01-May-24 08:00 AM A 16-May-24 05:00 PM A
25 A1520 Equipment Delivery at Site 13.50d 16-May-24 08:00 AM A 31-May-24 05:00 PM A
26 A1530 Wapda Inspection at Site 12.25d 01-Jun-24 08:00 AM A 17-Jun-24 08:00 AM
27 WBS: LCHS - B1.6.4 Laying of Cables 151.50d 23-Dec-24 08:00 AM A 24-Jun-25 03:00 PM 24-Jun-25 03:00 PM, WBS: LCHS - B1.6.4 Laying of Cables
28 A1210 Excavation 151.50d 23-Dec-24 08:00 AM A 14-Jun-25 03:00 PM Excavation
29 A1220 Thrust Bore and Installation of 8'' UPVC Pipe Class-D 144.50d 28-Dec-24 08:00 AM A 21-Jun-25 03:00 PM Thrust Bore and Installation of 8'' UPVC Pipe Class-D
30 A1230 Thrust Bore and Installation of 4'' UPVC Pipe Class-D 143.38d 28-Dec-24 08:00 AM A 20-Jun-25 01:00 PM Thrust Bore and Installation of 4'' UPVC Pipe Class-D
31 A1240 Sand Bedding 142.50d 28-Dec-24 08:00 AM A 19-Jun-25 03:00 PM Sand Bedding
32 A1250 Cable Laying 129.25d 15-Jan-25 08:00 AM A 20-Jun-25 03:00 PM Cable Laying
33 A1260 Bricks Laying with Warning Tape 146.50d 26-Dec-24 08:00 AM A 21-Jun-25 03:00 PM Bricks Laying with Warning Tape
34 A1270 Sand Top Cover 145.50d 27-Dec-24 08:00 AM A 21-Jun-25 03:00 PM Sand Top Cover
35 A1280 Laying of Bricks 142.75d 01-Jan-25 08:00 AM A 23-Jun-25 05:00 PM Laying of Bricks
36 A1290 Backfilling 142.50d 02-Jan-25 08:00 AM A 24-Jun-25 03:00 PM Backfilling
37 WBS: LCHS - B1.6.3 Installation of Equipment 55.75d 07-Apr-25 08:00 AM 12-Jun-25 05:00 PM 12-Jun-25 05:00 PM, WBS: LCHS - B1.6.3 Installation of Equipment
38 A1310 Installation of RMU 51.75d 07-Apr-25 08:00 AM 07-Jun-25 03:00 PM
39 A1320 Earthing of RMU 22.00d 14-May-25 08:00 AM 09-Jun-25 05:00 PM
40 A1330 Installation of Pad Mounted Transformer 52.75d 09-Apr-25 08:00 AM 11-Jun-25 05:00 PM
41 A1340 Earthing of Pad Mounted Transformer 21.00d 16-May-25 08:00 AM 10-Jun-25 05:00 PM
42 A1350 Installation of DBs 52.50d 09-Apr-25 08:00 AM 11-Jun-25 03:00 PM
43 A1360 Earthing of DBs 25.75d 12-May-25 08:00 AM 11-Jun-25 03:00 PM
44 A1370 Termination of Equipmen 21.25d 19-May-25 08:00 AM 12-Jun-25 05:00 PM
45 WBS: LCHS - B1.5 Finalization of Project 9.50d 13-Jun-25 08:00 AM 24-Jun-25 05:00 PM 24-Jun-25 05:00 PM, WBS: LCHS - B1.5 Finalization of Project
46 A1400 Testing and Commissioning 9.50d 13-Jun-25 08:00 AM 24-Jun-25 05:00 PM
47 A1410 Final Document & Project Handing Over 9.50d 13-Jun-25 08:00 AM 24-Jun-25 05:00 PM
48 A1420 Project Completion 9.50d 13-Jun-25 08:00 AM 24-Jun-25 05:00 PM

Actual Level of Effort Remaining Work summary


Page 1 of 1 Prepared By: Engr. Aleem Iqbal
Actual Work Critical Remaining Work Dated: 03/03/2025