cormos 2019
cormos 2019
PII: S1359-4311(18)31282-1
DOI: https://doi.org/10.1016/j.applthermaleng.2018.10.064
Reference: ATE 12808
Please cite this article as: A-M. Cormos, C-C. Cormos, Techno-economic assessment of combined hydrogen &
power co-generation with carbon capture: The case of coal gasification, Applied Thermal Engineering (2018), doi:
https://doi.org/10.1016/j.applthermaleng.2018.10.064
This is a PDF file of an unedited manuscript that has been accepted for publication. As a service to our customers
we are providing this early version of the manuscript. The manuscript will undergo copyediting, typesetting, and
review of the resulting proof before it is published in its final form. Please note that during the production process
errors may be discovered which could affect the content, and all legal disclaimers that apply to the journal pertain.
Techno-economic assessment of combined hydrogen & power
Abstract
The gasification technology has multiple key advantages for future low carbon power
generation scenario e.g. reduced energy and cost penalties for CO 2 capture, multi-fuel multi-
product operation capability, ability to process lower grade fuels, plant flexibility etc. This
paper is assessing the updated most important techno-economic aspects of IGCC power plant
equipped with pre-combustion CO2 capture. Several key design options were assess in view
of techno-economic indicators: selection of the gasification reactor, chemical vs. physical gas-
liquid absorption used for CO2 capture, F and H-class gas turbines used for the combined
cycle power block, flexible hydrogen and power co-generation etc. Evaluated coal-based
gasification concepts generate 400 - 600 MWe net power with a flexible hydrogen output from
zero up to 300 MWth with 90% carbon capture rate. The similar design without carbon capture
was also consider as a base case to quantify the technical and economical modifications
induced by the CO2 capture step. As the techno-economical results show, the optimised IGCC
plant (using dry fed entrained flow gasifier, H-class gas turbine, physical solvents, flexible
hydrogen and power co-generation etc.) provides improved results. In conclusion, the IGCC
with pre-combustion capture is one promising technology for the future low-carbon economy.
*
Corresponding author. Tel.: +40-264-593833, Fax: +40-264-590818
E-mail address: [email protected]
1
Keywords: IGCC; Flexible hydrogen and power co-generation; Carbon capture and storage
(CCS); Chemical vs. physical pre-combustion CO2 capture; Hydrogen-fuelled gas turbines.
1. Introduction
Currently, the energy sector is facing significant constraints and changes in terms of
reducing CO2 emissions for developing the future low carbon economy, on-growing
indicators of conventional fossil fuel-based power plants, electricity and fuel prices volatility,
modification of economic and environmental regulations etc. [1]. One of the most important
factors to be considered for transition to future power generation is representing the need to
reduce significantly the CO2 emissions as an active mean to combat climate change. Since the
fossil fuels are foreseen to remain a primary energy source for the next decades (according to
IEA World Energy Outlook and BP Statistical Review of World Energy, the global coal
reserves can cover more than 130 years, for oil and natural gas the reserves can cover more
than 50 years at current R/P ratio), there is a strong need to develop power generation
technologies with reduced fossil CO2 foot-print [2]. To facilitate the widespread development
and deployment of carbon capture technologies into energy sector as well as other industrial
sectors with high CO2 emissions, various regulating measures have been put into action e.g. at
European Union level ambitious targets have been defined and enforced aimed to
significantly reduce the greenhouse gas emissions and to boost the development of renewable
Carbon capture and storage (CCS) represents a group of technologies aimed to be used
applications (e.g. metallurgy, cement production, petro-chemistry etc.) for reducing the fossil
CO2 emissions. There are several conceptual methods that can be used for CO 2 capture [4]: (i)
2
post-combustion which focuses on capturing CO2 from the flue gases produced by
combustion; (ii) pre-combustion capture which removes CO2 from combustible gas before
instead of air combustion avoiding nitrogen contamination of the combustion flue gases. For
straightforward considering the higher CO2 partial pressure in the shifted syngas compared to
combustion flue gases (10 - 14 bar vs. 0.1 - 0.15 bar) [5]. After capture, CO2 can be
compounds or used for Enhanced Oil Recovery - EOR as considered in this paper).
Although, the gasification technology is quite old, there are significant and promising
advantages of this mature technology in the current situation [6-7]. The gasification
technology has multiple key advantages for the future low carbon power generation system
[8-9]: reduced energy and cost penalties for pre-combustion CO2 capture (compared to post-
various fuel types e.g. coal, lignite, biomass, solid wastes for generation of a wide range of
energy carries or chemicals e.g. power, hydrogen, synthetic fuels), ability to process lower
grade fuels (presumably cheaper than high grade fuels used preferably in the combustion-
based power plants), plant flexibility (capability to change the generated energy carrier
considering the instant grid demand with important techno-economic benefits) etc.
decarbonisation of the syngas prior to its combustion in the gas turbine [10-11]. By pre-
combustion capture, the syngas produced in the gasification reactor is then catalytically
shifted with steam to concentrate the carbon species as CO 2 (simultaneously with hydrogen
production). The shifted syngas is then decarbonised by removing the CO2 in an Acid Gas
Removal (AGR) unit and the hydrogen-rich gas can be used for production of various energy
3
carriers e.g. to generate power in a Combined Cycle Gas Turbine (CCGT) or hydrogen /
synthetic fuels by syngas chemical processing. Beside pre-combustion CO2 capture step, an
Integrated Gasification Combined Cycle (IGCC) plant with CCS requires the development of
gas turbines able to use hydrogen-rich gas as fuel. There is already a growing interest of main
gas turbine manufacturers to adapt the existing machines to hydrogen-rich fuels [12].
The main target of this paper is to assess from a techno-economic point of view the
combination of flexible hydrogen and power co-generation with CO2 capture applied to a
gasification plant. The evaluated pre-combustion CO2 capture methods are based on gas-
liquid absorption technology using chemical and physical solvents (e.g. MDEA, SelexolTM)
[13]. As hydrogen-fuelled gas turbines, state of the art F and H-class machines from the main
manufacturers (Siemens, General Electric and Mitsubishi Hitachi Power Systems) are used to
generate 400 - 600 MWe net power with a flexible hydrogen output from zero up to 300 MWth
with 90% carbon capture rate. Key plant design options are fully assess in term of techno-
economic indicators: selection of the gasification reactor, chemical vs. physical scrubbing
used for CO2 capture, hydrogen-fuelled F and H-class gas turbines, flexible hydrogen and
power co-generation etc. As a benchmark case used to evaluate the energy and cost penalties
In an IGCC power plant without carbon capture, the coal is first gasified with oxygen
and steam, the generated syngas is cooled down and then desulphurised in an AGR unit
(coupled with a Claus plant). The clean syngas is then used in a combined cycle for power
[11,14]: (i) a catalytic water gas shift stage is introduced to concentrate the carbon species as
CO2 and to transfer the thermal energy of the syngas in form of hydrogen; (ii) the AGR unit is
expanded to CO2 capture beside syngas desulphurisation together with captured CO2
4
conditioning (drying and compression); (iii) a hydrogen-fuelled gas turbine is used for the
(PSA) unit for hydrogen purification and then a compression stage is required. Figure 1 is
presenting the conceptual design of an IGCC plant for hydrogen and power co-generation
Figure 1. Design of IGCC plant for flexible hydrogen and power co-generation
In term of gasification reactors, there are many industrial-size gasifiers available but
for an IGCC design with pre-combustion CO2 capture, the oxygen-blown entrained-flow type
is the most suitable to be considered [5-6]. The air-blow gasifiers are not a solution for
designs with CCS due to syngas dilution with nitrogen which complicate the CO2 removal
process as well as reducing the overall plant energy efficiency. Moving and fluidised bed
gasifiers are not considered for CCS designs due to several reasons e.g. syngas downstream
clean-up issues (removing the pyrolysis products), lower fuel conversion rate and carbon
capture capabilities etc. Among various entrained-flow gasifiers on the market, this work is
considering a Shell gasifier operated at 40 bar which has several key advantages: high fuel
conversion rate (>99%) and cold gas efficiency (about 80%) due to a combination of dry fed
& syngas quench configuration, low syngas downstream clean-up issues (high operating
temperature of >1400oC significantly reduce pyrolysis products), good heat recovery potential
within the gasification island (syngas cooling is done by using heat recovery boilers) etc.
As for the acid gases (H2S and CO2) removal unit, technologically and commercially
mature gas-liquid absorption methods were considered [15]. Two solvents were assessed, one
5
presented evaluation of chemical vs. physical solvents used for CO 2 capture considered
several key elements: heat duty for solvent regeneration, ancillary energy consumptions of
AGR unit (heating, cooling and electricity consumptions), solvent loading and CO 2 capture
selectivity, cost elements etc. The considered configurations of AGR unit for the two solvents
are presented in Figures 2 (for MDEA-based process) and 3 (for SelexolTM-based process). As
can be noticed, for SelexolTM process, the solvent regeneration is done by pressure reduction
(several flashes) since for MDEA it is done by heating (steam has to be extracted from the
Rankine cycle with negative consequence of reducing the steam turbine output).
Regarding the hydrogen-fuelled gas turbines, three state of the art F and H-class units
from the main manufacturers (Siemens, General Electric - GE, Mitsubishi Hitachi Power
Systems - MHPS) were considered. The key elements in selecting a gas turbine for an IGCC
design with CCS are: gross and net power output (in accordance with the targeted plant
output), electrical efficiency and ability to process hydrogen-rich fuels, flexibility in varying
the load (an important aspect for hydrogen and power co-generation cases). Table 1 presents
the main design assumptions for the selected gas turbines considered in this work [16-18].
6
The Case 2 was evaluated using various F and H-class gas turbines (Case 2a: GE 9F05
gas turbine, Case 2b: MHPS 701G2 gas turbine and Case 2c: Siemens SGT5-8000H gas
turbine) as well as for flexible hydrogen and power co-generation design. All evaluated
concepts generate 400 - 600 MWe net power with a flexible hydrogen output in a range from
zero up to 300 MWth with 90% carbon capture rate. Table 2 presents the key design
assumptions of the main plant sub-systems [11,19-20]. As modelling and simulation software,
ChemCAD [21] and Thermoflex [22] were used. ChemCAD was used to simulate whole plant
concepts (both the chemical transformation units like gasification island, syngas water gas
shift, CO2 capture unit etc. and the steam generation & power block) and Thermoflex was
only used for simulation of power block and steam cycle since it provides better technical
specifications of the gas turbines. The simulation results were compared to the industrial data
of main plant units (e.g. gasification island, syngas treatment, acid gas removal, combined
For optimisation of the energy efficiency, all investigated concepts were subject of
detailed heat and power integration analysis [23]. In this respect, the pinch methodology was
followed for overall plant thermal integration analysis considering a 10oC minimum
the steam integration between various plant sub-systems (gasification unit, syngas treatment
line, acid gas removal unit and combined cycle). As an illustrative example, Figure 4 presents
the hot and cold composite curves for Case 2b (IGCC plant with Selexol-based CO2 capture
and MHPS 701G2 gas turbine): Figure 4a exhibits the composite curves for gasification
island, syngas treatment line and shift reactors and Figure 4b exhibits the composite curves
7
The mass and energy balances generated by simulation were then used to calculate the
concepts. Table 3 presents the technical performance indicators for Cases 1 to 3 considering
the same gas turbine (one MHPS 701G2) within the combined cycle. As can be noticed, the
IGCC designs with CCS (both having 90% carbon capture rate) show lower net power
efficiencies compared to the design without carbon capture (Case 1) due to the energy penalty
for CO2 capture (about 8 - 9 net efficiency percentage points). The SelexolTM design (Case 2)
has lower energy penalty for CO2 capture compared to the MDEA design (Case 3) with about
0.9 percentage points because of lower heat duty for solvent regeneration (0.22 vs. 0.7 MJ/kg
CO2). Case 3 requires higher steam extraction for solvent regeneration with negative
Power plant heat rate Capture Power plant heat rate No capture
SPECCA (1)
Specific CO2 emissions No capture Specific CO2 emissions Capture
The SPECCA values for SelexolTM (Case 2) and MDEA (Case 3) are 2.52 MJ/kg CO2
and respectively 2.88 MJ/kg CO2. One can notice the lower value for SelexolTM-based design
An important evaluated issue in this paper was dedicated to screening of various state
of the art gas turbines able to use hydrogen-rich fuels. Three top F and H-class gas turbines
were assessed using the same IGCC design with SelexolTM-based pre-combustion CO2
capture in the context of 90% carbon capture rate for all cases. Table 4 presents the technical
8
carbon capture using various gas turbines. As can be noticed, the highest net power efficiency
was obtained for Case 2c which is using a Siemens SGT5-8000H gas turbine followed by
Case 2b using a MHPS 701G2 gas turbine and then by Case 2a based on GE 9F05 gas
turbine. Considering the design specifications of the gas turbines (see Table 1), the Siemens
design (Case 2c) has an overall net power efficiency only with about 0.6 percentage points
higher than the Mitsubishi Hitachi design (Case 2b) although the efficiencies of the gas
turbines (in single cycle) differs by about 1.5 percentage points. The GE design (Case 2a) has
the lowest overall plant efficiency with about 1.5 percentage points compared to the
Mitsubishi Hitachi design (Case 2b). The overall conclusion of evaluating various F and H-
class gas turbines within the IGCC concept with CCS is that there is not much difference in
term of overall plant efficiencies among the most efficient gas turbines (see Siemens and
One promising feature of gasification plants is the ability of energy vector poly-
generation based on syngas processing. Beside electricity, the gasification plants can
produced other chemicals used as energy carriers e.g. hydrogen, substitute natural gas, liquid
fuels (methanol, Fischer-Tropsch fuel) [9,26]. This work was concentrated on flexible
hydrogen and power generation based on IGCC design [27-28]. The flexible co-generation
mode is very promising in current energy systems because the plant can change the load
according to grid demand. The operational scenario of flexible hydrogen and power co-
generation based on IGCC plant with CCS is that when hydrogen production is desired the
gas turbine is gradually turned down to displace the required hydrogen-rich stream to be then
Figure 1 presents the conceptual design of an IGCC plant with pre-combustion carbon
capture used for flexible hydrogen and power co-generation. The co-generation mode was
evaluated in the range of 0 to 300 MWth hydrogen thermal output (based on hydrogen LHV),
9
the gas turbine being gradually turned down in the range 65 – 100% from the nominal load.
combustion CO2 capture (Case 2b) was considered for flexible hydrogen and power co-
generation. The reason to select Mitsubishi Hitachi design as illustrative example lays in the
solid industrial experience of this gas turbine to process hydrogen-rich fuels [18].
Table 5 presents the variation of the key technical plant performance indicators vs. the
hydrogen thermal output (based on hydrogen lower heating value). As can be noticed, the
main performance indicators (e.g. cumulative energy efficiency, CO2 specific emissions) are
improving with increasing the hydrogen output while the ancillary energy consumption is not
changing significantly. This fact is very important and attractive for plant cycling considering
that during low electricity demand (during the night) the plant can produce mostly hydrogen
which, compared with power, can be stored to be used either for covering peak loads or for
The methodology chosen to calculate the investment costs of gasification plants with
pre-combustion CO2 capture was based on cost correlations [29-30]. The cost correlation
method is calculating the capital cost of equipment considering several designing elements:
size, materials of construction, design pressure & temperature etc. In term of equipment size,
a key mass / energy flow is to be considered as scaling parameter, for instance for the
gasification island, the coal flow is considered as scaling parameter to calculate the capital
cost. The mathematical equation to calculate the capital cost is the following:
Q M
CE CB * ( ) * f M * fT * f P (2)
QB
10
where:
fM, fT, fP - correction factors for material of construction, temperature and pressure.
Reference data used in equation (2) for estimation of capital costs for main plant sub-
systems (solid handling, gasification island, air separation unit, syngas treatment line, acid gas
removal, power block, hydrogen purification, captured CO 2 conditioning) are presented in [5].
Once the total investment cost is calculated for each investigated concept, specific capital
investment cost per kW net energy (power only of hydrogen and power co-generation) is
As common capital cost estimation assumptions for all cases, the utilities and offsite
units were considered as 25% of all main plant sub-systems. Owner's cost and contingency
were considered 20% and the costs associated with land purchase, permitting, surveying etc.
were considered 5% of the total installed cost [11,31-32]. Figures 5.a and 5.b present the
specific capital investment per kW net energy, Figure 5.a for power generation only concepts
and Figure 5.b for hydrogen and power co-generation based on Case 2b.
As can be observed from Figure 5.a, the specific capital investment costs for IGCC
power plants varied in the range between 1900 and 2665 Euro/kW net power, the lowest value
being for the concept without carbon capture (Case 1). The CCS concept with the lowest
11
specific capital investment cost is the Siemens-based design (Case 2c) with a value of about
2438 Euro/kW because of the combination of highest net power efficiency and gas turbine
power output. The rest of the CCS designs exhibits higher specific capital investment costs by
6.5% (Case 2a), 9.3% (Case 2b) and 7.3% (Case 3). When the hydrogen and power co-
generation scenario is applied, the specific capital investment cost is reducing dramatically
with the hydrogen thermal output from about 2645 Euro/kW for power only design to 1910
Euro/kW for a 300 MWth hydrogen thermal output. This evaluation emphasises once more the
For calculation of the operation & maintenance (O&M) costs, levelised cost of
electricity and hydrogen, CO2 capture costs and cash flow analysis, the main economic
assumptions presented in Table 6 were used [11]. Operational and maintenance (O&M) costs
have two main components: the fixed O&M costs which are independent of the generated
power & hydrogen which include: annual capital depreciation, direct labour cost, taxes,
insurances, administration, annual overhaul etc. and the variable O&M costs which are
proportional to the generated power & hydrogen which cover: fuel, chemicals, catalysts,
The levelised cost of electricity (LCOE) was calculated using the net present value
(NPV) method [11]. The CO2 removal and avoidance costs (important parameters when
compare various carbon capture technologies) were calculated with the following equations:
12
Table 7 presents the operation & maintenance (O&M) costs, CO2 capture costs and
levelised cost of electricity for IGCC plants operated in power only mode. As can be noticed,
for the same gasifier (Shell) and the same gas turbine (Mitsubishi Hitachi Power Systems -
SelexolTM - Case 2b or MDEA - Case 3) involves the increase of total fixed and variable costs
with about 11% (yearly basis) and with about 25% (reporting on MWh net power) compared
with design without CCS (Case 1). The cost of electricity is also increasing by about 39 - 41%
To assess the variation of electricity cost and CO2 avoided cost vs. various economic
parameters (e.g. capital cost, fuel cost, O&M cost, interest rate, availability factor etc.),
sensitivity analysis were performed. Figure 6 presents the variation of electricity cost and CO 2
avoided cost with capital cost (-/+ 10% variation range), fuel cost (-/+ 10% variation range),
operation and maintenance cost (-/+ 10% variation range), interest rate (-/+ 1% variation
range) and availability factor (+/- 5% variation range) for Case 2b (IGCC power plant with
Figure 6. Electricity cost and CO2 avoided cost sensitivity analysis for Case 2b
As can be noticed, the capital cost and the interest rate have the most pronounced
influence on the electricity cost and CO2 avoidance cost followed by the fuel cost and the
plant availability factor. The O&M cost has the minor influence on the electricity and CO 2
avoidance costs.
When evaluating various F and H-class gas turbines assessed in the same IGCC power
plant configuration (Shell gasifier with SelexolTM-based pre-combustion CO2 capture), the
best economic indicators are showed by Siemens gas turbine (Case 2c) followed by
Mitsubishi Hitachi gas turbine (Case 2b) and then General Electric gas turbine (Case 2a). For
13
instance, the cost of electricity for Case 2c is about 7% lower than for Case 2b and about 8%
lower than Case 2a. The main reasons for this situation lay in superior energy efficiency and
power output of Siemens SGT5-8000H machine compared to the other two (see Table 1 for
For hydrogen and power co-generation, the operation & maintenance (O&M) costs
were reported to the combined production energy (net power plus hydrogen thermal output
based on lower heating value). The levelised cost of electricity (LCOE) and the levelised cost
of hydrogen (LCOH) were calculated using the net present value (NPV) method on the whole
(IEAGHG) [11,27]. The allocation factors between the two energy carriers (power and
hydrogen) were calculated based on the plant energy outputs. Table 8 shows the operation &
maintenance (O&M) costs and levelised costs of electricity & hydrogen for IGCC plants
operated in co-generation mode. As can be clearly noticed from Table 8, the highest is the
hydrogen thermal output of the plant the improved economic indicators are. For instance, the
total fixed and variable costs (expressed per MWh net hydrogen and power) are reduced by
25% when hydrogen thermal output varies from 0 to 300 MWth. This finding corroborated
with the overall energy efficiency increase as well as reducing the specific capital investment
cost with the hydrogen thermal output increase underline the technical and economic benefits
when evaluating the plant economics over it’s entirely life [34-35]. In the current cash flow
analysis, 29 years was considered as project economic life divided as follow: 3 years for plant
construction (40% : 40% : 20% were considered as expenditure factors per each construction
year), 25 years for plant operation and 1 year for recovering the working capital. The cash
flow analysis was done according to the proposed International Energy Agency - Greenhouse
14
Gas Programme (IEAGHG) methodology [11]. The cumulative cash flows for the evaluated
Case 2b plant with hydrogen and power co-generation are presented in Figure 7.
Figure 7. Cumulative cash flow analysis for flexible hydrogen & power co-generation
One can noticed that the combination of flexible hydrogen and power co-generation as
well as pre-combustion CO2 capture induces an increase of the overall cumulative cash flow
of the IGCC plant compared to the design without carbon capture (considered as benchmark
case).
5. Conclusions
This paper is evaluating the key techno-economic aspects of IGCC power plant
equipped with pre-combustion CO2 capture coupled with flexible hydrogen and power co-
generation. The techno-economic evaluations were based on modelling and simulation work.
Important design options were assess in detail in view of theirs influence on the techno-
economic indicators e.g. gasification reactor, CO2 capture by chemical vs. physical gas-liquid
absorption, various F and H-class gas turbines used within the combined cycle, flexible
hydrogen and power co-generation etc. Evaluated coal-based gasification concepts generate
400 - 600 MWe net power with a flexible hydrogen output from zero up to 300 MWth with
90% carbon capture rate. An IGCC design without carbon capture was also consider as a
benchmark case to quantify the energy and cost penalties induced by CO2 capture.
applied to gasification plants for combined hydrogen & power co-generation with CCS. As
the results show, the pre-combustion CO2 capture based on physical gas-liquid absorption has
better performances than the chemical absorption (e.g. higher overall plant efficiency by
about 0.9 percentage points). The influence of various F and H-class gas turbines on the
15
overall techno-economic indicators was assessed considering the most important
manufacturers (Siemens, General Electric, Mitsubishi Hitachi Power Systems). The Siemens
design has the better techno-economic performances than other two concepts (e.g. higher net
power efficiency by about 0.6 - 2.1 percentage points, lower specific capital investment costs
by about 6.5 - 8.5, lower electricity cost by about 8% etc.) because of higher gas turbine
efficiency (41% vs. 38.2 - 39.5%) and net power output (450 MWe vs. 314 - 334 MWe).
performance improvement for flexible hydrogen & power co-generation based on gasification
plant with pre-combustion CO2 capture. As the results show, for flexible 0 to 300 MW
hydrogen thermal output, the overall (cumulative) plant energy efficiency is increasing up to
about 10.5 net percentage points, the specific capital investment cost is decreasing down to
about 28%, the total fixed and variable cost is decreasing down to about 25% and the
electricity cost is decreasing down by about 26%. As main conclusion of this paper is that the
gasification technology offers promising solutions for developing low carbon applications not
only for power generation but also for a flexible energy vector polygeneration operational
Acknowledgements
This work was supported by a grant of the Romanian National Authority for Scientific
References
[1] International Energy Agency (IEA), Energy Technology Perspective 2017 - Catalysing
16
[2] F. Johnsson, M. Odenberger, L. Göransson, Challenges to Integrate CCS into Low Carbon
[3] European Commission, A policy framework for climate and energy in the period from
[4] B. Metz, O. Davidson, H. de Coninck, M. Loos, L. Meyer, Carbon Dioxide Capture and
[5] C.C. Cormos, Techno-economic and environmental evaluations of large scale gasification-
[6] C. Higman, M. van der Burgt, Gasification, second ed., Burlington: Gulf Professional
2018).
[8] A. Pettinau, F. Ferrara, C. Amorino, Combustion vs. gasification for a demonstration CCS
(carbon capture and storage) project in Italy: A techno-economic analysis, Energy 50 (2013)
160-169.
[9] A.M. Cormos, C. Dinca, C.C. Cormos, Multi-fuel multi-product operation of IGCC power
plants with carbon capture and storage (CCS), Appl. Therm. Eng. 74 (2015) 20-27.
[10] C. Wolfersdorf, B. Meyer, The current status and future prospects for IGCC systems, In:
[11] International Energy Agency - Greenhouse Gas R&D Programme (IEAGHG), Potential
for improvement in gasification combined cycle power generation with CO 2 capture, Report
PH4/19, 2003.
[12] International Energy Agency - Greenhouse Gas R&D Programme (IEAGHG), CO2
17
[13] J. Urech, L. Tock, T. Harkin, A. Hoadley, F. Maréchal, An assessment of different
solvent-based capture technologies within an IGCC - CCS power plant, Energy 64 (2014)
268-276.
[14] C.C. Cormos, Integrated assessment of IGCC power generation technology with carbon
[15] A. Kohl, R. Nielsen, Gas purification. fifth ed., Huston: Gulf Publishing Company, 1997.
30 January 2018).
[17] GE Power, Aero derivative & heavy-duty gas turbines - GE 9F05, www.gepower.com,
[18] Mitsubishi Hitachi Power Systems, Large capacity gas turbines - MHPS 701G2,
[19] National Energy Technology Laboratory (NETL), Cost and performance baseline for
fossil energy plants. Vol. 1: Bituminous coal and natural gas to electricity, DOE/NETL-
2010/1397, 2010.
[20] C.C. Cormos, Evaluation of energy integration aspects for IGCC-based hydrogen and
electricity co-production with carbon capture and storage, Int. J. Hydrogen Energy 35 (2010)
7485-7497.
[23] G.S.K. Priya, S. Bandyopadhyay, Multi-objective pinch analysis for power system
18
[24] M. Gatti, E. Martelli, F. Marechal, S. Consonni, Review, modeling, heat integration, and
improved schemes of Rectisol®-based processes for CO2 capture, Appl. Therm. Eng. 70
(2014) 1123-1140.
cycle with SEWGS - Part A: Thermodynamic performances, Fuel 105 (2013) 206-219.
[26] H. Huang, H. Xiao, S. Yang, Carbon flow and energy flow analyses of a Lurgi coal-to-
[27] International Energy Agency - Greenhouse Gas R&D Programme (IEAGHG), Co-
production of hydrogen and electricity by coal gasification with CO 2 capture, Report 2008/9,
2008.
[28] F. Starr, E. Tzimas, S. Peteves S, Critical factors in the design, operation and economics
of coal gasification plants: the case of the flexible co-production of hydrogen and electricity,
[29] R. Smith, Chemical processes: Design and integration. second ed., West Sussex,
[30] M.S. Peters, K.S. Timmerhaus, Plant design and economics for chemical engineers. forth
[31] V. Tola, A. Pettinau, Power generation plants with carbon capture and storage: A techno-
economic comparison between coal combustion and gasification technologies, Appl. Energy
[32] C.C. Cormos, K. Vatopoulos, E. Tzimas, Assessment of the consumption of water and
19
[33] A. Śliwińska, D. Burchart-Korol, A. Smoliński, Environmental life cycle assessment of
methanol and electricity co-production system based on coal gasification technology, Sci.
[34] G. Towler, R.K. Sinnott, Chemical Engineering Design: Principles, practice and
approach for optimizing investments in process integration measures under uncertainty, Appl.
20
List of figures and tables
Figure 1. Design of IGCC plant for flexible hydrogen and power co-generation with pre-
Figure 6. Electricity cost and CO2 avoided cost sensitivity analysis for Case 2b
Figure 7. Cumulative cash flow analysis for flexible hydrogen & power co-generation
21
Table 1. Main design characteristics of evaluated gas turbines
Table 3. Overall technical performance indicators for Cases 1 to 3 using the same gas turbine
Table 4. Overall technical performance indicators for various hydrogen-fuelled gas turbines
Table 5. Overall performance indicators for hydrogen and power co-generation (Case 2b)
Table 6. Economic assumptions of IGCC plants with and without carbon capture
Table 7. Operation & maintenance (O&M) costs, CO2 capture costs and levelised cost of
Table 8. Operation & maintenance (O&M) costs and levelised costs of electricity & hydrogen
22
Air Coal + Transport gas (N2)
O2
Air Separation Unit Steam
Gasification
(ASU)
Syngas
N2 O2 quench Slag
Pressure Swing
Adsorption (PSA)
Combined Cycle
Gas Turbine (CCGT)
H2 compression
Figure 1. Design of IGCC plant for flexible hydrogen and power co-generation
23
Figure 2. Layout of acid gas removal unit based on MDEA process
24
Figure 3. Layout of acid gas removal unit based on SelexolTM process
25
Figure 4.a Gasifier island, syngas conditioning line and shift conversion
26
Figure 5.a Specific capital investment costs for IGCC plants (power only)
Figure 5.b Specific capital investment costs for IGCC plants (hydrogen & power)
27
Figure 6.a Cost of electricity (€/MWh)
Figure 6. Electricity cost and CO2 avoided cost sensitivity analysis for Case 2b
28
Figure 7. Cumulative cash flow analysis for flexible hydrogen & power co-generation
29
Table 1.
30
Table 2.
Unit Parameters
Fuel (coal) Proximate analysis (as received): 56% fixed carbon, 23%
Air Separation Unit (ASU) Oxygen purity (vol.): 95% oxygen, 2% nitrogen, 3% argon
Fuel handling and transport Power consumption for coal milling: 1 % of input coal LHV
Gasification reactor Shell gasifier (dry fed & syngas quench type)
Shift conversion: 96 – 98 %
31
Acid Gas Removal (AGR) Physical solvent: SelexolTM
CO2 quality specification >95% CO2, <2000 ppm CO, <250 ppm H2O, <100 ppm
Compressor efficiency: 85 %
MP steam reheat
32
Table 3.
Overall technical performance indicators for Cases 1 to 3 using the same gas turbine
Gas turbine power output (1 x MHPS 701G2) MWe 334.00 334.00 334.00
33
Table 4.
GE MHPS SGT5
34
Table 5.
Overall performance indicators for hydrogen and power co-generation (Case 2b)
35
Carbon capture rate % 90.00 90.00 90.00
36
Table 6.
Discount rate 8%
37
Table 7.
Operation & maintenance (O&M) costs, CO2 capture costs and levelised cost of electricity for IGCC plants (power only)
Administrative, support & overhead cost M€ / y 1.68 1.80 1.80 1.80 1.80
Total fixed O&M costs (year) M€ / y 34.77 39.65 38.94 46.53 38.38
Total fixed O&M costs (MWh net power) € / MWh 9.57 12.10 12.00 10.57 11.87
38
Waste disposal M€ / y 1.49 1.69 1.62 2.14 1.62
Total variable O&M costs (year) M€ / y 76.16 88.67 84.57 111.92 84.73
Total variable O&M costs (MWh net power) € / MWh 20.98 27.06 26.07 25.42 26.21
Total fixed and variable costs (year) M€ / y 110.93 128.32 123.51 158.45 123.11
Total fixed and variable costs (MWh net power) € / MWh 30.55 39.16 38.07 35.99 38.08
Levelised cost of electricity (LCOE) € / MWh 57.89 81.05 80.46 75.33 81.65
39
Table 8.
Operation & maintenance (O&M) costs and levelised costs of electricity & hydrogen for co-generation designs (Case 2b)
Total fixed O&M costs (MWh net energy) € / MWh 12.00 10.02 8.52
40
Chemicals M€ / y 1.83 1.58 1.50
Total variable O&M costs (MWh net energy) € / MWh 26.07 22.73 20.22
Total fixed and variable costs (MWh net energy) € / MWh 38.07 32.75 28.74
41
Research highlights
Evaluations of various gas turbine options suitable for gasification plants with CCS;
Flexible hydrogen & power co-generation based on gasification plants with CCS;
42