Chapter 4 Specifications (Final) Design - Design Data Collection
Chapter 4 Specifications (Final) Design - Design Data Collection
1. Dams
Reclamation Manual
Design Data Collection Guidelines
Chapter 4 – Specifications Designs
1. Dams. The Introduction (Chapter 1) for these design data collection guidelines contains
additional information concerning: preparing a design data collection request, design
data collection requirements, and coordinating the design data collection and submittal.
This paragraph lists data required for design of a storage dam; however, design data for a
diversion dam shall be submitted in accordance with the list so far as the items are
applicable. The Project Team and the Design Team for the dam will review the data used
for authorization and the changes that have occurred since that time, the damsite selected,
and the choice of structure type and recommend a design data collection program to the
design office and an estimated schedule.
(5) Locations of potential construction and permanent access roads, and sites
for contractor's staging areas, and construction facilities.
(6) Locations of borrow areas for natural construction materials and disposal
areas for waste excavation.
September 2007 1
Design Data Collection Guidelines
(1) The approximate distance from the nearest railroad shipping terminal to
the structure site; load restrictions and physical inadequacies of existing
roads and structures and an estimate of remedial improvements to
accommodate construction hauling; estimate of length and major
structures required for new construction access road; and possible
alternative means for delivering construction materials and equipment at
the structure site.
(5) Climatic conditions that will affect construction and operation and
maintenance procedures such as: amount, rate, and distribution of rain
and/or snow; ice conditions; summer and winter temperatures, with
extremes; extreme wind velocities and prevailing directions; and
probability of excessive dust or sand.
(6) Names and telephone numbers of local utilities and contacts within those
organizations.
C. Surface Data:
(1) Survey Control. Permanent horizontal and vertical survey control should
be established at the earliest possible time. A coordinate system on a true
north-south grid should be established with the origin located so that all of
the features (including borrow areas) at a major structure will be in one
quadrant, and so that the values of the coordinates for any major structure
are widely separated numerically. The coordinate system should be
related to a state or national coordinate system, if available. All preceding
survey work, including topography and location and ground surface
elevation of subsurface exploration, should be corrected to agree with the
permanent control system; and all subsequent survey work, including
location and ground surface elevation of subsurface exploration, should be
based on the permanent control. All surveys should be tied to the
established coordinate system at each construction site.
2 September 2007
Chapter 4 – Specifications Designs
1. Dams
These photographs should be taken from locations that would best show
the proposed structure and from a vertical angle of approximately 20E to
30E above the horizontal. Where possible, indicate known tie points to the
topographic maps. These photographs should be taken between 11 a.m.
and 2 p.m., so as not to show the principal area of the proposed structure
in shadow. Also submit the negatives or color slides.
D. Foundation Data:
September 2007 3
Design Data Collection Guidelines
must be based on site conditions and the type of structure. The complexity
of the site will determine the detail of the investigation.
(2) Geologic Data. The following list of geologic design data provides
general guidelines for the collection and reporting of geologic information
for this type of facility. The geologist should apply these guidelines with
good judgment and sound reasoning, elaborating upon them as required by
the particular geologic setting and engineering requirements. Because the
collection of geologic data is a dynamic process and often continues into
the preparation of final designs, all stages of the specification design
geologic exploration program must be constantly coordinated with the
designer through the appropriate geology office. The regional or
Technical Service Center (TSC) geologic and geophysical staff will
provide necessary assistance and guidance in the gathering of these design
data.
(b) Surface geologic map of dam and entire reservoir area showing
location of explorations. Locations of all existing explorations
should be indicated by coordinates or stationing of the permanent
survey control system for the facility. Include evaluation of water-
holding capability of reservoir.
4 September 2007
Chapter 4 – Specifications Designs
1. Dams
(m) Document past, present, and possible future petroleum, water, and
mineral extraction operations in vicinity.
E. Corrosion Survey:
September 2007 5
Design Data Collection Guidelines
(3) List of structures in the vicinity of (within 1/4 mile) the proposed structure
and appurtenant features. Determine if buried structures in the vicinity
have corrosion protection and, if so, the type of corrosion protection.
(4) List location, output, and purpose of the direct-current sources in the earth
situated within 1/4 mile of the proposed structure and appurtenant
features. If the purpose of the direct current is for cathodic protection,
describe the structure protected and its location.
(6) Report alkali conditions in soil and water which might affect the choice of
sulfate resisting cement.
(7) Statement of availability of timber for structural work and lumber for
other purposes.
6 September 2007
Chapter 4 – Specifications Designs
1. Dams
G. Water for Construction Purposes. For large rivers, this item may be
unimportant. For small streams and offstream reservoirs, the item becomes
critical. Determine if up to 2-cubic-foot-per-second (ft3/s) diversion flow for
construction purposes can be assured to the contractor. The Government should
obtain the water rights required. If necessary to use ground water, obtain
information on probable sources and yields. Furnish information on locations and
yields of existing wells in the vicinity. Determine restrictions, if any, to use of
ground water for this purpose. It may be necessary to obtain permits from State
or other governing agencies. Retrieve water quality samples for testing and
evaluation.
H. Hydrologic Data. The hydrologic data for a dam will be documented in a report
for the feasibility designs and will have been updated based on any additional
information developed since the feasibility designs. The specifications design
data submittal shall reference this document and thus eliminate the need to repeat
the information enumerated below. If, for any reason, the information
enumerated below is not contained or is not updated in the report prepared for the
feasibility design then this information should be provided for the specifications
design.
(1) Inflow design flood and possible preceding and recurring flood
hydrographs with recommended routing criteria. For a diversion dam
involving little or no storage, normally a probability curve of flood peak
discharges up to the 100-year point will be sufficient. However, if the
structure is judged to pose a significant threat to a downstream population,
the design flow may be based on a longer recurrence interval.
(2) Flood hydrographs for frequencies of 5, 10, and 25 years for use in
diversion during construction. Requirements for maintaining streamflow
or diversions during construction and maximum length, time, and number
of permitted interruptions.
(4) Method of reservoir operation for flood control and maximum permissible
releases.
I. Reservoir Data:
(1) Area capacity curves and/or tables to at least the dam crest elevation.
September 2007 7
Design Data Collection Guidelines
(2) Topography for small reservoirs, on a scale of 1 inch equals 400 feet and a
contour interval of 5 feet; for large reservoirs, on a scale of 1 inch equals
2,000 feet and a contour interval of 10 feet.
(5) Anticipated occurrence and amounts of sediment, ice (thickness), and drift
(trash), and possible effect on reservoir outlets, spillway, and other
appurtenances.
J. Operating Data:
(6) Required outlet and sluiceway capacities for respective reservoir water
surfaces; and sill elevations. Give type and purpose of reservoir releases
and the time of year to be made; include minimum release during winter.
If temperature or water quality control of releases is anticipated, the
degree and purpose of the control should be included.
(7) Type of operation, i.e., full-time resident caretaker, remote control, etc.
(8) The operational impacts of the project that require alternative designs, e.g.,
outlet works and downstream river temperature, spillways and gas
supersaturation, increased channel scour, and downstream channel
protection, etc.
8 September 2007
Chapter 4 – Specifications Designs
1. Dams
K. Miscellaneous Data:
(13) Anticipated recreation facilities that will affect the dam design and/or
should be included in original design.
(14) (For concrete storage dams), daily readings of maximum, minimum, and
mean temperatures of air and river water. Until a weather station is
September 2007 9
Design Data Collection Guidelines
(17) Unusual local pest (termites, borers, etc.) action and recommended
preventive measures.
(19) Provide data on the method(s) of brush and tree disposal permitted by
local and State pollution regulatory agencies.
(21) Description of existing project fire protection and security plans which
will be applied to this feature, together with any specific requirements for
this dam.
L. Cost Data:
(3) Estimates of cost for clearing reservoir area and for removing or replacing
private improvements in the area. Include supporting data.
(4) Estimates of cost for relocating railroads, highways, roads, water systems,
and other public utilities from the damsite or reservoir area. Include
supporting data. Where buildings are located within the area to be cleared
by the prime contractor, and if disposal will be his responsibility,
designate building groups by number and furnish detailed list of buildings
10 September 2007
Chapter 4 – Specifications Designs
1. Dams
for each group. Details should include general description, size, materials,
and general condition. Determine if disposal will be the responsibility of
prime contractor. If not, submit dates when disposition will be completed
by others.
September 2007 11
Design Data Collection Guidelines
(4) Indicate the suitability and possibility of present and future use of land
adjacent to Reclamation facilities by the public for recreation, hobbies,
sports, leisure, education, health, housing, etc. Provide data on zoning
regulations and subdivision proposals.
(5) Furnish data on allowable noise limits in the vicinity of the proposed plant
where fixed by law or local ordinance, or where otherwise considered
necessary or advisable; measurements of existing daytime or nighttime
ambient noise levels in the area; and distances to the nearest residential
units.
(8) Background on the need for fish facilities such as screens, fishways, and
barriers.
(10) Give borrow area and temporary haul road restoration requirements such
as stockpiling of top soil, regrading of the area, general cleanup, etc.
(13) The need for a field conference to resolve critical environmental problems
with participation of other agencies.
(14) Review of designs by other agencies including at what stage of design and
level of their review, and the findings of the Fish and Wildlife
Coordination Act Report.
12 September 2007
Chapter 4 – Specifications Designs
1. Dams
(17) Environmental permit requirements (401, 404, Storm Water Runoff, etc.)
(20) Location of any underground storage tanks within the reservoir basin.
O. Electrical Data. Data listed below will be required to initiate design. The data
furnished should be sufficient to permit designers to complete the basic design
(single-line diagram) for the dam. After designs have progressed enough to
develop details of electrical system needs, designers will prepare a list of
additional data required to complete final design of electrical installation.
(1) Names and telephone numbers of electrical power suppliers and contacts
within those organizations.
(3) System voltage at which power will be supplied, number of phases, and
whether service will be overhead or underground.
(8) Requirements for voice and data communications between the supervisory
master station and the remote facility.
September 2007 13
Design Data Collection Guidelines
14 September 2007
Chapter 4 – Specifications Designs
2. Powerplants and Pumping Plants
2. Powerplants and Pumping Plants. The Introduction (Chapter 1) for these design data
collection guidelines contains additional information concerning: preparing a design data
collection request, design data collection requirements, and coordinating the design data
collection and submittal. The following is a list of possible data required for design of
powerplants and pumping plants and additions, modifications, or rehabilitations to
existing powerplant and pumping plants. The size and complexity of the structure should
govern the amount and detail of the design data required. Where both pumping and
generating functions are to be provided in the same plant, furnish design data for both.
For existing non- Reclamation powerplants and pumping plants (i.e., Bureau of Indian
Affairs), single-line diagrams and switching diagrams which include equipment ratings
will be necessary for a proper evaluation of existing equipment within the scope of any
proposed changes.
(1) A key map locating the general map area within the State.
(4) Existing towns, highways, roads, railroads and shipping points, public
utilities such as electric power and telephone lines, pipelines, etc., and
stream-gauging stations.
(5) Locations of potential construction and permanent access roads, and sites
for contractor's staging areas and construction facilities.
(6) Locations of borrow areas for natural construction materials and disposal
areas for waste excavation.
September 2007 15
Design Data Collection Guidelines
(1) The approximate distance from the nearest railroad shipping terminal to
the structure site; load restrictions and physical inadequacies of existing
roads and structures and an estimate of remedial improvements to
accommodate construction hauling; estimate of length and major
structures required for new construction access road; and possible
alternative means for delivering construction materials and equipment at
the structure site.
(4) Climatic conditions that will affect design or construction and operation
and maintenance procedures such as: amount, rate, and distribution of rain
and/or snow; ice conditions; summer and winter temperatures, with
extremes; extreme wind velocities and prevailing directions; and
probability of excessive dust or sand.
(5) Names and telephone numbers of local utilities and contacts within those
organizations.
C. Surface Data:
(1) Survey Control. Permanent horizontal and vertical survey control should
be established at the earliest possible time. A coordinate system on a true
north-south grid should be established with the origin located so that all of
the features (including borrow areas) at a major structure will be in one
quadrant, and so that the values of the coordinates for any major structure
are widely separated numerically. The coordinate system should be
related to a State or national coordinate system, if available. All preceding
survey work, including topography and location and ground surface
elevation of subsurface exploration, should be corrected to agree with the
permanent control system; and all subsequent survey work, including
location and ground surface elevation of subsurface exploration, should be
based on the permanent control. All line surveys should be tied to the
established coordinate system at each plant site.
16 September 2007
Chapter 4 – Specifications Designs
2. Powerplants and Pumping Plants
scale of 1 inch equals 50 feet (a scale of 1 inch equals 100 feet is permitted
for large area sites) and a contour interval appropriate for the relief in the
project area (1 to 2 feet for flatter areas and 5 feet in areas where relief is
significant). For flat or gently sloping topography contour intervals as low
as 1 foot may be desirable. Show the coordinate system and existing land
survey corner monuments or special control points established for the
topographic survey. Show all manmade features in the included area.
These photographs should be taken from locations that would best show
the proposed structure and from an oblique angle of approximately 20° to
30° above the horizontal. Where possible, indicate known tie points to the
topographic maps. These photographs should be taken between 11 a.m.
and 2 p.m., so as not to show the principal area of the proposed structure
in shadow. Submit the negatives or color slides.
September 2007 17
Design Data Collection Guidelines
(a) Surficial soils (see Earth Manual, latest edition). Note geologic
sections and soil profiles in (1)(e) above.
18 September 2007
Chapter 4 – Specifications Designs
2. Powerplants and Pumping Plants
E. Corrosion Survey:
September 2007 19
Design Data Collection Guidelines
(3) List of structures in the vicinity of (within ¼ mile) the proposed structure
and appurtenant features. Determine if buried structures in the vicinity
have corrosion protection and, if so, the type of corrosion protection.
(4) List location, output, and purpose of the direct-current sources in the earth
situated within ¼-mile of the proposed structure and appurtenant features.
If the purpose of the direct current is for cathodic protection, describe the
structure protected and its location.
(1) Location of and distance to suitable borrow areas for permeable and
impermeable soil materials for fill or embankment; and for riprap for
channel or slope protection. If quantities are limited, give approximate
volumes available.
(4) Data on commercial concrete plants within practical hauling distance from
the structure site.
G. Hydrologic Data:
20 September 2007
Chapter 4 – Specifications Designs
2. Powerplants and Pumping Plants
Type and purpose of reservoir releases for the time of year to be made;
include minimum releases for various seasons.
(5) Source of pumping plant water supply other than reservoir: maximum
operating, and minimum operating water surface elevations; floodflows;
average flow; and anticipated occurrence and amounts of sediment and ice
(thickness). Recommend minimum trashrack or gate deck elevation.
Include data on possibility of flooding due to ice jams.
(6) Referring to subparagraphs (3) and (5) above, the water surface elevations
should be determined for floods of 100-, 50-, and 10-year frequencies.
(7) Analysis of water for chemical and physical characteristics and biological
quality. Analysis should include a water quality analysis of intake water
to include major ions and cations, corrosivity and parameters listed as
maximum contaminant limits in the Surface Water Treatment Rule, Safe
Drinking Water Act. See table 1 in the “Water Treatment Plant” section.
(1) Static head and head duration and flow duration curves to be developed
(maximum, minimum, weighted average, and rated).
September 2007 21
Design Data Collection Guidelines
(7) Local load requirements; and availability and capacity of reliable outside
sources for alternate supply of station-service power.
(10) Need for operation when isolated from power system, and including need
for black-start capability.
(a) Voltage.
(13) Need for bypass of water during generator shutdown or load rejection.
* There is no arbitrary rating limit for small hydroplants. However, ANSI C50.12
implies that small hydromachines are those below 5,000 kilovoltampere.
22 September 2007
Chapter 4 – Specifications Designs
2. Powerplants and Pumping Plants
(1) Types and quantities of trash (including terrestrial and aquatic weeds,
algae, etc.) anticipated at the plant intake; locations of trash-disposal areas.
Recommend methods of trash handling and disposal.
(2) Water use (municipal and industrial [M&I], irrigation) and distribution
requirements: necessity for treating water and recommended method;
consumption quantities by months, and locations; initial and ultimate
capacities; capacity-duration curves; location of distribution and treating
facilities; and special plant availability or reliability requirements. Discuss
maximum static head at which maximum capacity is required, or
minimum capacity which will suffice at maximum head.
(3) Profile, alignment, and outlet conditions and requirements for discharge
lines; recommended types of pipe and types of coatings and linings.
(4) Location, capacity, hydraulic section, and water surface elevation of intake
and discharge channels.
(6) Electrical data. Data listed below will be required to initiate design. The
data furnished should be sufficient to permit designers to complete the
basic design (single-line diagram) for the pumping plant. After designs
have progressed enough to develop details of electrical system needs,
designers will prepare a list of additional data required to complete final
design of electrical installation.
September 2007 23
Design Data Collection Guidelines
(9) Interest rate, pumping power rate, and plant factor for economic studies.
J. Miscellaneous Data:
(6) Housed and open operation and maintenance (O&M) storage requirements
at site; offsite storage provided; existing storage space and facilities.
24 September 2007
Chapter 4 – Specifications Designs
2. Powerplants and Pumping Plants
(12) State potable water standards, water quality report, and water treatment
requirements.
(14) Need for attended operation of plant during and following a nuclear attack.
(16) Recommendations for special protection of roof or yard from falling rocks
or boulders.
September 2007 25
Design Data Collection Guidelines
(20) Water for construction purposes. For large rivers, this item may be
unimportant. For small streams and offstream reservoirs, the item
becomes critical. Determine if up to 2-ft3/s, diversion flow for
construction purposes can be assured to the contractor. The Government
should obtain the water rights required. If necessary to use ground water,
obtain information on probable sources and yields. Furnish information
on locations and yields of existing wells in the vicinity. Determine restric
tions, if any, to use of ground water for this purpose. It may be necessary
to obtain permits from State or other governing agencies.
(24) Where a service area or machine shop is specified in a plant, furnish floor
area requirements and the name and size of machine tools, benches
required, and need for welding booths or rooms.
K. Cost Data:
(1) Where buildings are located within the area to be cleared by the prime
contractor, and if disposal will be his responsibility, designate building
groups by number and furnish detailed list of buildings for each group.
Details should include general description, size, materials, and general
conditions. Determine if disposal will be the responsibility of prime
contractor. If not, submit dates when disposition will be completed by
others.
26 September 2007
Chapter 4 – Specifications Designs
2. Powerplants and Pumping Plants
(5) Estimates of cost for relocating railroads, highways, roads, water systems,
and other public utilities. Include supporting data.
(2) The need for blending structures with the surroundings, including placing
transmission circuits under ground.
(5) Indicate the suitability and possibility of present or future use of land
adjacent to Reclamation facilities by the public for recreation, hobbies,
sports, leisure, education, health, housing, etc. Provide data on zoning
regulations and subdivision proposals.
(6) Furnish data on allowable noise limits in the vicinity of the proposed plant
where fixed by law or local ordinance, or where otherwise considered
necessary or advisable; measurements of existing daytime and nighttime
ambient noise levels in the area; and distances to the nearest residential
units.
September 2007 27
Design Data Collection Guidelines
(10) Background on the need for fish facilities such as screens, fishways, and
barriers.
(13) Furnish data on State or local restrictions on the use of soil herbicides, or
local factors limiting their use.
M. Plant Uprating:
(1) Design data should include that listed under this section for feasibility
designs, plus target date(s) for completing the uprate work and the outage
periods when the unit(s) may be removed from service. In addition, the
TSC should be asked for a specific list of design data required.
(1) The office responsible for design should be asked for a specific list of
design data required.
28 September 2007
Chapter 4 – Specifications Designs
2. Powerplants and Pumping Plants
(4) Requirements for emergency engine generator set for the plant/building.
Systems to be connected to the standby emergency engine generator set.
(5) Anticipated engine generator usage for sizing the fuel storage tank.
(6) Preferred fuel (diesel/propane/natural gas) for the engine generator set.
(8) Types of water supplies available at the site for plant/building fire
suppression and other water usage requirements.
(9) Preferences concerning the method of joining the piping components for
the various plant/building auxiliary mechanical systems. Are victaulic
type grooved coupling connections acceptable?
(10) Types of hazardous materials on the existing piping systems (i.e., lead
based paint, asbestos).
September 2007 29
Design Data Collection Guidelines
3. Visitors Centers. The Introduction (Chapter 1) for these design data collection
guidelines contains additional information concerning: preparing a design data collection
request, design data collection requirements, and coordinating the design data collection
and submittal. Much design data prepared for previously designed features may be
available and should be utilized for the design of the visitor center. Communication
between visitor center designers and project personnel is essential in arriving at adequate
design data.
A. Design Narrative:
(a) Accessibility.
(d) Visitor use of similar facilities within project area, river basin, or
Region.
B. Overall Planning:
(1) Relationship between the visitor center and planned recreation facilities.
(4) Community or other use of portions of the building during hours when it is
not open for public visitation.
30 September 2007
Chapter 4 – Specifications Designs
3. Visitors Centers
(9) Description of existing project fire protection and security plans which
will be applied to this feature, along with any specific requirements for
this visitor center.
(10) Special heating, ventilation, and air conditioning requirements for artifact
storage and preservation, and laboratory ventilation and exhaust.
(a) A key map locating the general map area within the State.
September 2007 31
Design Data Collection Guidelines
(3) Climatic and Physical Site Conditions. Include items that will affect
design, construction, and operation and maintenance such as: amount, rate,
and distribution of rain, snow, and hail; heating and air-conditioning
design temperatures; maximum wind velocities and their directions;
probability of excessive dust or sand; local frost depths; ground water
presence and depths; vegetation to be cleared or preserved including
kinds, sizes, and density of growth. Show exact locations of existing
utilities and/or other facilities on site which must be removed, avoided, or
where special criteria is provided for interference and restoration.
E. Foundation Data:
(2) Geological Data. The following list of geologic design data provides
general guidelines for the collection and reporting of geologic information
for this type of facility. The TSC geologic and geophysical staff will
provide necessary assistance and guidance in the gathering of these design
data.
32 September 2007
Chapter 4 – Specifications Designs
3. Visitors Centers
(l) Document past, present, and possible future petroleum water, and
mineral extraction operations in vicinity.
September 2007 33
Design Data Collection Guidelines
F. Corrosion Survey:
(3) List of structures in the vicinity of (within ¼ mile) the proposed structure
and appurtenant features. Determine if buried structures in the vicinity
have corrosion protection and, if so, the type of corrosion protection.
(4) List location, output, and purpose of the direct-current sources in the earth
situated within ¼ mile of the proposed structure and appurtenant features.
If the purpose of the direct current is for cathodic protection, describe the
structure protected and its location.
(6) Report alkali conditions in soil and water which might affect the choice of
sulfate resisting cement.
(7) Statement of availability of timber for structural work and lumber for
other purposes.
34 September 2007
Chapter 4 – Specifications Designs
3. Visitors Centers
(2) The need for blending the structure with surroundings. Include reasoning
for this suggested handling.
(4) A brief listing of the area's native and/or commonly used plant materials.
I. Electrical Data. Data listed below will be required to initiate design. The data
furnished should be sufficient to permit designers to complete the basic design
(single-line diagram) for the visitors’ center. After designs have progressed
enough to develop details of electrical system needs, designers will prepare a list
of additional data required to complete final design of electrical installation.
(1) Names and telephone numbers of electrical power suppliers and contacts
within those organizations.
(3) System voltage at which power will be supplied, number of phases, and
whether service will be overhead or underground.
September 2007 35
Design Data Collection Guidelines
J. Miscellaneous Data:
(4) Requirements for emergency engine generator set for the plant/building.
Systems to be connected to the standby emergency engine generator set.
(5) Anticipated engine generator usage for sizing the fuel storage tank.
(6) Preferred fuel (diesel/propane/natural gas) for the engine generator set.
(8) Types of water supplies available at the site for plant/building fire
suppression and other water usage requirements.
(9) Preferences concerning the method of joining the piping components for
the various plant/building auxiliary mechanical systems. Are victaulic
type grooved coupling connections acceptable?
(10) Types of hazardous materials on the existing piping systems (i.e., lead
based paint, asbestos).
36 September 2007
Chapter 4 – Specifications Designs
3. Visitors Centers
September 2007 37
Design Data Collection Guidelines
4. Tunnels. The Introduction (Chapter 1) for these design data collection guidelines
contains additional information concerning: preparing a design data collection request,
design data collection requirements, and coordinating the design data collection and
submittal.
A. General Map(s). The General Map should cover the project area and the area
immediately surrounding the project within approximately 2 or 3 miles. The scale
of the General Map should be adequate to clearly show listed details. A scale of
approximately 1 to 3 miles per inch is commonly used. The following data are
shown on a General Map for feasibility and specifications level design data
collection:
(1) A key map locating the general map within the State.
(b) Recreation areas; fish and wildlife areas; building areas; highways,
railroads, and shipping points; housing; areas of cultural
sensitivity; areas of archeological, historical, and mining or
paleontological interest; and bridges with special loads or size
limitations.
(5) Rights-of-way:
38 September 2007
Chapter 4 – Specifications Designs
4. Tunnels
B. Location Map (may be combined with General Map). Location maps are
commonly used as a condensed method of showing location and alignment of the
features and associated structures. The location map may be combined with the
general map, site plan, or plan and profile drawings for small areas. A scale of
1 inch = 1,000 feet to 1 inch = 2,000 feet is commonly used for location maps.
The location map should show:
(1) General:
September 2007 39
Design Data Collection Guidelines
(k) Where the scale does not permit proper detail of a congested area,
a blowup at a larger scale may be included elsewhere on the
drawing and referenced to its proper location.
(m) Linear feature (tunnel), together with structures, adits, and stations.
Structures and delivery locations are normally shown by symbol.
(1) Information relating to access for possible site visit by the design team,
access for foundation exploration and construction, and access limitations
due to environmental restrictions, etc.
(2) Access to the site for operation and maintenance (O&M) forces.
40 September 2007
Chapter 4 – Specifications Designs
4. Tunnels
(5) The approximate distance from the nearest railroad shipping terminal to
the structure site; load restrictions and physical inadequacies of existing
roads and structures and an estimate of remedial improvements to
accommodate construction hauling; estimate of access road length and
major structures required for new construction; and possible alternative
means for delivering construction materials and equipment to the structure
site.
(7) Climatic conditions that will affect design, construction, and O&M such
as amount, rate, and distribution of rain, snow, and hail; ice conditions;
heating and air-conditioning design temperatures; summer and winter
temperatures with extremes; maximum wind velocities and their
directions; probability of excessive dust or sand.
D. Surface Data:
(1) Survey Control. Permanent horizontal and vertical survey control should
be established at the earliest possible time. All line surveys should be tied
to the state plane coordinate system at each portal, and at points of
intersection where changes in the bearing of the tunnel centerline occur.
Grid to ground correction factors including altitude and coordinate system
correction should be furnished.
September 2007 41
Design Data Collection Guidelines
These photographs should be taken from locations that would best show
the proposed structure and from a vertical angle of approximately 20E to
30E above the horizontal. Where possible, indicate known tie points to the
topographic maps, tunnel portal site, and tunnel alignment. These
photographs should be taken between 11 a.m. and 2 p.m., so as not to
show the principal area of the proposed structure in shadow. Submit the
negatives or color slides.
42 September 2007
Chapter 4 – Specifications Designs
4. Tunnels
(2) Geologic Data. The following list of geologic design data provides
general guidelines for the collection and reporting of geologic information
for tunnels. The geologist should apply these guidelines with good
judgment and sound reasoning, elaborating upon them as required by the
particular geologic setting and engineering requirements. Because the
collection of geologic data is a dynamic process and often continues into
the preparation of final designs, all stages of the specification design
geologic exploration program must be constantly coordinated with the
designer through the appropriate geology office. The TSC geologic and
geophysical staff will provide necessary assistance and guidance in the
gathering of these design data.
September 2007 43
Design Data Collection Guidelines
(h) For pressure tunnel design, measure the in situ state of stress of the
rock. Discuss the creep of rock. Determine the permeability of the
rock in place. Discuss the relationship of jointing to deformation
modules.
(o) Document past, present, and possible future petroleum, water, and
mineral extraction operations in vicinity.
44 September 2007
Chapter 4 – Specifications Designs
4. Tunnels
F. Corrosion Survey.
(3) List of structures in the vicinity of (within ¼ mile) the proposed structure
and appurtenant features. Determine if buried structures in the vicinity
have corrosion protection and, if so, the type of corrosion protection.
(4) List location, output, and purpose of the direct-current sources in the earth
situated within 1/4 mile of the proposed structure and appurtenant
features. If the purpose of the direct current is for cathodic protection,
describe the structure protected and its location.
(1) Location of and distance of suitable borrow areas for permeable and
impermeable soil materials for fill or embankment; and for riprap for
channel or slope protection. If quantities are limited, give approximate
volumes available.
(4) Data on commercial concrete and cement plants within practical hauling
distance from the structure site.
September 2007 45
Design Data Collection Guidelines
H. Hydrologic Data:
(2) Anticipated occurrence and amounts of silt, ice (thickness), and drift
(trash), and possible effect on tunnel intakes or tunnel flow.
(5) Type and purpose of reservoir releases for the time of year to be made,
include minimum releases for various seasons, where relevant.
46 September 2007
Chapter 4 – Specifications Designs
4. Tunnels
(10) Analysis of water for chemical and physical characteristics and biological
quality.
I. Operating Data:
(3) Location, hydraulic section, and hydraulic grade line at inlet and outlet
channels, pipelines, or reservoirs.
(5) Flow controls and measurement required, including smallest and largest
flows to be controlled and/or measured; degree of automation of controls
(give estimated distance to point of central control).
(7) Water use (M&I. irrigation) and distribution requirements: necessity for
treating water and recommended method; consumption quantities by
months, and locations; initial and ultimate capacities; capacity-duration
curves; location of distribution and treating facilities; and special
reliability requirements. Discuss minimum upstream head at which
maximum capacity is required, minimum delivery capacity required for
both maximum and minimum upstream heads and degree of control and
accuracy of measurement required for these limiting conditions.
J. Miscellaneous Data:
(1) Permits required for railway and/or road crossings including any local
permits required, such as local Air Quality Permits.
September 2007 47
Design Data Collection Guidelines
(6) Housed and open O&M storage requirements at site; offsite storage to be
provided; existing storage space and facilities.
(8) Expected visitor load at site and special requirements for transport of
Government personnel in and out of tunnel.
(10) State potable water standards and water treatment requirements. These
requirements should be cleared with water quality agencies in the State
where tunnel is to be constructed.
(11) State requirements for waste water treatment and disposal, and
recommendations as to possible alternatives on prevention, control, and
abatement of air and water pollution. List any restrictions imposed on
construction activity by EPA waste water discharge permit.
48 September 2007
Chapter 4 – Specifications Designs
4. Tunnels
(15) Vegetation to be cleared (kinds, size, and density of growth) and clearing
methods not permitted, e.g. burning or disposing on site.
(22) Environmental Permit requirements (401, 404, Storm Water Runoff, etc.)
(23) Requirements for providing permanent access to the tunnel or adit portal
for operation and maintenance purposes.
K. Cost Data for Field Cost Estimate. The field cost estimate is an estimate of the
capital costs of a feature or project from award to construction; non-contract costs
are not included. Cost data developed in previous or other studies (either by
Reclamation or others) should be included with the design data submittal. Include
a description or outline of estimating methods and data used. The following
design data for feasibility and specifications levels designs should be considered
for submittal:
September 2007 49
Design Data Collection Guidelines
which will be set aside under socio-economic programs that may limit
competition or allow award to other than the lowest bid or proposal.
(2) Estimate of cost of ROW for all features including reservoirs, dams, and
appurtenant works.
(7) Power rate in mills per kilowatt-hour, interest rate, and plant factor for
economic tunnel, and pipeline sizing studies in cases where transported
water is pumped.
(8) Estimated cost for construction items which cannot readily be determined
in the design office and include the supporting data:
(9) Where buildings are located within the area to be cleared by the prime
contractor, and if disposal will be the contractor’s responsibility, designate
building groups by number and furnish detailed list of buildings for each
group. Details should include general description, size, materials, and
general condition. Drawings should be provided of these buildings, if
available, that depict dimensions, construction materials, the structural
50 September 2007
Chapter 4 – Specifications Designs
4. Tunnels
system for the building, and major electrical and mechanical equipment.
Determine if disposal will be the responsibility of the prime contractor. If
not, submit dates when disposal will be completed by others.
(4) Indicate the suitability and possibility of present or future use of land
adjacent to Bureau facilities by the public for recreation, hobbies, sports,
leisure, education, health, housing, etc. Provide data on zoning
regulations and subdivision proposals.
(5) Furnish data on allowable noise limits and blasting in the vicinity of the
proposed facilities where fixed by law or local ordinance, or where
September 2007 51
Design Data Collection Guidelines
(8) Background on the need for fish facilities such as screens, fishways, and
barriers.
(12) Furnish data on State or local restrictions on the use of soil herbicides, or
local factors limiting their use.
M. Electrical Data. Data listed below will be required to initiate design. The data
furnished should be sufficient to permit designers to complete the basic design
(single-line diagram) for the tunnel. After designs have progressed enough to
develop details of electrical system needs, designers will prepare a list of
additional data required to complete final design of electrical installation.
(1) Names and telephone numbers of electrical power suppliers and contacts
within their organizations.
(3) System voltage at which power will be supplied, number of phases, and
whether service will be overhead or underground.
52 September 2007
Chapter 4 – Specifications Designs
4. Tunnels
(c) If a threat to life or property will result if normal power supply is lost.
(7) Requirements for voice and data communications between the supervisory
master station and the remote facilities.
(4) Filling and draining criteria for dam, ponds, and pipelines
September 2007 53
Design Data Collection Guidelines
(7) Water for construction purposes. For large rivers, this item may be
unimportant. For small streams and offstream reservoirs, the item
becomes critical. Determine if up to 2 ft3/s of diversion flow for
construction purposes can be assured to the contractor. The Government
should obtain the water rights required. If it is necessary to use ground
water, obtain information on probable sources and yields. Furnish
information on locations and yields of existing wells in the vicinity.
Determine restrictions, if any, to use of ground water for this purpose. It
may be necessary to obtain permits from State or other governing
agencies. Retrieve water quality samples for testing and evaluation.
(13) Give borrow area and temporary haul road restoration requirements such
as stockpiling of topsoil, grading of the area, general cleanup, etc.
54 September 2007
Chapter 4 – Specifications Designs
5. Canals
5. Canals. The Introduction (Chapter 1) for these design data collection guidelines contains
additional information concerning: preparing a design data collection request, design
data collection requirements, and coordinating the design data collection and submittal.
A. General Map(s). The General Map should cover the project area and the area
immediately surrounding the project within approximately 2 or 3 miles. The scale
of the General Map should be adequate to clearly show listed details. A scale of
approximately 1 to 3 miles per inch is commonly used. The following data are
shown on a General Map for feasibility and specifications level design data
collection:
(1) A key map locating the general map within the State.
(b) Recreation areas; fish and wildlife areas; building areas; highways,
railroads, and shipping points; housing; areas of cultural
sensitivity; areas of archeological, historical, and mining or
paleontological interest; and bridges with special loads or size
limitations.
(5) Rights-of-way:
September 2007 55
Design Data Collection Guidelines
(1) General:
56 September 2007
Chapter 4 – Specifications Designs
5. Canals
(k) Where the scale does not permit proper detail of a congested area,
a blowup at a larger scale may be included elsewhere on the
drawing and referenced to its proper location. Where density of
the structures or other features is such that individual stationing
and naming is impractical, the information should be shown in
tabular form and station marks shown on the alignment.
(1) Information relating to access for possible site visit by the design team,
access for foundation exploration and construction, and access limitations
due to environmental restrictions, etc.
(2) Access to the site for operation and maintenance (O&M) forces.
(5) The approximate distance from the nearest railroad shipping terminal to
the structure site; load restrictions and physical inadequacies of existing
roads and structures and an estimate of remedial improvements to
accommodate construction hauling; estimate of access road length and
major structures required for new construction; and possible alternative
means for delivering construction materials and equipment to the structure
site.
September 2007 57
Design Data Collection Guidelines
(7) Climatic conditions that will affect design, construction, and O&M such
as amount, rate, and distribution of rain, snow, and hail; ice conditions;
heating and air-conditioning design temperatures; summer and winter
temperatures with extremes; maximum wind velocities and their
directions; probability of excessive dust or sand.
E. Topographic Maps.
(1) Strip Topography. Strip topography covering the proposed canal location
should generally be provided. The desired scale is 1 inch equals 200 feet
with a 2-foot contour interval and a minimum strip width of 200 feet. The
strip topography should be provided on plan and profile drawings. If the
project area is flat or small, a 1-foot contour interval may be required.
(2) Topographic maps at structure sites are required only where major or
complicated structures are planned, unusual conditions exist, or judgment
dictates that more information will be required for review or design.
These site maps normally will be on a scale of 1 inch equals 20 feet to
50 feet and a contour interval of 1 foot (scale should be enlarged and/or
contour interval decreased to 1 foot when necessary to clarify conditions
58 September 2007
Chapter 4 – Specifications Designs
5. Canals
(3) Topographic maps should be furnished covering all the project area
showing ownerships, gross acreage, and irrigable acreage for each owner
ship, proposed delivery location and type, and delivery water surface
elevation. The acreage information, delivery type, and delivery water
surface elevation may be omitted from the maps if the information is
submitted separately in tabular form.
(4) Where the source of the water is a canal, reservoir, or pipeline with
turnout or headworks located outside the distribution system area
boundary, topographic maps of the same scale and contour interval
provided for above, should be submitted covering all the areas in which
the connecting feeder main is to be located. The water surface elevation
range in the source canal or reservoir or hydraulic gradient range in the
source pipeline should be shown. Also, where appropriate, data such as
capacities, grades, etc., should be shown.
F. Plan and Profile Drawings. Plan and profile drawings are normally requested
for linear features such as roads, canals, and pipelines. Drawings are prepared so
that both plan and profile are plotted on one sheet. Strip topography may be used
for the plan view. The plan view may not be required if shown on other drawings.
These drawings are normally prepared with a 1 inch = 10 feet vertical scale and
the horizontal scales of 1 inch = 200 feet unless more or less detail is required.
The scale should be adjusted, as required, if it is necessary to show details. Plan
and profile drawings should show features such as:
(1) General:
(d) Ties and stationing for turnouts, sublaterals and deliveries, as well
as road crossings, railroad crossings and utility crossings. Grid
coordinates for major structures such as pumping plants, flow
control stations, tanks, reservoirs, etc.
(e) Land control survey lines with ties to alignment where appropriate.
September 2007 59
Design Data Collection Guidelines
(h) Existing utility lines within the right-of-way and requirements for
relocation.
(k) Low wire elevations and station of power lines (include voltage)
where they cross the alignment.
(m) Right-of-way.
• Railroad crossings.
60 September 2007
Chapter 4 – Specifications Designs
5. Canals
H. Foundation Data.
September 2007 61
Design Data Collection Guidelines
(2) Geologic Data. The following list of geologic design data provides
general guidelines for the collection and reporting of geologic information
for canals. The geologist should apply these guidelines with good
judgment and sound reasoning, elaborating upon them as required by the
particular geologic setting and engineering requirements. Because the
collection of geologic data is a dynamic process and often continues into
the preparation of final designs, all stages of the specification design
geologic exploration program must be constantly coordinated with the
designer through the appropriate geology office. The design engineer and
geologic and geophysical staff will provide necessary assistance and
guidance in the gathering of these design data.
62 September 2007
Chapter 4 – Specifications Designs
5. Canals
(m) Document past, present, and possible future petroleum, water, and
mineral extraction operations in vicinity.
September 2007 63
Design Data Collection Guidelines
I. Corrosion Survey.
(3) List location, output, and purpose of the direct-current sources in the earth
situated within ¼ mile of the proposed structure and appurtenant features.
If the purpose of the direct current is for cathodic protection, describe the
structure protected and its location.
(4) List of structures within ¼ mile of the vicinity of the proposed structure
and appurtenant features. Determine if buried structures in the vicinity
have cathodic protection and, if so, the type and location of the cathodic
protection groundbed.
(6) Report alkali conditions in soil and water, which might affect the choice of
sulfate resisting cement.
64 September 2007
Chapter 4 – Specifications Designs
5. Canals
• Obtain from the power company the order in which the phases
are arranged on the tower.
September 2007 65
Design Data Collection Guidelines
(1) Classification of all materials taken from test holes as soils, rock, etc.,
should be designed according to Unified Soils Classification System (see
Earth Manual). Location and extent of rock, areas of high ground water
(present and future), and other unusual conditions should be shown.
(1) Design flood frequency to be used for design of cross drainage structures.
(2) Peak design flow discharges for minor drainage areas, except where
temporary ponding time uphill of the canal is a design consideration, then
hydrographs of the design storms should be submitted, and topography
should extend uphill of the canal a sufficient distance to cover the
temporarily inundated area.
(3) Hydrographs of design floods for major cross-drainage areas if the canal
section extends across the natural channel or broad, poorly defined
drainage.
(4) The expected volume of sediment taken into the canal and/or accumulated
uphill of a canal drain inlet used for major cross-drainage areas for large
capacity canals.
66 September 2007
Chapter 4 – Specifications Designs
5. Canals
(2) Water surface elevations and capacities at control points along canal at
deliveries.
(5) A list of all structures showing stationing, type, size, and other control
data.
(8) Percent of design capacity that the canal is expected to carry each month,
and probable dates that it may be taken out of service for maintenance
each year.
(10) Explain any proposed rotational, scheduled irrigation, or full demand plan
and alternative types of systems considered.
(14) Type of water service for land (include planning report if available):
September 2007 67
Design Data Collection Guidelines
(c) Base of rail elevation for railroad, and crown elevation and width
of surfacing for road. Minimum clearance between top of culvert
or siphon and base of rail or crown of road.
68 September 2007
Chapter 4 – Specifications Designs
5. Canals
(a) Type of control (slide gate, radial gate, side overflow, siphonic
overflow) and capacity. Weather warning plan is required.
(5) Checks:
(6) Turnouts:
September 2007 69
Design Data Collection Guidelines
(b) Prevalence of any unusual local pest action such as termites, dry
rot, and marine borers; local practices for combating same.
70 September 2007
Chapter 4 – Specifications Designs
5. Canals
(1) The environmental setting, photographs, both black and white and color,
are helpful.
(4) Background on the need for fish facilities such as screens, fishways, and
barriers.
(5) The need for blending structures with the surroundings, restoring borrow
areas, and reseeding spoil banks.
(6) The need for a field conference to resolve critical environmental problems
with participation of other agencies.
(7) Review of designs by other agencies including the findings of the Fish and
Wildlife Coordination Act Report.
(9) The need for escape structures or crossings for human, deer, or other
wildlife including special fencing needs.
(11) Any threatened and/or endangered critical habitat in/or adjacent to the
canal alignment.
(12) The need for restoring borrow areas and reseeding spoil banks.
September 2007 71
Design Data Collection Guidelines
O. Electrical Data. Data listed below will be required to initiate design. The data
furnished should be sufficient to permit designers to complete the basic design
(single-line diagram) for the canal, wasteway, spillway, check, turnout, chute,
drop, or other structure. After designs of the facility have progressed enough to
develop details of electrical system needs, designers will prepare a list of
additional data required to complete final design of electrical installation.
(1) Name and telephone numbers of electrical power suppliers and contacts
within those organizations.
(3) System voltage at which power will be supplied, number of phases, and
whether service will be overhead or underground.
(8) Requirements for voice and data communications between the supervisory
master station and the remote facilities.
P. Cost Data for Field Cost Estimate. The field cost estimate is an estimate of the
capital costs of a feature or project from award to construction; non-contract costs
are not included. Cost data developed in previous or other studies (either by
Reclamation or others) should be included with the design data submittal. Include
a description or outline of estimating methods and data used. The following
72 September 2007
Chapter 4 – Specifications Designs
5. Canals
design data for feasibility and specifications levels designs should be considered
for submittal:
(2) Estimate of cost of ROW for all features including reservoirs, dams, and
appurtenant works. Include supporting data:
(7) Power rate in mills per kilowatt-hour, interest rate, and plant factor for
economic tunnel, and pipeline sizing studies in cases where transported
water is pumped.
(8) Estimated cost for construction items which cannot readily be determined
in the design office and include the supporting data:
September 2007 73
Design Data Collection Guidelines
(9) Where buildings are located within the area to be cleared by the prime
contractor, and if disposal will be the contractor’s responsibility, designate
building groups by number and furnish detailed list of buildings for each
group. Details should include general description, size, materials, and
general condition. Drawings should be provided of these buildings, if
available, that depict dimensions, construction materials, the structural
system for the building, and major electrical and mechanical equipment.
Determine if disposal will be the responsibility of the prime contractor. If
not, submit dates when disposal will be completed by others.
74 September 2007
Chapter 4 – Specifications Designs
5. Canals
(4) Filling and draining criteria for dam, ponds, and pipelines
(7) Water for construction purposes. For large rivers, this item may be
unimportant. For small streams and offstream reservoirs, the item
becomes critical. Determine if up to 2 ft3/s of diversion flow for
construction purposes can be assured to the contractor. The Government
should obtain the water rights required. If it is necessary to use ground
water, obtain information on probable sources and yields. Furnish
information on locations and yields of existing wells in the vicinity.
Determine restrictions, if any, to use of ground water for this purpose. It
may be necessary to obtain permits from State or other governing
agencies. Retrieve water quality samples for testing and evaluation.
September 2007 75
Design Data Collection Guidelines
(14) Give borrow area and temporary haul road restoration requirements such
as stockpiling of topsoil, grading of the area, general cleanup, etc.
76 September 2007
Chapter 4 – Specifications Designs
6. Pipelines
6. Pipelines. The Introduction (Chapter 1) for these design data collection guidelines
contains additional information concerning: preparing a design data collection request,
design data collection requirements, and coordinating the design data collection and
submittal. The design data collection requirements included in this section cover
pressure and gravity or open (low-pressure) pipeline systems.
A. General Map(s). The General Map should cover the project area and the area
immediately surrounding the project within approximately 2 or 3 miles. The scale
of the General Map should be adequate to clearly show listed details. A scale of
approximately 1 to 3 miles per inch is commonly used. The following data are
shown on a General Map for feasibility and specifications level design data
collection:
(1) A key map locating the general map within the State.
(b) Recreation areas; fish and wildlife areas; building areas; highways,
railroads, and shipping points; housing; areas of cultural
sensitivity; areas of archeological, historical, and mining or
paleontological interest; and bridges with special loads or size
limitations.
(5) Rights-of-way:
September 2007 77
Design Data Collection Guidelines
(1) General:
78 September 2007
Chapter 4 – Specifications Designs
6. Pipelines
(k) Where the scale does not permit proper detail of a congested area,
a blowup at a larger scale may be included elsewhere on the
drawing and referenced to its proper location.
(2) Distribution Systems. Where the source of the water is a canal, reservoir,
or pipeline with turnout or headworks located outside the distribution
system area boundary, topographic maps should be submitted covering all
the areas in which the connecting feeder main is to be located. The water
surface elevation range in the source canal or reservoir or hydraulic grade
line range in the source pipeline should be shown. Also, where
appropriate, data such as capacities, grades, etc., should be shown.
(1) Information relating to access for possible site visit by the design team,
access for foundation exploration and construction, and access limitations
due to environmental restrictions, etc.
(2) Access to the site for operation and maintenance (O&M) forces.
September 2007 79
Design Data Collection Guidelines
(5) The approximate distance from the nearest railroad shipping terminal to
the structure site; load restrictions and physical inadequacies of existing
roads and structures and an estimate of remedial improvements to
accommodate construction hauling; estimate of access road length and
major structures required for new construction; and possible alternative
means for delivering construction materials and equipment to the structure
site.
(7) Climatic conditions that will affect design, construction, and O&M such
as amount, rate, and distribution of rain, snow, and hail; ice conditions;
heating and air-conditioning design temperatures; summer and winter
temperatures with extremes; maximum wind velocities and their
directions; probability of excessive dust or sand.
D. Survey Control. Survey control is required for all surveys including surveys
associated with aerial photography. If existing facilities or features are affected or
incorporated into designs, then verification of original coordinate system with
current coordinate system and datum should be made.
E. Topographic Maps.
(1) Topographic maps, when used, should be furnished covering all the
project area showing ownerships, gross acreage, and irrigable acreage for
each ownership, proposed delivery location and type, and delivery water
surface elevation. The acreage information, delivery type, and delivery
80 September 2007
Chapter 4 – Specifications Designs
6. Pipelines
water surface elevation may be omitted from the maps if the information is
submitted separately in tabular form.
(2) Location and layout should be based on the latest system used in previous
designs or preliminary studies. A scale of 1 inch equals 100 feet to 1 inch
equals 400 feet and a contour interval of 2 feet is satisfactory. Structures
proposed on the pipeline should be shown by symbols; where proposed
pipeline locations are shown on these maps. If the project area is flat or
small, a 1-foot contour interval may be required.
(3) Where the source of the water is a canal, reservoir, or pipeline with
turnout or headworks located outside the distribution system area
boundary, topographic maps of the same scale and contour interval
provided for above, should be submitted covering all the areas in which
the connecting feeder main is to be located. The water surface elevation in
the source canal or reservoir or hydraulic gradient in the source pipeline
should be shown. Also, where appropriate, data such as capacities, grades,
etc., should be shown.
(4) Unless the information can be shown in adequate detail on the plan-profile
drawing and/or the location map, topographic maps should be furnished
for the proposed sites for pumping plants, flow control stations, reservoirs,
regulating tanks, surge stands, etc. Such maps should be prepared with a
scale of 1 inch equals 20 feet and a contour interval of 2 feet unless steep
terrain requires a greater interval for clarity. If the project area is flat or
small, a 1-foot contour interval may be required.
F. Plan and Profile Drawings. Plan and profile drawings are normally requested
for linear features such as roads, canals, and pipelines. Drawings are prepared so
that both plan and profile are plotted on one sheet. The plan view may not be
required if shown on other drawings. These drawings are normally prepared with
a 1 inch = 10 feet vertical scale and the horizontal scales from 1 inch = 100 feet to
1 inch = 200 feet unless more or less detail is required. The scale should be
adjusted, as required, if it is necessary to show details. Plan and profile drawings
should show features such as:
(1) General:
September 2007 81
Design Data Collection Guidelines
(e) Ties and stationing for turnouts, sublaterals and deliveries, as well
as road crossings, railroad crossings and utility crossings. Grid
coordinates for major structures such as pumping plants, flow
control stations, tanks, reservoirs, etc.
(f) Land control survey lines with ties to alignment where appropriate.
(i) Existing utility lines within the right-of-way and requirements for
relocation.
(l) Low wire elevations and station of power lines (include voltage)
where they cross the alignment.
(n) Right-of-way.
• Railroad crossings.
82 September 2007
Chapter 4 – Specifications Designs
6. Pipelines
G. Geologic Data. The following list of geologic design data provides general
guidelines for the collection and reporting of geologic information for this type of
facility. The geologist should apply these guidelines with good judgment and
sound reasoning, elaborating upon them as required by the particular geologic
setting and engineering requirements. Because the collection of geologic data is a
dynamic process and often continues into the preparation of final designs, all
stages of the specification design geologic exploration program must be
constantly coordinated with the designer through the appropriate geology office.
The TSC geologic and geophysical staff will provide necessary assistance and
guidance in the gathering of these design data.
September 2007 83
Design Data Collection Guidelines
(4) Factual narrative description of surficial deposits with attention being paid
to engineering geologic matters, such as swelling minerals, low-density
materials, presence of gypsum and other sulfates, caliche, erodibility (see
Earth Manual). Strength of the trench wall is necessary to determine
trench type for flexible pipe.
(7) Test pits shall be excavated at 2,500 ft. intervals and laboratory testing
shall be performed to determine proctor or relative densities. This
information will be used to determine trench type.
(8) Drill holes shall be drilled at 2,500 ft. intervals to a depth of 15 ft. below
the invert of the pipe or until bedrock is encountered. This information
will is used to determine where suitable pipe foundations exist.
(11) Determine ground water conditions with attention being paid to water
levels and their seasonal fluctuation, occurrence of unconfined and
confined aquifers, water-producing capabilities, chemistry, and ground
subsidence.
(12) Logs of exploration. Logs of drill holes advanced by churn drilling, chop
and wash, or other methods which result in less then adequate sample
recovery should be augmented by borehole electric (geophysical) logs
where appropriate.
(14) Document past, present, and possible future petroleum, water, and mineral
extraction operations in vicinity.
84 September 2007
Chapter 4 – Specifications Designs
6. Pipelines
(2) Performance history of construction materials that have been used in the
area.
(3) List of structures within ¼ mile of the vicinity of the proposed structure
and appurtenant features. Determine if buried structures in the vicinity
have cathodic protection and, if so, the type and location of the cathodic
protection groundbed.
(4) List location, output, and purpose of the direct-current sources in the earth
situated within ¼ mile of the proposed structure and appurtenant features.
If the purpose of the direct current is for cathodic protection, describe the
structure protected and its location.
(6) Report alkali conditions in soil and water which might affect the choice of
sulfate resisting cement.
September 2007 85
Design Data Collection Guidelines
86 September 2007
Chapter 4 – Specifications Designs
6. Pipelines
(1) Classification of all materials taken from test holes as soils, rock, etc.,
should be designated according to Unified Soils Classification System (see
Earth Manual). Location and extent of rock, areas of high ground water
(existing and future conditions), and other unusual conditions should be
shown.
(6) Maximum Standard Proctor and relative density tests of pipe trench for
determining trench type and soil strength.
(7) Embedment requirements for pipe (native soil, select material, gravel,
CLSM).
(8) Reference to service history of any material thought suitable for use on
project if previously used, to include results of sample analysis and tests.
(9) Types of pipe commonly used on the project or in the project area
including types of pipe which are not acceptable for use on the project.
J. Operating Data:
September 2007 87
Design Data Collection Guidelines
(c) Peak requirement. This is the basic criteria for sizing pipelines and
can be based on the maximum demand for a month, peak day, or
other time period. The demand should be stated as the number of
productive acres to be served by a flow of 1 ft3/s or a flow rate of a
specified number of gallons per minute required to irrigate 1 acre.
Note distribution of irrigable acres along the irrigation system.
(d) Criteria for reducing irrigable acres to productive acres. This can
be expressed as a percentage of the irrigable area.
(e) Basic criteria for sizing farm deliveries. This may be shown as a
table showing the maximum and minimum number of productive
acres to be served by deliveries of 1 ft3/s, 2 ft3/s, 3 ft3/s, etc.
88 September 2007
Chapter 4 – Specifications Designs
6. Pipelines
(c) Maximum and minimum water level elevations at raw water intake
and clearwell.
September 2007 89
Design Data Collection Guidelines
spread out equally over the entire year when better data is not
available.
(n) Peak requirement. This is the basic criteria for sizing pipelines and
can be based on the maximum demand for a month, peak day, or
other time period.
(o) Delivery demands can be stated in acre-feet per month or ft3/s and
pressure requirements at the delivery points.
K. Miscellaneous Data:
(3) If a pumped system, use data listed under Pumping Plants and
Powerplants, as applicable.
(4) Any limitations imposed on height of stands, tanks, and other structures
due to location, by the Federal Aviation Administration, Environmental
Protection Agency, State, county, municipal, or district regulations.
Maximum wind velocities expected at tank sites and requirements for
beacon lights.
(5) Minimum cover on lateral pipelines based on farming over pipe, frost
depth, depth to ground water, type of soils, vehicle wheel loadings, etc.
(6) Details of drainage system (if existing or proposed) that will influence
designs of irrigation pipe distribution system.
90 September 2007
Chapter 4 – Specifications Designs
6. Pipelines
(13) A list of previous Reclamation or other projects that have been constructed
in the area.
L. Electrical Data. Data listed below will be required to initiate design. The data
furnished should be sufficient to permit designers to complete the basic design
(single-line diagram) for the distribution systems. After designs of the facility
have progressed enough to develop details of electrical system needs, designers
will prepare a list of additional data required to complete final design of electrical
installation.
(1) Names and telephone numbers of electrical power suppliers and contacts
within their organizations.
(3) System voltage at which power will be supplied, number of phases, and
whether service will be overhead or underground.
September 2007 91
Design Data Collection Guidelines
(8) Requirements for voice and data communications between the supervisory
master station and the remote facilities.
(5) Any threatened and/or endangered critical habitat within or adjacent to the
pipeline system.
(7) The need for restoring borrow areas and reseeding spoil banks.
N. Right-of-Way (ROW).
(1) Determine the minimum ROW limits for construction and the permanent
ROW limits required.
92 September 2007
Chapter 4 – Specifications Designs
6. Pipelines
(3) The method for determining the ROW and how the ROW will be obtained
should be described.
O. Cost Data for Field Cost Estimate. The field cost estimate is an estimate of the
capital costs of a feature or project from award to construction; non-contract costs
are not included. Cost data developed in previous or other studies (either by
Reclamation or others) should be included with the design data submittal. Include
a description or outline of estimating methods and data used. The following
design data for feasibility and specifications levels designs should be considered
for submittal:
(2) Estimate of cost of ROW for all features including reservoirs, dams, and
appurtenant works. Include supporting data:
(7) Power rate in mills per kilowatt-hour, interest rate, and plant factor for
economic tunnel, and pipeline sizing studies in cases where transported
water is pumped.
(8) Estimated cost for construction items which cannot readily be determined
in the design office and include the supporting data:
September 2007 93
Design Data Collection Guidelines
(9) Where buildings are located within the area to be cleared by the prime
contractor, and if disposal will be the contractor’s responsibility, designate
building groups by number and furnish detailed list of buildings for each
group. Details should include general description, size, materials, and
general condition. Drawings should be provided of these buildings, if
available, that depict dimensions, construction materials, the structural
system for the building, and major electrical and mechanical equipment.
Determine if disposal will be the responsibility of the prime contractor. If
not, submit dates when disposal will be completed by others.
94 September 2007
Chapter 4 – Specifications Designs
6. Pipelines
(4) Filling and draining criteria for dam, ponds, and pipelines
(7) Water for construction purposes. For large rivers, this item may be
unimportant. For small streams and offstream reservoirs, the item
becomes critical. Determine if up to 2 ft3/s of diversion flow for
construction purposes can be assured to the contractor. The Government
should obtain the water rights required. If it is necessary to use ground
water, obtain information on probable sources and yields. Furnish
information on locations and yields of existing wells in the vicinity.
Determine restrictions, if any, to use of ground water for this purpose. It
may be necessary to obtain permits from State or other governing
agencies. Retrieve water quality samples for testing and evaluation.
September 2007 95
Design Data Collection Guidelines
(14) Give borrow area and temporary haul road restoration requirements such
as stockpiling of topsoil, grading of the area, general cleanup, etc.
96 September 2007
Chapter 4 – Specifications Designs
7. Access Roads and Railroad or Highway Relocation
7. Access Roads and Railroad or Highway Relocation. The Introduction (Chapter 1) for
these design data collection guidelines contains additional information concerning:
preparing a design data collection request, design data collection requirements, and
coordinating the design data collection and submittal. For a railroad or highway
relocation, the data should represent the standards of design and construction which, in
negotiations with the owner of the facility, have been agreed upon as satisfying the
principle of equivalent replacement.
(1) A key map locating the general map area within the State.
(2) The alignment of the railroad or highway relocation or of the access road.
(4) Existing towns, highways, roads, railroads and shipping points, public
utilities such as electric power and telephone lines, pipelines, etc., and
stream-gauging stations.
(6) Locations of borrow areas for natural construction materials and disposal
areas for waste excavation.
September 2007 97
Design Data Collection Guidelines
C. Foundation Data:
(2) Geologic Data. The following list of geologic design data provides
general guidelines for the collection and reporting of geologic information
for this type of facility. The geologist should apply these guidelines with
good judgment and sound reasoning, elaborating upon them as required by
the particular geologic setting and engineering requirements. Because the
collection of geologic data is a dynamic process and often continues into
the preparation of final designs, all stages of the specification design
geologic exploration program must be constantly coordinated with the
designer through the appropriate geology office. The TSC geologic and
geophysical staff will provide necessary assistance and guidance in the
gathering of these design data.
98 September 2007
Chapter 4 – Specifications Designs
7. Access Roads and Railroad or Highway Relocation
(l) Document past, present, and possible future petroleum water, and
mineral extraction operations in vicinity.
D. Corrosion Survey.
September 2007 99
Design Data Collection Guidelines
(3) List of structures in the vicinity of (within ¼ mile) the proposed structure
and appurtenant features. Determine if buried structures in the vicinity
have corrosion protection and, if so, the type of corrosion protection.
(4) List location, output, and purpose of the direct-current sources in the earth
situated within ¼ mile of the proposed structure and appurtenant features.
If the purpose of the direct current is for cathodic protection, describe the
structure protected and its location.
(1) Location of and distance to suitable borrow areas for permeable and
impermeable soil materials for fill or embankment; and for riprap for
channel or slope protection. If quantities are limited, give approximate
volumes available.
(4) Data on commercial concrete plants within practical hauling distance from
the bridge site.
(1) For railroad: Track classification, type of service, limiting grades and
curvature, design load limits, other operating limitations or requirements,
and typical roadbed section showing depth and type of ballast, weight of
rail, and size, spacing, and type of tie.
(3) For roads: Road classification, design speed, limiting grades and
curvature, design load limits, superelevation limits and typical roadway
section showing road width and thickness and type of surfacing.
G. Miscellaneous Data:
(2) For highway or road, drawing of typical roadway cross section showing:
(3) For railroad, alignment and profile drawings (prepared in the current or
compatible CADD software, 24 inches by 36 inches in plot size, with
horizontal scale of 1 inch equals 200 feet and vertical scale of 1 inch
equals 20 feet) showing:
(4) For highway or road, alignment and profile drawings (prepared in current
or compatible CADD software, 24 inches by 36 inches in plot size with
horizontal scale of 1 inch equals 100 feet and vertical scale of 1 inch
equals 10 feet) showing:
(c) For drainage structures: shape, size, slope, and character of each
catchment area, probable rainfall intensity, and anticipated runoff
through each structure; location, distance, physical dimensions,
and characteristics of, any downstream streamflow, control; and
recommendations for wingwalls or headwalls.
(e) For tunnel: cross section showing inside clearance line, roadbed
section with ditches and gutters, dimensions of safety niches (and
motorcar set-offs for railroad); recommended type of lining, if
required; profile on centerline showing ground surface, elevation
and grade of subgrade, and geologic data.
(g) For highway or road: standard designs and loadings for structures;
standards and specifications for surfacing; standard designs for
cattle guards, guardrails or guard posts, roadway signs and culvert
markers, and fencing; and any design or construction practices or
procedures not in accord with Bureau practice.
(6) Estimated quantities for all construction schedule items which cannot
readily be determined in design office, i.e., earthwork (common and rock),
overhaul of roadway excavation with free-haul distance, riprap guardrail,
culverts, and right-of-way fencing and gates.
H. Cost Data:
(4) Estimates of cost for relocating public utilities within the construction
area. Include supporting data.
(5) Estimates of cost for removal of buildings and other structures within the
construction area. Include a general description and recommended
disposal of the structures.
(2) The need for blending roadways and structures with the surroundings.
(4) Indicate the suitability and possibility of present or future use of land
adjacent to Reclamation facilities by the public for recreation, hobbies,
sports, leisure, education, health, housing, etc. Provide data on zoning
regulations and subdivision proposals.
(5) Furnish data on allowable noise limits in the vicinity of the proposed
railroad, highway, or access road alignment where fixed by law or local
ordinance, or where otherwise considered necessary or advisable;
measurements of existing daytime and nighttime ambient noise levels in
the area; and distances to the nearest residential units.
(8) Background on the need for fish protection during construction at stream
crossings.
(12) The need for a field conference to resolve critical environmental problems
with participation of other agencies.
(14) Railroad, highway, or access road clearing plan to consider fish and
wildlife requirements.
(16) Any threatened and/or endangered critical habitat in/or adjacent to the
potential alignments.
8. Drains. The Introduction (Chapter 1) for these design data collection guidelines contains
additional information concerning: preparing a design data collection request, design
data collection requirements, and coordinating the design data collection and submittal.
Specification design of drainage systems requires as a minimum the same type of basic
data as feasibility design. The data are brought up to date and in more detail to show
ground water conditions under irrigation and in addition includes data from any test
drains which may have been installed. At the specifications stage, project lands and farm
units are fixed, the irrigation distribution system has been completed, data from test
drains are probably available, and the specific drainage requirements for various areas
can be determined. The following paragraphs give a check list of drainage data required
for specifications design.
A. Basic Data. The design of open drains for the collection of surface and
subsurface water requires data primarily on surface conditions, i.e., topography;
flood runoff; soil erosion characteristics; outlet requirements for storm water and
waste water from irrigation and laterals; and county, State, Federal, and private
structure requirements. For subsurface drains to control ground water and
salinity, the primary data required are on soils and substrata. Design of
subsurface drains is based largely upon hydraulic conductivity of the various soil
strata above the uppermost slowly permeable barrier in the soil profile, the
position and thickness of these strata, landforms, surface infiltration rates,
contemplated land use and irrigation practices, precipitation records, topography,
and historic ground water conditions.
The amount and coverage of the drainage investigations will depend on the
knowledge, judgment, and experience of the drainage engineer. The reliability of
the drainage requirements will depend on obtaining sufficient and proper
information to be used for interpretation.
B. General Map. A general map showing project area with location of proposed
drains, nearby towns, road, railroads, and a key map locating the general map area
within the State.
C. Location Map. A location map usually at a scale of 1 inch equals 2,000 feet
showing location of the proposed drains and any existing drains, roads, railroads,
powerlines, and gravel sources. This map may be combined with the general map
for small areas.
(1) General. These drawings are normally prepared so that both plan and
profile are shown on a scale of 1 inch equals 200 feet horizontally with
1 inch equals 10 feet vertically on profile. The plan should depict location
of drains, location and size of manholes, drain stationing and significant
topographic features. The profile should depict bottom grade, ground
surface, hydraulic properties, and sections is usually required. Plan and
profile drawings should show features such as contours, roads, borrow
pits, original ground surface and drain alignment and curve data. All
features and details should be shown in ink.
(a) Stationing
(6) Natural surface drainage, flood history, and channel locations and
characteristics.
L. Hydrologic Data:
(2) Area-discharge curve of 5-, 10-, and 25-year storms for use in design of
drains to remove surface water from irrigable lands.
(4) Drain design capacity including water accretion from canal and lateral
losses, and surface waste and deep percolation losses from farm-water
application.
M. Existing Systems. Comparative data from lands in the vicinity having similar
soils and drainage conditions and already under irrigation:
(2) General discussions of soil and substrata characteristics and the depths,
capacities, and spacings of the drains.
(3) Detailed data on particular drains where the factors affecting drainage are
similar to those in the project area. The data will cover type of drain,
design, soil and substrata characteristics, ground water conditions,
construction and maintenance problems, discharge, land use, irrigation
practices, and area effectively drained for good crop production.
N. Miscellaneous Data:
P. Data Sheets. Data sheets and centerline borings for structures and drains which
cannot be obtained until after the definite drainage layout is established. Detailed
data sheets will be needed for such structures as:
9. Wells. The Introduction (Chapter 1) for these design data collection guidelines contains
additional information concerning: preparing a design data collection request, design
data collection requirements, and coordinating the design data collection and submittal.
The design of wells for water supply, drainage, and other similar purposes requires
extensive subsurface and other data. Because of the nature of the environment of ground
water, maximum reliance for correct interpretation and use of the data must be based on
the competence, experience, and judgment of the ground water engineer or geologist.
The following is a minimum checklist of data necessary for specification design and cost
estimates for wells and well fields.
A. Maps.
(1) A general location map showing locations of the well site(s) and
communities, transportation facilities, and other cultural features.
B. General Conditions.
(7) Location and type of power sources, utility easements, buried cables,
pipelines, etc.
D. Subsurface Conditions.
(1) Logs, geologic sections, and other material showing stratigraphic and
lithologic conditions including rock or soil types, sequence, attitude of
beds, and other available geologic data.
E. Aquifer Conditions.
(1) Depth.
(2) Thickness.
F. Ground-Water Conditions.
(4) Locations, amounts, and usage of existing and planned future withdrawals.
(6) Quality of water to include the concentration of major ions and all
parameters having primary and secondary maximum contaminant levels as
defined by the Safe Drinking Water Act.
G. Well Conditions.
H. Sections and Details. Sections and details of a typical well showing relationship
of the general components and details, where applicable.
I. Well Dimensions. Tabular material showing total depths, casing and screen
lengths, and other known or estimated dimensions of the well.
(1) Location, size and type of wetlands that could be influenced by the
drawdown core or by discharge from the well.
M. Report. The foregoing data should be included in a report together with a brief,
descriptive summary of the geology of the area, existing ground-water conditions
and ground-water development to date.
N. Electrical Data. Data listed below will be required to initiate design. The design
furnished should be sufficient to permit designers to complete the basic design
(single-line diagram) for the facility. After designs of the facility have progressed
enough to develop details of electrical system needs, designers will prepare a list
of additional data required to complete final design of electrical installation.
(1) Names and telephone numbers of electrical power suppliers and contacts
within those organizations.
(3) System voltage at which power will be supplied, number of phases, and
whether service will be overhead or underground.
(7) Requirements for voice and data communications between the supervisory
master station and the remote facilities.
10. Switchyards and Substations. The Introduction (Chapter 1) for these design data
collection guidelines contains additional information concerning: preparing a design data
collection request, design data collection requirements, and coordinating the design data
collection and submittal.
(1) A key map locating the general map area within the State.
(4) Existing towns, highways, roads, railroads and shipping points, public
utilities such as electric power and telephone lines, pipelines, etc.
(5) Locations of potential construction and permanent access roads, a sites for
contractor's staging areas and construction facilities.
(6) Locations of borrow areas for natural construction materials and disposal
areas for waste excavation.
(1) The approximate distance from the nearest railroad shipping terminal to
site; load restrictions and physical inadequacies of existing roads and
structures and an estimate of remedial improvements to accommodate
construction hauling; estimate of length and major structures required for
new construction access road; and possible alternative means for
delivering construction materials and equipment at the structure site.
(4) Climatic conditions that will affect design, construction, and operation and
maintenance procedures such as: amount, rate, and distribution of rain
and/or snow; ice conditions; summer and winter temperatures, with
C. Surface Data:
(c) Giving elevation above sea level and having a contour interval
between 1 and 5 feet.
(f) Showing the direction and relative order of all transmission lines
and other existing facilities within the area.
(a) Taken from a high oblique angle, showing the area covered by the
topographic map. (Aerial photographs if practicable.)
(a) Include kinds, sizes, and density of growth of trees and brush.
normally be less than 10 feet deep and seldom greater than 20 feet deep. The sites
are normally leveled by balancing the cut and embankment. The TSC geologic
and geophysical staff will provide necessary assistance and guidance in the
gathering of these design data.
E. Corrosion Survey.
(3) List of structures in the vicinity of (within ¼ mile) the proposed structure
and appurtenant features. Determine if buried structures in the vicinity
have corrosion protection and, if so, the type of corrosion protection.
(4) List location, output, and purpose of the direct-current sources in the earth
situated within ¼ mile of the proposed structure and appurtenant features.
If the purpose of the direct current is for cathodic protection, describe the
structure protected and its location.
(1) Location of and distance to suitable borrow areas for soil materials for fill
or embankment. If quantities are limited, give approximate volumes
available.
(3) Data on commercial concrete plants within practical hauling distance from
the structure site.
(4) Results of sampling and analysis of potential concrete aggregate and other
materials, including previous tests conducted at the TSC.
H. Electrical Data:
(c) Data to determine the type of metering required for each foreign
line. (Indicating watt-hour demand meters will be provided unless
otherwise specified.)
(f) Minimum voltage during heavy load and maximum voltage during
light load for both normal and emergency conditions.
(g) Names and telephone numbers of owners for each foreign line and
contacts within their organizations.
(b) Type of primary system relays (distance, overcurrent, etc.) and the
relay operating characteristics. The actual relay settings will be
required to make coordinating settings of Reclamation relays, but
these data need not be provided initially if it will delay receipt of
other information. Relay coordination problems, such as slow
relaying on primary system, should be presented.
(e) Length and characteristics of primary lines and whether they are
three-wire or four-wire circuits.
(6) Heights and locations of existing buildings, transmission lines, and other
obstructions which are not associated with the station but are in or near the
station site and will present clearance problems.
(8) Capacity charge, energy charge, interest rate, and plant factor to be used in
evaluation of transformer losses.
I. Building Facilities:
(a) Space requirements for equipment, office, work area, vehicles, and
storage.
(3) The need for blending structures with the surroundings, restoring borrow
areas, and reseeding spoil banks.
(4) The need for a field conference to resolve critical environmental problems
with participation of other agencies.
11. Transmission Lines. The Introduction (Chapter 1) for these design data collection
guidelines contains additional information concerning: preparing a design data collection
request, design data collection requirements, and coordinating the design data collection
and submittal.
A. Location Map. A location map showing proposed routes for the transmission
line and showing terminal and intermediate substation locations.
B. Miscellaneous Data:
(4) Delivery points for materials, and proportion of total material required at
each point.
(5) Key map, plan and profile sheets, and special crossing drawings for the
transmission line prepared in accordance with the manual of instructions
for transmission line surveys.
(6) Average value of energy, in mills per kilowatt-hour, for transmission line
losses.
tangent structures in good material will normally vary in depth between 6 feet and
12 feet deep, however foundations for angle and dead-end structures in poorer
materials may be considerably deeper. The TSC geologic and geophysical staff
will provide necessary assistance and guidance in the gathering of these design
data.
(d) A surface geology map, or series of maps, with the route marked
thereon (supplemented by annotated colored aerial photos). Inserts
at a larger scale must be shown when localized, complex
geological conditions exist which may affect tower locations.
Reaches of reasonably uniform and typical foundation conditions
along the route should be indicated, based on surface inspection,
foundation exploration, and general knowledge of the geology of
the area. Non-Reclamation geologic investigations and reports
should be referenced.
E. Corrosion Survey:
(3) List of structures in the vicinity of (within ¼ mile) the proposed structure
and appurtenant features. Determine if buried structures in the vicinity
have corrosion protection and, if so, the type of corrosion protection.
(4) List location, output, and purpose of the direct-current sources in the earth
situated within ¼ mile of the proposed structure and appurtenant features.
If the purpose of the direct current is for cathodic protection, describe the
structure protected and its location.
(2) Data on commercial concrete plants within practical hauling distance from
the transmission line.
(3) The need for blending structure with the surroundings, restoring borrow
areas, and reseeding spoil banks.
(4) The need for a field conference to resolve critical environmental problems
with participation of other agencies.
12. General Purpose Buildings, Office Buildings, and Operation and Maintenance
Facilities. The Introduction (Chapter 1) for these design data collection guidelines
contains additional information concerning: preparing a design data collection request,
design data collection requirements, and coordinating the design data collection and
submittal. (Use specifications design data for both feasibility and specifications.)
(1) A key map locating the general map area within the State.
(5) Locations of potential construction and permanent access roads, sites for
contractor's staging areas, and construction facilities.
(6) Locations of borrow areas for natural construction materials and disposal
areas for waste excavation.
(1) The approximate distance from the nearest railroad shipping terminal to
site; load restrictions and physical inadequacies of existing roads and
structures and an estimate of remedial improvements to accommodate
construction hauling; estimate of length and major structures required for
new construction access road; and possible alternative means for
delivering construction materials and equipment at the building site.
(4) Climatic conditions that will affect design, construction, and operation and
maintenance procedures such as: amount, rate, and distribution of rain
and/or snow; ice conditions; summer and winter temperatures, with
(5) Copy of county or city development Master Plan, if available, along with
codes and regulations for development of land.
(6) Design code. Unless otherwise stated, the architectural and engineering
design shall be in accordance with the latest adopted version of the
International Building Code (IBC), as developed by the International Code
Council (ICC).
C. Surface Data:
(c) Giving elevation above sea level and having a contour interval of
1 foot, depending on the degree of slope.
(e) Showing the suggested location and size of all proposed utilities
and facilities.
(f) Showing the location and size of all existing utilities and other
existing facilities within the area.
(a) Taken from a high oblique angle, showing the area covered by the
topographic map. (Aerial photographs if practicable.)
(a) Include kinds, sizes, and density of growth of trees and brush.
D. Foundation Data:
(2) Geologic Data. The following list of geologic design data provides
general guidelines for the collection and reporting of geologic information
for this type of facility. The geologist should apply these guidelines with
good judgment and sound reasoning, elaborating upon them as required by
the particular geologic setting and engineering requirements. Because the
collection of geologic data is dynamic process and often continues into the
preparation of final designs, all stages of the specifications design
geologic exploration program must be constantly coordinated with the
designer through the appropriate geology office. The TSC geologic and
geophysical staff will provide necessary assistance and guidance in the
gathering of these design data.
(k) If a building is in a high seismic risk zone and near an active fault,
determine age of faulting in vicinity, especially if suspected to be
late Pleistocene or Holocene, to assist in the determination of the
seismic loading by specialists in the TSC
(l) Document past, present, and possible future petroleum, water, and
mineral extraction operations in vicinity.
E. Corrosion Survey:
(3) List of structures in the vicinity of (within ¼ mile) the proposed structure
and appurtenant features. Determine if buried structures in the vicinity
have corrosion protection and, if so, the type of corrosion protection.
(4) List location, output, and purpose of the direct-current sources in the earth
situated within ¼ mile of the proposed structure and appurtenant features.
If the purpose of the direct current is for cathodic protection, describe the
structure protected and its location.
(6) Report alkali conditions in soil and water which might affect the choice of
sulfate resisting cement.
(7) Statement of availability of timber for structural work and lumber for
other purposes.
(3) The need for blending the development with the surroundings.
(4) The need for a field conference to resolve critical environmental problems
with participation of other agencies.
(10) A brief listing of the area's native and/or commonly used plant materials.
H. Miscellaneous Data:
(2) Type and size of office building, dormitory, laboratory, garage, fire
station, warehouse, or other buildings.
(a) Reference to local and State codes or guidelines for treatment and
disposal of sewage.
(5) Types of surfacing for walks and streets in temporary and permanent
areas.
(6) Separate preliminary cost estimate for the following: water and sewage
systems, electrical distribution system, streets and sidewalks, and each
type of building or house required.
(7) Fire protection plan for the community, including information on available
fire protection services.
I. Electrical Data. Data listed below will be required to initiate design. The data
furnished should be sufficient to permit designers to complete the basic design
(single-line diagram) for the visitors’ center. After designs have progressed
enough to develop details of electrical system needs, designers will prepare a list
of additional data required to complete final design of electrical installation.
(1) Names and telephone numbers of electrical power suppliers and contacts
within those organizations.
(3) Source and description of power for the facility. If a transmission line is
to be built by Reclamation, the information listed under “Transmission
Lines” of this chapter should be furnished.
(4) System voltage at which power will be supplied, number of phases, and
whether service will be overhead or underground.
(8) Use of electric ranges, electric water heaters, and/or electric heating in
residences.
(10) Other requirements for power, such as water pumps, warehouse cranes,
machine shops, etc.
(11) Fire protection plan for the community, including information on available
fire protection services.
13. Recreational Facilities. The Introduction (Chapter 1) for these design data collection
guidelines contains additional information concerning: preparing a design data collection
request, design data collection requirements, and coordinating the design data collection
and submittal.
This paragraph lists data required for design of recreation facilities. Small scale site
development, such as a single campground loop, would need much of the data listed
below but only for the area encompassing and immediately surrounding the project site.
(2) The general project area and the area immediately surrounding the project
within 2 or 3 miles.
(3) Any other recreation areas in the general vicinity and facilities available
there.
(6) Land uses in general terms, with private land labeled “private.”
(8) Locations for borrow areas, storage of construction materials, and sites for
stockpiling of topsoil.
(1) Topography covering an area large enough to include all potential site
development. The extent of the topography should include the access road
and the probable site entrance area. Contours should be at 2-foot intervals
or 1 foot intervals if the site is very flat. The data should be in the form of
an electronic drawing file which can be used to create a base map. All
points contained in the drawing file should have z axis values that
correspond to onsite elevation.
(3) Surface drainage features such as streams and ravines and any existing
bridges or culverts.
(4) Existing built site features, such as roads, parking, turnarounds, buildings,
structures, power lines, buried utility lines and tanks, campgrounds, leach
fields, picnic areas, and marinas.
C. Survey Data:
(1) Survey Control. Permanent horizontal and vertical survey control should
be established at the earliest possible time. A coordinate system on a true
north-south grid should be established with the origin located so that all of
the features (including borrow areas) will be in one quadrant, and so that
the values of the coordinates for any major development are widely
separated numerically. The coordinate system should be related to a state
or national coordinate system, if available. All preceding survey work
should be corrected to agree with the permanent control system; and all
subsequent survey work should be based on the permanent control. All
surveys should be tied to the established coordinate system at each
construction site.
(2) Color Photographs of the Site. All photos should be keyed to the site
topographic map. Photos should show problem or hazardous areas,
location of proposed facilities, location of possible access points to the site
from existing routes, and close ups of existing features such as buildings
or structures. These photos should also show favorable offsite views
which should be preserved and considered when siting buildings. Photos
should also be taken of unfavorable onsite features which should be
screened from view or otherwise considered when siting facilities. Photos
should show the condition of existing roads and buildings, if possible.
(3) Significant sight lines onto the site from offsite. This would be important
if there were a need to locate the development where it would not be seen
from certain vantage points offsite.
(4) Major site features of interest to be developed into the design as focal
points.
(6) The need for blending buildings and structures with the surroundings.
F. Biological Data:
(2) Wildlife. List of threatened and endangered species that have migration
routes, critical habitat, or outstanding habitat in the immediate area. Map
of any species’ migration patterns, critical habitat, and outstanding habitat
that occurs on or adjacent to the project site. List of animals which may
pose a danger to users or which may require special accommodations in
site design, for example bears or moose.
(1) Depth to bedrock, ground water, and frost line for siting underground
utility lines, buried tanks, and foundations.
(2) Location of underground water and springs which may impact location or
construction of facilities such as campgrounds and roads.
(4) Soil survey and map of soil texture for determining susceptibility of soils
to erosion, and suitability of soils for building foundations, roads, trails,
and leach fields.
(5) Areas of existing erosion, subsidence, or high soil moisture, which should
be avoided.
(8) Availability of potential fill materials on site and nearby, and a description
of the type of materials.
H. Flood Plain Data: Map of 5-, 10-, 25-, and 100-year flood plain levels.
Buildings and campgrounds within frequently flooding areas should be avoided.
J. User Data:
(5) Seasons of use and differing uses by different users as the seasons change.
(6) Number of users expected at one time to use the site for an average
weekend; for a holiday.
(7) Type of equipment the user is expected to bring along and the
spatial/physical site requirements to accommodate that equipment.
K. Utilities:
(1) Electricity:
(5) Gray Water: Opportunities to use gray water for landscape irrigation or
in other nonpotable ways, considering code and environmental
restrictions.
L. Roads Data:
(a) Turning radii required for roads and parking lots, based on vehicles
which are anticipated to use the facility.
(b) Wheel loading of anticipated vehicles which will use the facility.
(f) Width, depth, length, and materials needed for new roads.
(3) Carrying capacities of the particular site, for example: proposed density of
campsites or maximum number of boats in the marina and on the
reservoir.
(6) Requirements for interpretation and the desired associated facilities, such
as kiosks, bulleting boards, or signs. This includes interpretation for
accessibility features as required by American with Disabilities Act
Accessibility Guidelines (ADAGG) and the Uniform Federal Accessibility
Standards (UFAS).
(8) Site specific issues relative to development that were identified during the
planning stage.
O. Concessionaire=s Requirements:
(1) Type of equipment the user is expected to rent onsite from the
concessionaire and the spatial/physical site requirements and location(s) to
accommodate the storage and servicing of that equipment.
(1) Fee collection methods and location requirements for facility security.
Methods to achieve security.
(2) Requirements to close off one part of a recreation are from another.
(4) Requirements for fire safety, such as the need for fire trucks and
ambulances to traverse the site. Need for emergency vehicles to be able to
reach facilities and acceptable limits of access.\
(5) Roads and buildings needed for general maintenance of the area and their
associated spatial and functional requirements.
(1) Availability of nursery grown plants of the desired tree and shrub species.
Availability of grass and forb seeds of the desired species.
(3) Cost effectiveness of collecting versus purchasing large trees and cacti.
(4) Irrigation needs, based on water regime requirements of the plants that
will be used, and local growing conditions.
(10) Need for design of erosion control plan including silt fences, temporary
seeding, erosion control blankets, etc. during construction to mitigate soil
erosion and potential siltation of streams and water bodies.
(1) Site topography covering an area large enough to include all potential
marina development sites, with contours at 2-foot intervals or 1-foot
intervals if the site is very flat.
(3) General slope and landform characteristics required for good marina
development.
(8) Condition of roads and their suitability for use by vehicles towing boat
trailers.
S. Miscellaneous Data:
(8) Unusual local pest that would influence type of construction materials and
the selection of plant materials to use in planting plans.
14. Fishways. The Introduction (Chapter 1) for these design data collection guidelines
contains additional information concerning: preparing a design data collection request,
design data collection requirements, and coordinating the design data collection and
submittal.
(1) A key map locating the general map area within the State.
(4) Existing towns, highways, roads, railroads, public and private utilities,
transmission lines, substations, canals, rivers, streams, and stream-gauging
stations.
(5) Locations of construction access road and sites for required construction
facilities.
(9) Scale of the general map should be adequate to clearly show listed details.
(6) Existing utility lines within the right-of-way and requirements for
relocation.
(7) Fences.
(8) Contours.
(2) Names and telephone numbers of local utilities and irrigation districts and
contacts within those organizations.
(3) Name and brief description of similar construction in the area or region.
Preferable to use Reclamation projects if possible.
(7) Climatic conditions that will affect construction and operation procedures
such as: amount, rate, and distribution of rain and/or snow; ice conditions;
summer and winter temperatures, with extremes; and extreme wind
velocities and prevailing directions. (Extensive tabulations are not
necessary.)
(9) Photographs of construction site and existing features which may effect
design.
F. Foundation Data:
G. Geologic Data. The following list of geologic design data provides general
guidelines for the collection and reporting of geologic information. The geologist
should apply these guidelines with good judgment and sound reasoning,
elaborating upon them as required by the particular geologic setting and
engineering requirements. Because the collection of geologic data is a dynamic
process and often continues into the preparation of final designs, all stages of the
specification design geologic exploration program must be constantly coordinated
with the designer through the appropriate geology office. The TSC geologic and
geophysical staff will provide necessary assistance and guidance in the gathering
of these design data.
(2) Surface geologic map of the fish ladder site showing location of
explorations. Locations of all existing explorations should be indicated by
coordinates or stationing of the permanent survey control system for the
canal.
(4) Factual narrative description of surficial deposits with attention being paid
to engineering geologic matters, such as swelling minerals, low-density
material, presence of gypsum and other sulfates, caliche, erodibility (see
Earth Manual).
(9) Determine ground water conditions with attention being paid to water
levels and their seasonal fluctuation, occurrence of unconfined and
confined aquifers, potential leakage, water-producing capabilities
including permeability tests, chemistry, and land subsidence.
(10) Logs of exploration. Logs of drill holes advanced by churn drilling, chop
and wash, or other methods which result in less than adequate sample
recovery should be augmented by borehole electric (geophysical) logs
where appropriate.
(13) Document past, present, and possible future petroleum, water, and mineral
extraction operations in vicinity.
(15) Samples of foundation materials and ground water should be obtained and
tested to determine any possible chemical reaction with the concrete or
metalwork.
H. Corrosion Survey:
(3) List of structures in the vicinity of (within ¼ mile) the proposed structure
and appurtenant features. Determine if buried structures in the vicinity
have corrosion protection and, if so, the type of corrosion protection.
(4) List location, output, and purpose of the direct-current sources in the earth
situated within ¼ mile of the proposed structure and appurtenant features.
If the purpose of the direct current is for cathodic protection, describe the
structure protected and its location.
J. Biological Data:
(3) Behavior.
K. Hydrological Data:
(4) Both tailwater and forebay rating curves over range of flows.
(7) Provide seasonal 1-year, 2-year, 5-year, 10-year, 25-year, 50-year, and
100-year river flow rates and water surfaces for evaluating construction
related structures such as cofferdams and bypasses.
L. Agency Coordination:
(2) Review of designs by other agencies, including the findings of the Fish
and Wildlife Coordination Act Report (if available).
(3) The need for a field conference to resolve critical environmental problems
with participation of other agencies.
M. Sedimentation Data: Sufficient data on the soil at the proposed structure site(s)
must be included to determine whether sedimentation will be a problem.
O. Fishways Data:
• Vertical slot
• Pool and weir ladder
• Weir and orifice ladder
• Full width stream weir
(b) Baffled channel
• Alaska Steeppass
• Denil
• Roughened stream channel
• Pool-chute fish ladder
(4) Maximum and minimum head loss or drop through the slots, orifice and
weirs.
(13) Location of fishway exit from dam crest, spillways or any river outlet
gates, etc.
(14) Requirement for stoplog slots or gates to be provided for dewatering the
ladder.
(15) Requirement for entire fishway, including entrance and exit structures, to
be covered with grating.
(1) Field observations and sketches of flow patterns above and below the
barrier should be made, especially at high flows.
(4) Type of fishway entrance (e.g., suppressed weir, contracted weir, vertical
slot or orifice).
(15) Location of attraction pipe outlet and orientation to the river flow.
R. Other Features:
S. Construction Data:
(1) Plan of operation for fish ladder facilities, dam and canal.
(2) Portion of year structures should be designed to operate.
(3) O&M access requirements.
U. Miscellaneous Information:
(1) Prevalence of any unusual local pest action such as termites, dry rot, and
marine borers; local practices for combating same.
(1) The environmental setting, photographs, both black and white and color,
are helpful.
(4) The need for blending structures with the surroundings, restoring borrow
areas, and reseeding spoil banks.
(5) The need for a field conference to resolve critical environmental problems
with participation of other agencies.
(6) Review of designs by other agencies, including the findings of the Fish
and Wildlife Coordination Act Report (if available).
(8) Any threatened and/or endangered critical habitat in or adjacent to the fish
ladder.
(3) Percent of design capacity that the fish ladder is expected to carry each
month, and probable dates that it may be taken out of service for
maintenance each year.
X. Electrical Data. Data listed below will be required to initiate design. After
designs of the facility have progressed enough to develop details of electrical
system needs, designers will prepare a list of additional data required to complete
final design of electrical installation.
(1) Name and telephone numbers of electrical power suppliers and contacts
within those organizations.
(3) System voltage at which power will be supplied, number of phases, and
whether service will be overhead or underground.
(8) Requirements for voice and data communications between the supervisory
master station and the remote facilities.
15. Fish Barriers. The Introduction (Chapter 1) for these design data collection guidelines
contains additional information concerning: preparing a design data collection request,
design data collection requirements, and coordinating the design data collection and
submittal.
(1) A key map locating the general map area within the State.
(4) Existing towns, highways, roads, railroads, public and private utilities,
transmission lines, substations, rivers, streams, and stream-gauging
stations.
(5) Locations of construction access road and sites for required construction
facilities.
(9) Scale of the general map should be adequate to clearly show listed details.
(5) Existing utility lines within the right-of-way and requirements for
relocation.
(6) Fences.
(7) Contours.
(2) Names and telephone numbers of local utilities and irrigation districts and
contacts within those organizations.
(3) Name and brief description of similar construction in the area or region.
Preferable to use Reclamation projects if possible.
(7) Climatic conditions that will affect construction and operation procedures
such as: amount, rate, and distribution of rain and/or snow; ice conditions;
(10) Photographs of the construction site and existing features which may
effect design.
F. Foundation Data:
G. Geologic Data. The following list of geologic design data provides general
guidelines for the collection and reporting of geologic information. The geologist
should apply these guidelines with good judgment and sound reasoning,
elaborating upon them as required by the particular geologic setting and
engineering requirements. Because the collection of geologic data is a dynamic
process and often continues into the preparation of final designs, all stages of the
specification design geologic exploration program must be constantly coordinated
with the designer through the appropriate geology office. The TSC geologic and
geophysical staff will provide necessary assistance and guidance in the gathering
of these design data.
(2) Surface geologic map of the fish screen facilities site showing location of
explorations. Locations of all existing explorations should be indicated by
coordinates or stationing of the permanent survey control system for the
canal.
(4) Factual narrative description of surficial deposits with attention being paid
to engineering geologic matters, such as swelling minerals, low-density
material, presence of gypsum and other sulfates, caliche, erodibility (see
Earth Manual).
(9) Determine ground water conditions with attention being paid to water
levels and their seasonal fluctuation, occurrence of unconfined and
confined aquifers, potential leakage, water-producing capabilities
including permeability tests, chemistry, and land subsidence.
(10) Logs of exploration. Logs of drill holes advanced by churn drilling, chop
and wash, or other methods which result in less than adequate sample
recovery should be augmented by borehole electric (geophysical) logs
where appropriate.
(13) Document past, present, and possible future petroleum, water, and mineral
extraction operations in vicinity.
(15) Samples of foundation materials and ground water should be obtained and
tested to determine any possible chemical reaction with the concrete or
metalwork.
H. Corrosion Survey:
(3) List of structures in the vicinity of (within ¼ mile) the proposed structure
and appurtenant features. Determine if buried structures in the vicinity
have corrosion protection and, if so, the type of corrosion protection.
(4) List location, output, and purpose of the direct-current sources in the earth
situated within ¼ mile of the proposed structure and appurtenant features.
If the purpose of the direct current is for cathodic protection, describe the
structure protected and its location.
J. Biological Data:
(3) Behavior.
K. Hydrological Data:
(6) Provide seasonal 1-year, 2-year, 5-year, 10-year, 25-year, 50-year, and
100-year river flow rates and water surfaces for evaluating construction
related structures such as cofferdams and bypasses.
M. Agency Coordination:
(2) Review of designs by other agencies, including the findings of the Fish
and Wildlife Coordination Act Report (if available).
(3) The need for a field conference to resolve critical environmental problems
with participation of other agencies.
(4) Maximum allowable time of travel for fish moving along the screen face
before entering a bypass.
(7) If applicable, are drum screens to operate at optimum submergence for all
flows?
Q. Trashrack Data:
R. Other Features:
S. Construction Data:
(7) Type of equipment to remove screens for service (e.g., gantry, jib crane,
mobile truck).
(11) Percent of design capacity that the fish screen facilities is expected to
carry each month, and probable dates that it may be taken out of service
for maintenance each year.
U. Miscellaneous Information:
(1) Prevalence of any unusual local pest action such as termites, dry rot, and
marine borers; local practices for combating same.
(1) The environmental setting, photographs, both black and white and color
are helpful.
(4) The need for blending structures with the surroundings, restoring borrow
areas, and reseeding spoil banks.
(5) The need for a field conference to resolve critical environmental problems
with participation of other agencies.
(6) Review of designs by other agencies, including the findings of the Fish
and Wildlife Coordination Act Report (if available).
(8) Any threatened and/or endangered critical habitat in or adjacent to the fish
screen facilities.
W. Electrical Data. Data listed below will be required to initiate design. After
designs of the facility have progressed enough to develop details of electrical
system needs, designers will prepare a list of additional data required to complete
final design of electrical installation.
(1) Name and telephone numbers of electrical power suppliers and contacts
within those organizations.
(3) System voltage at which power will be supplied, number of phases, and
whether service will be overhead or underground.
(8) Requirements for voice and data communications between the supervisory
master station and the remote facilities.
16. Wetlands. The Introduction (Chapter 1) for these design data collection guidelines
contains additional information concerning: preparing a design data collection request,
design data collection requirements, and coordinating the design data collection and
submittal. Biological data other than that requested in this guideline may be required.
This section lists data which may be required for specifications design of wetlands
projects. The project team and the design team should review these guidelines to
determine and assemble the final data request for a specific project. All wetlands projects
should involve appropriate specialists in biology, hydrology (surface and groundwater),
landscape site planning, and/or water quality (chemical limnology) disciplines.
Depending on the scope and complexity, wetlands project plans should be developed or
reviewed by a certified Professional Wetlands Scientist (PWS) or at a minimum by a
member of the Society of Wetlands Scientists (SWS).
• Coastal Wetlands – “found along the Atlantic, Pacific, Alaskan, and Gulf coasts.
They are closely linked to our nation’s estuaries, where sea water mixes with
fresh water to form an environment of varying salinities.”
(2) General Purpose and Function (Definitions are provided at the back
of this section):
(iv) Recreation:
(a) Describe the source(s) of water for the wetlands: river, reservoir,
ground water, overland flow, or piped in.
• The need for restoring and seeding cuts and fills and
spoil banks.
B. Coordination Requirements
(2) Identify any “land use agreements”, or similar mechanisms which secure
short- or long-term commitments by the parties to manage the site for a set
of established objectives. This should include issues related to water
rights/entitlements which are anticipated for the management and
operation of the wetland system.
• Community type.
• Surface cover.
(i) Include the animals targeted for use and their specific needs
and uses for the site, including feeding, cover, loafing, nesting,
etc. Include the specific predator-prey relationships and how
that influences design requirements such as the need for islands
or specific landform types.
(g) Land use survey of upland areas, areas adjacent to the wetlands
site, and the wetlands site.
(h) Soils:
(iv) If the wetland will be constructed from dry land, what is the
availability of topsoil, either on site or locally? Typically
the top six inches of soil over an area that will be cut or
filled would be stripped, stockpiled, and spread back over
new contours to create the final grade.
(j) Provide data on the method(s) of brush and tree disposal permitted
by local and State pollution regulatory agencies.
(3) Water Supply and Water Quality Factors. If hydrologic data were
documented in a report for the Feasibility Designs, they should be updated
based on additional information developed since the Feasibility Designs.
The Specifications Design data submittal shall reference the feasibility
design document and thus eliminate the need to repeat the information
enumerated below. If the information enumerated below is not contained
or is not updated in the report prepared for the Feasibility Design then this
information should be provided for the Specifications Design:
(d) Reservoirs:
(4) Climate. Climatic conditions that will affect construction and operation
and maintenance procedures such as: amount, rate, and distribution of rain
and/or snow; ice conditions; summer and winter temperatures, with
extremes; and probability of excessive dust or sand.
(a) Surveying:
• Channel modifications.
(c) Photographs:
(5) Electrical Data. Data listed below will be required to initiate design of
any facilities requiring electric power. The data furnished should be
sufficient to permit designers to complete the basic design (single-line
diagram) for the required features. After designs have progressed enough
to develop details of electrical system needs, designers will prepare a list
of additional data required to complete final design of electrical
installation:
(d) Unusual local pest (termites, borers, etc.) action and recommended
preventive measures.
(g) Water for construction purposes. For large rivers, this item may be
unimportant. For small streams and offstream reservoirs, the item
becomes critical. Determine if up to 2-ft3/s diversion flow for
Construction purposes can be assured to the contractor. The
Government should obtain the water rights required. If necessary
to use ground water, obtain information on probable sources and
yields. Furnish information on locations and yields of existing
wells in the vicinity. Determine restrictions, if any, to use of
ground water for this purpose. It may be necessary to obtain
permits from State or other governing agencies. Retrieve water
quality samples for testing and evaluation.
(d) Estimates of cost for clearing construction area and for removing
or replacing private improvements in the area. Include supporting
data.
• Bog– A bog is a wetland type that accumulates acidic peat, a deposit of dead plant
material.
• Creation – Construction of a wetland in an area that was not a wetland in the recent past
(within the last 100-200 years) and that is isolated from existing wetlands (i.e., not
directly adjacent).
• Marsh – A marsh is a type of wetland, featuring grasses, rushes, reeds, typhas, sedges,
cat tails, and other herbaceous plants (possibly with low-growing woody plants) in a
context of shallow water. A marsh is different from a swamp, which is dominated by
trees rather than grasses and low herbs. The water of a marsh can be fresh, brackish or
saline.
• Playas – Playa lakes are round hollows in the ground in the Southern High Plains of the
United States. They are ephemeral, meaning that they are only present at certain times of
the year.
take over the deeper water in the middle of the pothole while bulrushes and cattails grow
closer to shore. Wet, sedgy marshes lie next to the upland.
• Restoration – The term indicates that degraded and destroyed natural wetland systems
will be reestablished to sites where they once existed. But, what wetland ecosystems are
we talking about? How far back in time should we go to find target ecosystems? Is
establishing any type of wetland enough to be called "restoration"?
o Guiding principles:
• Vernal pools – A vernal pool is usually a shallow, natural depression in level ground,
with no permanent above-ground outlet, that holds water seasonally. They could
colloquially be referred to as temporary wetlands. In the Northeast United States (Maine,
Massachusetts, and perhaps others) vernal pools fill with the rising water table or with the
melt water and rain of spring. Many vernal pools in the northeast are covered with ice in
the winter.
17. Bridges. The Introduction (Chapter 1) for these design data collection guidelines
contains additional information concerning: preparing a design data collection request,
design data collection requirements, and coordinating the design data collection and
submittal.
The following data and information are required for specifications (final) design of
vehicular bridges. This document can be used to request design data for railroad and
pedestrian bridges along with buried box, round, or arch culverts to be constructed under
roadways. These buried structures qualify as bridges under the American Association of
State Highway and Transportation Officials.
(1) A key map locating the general map area within the State.
(3) The location of the structure site, alignment of the roadway, highway,
access road or railway.
(4) Existing towns, highways, roads, railroads and shipping points, public and
private utilities such as electric power, telephone lines, pipelines, etc.,
transmission lines, substations, canals, dams, rivers and streams, stream-
gauging stations (required only for bridges crossing rivers or streams),
county, township, range, and section lines.
(11) Scale on the general map should be adequate to clearly show listed details
and north arrow.
C. Surface Data:
(1) Survey Control. Survey control is required for all surveys including
surveys associated with aerial photography. Show coordinate system and
existing land survey monuments and special control points established for
the survey. All preceding survey work and all subsequent survey work,
including topography and location, and ground surface elevations of
subsurface exploration, should be revised to conform with the permanent
control system.
All points contained in the electronic files should have coordinates for
northing and easting and values which correspond to the ground level
elevations. Specify the vertical datum, such as National Geodetic Vertical
Datum (NGVD), and the horizontal datum, such as the State Plane
Coordinates (NAD83) along with epoch date.
Legends should show grid factors and reduction to sea level factor, or a
combination of the two.
(f) Provide water surface elevations on the date of the survey and a
thalweg of the stream bottom where practical for a minimum
distance of 500 feet upstream and 500 feet downstream from the
centerline of the proposed bridge. These profiles should be plotted
to a horizontal scale of 1 inch equals 50 feet and a vertical scale
equals 10 feet.
(g) Provide at least four cross sections of the stream. Sections should
be taken immediately upstream and downstream of the structure,
and the other sections should be taken at each end of the stream
profile. These cross sections should be typical of the stream.
Indicate the elevations of low, present, and high water.
(a) All photos should be keyed to the site map. Photos should show
problem or hazardous areas, location of the proposed bridge,
location of possible access points to the site from existing routes,
and close ups of existing features such as buildings and other
structures. These photos should also show favorable offsite views
that should be preserved and considered when determining bridge
location.
The TSC design team will prepare preliminary bridge design layouts and a
field exploration request. The TSC geologic and geophysical staff will
work with the appropriate field staff and provide necessary assistance and
guidance in the gathering of these design data.
(2) Geologic Data. The following list of geologic design data provides
general guidelines for the collection and reporting of geologic information
for bridges. The data should reflect a recognition and consideration of the
scope and size of bridge structure anticipated. The geologist should apply
these guidelines with good judgment and sound reasoning, elaborating
upon them as required by the particular geologic setting and engineering
requirements. Because the collection of geologic data is a dynamic
process and often continues into the preparation of final designs, all stages
of the specification design geologic exploration program must be
constantly coordinated with the designer through the appropriate geology
office.
(k) For bridges over rivers and streams, in-stream material samples to
determine D50 for scour analysis.
(a) Surficial soils (see Earth Manual, latest edition). Note geologic
sections and soil profiles in (2) (c) above.
(2) Flood frequency design flows for 50 and 100 year intervals.
(4) Provide a profile of the centerline of the river or stream bottom where
practical for a minimum distance of 500 feet upstream and 500 feet
downstream from the centerline of the proposed bridge structure. The
profile should be plotted to a horizontal scale of 1 inch equals 50 feet and
a vertical scale of 1 inch equals 10 feet.
(5) Provide at least three cross sections of the stream. One section should be
taken at or near the centerline of the bridge and the other sections at each
end of the stream profile. These cross sections should be typical of the
stream. Indicate the elevations of low, present, and high water.
(10) Anticipated occurrence and amounts of sediment, ice (thickness), and drift
(trash).
(11) Analysis of water for chemical and physical characteristics and biological
quality. Analysis should include a water quality analysis of intake water
to include major ions and cations, corrosivity, and parameters listed as
maximum contaminant limits in the Surface Water Treatment Rule, Safe
Drinking Water Act.
(12) Erosion protection requirements and calculated scour depths, which will
be used for support structure foundation design.
F. Design Standards: For vehicular bridges, the design code is the AASHTO
LRFD Design Specifications published by AASHTO. Applicable state design
standards will also be followed when these requirements are more stringent than
AASHTO’s. The following is a list of the types of facilities carried by the bridge
structures that are designed at the TSC.
(b) Replacement in kind shall be used where the existing bridge design
live load and roadway width are equivalent to current standards
and are considered adequate or where there is no justification for
upgrading to higher or current standards.
(c) Live load requirements higher than current standards shall be used
only when there is a special need or consideration. An example is
heavy construction vehicle traffic.
(2) Access roads. Designs shall be based on AASHTO design guidelines for
access roads with modifications for unusual circumstances such as the
need for higher standards due to the magnitude of the project, special haul
problems, recreation needs, etc.
(3) Recreation roads. Relocated roads, highways, or access roads intended for
recreation purposes or which will contribute to such purposes may be
constructed to higher standards with justifications, and shall be fully
identified and described, including the proposed standards, at the
feasibility design.
(7) Other unique purpose. They shall be fully identified and described,
including proposed standards.
(2) Current and future activities and needs: The current and future road
classification. The future classification from the county or State
Department of Transportation responsible for road maintenance. Include
type of equipments or vehicles that will cross the bridge.
(1) For highway or road bridges, the plan and profile drawings (prepared in
electronic format and plotted on 22 inches by 34 inches, Architectural D,
with horizontal scale of 1 inch equals 100 feet and vertical scale of 1 inch
equals 10 feet) showing:
(2) For railroad bridges, the plan and profile drawings (prepared in electronic
format and plotted on 22 inches by 34 inches, Architectural D, with
horizontal scale of 1 inch equals 200 feet and vertical scale 1 inch equals
20 feet) showing:
(4) Data on commercial concrete and precast concrete plants within practical
hauling distance from the bridge site.
(5) Estimated quantities for all construction schedule items which cannot
readily be determined in design office, i.e., earthwork (common and rock),
overhaul of roadway excavation with free-haul distance, riprap guardrail,
culverts, and right-of-way fencing and gates.
J. Cost Data:
(4) Estimates of cost for relocating public utilities within the construction
area. Include supporting data.
(5) Estimates of cost for removal of buildings and other structures within the
construction area. Include a general description and recommended
disposal of the structures.
(6) Provide any pertinent cost estimates or information that has been prepared
or obtained by Reclamation or the owner. The cost estimates shall include
a description or outline of estimating methods and data used.
(2) The need for blending the bridge structure with the surroundings and the
need for restoring and for reseeding cuts and fills.
(4) Indicate the suitability and possibility of present or future use of land
adjacent to Reclamation facilities by the public for recreation, hobbies,
sports, leisure, education, health, housing, etc. Provide data on zoning
regulations and subdivision proposals.
(5) Furnish data on allowable noise limits in the vicinity of the proposed
bridge where fixed by law or local ordinance, or where otherwise
considered necessary or advisable; measurements of existing daytime and
nighttime ambient noise levels in the area; and distances to the nearest
residential units.
(8) Background on the need for fish protection and passage during
construction at stream crossings.
(10) Any threatened and/or endangered critical habitat in/or adjacent to the
potential alignments.
(11) The need for game/livestock protection, including crossings, fencing, etc.
(16) The need for a field conference to resolve critical environmental problems
with participation of other agencies.
(18) Railroad, highway, or access road clearing plan to consider fish and
wildlife requirements.
18. Removal of Dams and Hydroelectric Facilities. (A design data collection section has
not been prepared for these features. Until a section is prepared, the following reference
should be used, “Guidelines for Retirement of Dams and Hydroelectric Facilities,” Task
Committee on Guidelines for Retirement of Dams and Hydroelectric Facilities, American
Society of Civil Engineers (1997)).
The Introduction (Chapter 1) for these design data collection guidelines contains
additional information concerning: preparing a design data collection request, design
data collection requirements, and coordinating the design data collection and submittal.
19. Water Treatment Plants. The Introduction (Chapter 1) for these design data collection
guidelines contains additional information concerning: preparing a design data collection
request, design data collection requirements, and coordinating the design data collection
and submittal.
The following is a list of possible data required for specifications design of water
treatment facilities. The size and complexity of the process system and structures should
govern the amount and detail of the design data required.
(1) A key map locating the general map area within the State.
(3) Existing towns, highways, roads, railroads, public utilities (electric power,
telephone lines, pipelines, etc.), streams, stream-gauging stations, canals,
drainage channels.
(5) County lines, township lines, range lines, and section lines.
(6) Locations of construction access roads, permanent roads, and sites for
required construction facilities.
(7) Sources of natural construction materials and disposal areas for waste
material, including the extent of mitigation required.
(a) Location of disposal areas for debris, sediment, sludge, and spent
chemicals from cleaning or storage solutions.
(b) Location of channels and storage locations for brines, sludge, and
chemicals.
(11) Scale of general map should be adequate to clearly show listed details.
(1) The approximate distance from the nearest railroad shipping terminal to
the structure site; load restrictions and physical inadequacies of existing
roads and structures and an estimate of remedial improvements to
accommodate construction hauling; estimate of length and major
structures required for new construction access road; and possible
alternative means for delivering construction materials and equipment at
the structure site.
(4) Climatic conditions that will affect construction and operation and
maintenance procedures such as: amount, rate, and distribution of rain
and/or snow; ice conditions; monthly maximum and minimum (or at least
summer and winter) temperatures, and relative humidity; extreme wind
velocities and prevailing directions; and probability of excessive dust or
sand.
(5) Names, telephone numbers, email addresses and web sites of local
utilities; and contacts within those organizations.
C. Surface Data:
(1) Survey Control. Permanent horizontal and vertical survey control should
be established at the earliest possible time. A coordinate system on a true
north-south grid should be established with the origin located so that all of
the features (including borrow areas) at a major structure will be in one
quadrant, and so that the values of the coordinates for any major structure
are widely separated numerically. The coordinate system should be
All line surveys should be tied to the established coordinate system at each
plant site.
These photographs should be taken from locations that would best show
the proposed structure and from a vertical angle of approximately 20 to
30 degrees above the horizontal. Where possible, indicate known tie
points to the topographic maps. These photographs should be taken
between 11 a.m. and 2 p.m., so as not to show the principal area of the
proposed structure in shadow. Also submit the negatives or color slides.
(4) Photographs:
D. Foundation Data:
The amount and detail of foundation data required for a specifications design will
vary. The guiding criteria should be to provide sufficient data to allow the
designer to determine the type of foundation required for the structures and to
identify major foundation problems. Adequate foundation data may be obtained
for small structures from an inspection of surface conditions and one or two
exploratory holes to determine type of overburden and foundation conditions
some distance below the base of the structure. These data, and any other data in
the following paragraph that are relevant, along with a brief description of
geologic conditions of the site, can be included in the design data.
(a) Surficial soils (see Earth Manual, latest edition). Note geologic
sections and soil profiles in (1)(e) above.
E. Corrosion Survey:
(2) Performance history of construction materials that have been used in the
area.
(3) List of structures in the vicinity of (within ¼ mile) the proposed structure
and appurtenant features. Determine if buried structures in the vicinity
have corrosion protection and, if so, the type of corrosion protection.
(4) List location, output, and purpose of the direct-current sources in the earth
situated within ¼ mile of the proposed structure and appurtenant features.
If the purpose of the direct current is for cathodic protection, describe the
structure protected and its location.
(2) Location and distance to suitable borrow areas for permeable and
impermeable soil materials for fill or embankment; and for riprap for
channel or slope protection. If quantities are limited, give approximate
volumes available.
(5) Data on commercial concrete plants within practical hauling distance from
the structure site.
G. Hydrologic Data:
(1) Description of feed water source (surface water, ground water, drains,
wells, wastewater, partially treated wastewater, etc.).
(6) Potential location for and volume of reservoir(s) suitable for leveling of
daily or annual fluctuation in flow or salinity of water source.
(8) Determine composition of feed water; see table 2 at the end of this section.
(9) For brine disposal ponds obtain flood frequency flows for major surface
channels.
H. Operating Data:
(2) Results of pretreatment studies carried out at or near the proposed facility
site.
(3) Commitments for water delivery. Product water use and distribution
requirements. Projected monthly quantity of product water delivery on
demand basis or minimum delivery required over useful plant life.
(6) Future plans for facility expansion. Proposed initial and ultimate plant
capacity, and staged construction recommendations.
(a) Desired salinity and pH of product water and limits on specific ion
levels, if applicable.
(a) Published guidelines and regulations for air and water quality
standards.
(9) Maximum acceptable cost of product water, dollars per thousand gallons.
(10) Profile, alignment, and requirements for intake, product, and reject lines;
recommended types of pipe and types of coatings and linings.
(g) Provisions for cleaning ponds and delineation of disposal areas for
residue from ponds.
(26) Disposition of existing facilities in the area such as pipelines, power and
telephone lines, and fences.
(30) Housed and open O&M storage requirements at site; offsite storage to be
provided; existing storage space and facilities.
(2) Impact of product water quality on proposed use of water or the mixing
with natural waters.
(4) Background on the need for fish facilities, such as fishways and barriers.
(9) The need for blending structures with the surroundings, including placing
transmission circuits underground.
(10) The need for a field conference to resolve critical environmental problems
with participation of other agencies.
(12) Furnish data on allowable noise limits in the vicinity of the proposed
facility where fixed by law or local ordinance, or where otherwise
considered necessary or advisable; measurements of existing daytime and
nighttime ambient noise levels in the area: and distances to the nearest
residential units.
(13) Published guidelines and regulations concerning air and water quality
standards.
(14) Furnish data on state or local restrictions on the use of soil herbicides or
local factors limiting their use.
(a) The need for escape structures and/or protective fences for human
beings, deer, or other wildlife.
(1) Where buildings are located within the area to be cleared by the prime
contractor, and if disposal will be the contractor’s responsibility, designate
building groups by number and furnish detailed list of buildings for each
group. Details should include general description, size, materials, and
general condition. Determine if disposal will be the responsibility of
prime contractor. If not, submit dates when disposition will be completed
by others.
(2) Information on local labor supply and labor problems. Note if there are
labor shortages for key trade groups or other concerns which may require
premium pay.
L. Site Security:
(2) Expected visitor load at plant. Requirements for public safety and visitors
facilities.
M. Construction Considerations:
(1) Water for Construction Purposes. For large rivers, this item may be
unimportant. For small streams and offstream reservoirs, the item
becomes critical. Determine if up to 2-ft3/s diversion flow for
Construction purposes can be assured to the contractor. The Government
should obtain the water rights required. If necessary to use ground water,
obtain information on probable sources and yields. Furnish information
on locations and yields of existing wells in the vicinity. Determine
restrictions, if any, to use of ground water for this purpose. It may be
necessary to obtain permits from State or other governing agencies.
Retrieve water quality samples for testing and evaluation.
(1) List of agencies and organizations outside of Reclamation which will have
design and construction requirements inputs. Also, give names of contact
persons, mailing addresses, telephone numbers, email addresses, and web
sites.
O. Miscellaneous Data:
(3) Recommendations for special protection of roof or yard from falling rocks
or boulders.
Parameter Units
Total Hardness as CaCO3 mg/L
+2
Calcium (Ca ) mg/L
+2
Magnesium (Mg ) mg/L
+
Sodium (Na ) mg/L
+
Potassium (k ) mg/L
Total Cations meq/L
+3
Aluminum (Al ) mg/L
+2
Barium (Ba ) mg/L
+2
Copper (Cu ) mg/L
Iron (Total) mg/L
+2
Iron (Dissolved-Fe ) mg/L
Manganese (Total) mg/L
+2
Manganese (Dissolved-Mn ) mg/L
+3
Arsenic (As ) µg/L
Selenium (Total) mg/L
-2
Selenium (Dissolved-Se ) µg/L
+2
Strontium (Sr ) mg/L