1. Introduction to Construction Site Management.
1. Introduction to Construction Site Management.
• Tender drawings
Assist the tenderers come up with price for construction
of the works
Not meant for construction
Engineering drawings
Presentation of drawings
• Plans
Site plan
Floor plan
• Elevations
• Sections
• Details
• Schedules
Engineering drawings
Interpretation of drawings
• Scales
• Symbols
• Projections
• Line work
BUILDING REGULATIONS
A. Building Regulations
• A Statutory Instrument
• Specify the minimum specifications (performance
standards) for design and construction of buildings
• In Zimbabwe, the Model Building By-laws is the chief
of these regulations
BUILDING REGULATIONS
Building Regulations
B. Building Control
• Although Engineers are engaged to supervise works,
the control of works is vested in the Local Authority
Building Inspectors
CONSTRUCTION REGULATIONS
Construction Regulations
• Are Statutory Instruments made under the Factories
Works Act , Health & Safety Act & Environmental
Management Act
• They set out the minimum legal requirements for
construction works
• Relate primarily to the health, safety, welfare of the
workforce and environmental protection
• Requirements contained in these documents must be
adhered to during planning as well as actual construction
Contract documents
• Conditions of contract
Sets out the duties, rights, privileges and obligations
of the parties concerned
Contract documents
• Drawings
Set out the situation and constructional and other
details of the works and may include details of the
construction programmes
Contract documents
• Specification
They supplements the drawings in giving a detailed
engineering and technical description of the works
and nature and quality of materials, workmanship
and where necessary, methods to be used in
construction
Contract documents
• Bill of Quantities
A document containing a list of items giving the
estimated quantities and descriptions of all the work
to be performed and materials to be provided under
the contract
The quantities and descriptions are derived from
drawings and specifications
Payment Certificates
The Client
• Responsible for making the decision to invest in the Project
• Responsible for the approval of the project and thereafter providing a sustained
commitment to the project.
• To clearly define the scope of the project.
• Ensures that a brief is developed that clearly reflects the projects objectives.
• He/she Resolve issues pertaining project.
• Approve major changes to the project.
• Appoints the Project Sponsor for example many people want to sponsor a project
targeting profit returns, therefore he/she has to choose from the pool of sponsors
available.
Duties and responsibilities of construction team
The Architect
• The architect help the client to formulate his requirements in an
understandable form, bearing in mind any statutory conditions that
may apply. He or she helps the client to come up with the desired
structure putting into consideration the beauty of the structure. It
will be advantageous to the client at this stage if he could be shown
work of a similar nature so that he could obtain a visual impression of
shape, type of materials, size etc. if this is not possible, pictorial sketches
and/or model can be used, but it is often difficult for the client to visualize
the true structure from these very artistic representations.
• A professional person who prepares architectural designs, which will be
handed over to the engineer for structural design. His work gives shape to
buildings; the architect is only involved in building projects and not in civil
works projects like roads and dams.
Duties and responsibilities of construction team
• Project Management
• Undefined Goals
• Changing Scope
• No Accountability
• Lack of Risk Management
• Poor Communication
• Unrealistic Expectations etc.
Site Productivity
Factors affecting site productivity: external and internal
• Unforeseen events (weather, ground conditions, on-site accidents,
acts of God, natural disasters.
• Inflation/fluctuations in material prices.
• Energy crisis/costs
• Changes in government policies
• Rapid technological advances
• Late payments
• Reworks
• Undervalued work/poor estimations
• Disputes/ conflicts
• Inadequate supply or high cost of needed resources: money, labour,
etc.
Site Productivity
Factors affecting site productivity: workforce related
1) Level of commitment;
2) Level of empowerment;
3) Level of skill and experience
4) Level of familiarity with current job and conditions:
5) Level of involvement of direct labor or subcontract;
6) Workforce Absenteeism;
7) Level of staff turnover/churn rate;
8) Health of the workforce;
Site Productivity
Factors affecting site productivity: project management
issues
1) Adequacy of planning and risk management process;
2) Coordination; supervision; performance monitoring & control;
3) Project organizational culture;
4) Relationship management;
5) Competencies of the project team;
6) Project management style;
7) Frequency of design changes;
8) Client's over influence on the construction process;
Site Productivity
Factors affecting site productivity: technology/process
1) Suitability or adequacy of: Plant & equipment;
2) Method of construction;
3) Technology employed;
4) Lack of awareness of or training on new technologies;
5) Resistance to accept new technologies;
6) Inadequate IT infrastructure and application in construction
industry;
Site Productivity
Factors affecting site productivity: project
characteristics
1) Site conditions: access, subsoil; topography;
2) Project complexity;
3) Buildability issues;
4) Site location and environment;
5) Type of procurement adopted;
Site Productivity
Suggest ways of improving productivity at a
construction site.
Introduction to methods of planning and
scheduling
• These activities have some float. Hence the available float can be used for doing
adjustment in the start or finish of the concerned activities. Thus the peak demand
may be lowered by staggering the resource requirements with out delaying the
project duration.
Resource levelling
• In a project, there are many activities which need varying
resources.
• The demand on specific resource should not increase beyond
the prescribed limit.
• If the demand of a resource increases more than its availability,
then the only alternative is to delay the activity having maximum
float. This process is called resource levelling.
• If there are more than one activities requiring the same
amount of resources, in that case activity having minimum
duration is chosen for resource reallocation.
• Resource levelling if adopted in case, there is restriction on the
availability of resources
Resource levelling
ASANTE SANA!