PERT Exercise Problems With Solution

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
3 views

PERT Exercise Problems With Solution

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 5

Activity Duration Immediate predecessor

A 2 -

B 3 A

C 4 A

D 5 A

E 6 B

F 4 C,D

G 7 D

H 2 B

I 3 E,F,G

J 3 G

1) Exercise problem given in PPT

Solution:

2 H
B 6 0
3
E
2 4 3
4
S A C
3 0
4 F I FINISH
5
D 3

7 0
G
J
3
A-B-H => 2+3+2=7

A-B-E-I => 2+3+6+3=14

A-C-F-I => 2+4+4+3 = 13

A-D-F-I => 2+5+4+3 = 14

A-D-G-J => 2+5+7+3 = 17 (Critical Path)

A-D-G-I => 2+5+7+3 = 17 (Critical Path)

A-D-G-J (or) A-D-G-I is the critical path with 17days of duration.

2)
Activity Immediate Predecessors Estimated duration
in weeks
A - 2
B A 4
C B 10
D C 6
E C 4
F E 5
G D 7
H E,G 9
I C 7
J F,I 8
K J 4
L J 5
M H 2
N K,L 6

Draw the PERT network diagram and identify the Critical path.

Sol:
7 9 2
D G H M 0
6
9
4 10
2 4 FINISH
F K 6
S A B C E 8 4
5
0
J N
7

I 8 5 L 6

A-B-C-D-G-H-M => 2+4+ +10+ 6+ 7+ 9+2 = 40 Weeks

A-B-C-E-H-M=> 2+4+10+4+9+2 = 31 Weeks

A-B-C-E-F-J-K-N=> 2+4+10+4+5+8+4+6 = 43 Weeks

A-B-C-E-F-J-L-N=> 2+4+10+4+5+8+5+6 = 44 Weeks (Critical Path)

A-B-C-I-J-K-N=> 2+4+10+7+8+4+6 = 41 Weeks

A-B-C-I-J-L-N=> 2+4+10+7+8+5+6 = 42 Weeks

3)
Activity Preceding Activity Duration (days)
A - 3
B - 4
C - 2
D A,B 5
E B 1
F B 3
G F,C 6
H B 4
I E,H 4
J E,H 2
K C,D,F,J 1
L K 5

Draw the network diagram and identify the Critical path.

D
5
1
1 E
A 2
3 4
5 4
4 I
H 2
S B 3 J
4
1 1 5
F
6 K L
2 6 G

C 1

A-D-K-L => 3+5+1+5 = 14days

B-D-K-L=> 4+5+1+5 = 15days

B-E-I => 4+1+4 = 9days

B-E-J-K-L => 4+1+2+1+5 = 13days

B-H-I => 4+4+4 =12days

B-H-J-K-L => 4+4+2+1+5 = 16days

B-F-G => 4+3+6 = 13days


B-F-K-L => 4+3+1+5 = 13days

C-G => 2+6 = 8days

C-K-L => 2+1+5 = 8days

B-H-J-K-L is the critical path with 16days duration.