UNIT 4 SPM
UNIT 4 SPM
RISK : any uncertain event that may/may not occur and can cause loss to the project or could lead to
an unsuccessful project.
RISK MANAGEMENT: refers to identification of the possible risksand drawing up plans to minimise
their effect on a project.
Risk identification
Identify project, product and business risks;
Risk analysis
Assess the likelihood and consequences of these risks;
Risk planning
Draw up plans to avoid or minimise the effects of the risk;
Risk monitoring
Monitor the risks throughout the project;
RISK IDENTIFICATION :
Identifying risk is one of most important or essential and initial steps in risk management
process. Generally, identification of risk is an iterative process. It basically includes generating or
creating comprehensive list of threats that are based on events that can delay successful
achievement of objectives. In simple words, if you don’t find or identify risk, you won’t be able to
manage it.
STEPS :
1. Prepare a risk item check list based on components like product size,staff size ,business
impact etc.
2. Create risk components and driver list along with the probability of occurrence .
Risk components: performance, cost,support ,schedule
1 Avoidance strategies
The probability that the risk will arise is reduced;
2 Minimisation strategies
The impact of the risk on the project or product will be reduced;
3 Contingency plans
If the risk arises, contingency plans are plans to deal with that risk;
RISK MONITORING
Assess each identified risks regularly to decide whether or not it is becoming less or more probable.
Also assess whether the effects of the risk have changed.
Each key risk should be discussed at management progress meetings.
Risk Mitigation :
Risk Monitoring:
As the project proceeds, risk monitoring activities commence. The project manager monitors
factors that may provide an indication of whether the risk is becoming more or less likely.
Has following objectives :
1. To check if predicted risks occur or not.
2. To ensure proper application of risk aversion steps defined for risk.
3. To collect data for future risk analysis.
4. To allocate what problems are caused by which risks throughout the project.
It assumes that the mitigation activity failed and the risk is a reality. This task is done by Project
manager when risk becomes reality and causes severe problems. If the project manager effectively
uses project mitigation to remove risks successfully then it is easier to manage the risks. This shows
that the response that will be taken for each risk by a manager. The main objective of the risk
management plan is the risk register. This risk register describes and focuses on the predicted
threats to a software project.
The risk analysis will give the project manager information to say to the customer, “My risk analysis
indicates that the date you imposed on this project has only a 3 percent likelihood of occurring. You
need an extra two months to bring this up to the 50–50 point.
PERT assumes that the schedule logic represents how the project is going to be accomplished. Also,
similar to schedule risk analysis, PERT focuses on the uncertainty of the activity durations.
STATUS REPORT
A project status report is a document that describes the progress of a
project within a specific time period and compares it against the
project plan. Project managers use status reports to keep stakeholders
informed of progress and monitor costs, risks, time and work.
GREEN: ON TRACK
5. ISSUE AND RISKS: anything that impacts scope,time and budget. How
are you going to address such problems is mentioned.
MILESTONE REPORT
A change control process is a way for project managers to submit requests to stakeholders for
review, that are then approved or denied.
When it comes to managing multiple projects, things can get complicated. From coordinating work
timelines to tracking objectives and results, the last thing you want to deal with is a major project
change. But with a change control process in place, submitting project change requests is a
breeze.
Change control is a process used to manage change requests for projects and big initiatives. It’s
part of a change management plan, which defines the roles for managing change within a team or
company.
In most cases, any stakeholder will be able to request a change. A request could be as small as a
slight edit to the project schedule or as large as a new deliverable. It’s important to keep in mind
that not all requests will be approved, as it’s up to key stakeholders to approve or deny change
requests.
1. Increased productivity
2. Effective communication
. Assurance that all agreed upon project management processes have been executed, and
If a project is not closed properly, the project management team and the project
team's efforts, time, and credibility may be negatively perceived for matters that are
not their fault or responsibility.
Well, it is important to write a lessons learned report to record the desired outcomes
and solutions for all future projects. In this way, it helps in avoiding the same
mistakes again. The lessons learned report from the previous projects can be viewed
and analyzed before starting a new project to remember the mistakes that are not to
be made
When you plan to write a lessons learned report for your project, an important thing
to consider is that which will be the healthiest and best steps to write it.
Process: