PS-I UNIT-III FINAL
PS-I UNIT-III FINAL
UNIT-III: SUBSTATIONS
Classification of substations: Air Insulated Substations – indoor & outdoor substations,
substations layouts of 33/11 kV showing the location of all the substation equipment. Bus bar
arrangements in the sub-stations: simple arrangements like single bus bar, sectionalized
single bus bar, double bus bar with one and two circuit breakers, main and transfer bus bar
system with relevant diagrams. Gas Insulated Substations (GIS) – advantages of gas
insulated substations, different types of gas insulated substations, single line diagram of gas
insulated substations, constructional aspects of GIS, installation and maintenance of GIS,
comparison of air insulated substations and gas insulated substations.
Learning Objective : To study the constructional and operation of different components of
an Air and Gas Insulated substations.
Learning Outcome: After the completion of the course the student should be able to
1
identify the different components of air and gas insulated substations.
Department of Electrical & Electronics Engineering POWER SYSTEMS - I
OVERVIEW OF UNIT-III
S. No Major Concept Sub Concepts Applications
To understand the
Classification of Air Insulated Substations (AIS) – indoor & outdoor
necessity of
3.1 substations substations. substations layouts of 33/11 kV showing
substations & types of
the location of all the substation equipment.
substations
simple arrangements like single bus bar, sectionalized To understand various
Bus bar
single bus bar, double bus bar with one and two types of arrangements
3.2 arrangements in the
circuit breakers, main and transfer bus bar system of Bus bars in a
sub-stations
with relevant diagrams. substation
advantages of gas insulated substations, different To understand design
Gas Insulated types of gas insulated substations, single line diagram and working, types of
3.3
Substations (GIS) of gas insulated substations, constructional aspects of GIS
GIS, installation and maintenance of GIS,
Comparison of AIS
3.4 -----
& GIS
2
Department of Electrical & Electronics Engineering POWER SYSTEMS - I
4) Secondary Substation:
The secondary substations are lined alongside secondary transmission
lines adjacent to loads. The voltages here are further stepped-down for
purpose of distribution.
8
Department of Electrical & Electronics Engineering POWER SYSTEMS - I
10
Department of Electrical & Electronics Engineering POWER SYSTEMS - I
13
Department of Electrical & Electronics Engineering POWER SYSTEMS - I
Power Transformers
15
Department of Electrical & Electronics Engineering POWER SYSTEMS - I
16
Department of Electrical & Electronics Engineering POWER SYSTEMS - I
• The space between the conductor and the enclosure is filled with sulfur
hexafluoride gas under moderate pressure.
Gas Insulated Substations
(G.I.S)
Usage :
Gas insulated substation
mainly used for a power
transmission system or a
substation system, of which
outgoing bus-bar is shortened
to reduce consumption of the
outgoing bus-bar.
Its dielectric strength is greatly superior to that of air, and it is close to 100 times
as effective as air in quenching an electric arc.
The following requirement are important to satisfy, the
requirement of GIS can be summarized as
1. Conductors which conduct the main circuit current and transfer power these are
of copper or aluminum tubes.
4.Various circuit components in main circuit are: CB, Isolator, Earthing witches for
conductors, CTs, VTs, cable-ends, Bushing-ends and Bus-Bars, each of these
main components has its own gas -filled metal enclosed module.
5. Gas filling, monitoring system.
6. Auxiliary low voltage DC and low voltage AC supply system, control, protection
and Monitoring systems.
7. The bus-bars are conducting bars to which various incoming and outgoing
bays are connected. In SF6 GIS the bus-bars are laid longitudinally in GIS hall.
The bays are connected to bus-bars cross- wise, bus-bars are either with a three-
phase enclosure or single phase enclosure.
ADVANTAGES OF GAS INSULATED SUBSTATIONS
Compactness of GIS
The space occupied by SF6 installation is only about 10% of that of a
conventional outdoor substation. High cost is partly compensated by saving in
cost of space.
Protection from pollution
The moisture, pollution, dust etc., have little influence on SF6 insulated sub-
stations. However, to facilitate installation and maintenance, such substations are
generally housed inside a small building. The construction of the building need not
be very strong like conventional power houses.
Reduced Switching over voltages
The over voltages while closing and opening line, cables motors capacitors etc. are
low.
Reduced Installation Time
The principle of building-block construction (modular construction) reduces the
installation time to a few weeks. Conventional sub-stations require a few months
for installation.
Superior Arc Interruption
SF6 gas is used in the circuit-breaker unit for arc quenching. This type of breaker
can interrupt current without over voltages and with minimum acing time. Contacts
have long life and the breaker is maintenance free.
Gas Pressure
The gas pressure (4 kgf/cm2) is relatively low and does not pose serious leakage
problems.
Increased Safety
As the enclosures are at earth potential, there is no possibility of accidental contact
by service personnel to live parts.
Demerits of GIS
The following are the main disadvantages of Gas Insulated Substations over Air
Insulated Substations and Hybrid Substations.
•High cost compared to conventional outdoor sub-station.
•Excessive damage in case of internal fault. Long outage periods as repair of
damaged part at site may be difficult.
•Requirements of cleanliness are very stringent. Dust or moisture can cause internal
flashovers.
•Such sub-stations generally indoor. They need a separate building. This is
generally not required for conventional outdoor sub-stations. Procurement of gas
and supply of gas to site is problematic. Adequate stock of gas must be maintained.
Differences Between AIS and GIS
various tests performed on the gas insulted
substations
Routine tests, often referred to as production tests, are performed to ensure that
each GIS operates as it has been designed and type-tested for. The routine tests are
performed for each GIS after assembly and marks a major quality gate before the
GIS leaves the factory. The test parameters are based on the type test results, which
means that, within certain tolerances, the routine tests need to reflect the type test
data.
Dielectric Tests: The dielectric tests are done after the mechanical routine testing and
demonstrate the dielectric performance of the GIS, ensuring the correct assembly, correctly
manufactured parts from a dielectric point of view, and the absence of particles and other
contaminants
Power frequency dielectric test: For routine tests, the dielectric test is a power frequency
withstand voltage test. Impulse testing, such as lighting and switching impulse, is not
typically part of the routine testing. At minimum functional SF6 pressure, the following
conditions are tested: phase-to-ground, phase to-phase (in the case of three phases in one
enclosure design), and across open switching devices. Successfully withstanding the one
minute withstand level without a disruptive discharge is the main criteria to mark that the
test passed successfully.
The measurement of partial discharges: shall be performed to detect possible material and
manufacturing defects. The measurement of partial discharges shall be performed with
dielectric tests after mechanical routine tests. The test shall be carried out on all components
of the gas-insulated switchgear.
Measurement of the Resistance of the Main Circuits: Typically, the voltage drop or
resistance of main circuits are measured using a DC current of 100 A. this test. The test data
should be within a 20% tolerance band compared with the type test data.
Tightness Tests: Using devices such as SF6 piping, adaptation of SF6 leakage detectors, all
areas of enclosures assemblies, SF6 gauges, and SF6 density monitoring will be checked for
leaks.
Pressure Tests of Enclosures: After complete machining of enclosures, pressure tests are
made at 1.3 times the design pressure for welded aluminum and welded steel enclosures and
at 2 times the design pressure for cast enclosures. Automated test stations facilitate the
inclusion of a tightness test using helium after the pressure test of the enclosure. The
standard test pressure shall be:
•1.3 times design pressure for welded aluminum and welded steel enclosures.
•2 times design pressure for cast aluminum and composite aluminum enclosures.
The test pressure shall be maintained for at least 1 min. No rupture or permanent
deformation should occur during this test.
Mechanical Operation Tests :Mechanical operation tests include all devices of the GIS that
will be mechanically operated, such as a circuit breaker, disconnect switches, ground
switches, and high-speed ground switches. The tests include a certain number of operation
cycles at different control voltage levels and the correct function of the related auxiliary
equipment; for example, auxiliary switches to indicate the position of the circuit breaker and
switches.
Tests on Auxiliary and Control Circuits: These tests confirm that, during manufacturing,
all wiring has been done correctly according the related circuit diagrams. Auxiliary and
control circuits shall conform to the schematics, wiring diagrams, and technical data
provided by the manufacturer. Technical data may include the number, class, type, capacity
of available contacts, and electrical power of shunt releases (other than auxiliary and control
contacts, electrical power of shunt releases, etc.) This test have following sections:
Functional tests:
Verification of protection against electrical shock:
Dielectric tests on auxiliary and control circuits:
Pressure Tests on Partitions: Partitions are gas tight insulators that separate one gas
compartment from the other. They allow full pressure on one side and vacuum on the other.
Each partition has to be tested to twice that of the design pressure. It has to be ensured that
the weakest mechanical direction of the device is being considered for the test. This test
verifies that the partition has been manufactured correctly to withstand the pressure the
partition is designed for. Partitions will also be tested to the dielectric withstand capability
and a sensitive partial discharge measurement. Pressure tests shall be made on enclosures
after complete machining. Each partition shall be subjected to a pressure test at twice the
design pressure for 1 min in the weakest direction. For the pressure test the partition shall be
secured in exactly the same manner as in service. The partition shall not show any sign of
over stress or leakage.
What is a Bus Bar: Types & Their Working
The use of an electrical type will reduce the cost of labor, maintenance
cost, and installation costs. These are connected very easily and quickly.
These are used in various applications like hospitals, industries, data
centers, railways, metros, institutions, computer technology, and many
more.
It contains an isolator and the circuit breaker. If any fault occurs, the
circuit breaker gets tripped off and the part of the bus bar, which is
faulty can easily be disconnected. Mostly rectangular type is used in
electrical power distribution systems.
The bus bars are available in the sizes of 40x4mm, 40x5mm, 60x8mm,
50x6mm, 80x8mm, and 100x10mm. These are used in the distribution of
power depend on factors like cost, flexibility, reliability, etc. While
selecting its arrangement, consider that the arrangement should be easy
and simple, cheap and the maintenance should not affect the process of
distribution of power.
The single type is used in small substations where the process of the
continuous power supply is not required. An additional type is used in
large substations to avoid interruption in the power distribution. The
different types are explained below.
The single bus bar arrangement is very simple and easy. This type of
arrangement consists of a single bus with a switchboard.
The transformers, feeders, and generators are connected to the bus bar as
shown in the figure below.
The circuit breakers control the transformers, generators, and feeders.
During the maintenance, the isolators are used to isolate the
transformers, generators, and feeders from the bus bar.
The advantages of the single bus bar arrangement are
Low cost
Less maintenance
This type of arrangement is used in large stations where several units are
installed using a bus sectionalized. In this type, the circuit breakers and
isolators are used as shown in the figure below.
The isolator in the arrangement used to separate the faulty section to
protect the system from the shutdown. There is no increase in cost even
though an additional circuit breaker is used.
Advantages
Easy to remove the fault section, without any loss in the supply
continuity
The current limiting reactor helps to reduce the faults in the sections
of the bus.
Disadvantages
This type of bus bar is designed by combining the auxiliary type and the
main bus bar by using a bus coupler to connect the circuit breaker and
isolated switches. In case of overloading, the load is transferred from one
to another bus bar by using a bus coupler. In this case, the potentials of
the two bus bars should be the same to transfer the load and the main
bar should be opened and should be kept closer to transfer the load.
Advantages
The main advantage is shifting the load from one type to another
type if any fault occurs loss of continuity.
The cost of repair and maintenance is less
Disadvantages
As the whole systems use two bus bars, the cost would increase
The whole system may breakdown if any fault occurs in any of the
sections on the bus.
In this type, two bus bars with two circuit breakers are used. So, that it
doesn’t require any special types of equipment like a switch and bus
coupler.
Advantages
Disadvantages
The cost of the system and maintenance is more due to the additional
circuit breakers and two buses. So, these types of bus bar systems are
used in substations
In this type, an auxiliary type is also used along with the sectionalized
main bus bar system. Any of the sections in the main type can be
removed for repair and maintenance and can be connected to any of the
auxiliary bus bars in the system. There is no need to sectionalize the
auxiliary type because of its highest cost.
Disadvantages
Due to the ring arrangement, two paths are available for the supply.
So, the working of the system will not be affected due to the faults.
Disadvantages
Mesh Arrangement